SlideShare a Scribd company logo
1 of 10
 
M&R Day
Iwan - Abadi
One of the biggest HDPE Plant in Indonesia located at Cilegon, Banten Indonesia
experienced failures on two extruder screw shafts of 1-X-840 (extruder shaft #1) and
2-X-840 (extruder shaft #2).
Extruder Process Design Data
1. Feed Materials : HDPE or LLDPE
2. Feed Mat’l Melt Index: 0.1 to 50 (LLDPE 0.1 – 30; HDPE 5 to 50)
3. Feed Mat’l Water content: less than 700 ppm
4. Process Temperature: <240 C for LLDPE or <260 C for HDPE
5. Machine Capacity : 17.4 ton/h
6. Screw Speed : 224/156 rpm
7. Screw and Barrel : - Feed and Mixing Section 300 mm dia.
- Discharge Section 226 mm dia.
- Slot Clearance Adjustment 8 to 70 mm
- Operating Pressure : hopper cylinder 5 barg, others 4 barg
- Design Pressure: hopper cylinder 9 barg, others 6 barg
Extruder Zone
Broken Area at
Kneading zone
Fracture
surface
2
• Multiple crack origins
• Initiation 1 created a
stable crack
• Initiation 2 did not
create a stable crack
2
Extruder screw shaft #1 Extruder screw shaft #2
Extruder Operational Data and Failure History
1. Installation date : 1991
2. Both extruder were used to extrude Polyethylene with similar operational data history.
3. Processing temp. : Below 240 C
4. 1991 – 1998 : 15 - 16 ton/hour operating capacity
5. 1998 : Modification on kneading screw
6. 1998 – 2002 : Low operating capacity
7. 2003 – 2006 : Idle, not operated
8. 2006 – current : 21 ton/hour operating capacity
9. 2008 – 2009 : Barrel temp. inverter was in troubled
10. 2009 : Indication of vibration increased, Gland packing leakage
11. 2009 : Shaft gear pump coupling was broken (extruder #1)
12. 2010 : The temperature inverter problem was solved.
13. 2010 : Trial of HMW-PE on both extruder, very low MFI (0.02 up to 0.05)
14. 9 April 2010 : Extruder shaft #1 was failed, Broken shafts were on the right side of the
extruder (from motor view), After replacement, the gear box was broken
15. 2010 : The original screw was re-installed after the extruder shaft #1 was broken.
16. 9 Mei 2011 : Extruder shaft #2 was failed, Broken shafts were on the right side of the
extruder (from motor view)
 The failure point of the two extruder shaft #1 and #2 was located
before kneading/mixing zone, where the high pressure of
polyethylene melt was built up and high bending moment on shaft
was exist.
 Visual examination and SEM data strongly indicates a strong
contribution of fatigue bending moment failure with large
propagation area and minor contribution of torsion fatigue.
 Crack initiation sites on both extruder shafts have multiple crack
origins, although only one crack origin developed a stable crack and
propagated through shaft cross section and developed large
propagation area.
 Large propagation area indicated the applied stress after crack
initiation was considerably low. The crack initiation was likely
occurred when the loading was not distributed evenly to all
hexagonal surfaces and during overload period.
Physical Cause :
• The concentrated load was only possible when the fitness between shaft
surface to inner hexagonal surface of the screw is not zero clearance.
Non zero clearance will cause inhomogeneity contact between both surfaces;
the torsion moment has not been transmitted homogeneously to all
hexagonal surfaces but only been transmitted through the hexagonal shaft
corner.
Human Cause :
• The root cause of 1-X-840 and 2-X-840 extruder shaft failure was due to
fatigue failure initiated by domination of concentrated load on hexagonal shaft
surface during overload period.
Design Machine Capacity 17.4 ton/h
Historical, Machine in could be running at 21 ton/h
• Start and stop operation mode of this machine might contributed to increase
fatigue cycle.
Latent Cause :
• Inadequate procedure that allows operation of the machine above design
capacity & excessive start-stop mode.
Thank You

More Related Content

What's hot

Lab 5 measurement of gel strength of drilling mud by viscometer.
Lab 5 measurement of gel strength of drilling mud by viscometer.Lab 5 measurement of gel strength of drilling mud by viscometer.
Lab 5 measurement of gel strength of drilling mud by viscometer.Awais Qureshi
 
Liner hanger design and operations
Liner hanger design and operationsLiner hanger design and operations
Liner hanger design and operationsAbdulkadir Tekin
 
Rocker arm for vertical mill
Rocker arm for vertical millRocker arm for vertical mill
Rocker arm for vertical millIris Han
 
Plug & Abandonment
Plug & AbandonmentPlug & Abandonment
Plug & AbandonmentStatoil
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1Elsayed Amer
 
Planetary Mixer, High Shear Mixer Granulator, Plough Shear Mixer
Planetary Mixer, High Shear Mixer Granulator, Plough Shear MixerPlanetary Mixer, High Shear Mixer Granulator, Plough Shear Mixer
Planetary Mixer, High Shear Mixer Granulator, Plough Shear MixerVM Sethi
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
Impact crusher used in the coal industry
Impact crusher used in the coal industryImpact crusher used in the coal industry
Impact crusher used in the coal industrysmilewei005
 
perforated joint, flow coupling and blast joint
perforated joint, flow coupling and blast jointperforated joint, flow coupling and blast joint
perforated joint, flow coupling and blast jointElsayed Amer
 
10 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 2910 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 29Will Butler, P.Eng
 
02 wireline
02 wireline02 wireline
02 wirelineJohan RC
 
Well completion techniques
Well completion techniquesWell completion techniques
Well completion techniquesvelMurugan260
 

What's hot (19)

IntegraLine Brochure
IntegraLine BrochureIntegraLine Brochure
IntegraLine Brochure
 
Lab 5 measurement of gel strength of drilling mud by viscometer.
Lab 5 measurement of gel strength of drilling mud by viscometer.Lab 5 measurement of gel strength of drilling mud by viscometer.
Lab 5 measurement of gel strength of drilling mud by viscometer.
 
Liner hanger design and operations
Liner hanger design and operationsLiner hanger design and operations
Liner hanger design and operations
 
Rocker arm for vertical mill
Rocker arm for vertical millRocker arm for vertical mill
Rocker arm for vertical mill
 
ACT Tools
ACT Tools ACT Tools
ACT Tools
 
Plug & Abandonment
Plug & AbandonmentPlug & Abandonment
Plug & Abandonment
 
Well completion
Well completionWell completion
Well completion
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1
 
Packers
PackersPackers
Packers
 
intoduction
intoductionintoduction
intoduction
 
Planetary Mixer, High Shear Mixer Granulator, Plough Shear Mixer
Planetary Mixer, High Shear Mixer Granulator, Plough Shear MixerPlanetary Mixer, High Shear Mixer Granulator, Plough Shear Mixer
Planetary Mixer, High Shear Mixer Granulator, Plough Shear Mixer
 
Tubing string
Tubing stringTubing string
Tubing string
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Impact crusher used in the coal industry
Impact crusher used in the coal industryImpact crusher used in the coal industry
Impact crusher used in the coal industry
 
perforated joint, flow coupling and blast joint
perforated joint, flow coupling and blast jointperforated joint, flow coupling and blast joint
perforated joint, flow coupling and blast joint
 
Production packer
Production packerProduction packer
Production packer
 
10 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 2910 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 29
 
02 wireline
02 wireline02 wireline
02 wireline
 
Well completion techniques
Well completion techniquesWell completion techniques
Well completion techniques
 

Similar to M&R Day: Failure Analysis of Two Extruder Screw Shafts in a HDPE Plant

The general tyre and rubber company
The general tyre and rubber companyThe general tyre and rubber company
The general tyre and rubber companyRaza Jahangir
 
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...IRJET Journal
 
Development of Process for Replacement of Mill Roller
Development of Process for Replacement of Mill RollerDevelopment of Process for Replacement of Mill Roller
Development of Process for Replacement of Mill RollerIRJET Journal
 
BWEL Project Report
BWEL Project ReportBWEL Project Report
BWEL Project ReportASHISH KUMAR
 
Faults Analysis and Reliability Improvement of Pot Motor
Faults Analysis and Reliability Improvement of Pot MotorFaults Analysis and Reliability Improvement of Pot Motor
Faults Analysis and Reliability Improvement of Pot MotorIRJET Journal
 
small-hole-edm-manual.pdf
small-hole-edm-manual.pdfsmall-hole-edm-manual.pdf
small-hole-edm-manual.pdfRobin Yu
 
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitField Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitIRJET Journal
 
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...Moaz Emad gaber
 
Intelligent PdM Horizontal Vibration Centrifuge-ALPHA
Intelligent PdM Horizontal Vibration Centrifuge-ALPHAIntelligent PdM Horizontal Vibration Centrifuge-ALPHA
Intelligent PdM Horizontal Vibration Centrifuge-ALPHAKyle Lee
 
Superbolt Applications for Power Plants
Superbolt Applications for Power PlantsSuperbolt Applications for Power Plants
Superbolt Applications for Power PlantsCliff Fong
 
Report steffones
Report steffonesReport steffones
Report steffonesSteffones K
 
Mizztech slurry pump profile in English
Mizztech slurry pump profile in EnglishMizztech slurry pump profile in English
Mizztech slurry pump profile in EnglishCharles Cheng
 
6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRA
6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRA6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRA
6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRAshashi jaiswal
 
Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...
Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...
Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...Kinetrol USA
 

Similar to M&R Day: Failure Analysis of Two Extruder Screw Shafts in a HDPE Plant (20)

Bhel presentation
 Bhel presentation Bhel presentation
Bhel presentation
 
Turbine design need of the hour
Turbine design need of the hourTurbine design need of the hour
Turbine design need of the hour
 
The general tyre and rubber company
The general tyre and rubber companyThe general tyre and rubber company
The general tyre and rubber company
 
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
 
SPE 134239
SPE 134239SPE 134239
SPE 134239
 
Development of Process for Replacement of Mill Roller
Development of Process for Replacement of Mill RollerDevelopment of Process for Replacement of Mill Roller
Development of Process for Replacement of Mill Roller
 
BWEL Project Report
BWEL Project ReportBWEL Project Report
BWEL Project Report
 
Faults Analysis and Reliability Improvement of Pot Motor
Faults Analysis and Reliability Improvement of Pot MotorFaults Analysis and Reliability Improvement of Pot Motor
Faults Analysis and Reliability Improvement of Pot Motor
 
small-hole-edm-manual.pdf
small-hole-edm-manual.pdfsmall-hole-edm-manual.pdf
small-hole-edm-manual.pdf
 
Core plugging test
Core plugging test   Core plugging test
Core plugging test
 
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitField Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer Bit
 
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
 
Design and development of a tool
Design and development of a toolDesign and development of a tool
Design and development of a tool
 
Intelligent PdM Horizontal Vibration Centrifuge-ALPHA
Intelligent PdM Horizontal Vibration Centrifuge-ALPHAIntelligent PdM Horizontal Vibration Centrifuge-ALPHA
Intelligent PdM Horizontal Vibration Centrifuge-ALPHA
 
Superbolt Applications for Power Plants
Superbolt Applications for Power PlantsSuperbolt Applications for Power Plants
Superbolt Applications for Power Plants
 
Report steffones
Report steffonesReport steffones
Report steffones
 
Mizztech slurry pump profile in English
Mizztech slurry pump profile in EnglishMizztech slurry pump profile in English
Mizztech slurry pump profile in English
 
6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRA
6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRA6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRA
6 MONTHS TRAINING REPORT AT MAHINDRA AND MAHINDRA
 
Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...
Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...
Installation, Operation & Maintenance Instructions for Kinetrol Rotary Actuat...
 
molding.pdf
molding.pdfmolding.pdf
molding.pdf
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

M&R Day: Failure Analysis of Two Extruder Screw Shafts in a HDPE Plant

  • 2. One of the biggest HDPE Plant in Indonesia located at Cilegon, Banten Indonesia experienced failures on two extruder screw shafts of 1-X-840 (extruder shaft #1) and 2-X-840 (extruder shaft #2).
  • 3. Extruder Process Design Data 1. Feed Materials : HDPE or LLDPE 2. Feed Mat’l Melt Index: 0.1 to 50 (LLDPE 0.1 – 30; HDPE 5 to 50) 3. Feed Mat’l Water content: less than 700 ppm 4. Process Temperature: <240 C for LLDPE or <260 C for HDPE 5. Machine Capacity : 17.4 ton/h 6. Screw Speed : 224/156 rpm 7. Screw and Barrel : - Feed and Mixing Section 300 mm dia. - Discharge Section 226 mm dia. - Slot Clearance Adjustment 8 to 70 mm - Operating Pressure : hopper cylinder 5 barg, others 4 barg - Design Pressure: hopper cylinder 9 barg, others 6 barg
  • 4. Extruder Zone Broken Area at Kneading zone
  • 5. Fracture surface 2 • Multiple crack origins • Initiation 1 created a stable crack • Initiation 2 did not create a stable crack 2
  • 6. Extruder screw shaft #1 Extruder screw shaft #2
  • 7. Extruder Operational Data and Failure History 1. Installation date : 1991 2. Both extruder were used to extrude Polyethylene with similar operational data history. 3. Processing temp. : Below 240 C 4. 1991 – 1998 : 15 - 16 ton/hour operating capacity 5. 1998 : Modification on kneading screw 6. 1998 – 2002 : Low operating capacity 7. 2003 – 2006 : Idle, not operated 8. 2006 – current : 21 ton/hour operating capacity 9. 2008 – 2009 : Barrel temp. inverter was in troubled 10. 2009 : Indication of vibration increased, Gland packing leakage 11. 2009 : Shaft gear pump coupling was broken (extruder #1) 12. 2010 : The temperature inverter problem was solved. 13. 2010 : Trial of HMW-PE on both extruder, very low MFI (0.02 up to 0.05) 14. 9 April 2010 : Extruder shaft #1 was failed, Broken shafts were on the right side of the extruder (from motor view), After replacement, the gear box was broken 15. 2010 : The original screw was re-installed after the extruder shaft #1 was broken. 16. 9 Mei 2011 : Extruder shaft #2 was failed, Broken shafts were on the right side of the extruder (from motor view)
  • 8.  The failure point of the two extruder shaft #1 and #2 was located before kneading/mixing zone, where the high pressure of polyethylene melt was built up and high bending moment on shaft was exist.  Visual examination and SEM data strongly indicates a strong contribution of fatigue bending moment failure with large propagation area and minor contribution of torsion fatigue.  Crack initiation sites on both extruder shafts have multiple crack origins, although only one crack origin developed a stable crack and propagated through shaft cross section and developed large propagation area.  Large propagation area indicated the applied stress after crack initiation was considerably low. The crack initiation was likely occurred when the loading was not distributed evenly to all hexagonal surfaces and during overload period.
  • 9. Physical Cause : • The concentrated load was only possible when the fitness between shaft surface to inner hexagonal surface of the screw is not zero clearance. Non zero clearance will cause inhomogeneity contact between both surfaces; the torsion moment has not been transmitted homogeneously to all hexagonal surfaces but only been transmitted through the hexagonal shaft corner. Human Cause : • The root cause of 1-X-840 and 2-X-840 extruder shaft failure was due to fatigue failure initiated by domination of concentrated load on hexagonal shaft surface during overload period. Design Machine Capacity 17.4 ton/h Historical, Machine in could be running at 21 ton/h • Start and stop operation mode of this machine might contributed to increase fatigue cycle. Latent Cause : • Inadequate procedure that allows operation of the machine above design capacity & excessive start-stop mode.