SlideShare a Scribd company logo
1 of 36
Download to read offline
Asset Life Extension Process
Platform Slot Recovery
GULF OF SUEZ PETROLEUM Co. GUPCO

KAMEL ELSAYED
DRILLING ENGINEER
Slot recovery on J58-82
Site preparation for SB293-4 ERD WELL
ST BAHARI-1 TEAM

As operators cope with
maturing fields and
challenging market
conditions, it has become
increasingly important to
manage and extend the life
of assets
CONTENTS

STAGE I :

SECURING THE STRING FOR CUTTING

STAGE II : MULTI STRING CUTTER
STAGE III : PULL THE CUT-OFF STRING

STAGE IV : CUTTING STRING INTO PIECES
STAGE V : P/U DCS
1
1
Before start cutting the multi-string conductor,
we had to apply tension on the string so it
would come out easily when cutting is finished.
Applying tension would also make cutting faster.
We did that using CTU, C-plate and a spider
elevator
FIRST … WHAT IS A CTU ?!
CONDUCTOR TENSIONER UNIT

• A conductor tensioner unit is installed on an offshore jackup rig to apply
upward tension on the conductor.
• A Conductor Tensioning System consists of an elevated tensioning ring
pinned to and supported by hydraulic tensioning cylinders, each of which
are interconnected to a compensated hydraulic circuit employing bladder
type accumulators.
• When the cylinders are hydraulically extended to their mid-stroke, the
tensioning ring exerts a balanced upward pressure against a collar fitted
around the conductor, thereby imposing vertical tension on the conductor
string.
LARGE SKID-MOUNTED SPLIT CTU

TYPICAL SPECIFICATION
Tensioning capacity: 400 TON
Max. conductor diameter: 36”
(Adaptors available for smaller
conductor diameters)
Hydraulic cylinders: 8-Off (4-Off
per half)
Cylinder stroke: 610mm
Accumulators: Up to 11-Off
bladder type Nitrogen filled
Mode of travel: Slot and claw type
Skidding mechanism for travel
across CTP structure
WHAT IS A CTU ?!
Conductor Tensioning Unit

Cantilever

CTU, inside
STAGE #1: SECURING THE STRING FOR CUTTING
Removed the THS, then install 13-3/8” pulling tool onto the Braden head
STAGE #1: SECURING THE STRING FOR CUTTING
The C-plate supports the Spider elevator, which clamps on the pulling tool. Then the CTU pistons can be
extended to apply the desired amount of pulling force.

13-3/8” CSG
Pulling tool

CTU
Spider
Elevator

Hydraulic
Pistons

C-Plate

CTU
2
2
Now that we have the enough tension on the
string to be cut, cutting operation can
commence.
STAGE #2: MULTI STRING CUTTER
STAGE #2: MULTI STRING CUTTER
MSC knives protruding from the 24” conductor due to eccentricity of casing strings
Note

Multi-String Cutter

MSC got stuck while trying to cut the rest of the 24” Conductor (due to
eccentricity)
After many trials of rotating and applying overpull, we were successful to pull the
MSC out with all knives recovered
STAGE #2: MULTI STRING CUTTER
Damaged knives after POH … and knives were stuck in place and back-loaded as it is .
Note

Multi-String Cutter

We think that knives got bent laterally due to high torque applied to them … not
because of the over pull or slack
As a result we couldn’t get the knives back in place and that why we had to put
extra pull to retract them.

The sides of the knives had peeled off while trying to retract knives into place.
STAGE #2: MULTI STRING CUTTER
The sides of the knives had peeled off while trying to retract knives into place.
STAGE #2: MULTI STRING CUTTER
We ran in hole again with new set of knives and could successfully cut thru.

Cut-off
string

CSG Stump
Eccentricity of CSG
strings is very clear
3
Now we can recover the cut-off string to the
surface, but first we have to secure it.
STAGE #3: Pull the cut-off string
1- On the Production deck, Below the braden head, Cut window thru the 3 CSG strings and install a pin as a
securing pin (not to allow any string to slip off) and as a lifting pin as well.
STAGE #3: PULL THE CUT-OFF STRING
2- Remove the Spider Elevator and C-plate
3- Pull the string till the Braden head is above the rig floor
4
Now we have to cut the string into smaller
pieces that can be handled and transported
We’re going do that using:
1- BORAIS Dual pin drill
&
2- BORAIS Guillotine pipe saw
Quick Note

DUAL PIN DRILL

• Dual Pin Drill with hydraulically-powered twin opposed drills are used to
prepare cut sections of casing for securing and rigging.
• Dual Pin Drill incorporates two opposed drills on a mounting frame for drilling
precisely aligned holes through which bolts or pins can be inserted to secure
multiple-layered casings. Holes up to 4” can be drilled.
BORAIS DUAL HOLE DRILLING MACHINE
BORAIS DUAL HOLE DRILLING MACHINE IN ACTION
STAGE #4: CUTTING STRING INTO PIECES
Carbide inserts

Cut-off pieces due to hole drilling

24”

13-3/8”

9-5/8”
Quick Note

GUILLOTINE PIPE SAW

• Designed to cold cut 16” to 32” pipe of all materials, as well as solids , and
multi-stranded casing strings, can work in sub-sea conditions.
• It has Auto-clamp & Auto-feed features.
• A 16” diameter 3/4” wall steel pipe is cut in only 24 minutes.
• A 32” diameter multi-stranded casing string is cut in about 48 minutes.
BORAIS GUILLOTINE PIPE SAW
STAGE #4: CUTTING STRING INTO PIECES
Cut-off the first joint by BORAIS Guillotine pipe saw, and L/D on cantilever
STAGE #4: CUTTING STRING INTO PIECES
Securing Pins … is inserted into the drilled hole to prevent any of the casing string of slipping off.
It’s also secured by welding and wedges preparing for backload
5
P/U DCS parts and weld it on rig floor
5-7/8” VX-57 DRILL PIPES
XO 4-1/2” IF PIN x 5-7/8” VX-57 BOX

XO 30” XLF PIN x 4-1/2” IF BOX

2 x 30” XLF CONDUCTOR JOINTS

STAGE #5: P/U DCS
DCS ASSEMBLY
XLF BOX THREAD

DCS PART #2
ALL WELDED

DCS PART #1

BLIND BTM WITH SPIKES
STAGE #5: STAGE #5: P/U DCS
DCS part #1
STAGE #5: P/U DCS
Blind end with spikes that will grip into sea bed and prevent DCS movement with sea current
6
WAIT ON WEATHER TO RUN WITH ROV TO
ENSURE AREA AROUND OLD CASING STUMP
IS CLEAR FROM ANY DEBRIS
WAIT ON WEATHER TO RUN WITH DCS
Forward Plan

Production deck

Cellar deck

After Running with the
DCS, orienting it in the
new well direction, it
should be secured to the
platform by clamps to the
cellar deck and the
production deck, then
cold-cut the DCS just
above the production
deck
Later after the rig leaves
the platform, other
clamps can be installed on
the subsea bracings.
THANKS FOR YOUR TIME

KAMEL ELSAYED
DRILLING ENGINEER
BAHARI-1 RIG TEAM
BELLIHYKE@GUPCO.NET
0122 910 2341

More Related Content

What's hot

Wellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACEWellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACEAmir Rafati
 
Production Packer setting and types
Production Packer setting and typesProduction Packer setting and types
Production Packer setting and typesElsayed Amer
 
Wellhead function, rating and selection
Wellhead function, rating and selectionWellhead function, rating and selection
Wellhead function, rating and selectionElsayed Amer
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1Elsayed Amer
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN Elsayed Amer
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1Elsayed Amer
 
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی Reza Mostafavi Tabatabaei
 
Liner hanger design and operations
Liner hanger design and operationsLiner hanger design and operations
Liner hanger design and operationsAbdulkadir Tekin
 
Stuck up– packing and bridging dd
Stuck up– packing and bridging   ddStuck up– packing and bridging   dd
Stuck up– packing and bridging ddMohan Doshi
 
WELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptxWELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptxHandaBinAdi
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
Sequence of well drilling part 1
Sequence of well drilling part 1Sequence of well drilling part 1
Sequence of well drilling part 1Elsayed Amer
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operationsElsayed Amer
 

What's hot (20)

Wellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACEWellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACE
 
Production Packer setting and types
Production Packer setting and typesProduction Packer setting and types
Production Packer setting and types
 
Ssd spm
Ssd   spmSsd   spm
Ssd spm
 
Wellheads Training .pdf
Wellheads Training .pdfWellheads Training .pdf
Wellheads Training .pdf
 
Wellhead function, rating and selection
Wellhead function, rating and selectionWellhead function, rating and selection
Wellhead function, rating and selection
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN
 
Production packer
Production packerProduction packer
Production packer
 
Well head replacement
Well head replacementWell head replacement
Well head replacement
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1
 
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی
 
Liner hanger design and operations
Liner hanger design and operationsLiner hanger design and operations
Liner hanger design and operations
 
Wellhead
WellheadWellhead
Wellhead
 
Brocas IADC
Brocas IADCBrocas IADC
Brocas IADC
 
Stuck up– packing and bridging dd
Stuck up– packing and bridging   ddStuck up– packing and bridging   dd
Stuck up– packing and bridging dd
 
WELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptxWELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptx
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Sequence of well drilling part 1
Sequence of well drilling part 1Sequence of well drilling part 1
Sequence of well drilling part 1
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
 
Wellheads and Flow Lines.pdf
Wellheads and Flow Lines.pdfWellheads and Flow Lines.pdf
Wellheads and Flow Lines.pdf
 

Viewers also liked

Deep water drilling final
Deep water drilling finalDeep water drilling final
Deep water drilling finalTamer Bashandy
 
Claxton products and services overview
Claxton products and services overviewClaxton products and services overview
Claxton products and services overviewClaxton Engineering
 
MSc Subsea Engineering Final Thesis
MSc Subsea Engineering Final ThesisMSc Subsea Engineering Final Thesis
MSc Subsea Engineering Final ThesisChukwunonso Okereke
 
Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...
Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...
Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...Marcellus Drilling News
 
Offshore Rig Life Extension
Offshore Rig Life ExtensionOffshore Rig Life Extension
Offshore Rig Life ExtensionImran Choudury
 
Development of Guidelines and Standards for Life Extension
Development of Guidelines and Standards for Life ExtensionDevelopment of Guidelines and Standards for Life Extension
Development of Guidelines and Standards for Life ExtensionE.ON Exploration & Production
 
Wood Group - A Holistic Approach to Life Extension
Wood Group - A Holistic Approach to Life ExtensionWood Group - A Holistic Approach to Life Extension
Wood Group - A Holistic Approach to Life ExtensionTravis Cummins
 
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated ContractsFPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated ContractsDavid Seah
 
Abo Oml125
Abo Oml125Abo Oml125
Abo Oml125ennioeni
 
Fpso – general overview of conversion & topside process description -abstract
Fpso – general overview of conversion & topside process description -abstractFpso – general overview of conversion & topside process description -abstract
Fpso – general overview of conversion & topside process description -abstractAnoop Rajendran Nair
 
Halliburton Deepwater Cementing Presentation
Halliburton Deepwater Cementing PresentationHalliburton Deepwater Cementing Presentation
Halliburton Deepwater Cementing Presentationfiredoglake
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO RedeploymentDan Benson
 
Halliburton and Baker Hughes
Halliburton and Baker HughesHalliburton and Baker Hughes
Halliburton and Baker HughesJohn Jellinek
 
Life extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshoreLife extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshoreE.ON Exploration & Production
 
Drilling waste management_technology_1_
Drilling waste management_technology_1_Drilling waste management_technology_1_
Drilling waste management_technology_1_kelvins_luv
 
Oil & Gas industry Waste Management
Oil & Gas industry Waste ManagementOil & Gas industry Waste Management
Oil & Gas industry Waste Managementmamdouh sabour
 
Final Halliburton Presentation 10-17
Final Halliburton Presentation 10-17Final Halliburton Presentation 10-17
Final Halliburton Presentation 10-17Collette Latiolais
 

Viewers also liked (20)

Deep water drilling final
Deep water drilling finalDeep water drilling final
Deep water drilling final
 
Introduction to offshore structure
Introduction to offshore structure Introduction to offshore structure
Introduction to offshore structure
 
Claxton products and services overview
Claxton products and services overviewClaxton products and services overview
Claxton products and services overview
 
MSc Subsea Engineering Final Thesis
MSc Subsea Engineering Final ThesisMSc Subsea Engineering Final Thesis
MSc Subsea Engineering Final Thesis
 
Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...
Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...
Environmental Impacts During Marcellus Shale Gas Drilling: Causes, Impacts, a...
 
Offshore Rig Life Extension
Offshore Rig Life ExtensionOffshore Rig Life Extension
Offshore Rig Life Extension
 
apl-brochure
apl-brochureapl-brochure
apl-brochure
 
Development of Guidelines and Standards for Life Extension
Development of Guidelines and Standards for Life ExtensionDevelopment of Guidelines and Standards for Life Extension
Development of Guidelines and Standards for Life Extension
 
Wood Group - A Holistic Approach to Life Extension
Wood Group - A Holistic Approach to Life ExtensionWood Group - A Holistic Approach to Life Extension
Wood Group - A Holistic Approach to Life Extension
 
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated ContractsFPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
 
Abo Oml125
Abo Oml125Abo Oml125
Abo Oml125
 
Fpso – general overview of conversion & topside process description -abstract
Fpso – general overview of conversion & topside process description -abstractFpso – general overview of conversion & topside process description -abstract
Fpso – general overview of conversion & topside process description -abstract
 
Halliburton Deepwater Cementing Presentation
Halliburton Deepwater Cementing PresentationHalliburton Deepwater Cementing Presentation
Halliburton Deepwater Cementing Presentation
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO Redeployment
 
Halliburton and Baker Hughes
Halliburton and Baker HughesHalliburton and Baker Hughes
Halliburton and Baker Hughes
 
FPSO Requirements
FPSO RequirementsFPSO Requirements
FPSO Requirements
 
Life extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshoreLife extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshore
 
Drilling waste management_technology_1_
Drilling waste management_technology_1_Drilling waste management_technology_1_
Drilling waste management_technology_1_
 
Oil & Gas industry Waste Management
Oil & Gas industry Waste ManagementOil & Gas industry Waste Management
Oil & Gas industry Waste Management
 
Final Halliburton Presentation 10-17
Final Halliburton Presentation 10-17Final Halliburton Presentation 10-17
Final Halliburton Presentation 10-17
 

Similar to Offshore platform slot recovery process

Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
Coupler (08102015)
Coupler (08102015)Coupler (08102015)
Coupler (08102015)Khairul Amri
 
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app689198f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891AkashPatel747
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am newAhmed Radwan
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsVijay Raj
 
Design of cotter joint (machine design & industrial drafting )
Design of cotter joint (machine design & industrial drafting )Design of cotter joint (machine design & industrial drafting )
Design of cotter joint (machine design & industrial drafting )Digvijaysinh Gohil
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Thorne & Derrick International
 
Mechanical Assembly and Types
Mechanical Assembly and TypesMechanical Assembly and Types
Mechanical Assembly and TypesMuhammadUsman1795
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-AThorne & Derrick International
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptssuserea7ebc
 
Report steffones
Report steffonesReport steffones
Report steffonesSteffones K
 
00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling - 00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling - Adam Guo
 
igs and fixtures are specialised tools used in manufacturing to secure workpi...
igs and fixtures are specialised tools used in manufacturing to secure workpi...igs and fixtures are specialised tools used in manufacturing to secure workpi...
igs and fixtures are specialised tools used in manufacturing to secure workpi...yhchauhan
 
Drilling and producing well
Drilling and  producing wellDrilling and  producing well
Drilling and producing wellRaja Rosenani
 
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 CablesThorne & Derrick International
 

Similar to Offshore platform slot recovery process (20)

Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Coupler (08102015)
Coupler (08102015)Coupler (08102015)
Coupler (08102015)
 
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app689198f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am new
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressureparts
 
Cotter joint
Cotter jointCotter joint
Cotter joint
 
Design of cotter joint (machine design & industrial drafting )
Design of cotter joint (machine design & industrial drafting )Design of cotter joint (machine design & industrial drafting )
Design of cotter joint (machine design & industrial drafting )
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
 
Mechanical Assembly and Types
Mechanical Assembly and TypesMechanical Assembly and Types
Mechanical Assembly and Types
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.ppt
 
Mechanical assembly
Mechanical assembly Mechanical assembly
Mechanical assembly
 
Report steffones
Report steffonesReport steffones
Report steffones
 
00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling - 00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling -
 
igs and fixtures are specialised tools used in manufacturing to secure workpi...
igs and fixtures are specialised tools used in manufacturing to secure workpi...igs and fixtures are specialised tools used in manufacturing to secure workpi...
igs and fixtures are specialised tools used in manufacturing to secure workpi...
 
WP_May_2015
WP_May_2015WP_May_2015
WP_May_2015
 
9793339.ppt
9793339.ppt9793339.ppt
9793339.ppt
 
Drilling and producing well
Drilling and  producing wellDrilling and  producing well
Drilling and producing well
 
Brochure ENG (1)
Brochure ENG (1)Brochure ENG (1)
Brochure ENG (1)
 
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
 

Recently uploaded

Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 

Recently uploaded (20)

Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 

Offshore platform slot recovery process

  • 1. Asset Life Extension Process Platform Slot Recovery GULF OF SUEZ PETROLEUM Co. GUPCO KAMEL ELSAYED DRILLING ENGINEER
  • 2. Slot recovery on J58-82 Site preparation for SB293-4 ERD WELL ST BAHARI-1 TEAM As operators cope with maturing fields and challenging market conditions, it has become increasingly important to manage and extend the life of assets
  • 3. CONTENTS STAGE I : SECURING THE STRING FOR CUTTING STAGE II : MULTI STRING CUTTER STAGE III : PULL THE CUT-OFF STRING STAGE IV : CUTTING STRING INTO PIECES STAGE V : P/U DCS
  • 4. 1 1 Before start cutting the multi-string conductor, we had to apply tension on the string so it would come out easily when cutting is finished. Applying tension would also make cutting faster. We did that using CTU, C-plate and a spider elevator
  • 5. FIRST … WHAT IS A CTU ?! CONDUCTOR TENSIONER UNIT • A conductor tensioner unit is installed on an offshore jackup rig to apply upward tension on the conductor. • A Conductor Tensioning System consists of an elevated tensioning ring pinned to and supported by hydraulic tensioning cylinders, each of which are interconnected to a compensated hydraulic circuit employing bladder type accumulators. • When the cylinders are hydraulically extended to their mid-stroke, the tensioning ring exerts a balanced upward pressure against a collar fitted around the conductor, thereby imposing vertical tension on the conductor string.
  • 6. LARGE SKID-MOUNTED SPLIT CTU TYPICAL SPECIFICATION Tensioning capacity: 400 TON Max. conductor diameter: 36” (Adaptors available for smaller conductor diameters) Hydraulic cylinders: 8-Off (4-Off per half) Cylinder stroke: 610mm Accumulators: Up to 11-Off bladder type Nitrogen filled Mode of travel: Slot and claw type Skidding mechanism for travel across CTP structure
  • 7. WHAT IS A CTU ?! Conductor Tensioning Unit Cantilever CTU, inside
  • 8. STAGE #1: SECURING THE STRING FOR CUTTING Removed the THS, then install 13-3/8” pulling tool onto the Braden head
  • 9. STAGE #1: SECURING THE STRING FOR CUTTING The C-plate supports the Spider elevator, which clamps on the pulling tool. Then the CTU pistons can be extended to apply the desired amount of pulling force. 13-3/8” CSG Pulling tool CTU Spider Elevator Hydraulic Pistons C-Plate CTU
  • 10. 2 2 Now that we have the enough tension on the string to be cut, cutting operation can commence.
  • 11. STAGE #2: MULTI STRING CUTTER
  • 12. STAGE #2: MULTI STRING CUTTER MSC knives protruding from the 24” conductor due to eccentricity of casing strings
  • 13. Note Multi-String Cutter MSC got stuck while trying to cut the rest of the 24” Conductor (due to eccentricity) After many trials of rotating and applying overpull, we were successful to pull the MSC out with all knives recovered
  • 14. STAGE #2: MULTI STRING CUTTER Damaged knives after POH … and knives were stuck in place and back-loaded as it is .
  • 15. Note Multi-String Cutter We think that knives got bent laterally due to high torque applied to them … not because of the over pull or slack As a result we couldn’t get the knives back in place and that why we had to put extra pull to retract them. The sides of the knives had peeled off while trying to retract knives into place.
  • 16. STAGE #2: MULTI STRING CUTTER The sides of the knives had peeled off while trying to retract knives into place.
  • 17. STAGE #2: MULTI STRING CUTTER We ran in hole again with new set of knives and could successfully cut thru. Cut-off string CSG Stump Eccentricity of CSG strings is very clear
  • 18. 3 Now we can recover the cut-off string to the surface, but first we have to secure it.
  • 19. STAGE #3: Pull the cut-off string 1- On the Production deck, Below the braden head, Cut window thru the 3 CSG strings and install a pin as a securing pin (not to allow any string to slip off) and as a lifting pin as well.
  • 20. STAGE #3: PULL THE CUT-OFF STRING 2- Remove the Spider Elevator and C-plate 3- Pull the string till the Braden head is above the rig floor
  • 21. 4 Now we have to cut the string into smaller pieces that can be handled and transported We’re going do that using: 1- BORAIS Dual pin drill & 2- BORAIS Guillotine pipe saw
  • 22. Quick Note DUAL PIN DRILL • Dual Pin Drill with hydraulically-powered twin opposed drills are used to prepare cut sections of casing for securing and rigging. • Dual Pin Drill incorporates two opposed drills on a mounting frame for drilling precisely aligned holes through which bolts or pins can be inserted to secure multiple-layered casings. Holes up to 4” can be drilled.
  • 23. BORAIS DUAL HOLE DRILLING MACHINE
  • 24. BORAIS DUAL HOLE DRILLING MACHINE IN ACTION
  • 25. STAGE #4: CUTTING STRING INTO PIECES Carbide inserts Cut-off pieces due to hole drilling 24” 13-3/8” 9-5/8”
  • 26. Quick Note GUILLOTINE PIPE SAW • Designed to cold cut 16” to 32” pipe of all materials, as well as solids , and multi-stranded casing strings, can work in sub-sea conditions. • It has Auto-clamp & Auto-feed features. • A 16” diameter 3/4” wall steel pipe is cut in only 24 minutes. • A 32” diameter multi-stranded casing string is cut in about 48 minutes.
  • 28. STAGE #4: CUTTING STRING INTO PIECES Cut-off the first joint by BORAIS Guillotine pipe saw, and L/D on cantilever
  • 29. STAGE #4: CUTTING STRING INTO PIECES Securing Pins … is inserted into the drilled hole to prevent any of the casing string of slipping off. It’s also secured by welding and wedges preparing for backload
  • 30. 5 P/U DCS parts and weld it on rig floor
  • 31. 5-7/8” VX-57 DRILL PIPES XO 4-1/2” IF PIN x 5-7/8” VX-57 BOX XO 30” XLF PIN x 4-1/2” IF BOX 2 x 30” XLF CONDUCTOR JOINTS STAGE #5: P/U DCS DCS ASSEMBLY XLF BOX THREAD DCS PART #2 ALL WELDED DCS PART #1 BLIND BTM WITH SPIKES
  • 32. STAGE #5: STAGE #5: P/U DCS DCS part #1
  • 33. STAGE #5: P/U DCS Blind end with spikes that will grip into sea bed and prevent DCS movement with sea current
  • 34. 6 WAIT ON WEATHER TO RUN WITH ROV TO ENSURE AREA AROUND OLD CASING STUMP IS CLEAR FROM ANY DEBRIS WAIT ON WEATHER TO RUN WITH DCS
  • 35. Forward Plan Production deck Cellar deck After Running with the DCS, orienting it in the new well direction, it should be secured to the platform by clamps to the cellar deck and the production deck, then cold-cut the DCS just above the production deck Later after the rig leaves the platform, other clamps can be installed on the subsea bracings.
  • 36. THANKS FOR YOUR TIME KAMEL ELSAYED DRILLING ENGINEER BAHARI-1 RIG TEAM BELLIHYKE@GUPCO.NET 0122 910 2341