SlideShare a Scribd company logo
1 of 2
Download to read offline
12573 Route 9W • West Coxsackie, NY 12192 • www.igga.net • (518) 731–7450
June 2020
Rebuilt to Last
DOWEL BAR RETROFIT (DBR) is a Concrete Pavement Preservation
(CPP) tool that restores load transfer across joints and cracks by
installing dowel bars linking the adjoining slabs. By linking slabs, the
traffic load is shared, preventing differential vertical movement of the
slabs at the joints and cracks, thereby eliminating the formation of
faults or stepoffs. It is these faults that cause the rough ride and wheel
slap that is sensed when traveling on a concrete roadway that has lost
its ability to transfer load from one panel to the next.
DBR, in conjunction with other CPP practices such as diamond
grinding, can return a concrete roadway to a structurally sound,
smooth condition that can exceed the smoothness and noise values
attained at the time of construction.
» BACKGROUND
In 1992, the Washington State Department of Transportation (WSDOT)
constructed a DBR test section to determine the appropriateness of
DBR and diamond grinding to restore the functionality of concrete
pavements by providing a smooth, structurally sound, rut-free surface.
Due to the success of the test section, the first large scale DBR
project was constructed on I-90 in 1993. Since that time, WSDOT
has rehabilitated well over 300 miles of existing concrete pavement
by employing DBR followed by diamond grinding. According to WSDOT
research, the average construction costs for DBR was approximately
16 percent less (2006 dollars) than the typical cost of a four-inch
asphalt overlay, which is the minimum recommended overlay depth
for rehabilitating a faulted concrete pavement. The success realized
by WSDOT has promoted widespread acceptance of the process and
as a result, 20 states and one Canadian province have completed
numerous successful projects.
» BENEFITS OF DBR PROJECTS:
dowel bar retrofit
DBR Restores
Concrete Roadways
to Structurally
Sound, Smooth
Conditions
LONG
LASTING
When properly constructed, DBR lasts 15 to 20
years.
ENVIRON-
MENTALLY
FRIENDLY
DBR maintains the existing surface with very little
new material required. Also, keeping the pavement
light reduces the heat island effect as these
pavements reflect more light, which in turn reduces
roadside lighting requirements.
TRAFFIC
FRIENDLY
Projects can be completed during off-peak hours
with short single lane closures.
FLEXIBLE
DBR only has to be applied to the lanes that show
distress, whereas other treatments require the entire
roadway to be treated.
EASY TO
BID
Its simple design process allows projects to be
designed and advertised in a fraction of the time
required for competitive processes.
SAFETY
Diamond grinding enhances surface friction and
safety. In Wisconsin, researchers found that the
overall wet weather accident rate for diamond ground
surfaces was only 57 percent of the rate for non-
ground surfaces.
SMOOTH
Diamond ground roadways typically have a smooth-
ness level equal to or better than original construc-
tion.
COST
EFFECTIVE
DBR is considered cost effective since it is only
applied to the faulted lane, while an asphalt overlay
would be required on all lanes and shoulders,
significantly increasing costs unnecessarily. When
utilizing the asphalt overlay option, guide rails,
overhead signs and bridges may need to be raised,
increasing overall project cost.
ABOUT IGGA
The International Grooving & Grinding Association (IGGA) is a non-profit trade association founded in 1972 by a group of dedicated industry
professionals committed to the development of the diamond grinding and grooving process for surfaces constructed with Portland cement
concrete and asphalt. In 1995, the IGGA joined in affiliation with the American Concrete Pavement Association (ACPA) to form what is now
referred to as the Concrete Pavement Preservation Partnership (IGGA/ACPA CP3). The IGGA/ACPA CP3 now serves as the lead industry
representative and technical resource in the development and marketing of optimized pavement surfaces, concrete pavement restoration
and pavement preservation around the world.
12573 Route 9W • West Coxsackie, NY 12192 • www.igga.net • (518) 731–7450
June 2020
Before completing any work, the owner must determine that the
existing pavement has the structural integrity to warrant DBR. A good
DBR candidate is a roadway in which a majority of the pavement slabs
exhibit a sound surface and provide significant remaining load carrying
capacity. Roadways that have extensive spalling of the surface, with
special attention paid to joint and crack locations, require further
evaluation. Extensive deterioration may be an indication of larger
problems within the slab not visible from the surface. Cores should
be taken at these locations to determine the level of deterioration.
Excessive bottom-up deterioration and spalling will inhibit bonding and
may lead to premature DBR failure.
The DBR must be placed on sound concrete, which is a requirement
for a successful and long-lasting installation. Working joints or cracks
that have opened up 1 inch or more at the surface require further
investigation. Areas demonstrating this bottom-up deterioration
below the pavement surface should be considered as full-depth repair
candidates. Areas that demonstrate heavy spalling at joints and cracks
but minimal bottom-up deterioration should be repaired utilizing partial
depth repairs prior to DBR installation.
Corner cracking may be an indication of voids under the slabs. Further
testing with ground penetrating radar or other devices may be required
to determine if undersealing should be included as a part of the project.
» INSTALLATION
To begin, diamond saw blades mounted on a gang saw capable of
forming a minimum of three slots at a time are used to saw-cut the
perimeter of the slots. The slot dimensions should be based on the
length and diameter of the bar being used, allowing enough room
for the aggregate within the mix to move freely around the bar and
chairs. The most common slot width is 2 ½ inches when using a 1
½ inch diameter dowel bar. The slots should be placed on 1-foot
centers, centered over the transverse joint or crack and parallel to
the centerline with three or four slots per wheel path.
Next, the team must remove the existing concrete within dowel bar
slots utilizing light-weight jackhammers. To clean the slot, the team
will utilize sandblasting to remove saw slurry and other debris from
the slot. They then seal the existing joint or crack with a caulking
compound and place the DBR assembly (bar, cap, coreboard and
chair) into the slot centered over the joint or crack. Prior to backfilling,
all surfaces of the slot are moistened. Non-shrink patching material
is placed and consolidated into the slot and cured according to
manufacturer recommendations.
Diamond grinding is then used to provide a safe, smooth and quiet
pavement surface followed by a joint resealing operation to prevent
moisture and incompressibles from entering the repair area.
For more information on DBR and diamond grinding, as well as a
complete set of industry recommended specifications, please visit
www.igga.net.
WHERE TO CONSIDER DBR
Pavements that exhibit load transfer below 60 percent.
Joint and crack faulting between 1/8 to 3/4 inch.
Transverse cracks that are reasonably tight with minimal spalling. If
applied early, diamond grinding costs may be greatly reduced.
Pavements that were constructed as non-doweled jointed
pavements can have DBR applied to prevent future faulting as an
effective pavement preservation treatment.
WHERE NOT TO CONSIDER DBR
Pavements that demonstrate extreme deterioration at the joints
or cracks require coring and joint sounding to determine if the
pavement has the structural integrity to support the DBR process.
Pavements that exhibit severe signs of chemical deterioration
such an ASR or D cracking should be examined closely before
considering DBR.
Under-designed pavements that are cracking due to loading may
require structural enhancement through the use of an overlay.
Pavements with significant base deterioration and/or erosion should
be addressed with undersealing prior to applying the DBR process.
» THE PROCESS: INVESTIGATION

More Related Content

What's hot

Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular ConcreteJill Reeves
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)alamrintu
 
Concrete Pavement Rehabilitation Method
Concrete Pavement Rehabilitation MethodConcrete Pavement Rehabilitation Method
Concrete Pavement Rehabilitation MethodDenish Sonani, CMIT
 
Shree Sai Pavers Presentation.pptx
Shree Sai Pavers Presentation.pptxShree Sai Pavers Presentation.pptx
Shree Sai Pavers Presentation.pptxshree sai pavers
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. IGauri kadam
 
INVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATE
INVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATEINVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATE
INVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATEIAEME Publication
 
Sustainable road maintenance strategies
Sustainable road maintenance strategiesSustainable road maintenance strategies
Sustainable road maintenance strategiesDragos Andrei
 
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDERMANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDERIAEME Publication
 
Types Of Porous Pavements Final
Types Of Porous Pavements FinalTypes Of Porous Pavements Final
Types Of Porous Pavements Finalmayhew50
 
HIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEMHIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEMseminarppts
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance inKulbir Singh gill
 
Pavement design
Pavement designPavement design
Pavement designhusna004
 

What's hot (20)

Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular Concrete
 
Interlocking pavement
Interlocking pavementInterlocking pavement
Interlocking pavement
 
Pavements ( BASICS)
Pavements  ( BASICS)Pavements  ( BASICS)
Pavements ( BASICS)
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)
 
Advantages of interlocking paver block
Advantages of interlocking paver blockAdvantages of interlocking paver block
Advantages of interlocking paver block
 
Concrete Pavement Rehabilitation Method
Concrete Pavement Rehabilitation MethodConcrete Pavement Rehabilitation Method
Concrete Pavement Rehabilitation Method
 
Complete report1123121
Complete report1123121Complete report1123121
Complete report1123121
 
Shree Sai Pavers Presentation.pptx
Shree Sai Pavers Presentation.pptxShree Sai Pavers Presentation.pptx
Shree Sai Pavers Presentation.pptx
 
Ramesh kumar
Ramesh kumarRamesh kumar
Ramesh kumar
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
INVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATE
INVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATEINVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATE
INVESTIGATING CAUSES OF PAVEMENT DETERIORATION IN KHARTOUM STATE
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 
2016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-162016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-16
 
Sustainable road maintenance strategies
Sustainable road maintenance strategiesSustainable road maintenance strategies
Sustainable road maintenance strategies
 
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDERMANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
 
Types Of Porous Pavements Final
Types Of Porous Pavements FinalTypes Of Porous Pavements Final
Types Of Porous Pavements Final
 
HIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEMHIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEM
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance in
 
Pavement design
Pavement designPavement design
Pavement design
 
History of pavement
History of pavementHistory of pavement
History of pavement
 

Similar to Dowel Bar Retrofit: Restore Load Transfer in Concrete Pavement

PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forVishalshukla347388
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
RoaDrain Brochure Web spreads
RoaDrain Brochure Web spreadsRoaDrain Brochure Web spreads
RoaDrain Brochure Web spreadsRobin Vodenlic
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadIRJET Journal
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxDolanGhosh4
 
How nanotechnology provides great solutions to road construction issues
How nanotechnology provides great solutions to road construction issuesHow nanotechnology provides great solutions to road construction issues
How nanotechnology provides great solutions to road construction issueszydexindustries
 
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET Journal
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavementAminat Aliu
 
VDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable PavementVDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable PavementPatrick McPartland, E.I.T.
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Transportation Pavement.pptx
Transportation Pavement.pptxTransportation Pavement.pptx
Transportation Pavement.pptxWajehUlHassan
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37Amardeep Singh
 
ppt on construction and design of flexible pavement
ppt on construction and design of flexible pavementppt on construction and design of flexible pavement
ppt on construction and design of flexible pavementSUSMITAMAITY4
 

Similar to Dowel Bar Retrofit: Restore Load Transfer in Concrete Pavement (20)

PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx for
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
porous and previous roads
porous and previous roadsporous and previous roads
porous and previous roads
 
RoaDrain Brochure Web spreads
RoaDrain Brochure Web spreadsRoaDrain Brochure Web spreads
RoaDrain Brochure Web spreads
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing Road
 
Pavement Deterioration
Pavement DeteriorationPavement Deterioration
Pavement Deterioration
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptx
 
How nanotechnology provides great solutions to road construction issues
How nanotechnology provides great solutions to road construction issuesHow nanotechnology provides great solutions to road construction issues
How nanotechnology provides great solutions to road construction issues
 
STITCHING CONCRETE PAVEMENT CRACKS AND JOINTS
STITCHING CONCRETE PAVEMENT CRACKS AND JOINTSSTITCHING CONCRETE PAVEMENT CRACKS AND JOINTS
STITCHING CONCRETE PAVEMENT CRACKS AND JOINTS
 
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavement
 
VDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable PavementVDOT BMP Clearinghouse Specification 7- Permeable Pavement
VDOT BMP Clearinghouse Specification 7- Permeable Pavement
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Transportation Pavement.pptx
Transportation Pavement.pptxTransportation Pavement.pptx
Transportation Pavement.pptx
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37
 
ppt on construction and design of flexible pavement
ppt on construction and design of flexible pavementppt on construction and design of flexible pavement
ppt on construction and design of flexible pavement
 

More from International Grooving & Grinding Association

Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...
Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...
Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...International Grooving & Grinding Association
 

More from International Grooving & Grinding Association (11)

Joint Resealing is a Vital Tool in the Concrete Pavement Preservation Toolbox
Joint Resealing is a Vital Tool in the Concrete Pavement Preservation ToolboxJoint Resealing is a Vital Tool in the Concrete Pavement Preservation Toolbox
Joint Resealing is a Vital Tool in the Concrete Pavement Preservation Toolbox
 
CPP Rebuilt to Last: Diamond Grinding and Patching Restore U.S. 67 in Arkansas
CPP Rebuilt to Last: Diamond Grinding and Patching Restore U.S. 67 in ArkansasCPP Rebuilt to Last: Diamond Grinding and Patching Restore U.S. 67 in Arkansas
CPP Rebuilt to Last: Diamond Grinding and Patching Restore U.S. 67 in Arkansas
 
Good for the Road - Good for the Soil
Good for the Road - Good for the SoilGood for the Road - Good for the Soil
Good for the Road - Good for the Soil
 
Concrete Grinding Residue (Aka Slurry): Research Studies Document Slurry’s Sa...
Concrete Grinding Residue (Aka Slurry): Research Studies Document Slurry’s Sa...Concrete Grinding Residue (Aka Slurry): Research Studies Document Slurry’s Sa...
Concrete Grinding Residue (Aka Slurry): Research Studies Document Slurry’s Sa...
 
Ohio DOT Grooves Asphalt for Safety
Ohio DOT Grooves Asphalt for SafetyOhio DOT Grooves Asphalt for Safety
Ohio DOT Grooves Asphalt for Safety
 
Pavement Surface: an important consideration in Korea's long tunnels
Pavement Surface: an important consideration in Korea's long tunnelsPavement Surface: an important consideration in Korea's long tunnels
Pavement Surface: an important consideration in Korea's long tunnels
 
Area Mayors Secure Next Generation Concrete Surface (NGCS) for Houston’s Katy...
Area Mayors Secure Next Generation Concrete Surface (NGCS) for Houston’s Katy...Area Mayors Secure Next Generation Concrete Surface (NGCS) for Houston’s Katy...
Area Mayors Secure Next Generation Concrete Surface (NGCS) for Houston’s Katy...
 
ODOT uses longitudinal grooving for safety on asphalt as well as concrete pav...
ODOT uses longitudinal grooving for safety on asphalt as well as concrete pav...ODOT uses longitudinal grooving for safety on asphalt as well as concrete pav...
ODOT uses longitudinal grooving for safety on asphalt as well as concrete pav...
 
Put Your Seal on Better Pavement Performance
Put Your Seal on Better Pavement PerformancePut Your Seal on Better Pavement Performance
Put Your Seal on Better Pavement Performance
 
Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...
Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...
Next Generation Concrete Surface (NGCS): What is NGCS…Who is Using it…What ar...
 
A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...
A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...
A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...
 

Recently uploaded

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Dowel Bar Retrofit: Restore Load Transfer in Concrete Pavement

  • 1. 12573 Route 9W • West Coxsackie, NY 12192 • www.igga.net • (518) 731–7450 June 2020 Rebuilt to Last DOWEL BAR RETROFIT (DBR) is a Concrete Pavement Preservation (CPP) tool that restores load transfer across joints and cracks by installing dowel bars linking the adjoining slabs. By linking slabs, the traffic load is shared, preventing differential vertical movement of the slabs at the joints and cracks, thereby eliminating the formation of faults or stepoffs. It is these faults that cause the rough ride and wheel slap that is sensed when traveling on a concrete roadway that has lost its ability to transfer load from one panel to the next. DBR, in conjunction with other CPP practices such as diamond grinding, can return a concrete roadway to a structurally sound, smooth condition that can exceed the smoothness and noise values attained at the time of construction. » BACKGROUND In 1992, the Washington State Department of Transportation (WSDOT) constructed a DBR test section to determine the appropriateness of DBR and diamond grinding to restore the functionality of concrete pavements by providing a smooth, structurally sound, rut-free surface. Due to the success of the test section, the first large scale DBR project was constructed on I-90 in 1993. Since that time, WSDOT has rehabilitated well over 300 miles of existing concrete pavement by employing DBR followed by diamond grinding. According to WSDOT research, the average construction costs for DBR was approximately 16 percent less (2006 dollars) than the typical cost of a four-inch asphalt overlay, which is the minimum recommended overlay depth for rehabilitating a faulted concrete pavement. The success realized by WSDOT has promoted widespread acceptance of the process and as a result, 20 states and one Canadian province have completed numerous successful projects. » BENEFITS OF DBR PROJECTS: dowel bar retrofit DBR Restores Concrete Roadways to Structurally Sound, Smooth Conditions LONG LASTING When properly constructed, DBR lasts 15 to 20 years. ENVIRON- MENTALLY FRIENDLY DBR maintains the existing surface with very little new material required. Also, keeping the pavement light reduces the heat island effect as these pavements reflect more light, which in turn reduces roadside lighting requirements. TRAFFIC FRIENDLY Projects can be completed during off-peak hours with short single lane closures. FLEXIBLE DBR only has to be applied to the lanes that show distress, whereas other treatments require the entire roadway to be treated. EASY TO BID Its simple design process allows projects to be designed and advertised in a fraction of the time required for competitive processes. SAFETY Diamond grinding enhances surface friction and safety. In Wisconsin, researchers found that the overall wet weather accident rate for diamond ground surfaces was only 57 percent of the rate for non- ground surfaces. SMOOTH Diamond ground roadways typically have a smooth- ness level equal to or better than original construc- tion. COST EFFECTIVE DBR is considered cost effective since it is only applied to the faulted lane, while an asphalt overlay would be required on all lanes and shoulders, significantly increasing costs unnecessarily. When utilizing the asphalt overlay option, guide rails, overhead signs and bridges may need to be raised, increasing overall project cost.
  • 2. ABOUT IGGA The International Grooving & Grinding Association (IGGA) is a non-profit trade association founded in 1972 by a group of dedicated industry professionals committed to the development of the diamond grinding and grooving process for surfaces constructed with Portland cement concrete and asphalt. In 1995, the IGGA joined in affiliation with the American Concrete Pavement Association (ACPA) to form what is now referred to as the Concrete Pavement Preservation Partnership (IGGA/ACPA CP3). The IGGA/ACPA CP3 now serves as the lead industry representative and technical resource in the development and marketing of optimized pavement surfaces, concrete pavement restoration and pavement preservation around the world. 12573 Route 9W • West Coxsackie, NY 12192 • www.igga.net • (518) 731–7450 June 2020 Before completing any work, the owner must determine that the existing pavement has the structural integrity to warrant DBR. A good DBR candidate is a roadway in which a majority of the pavement slabs exhibit a sound surface and provide significant remaining load carrying capacity. Roadways that have extensive spalling of the surface, with special attention paid to joint and crack locations, require further evaluation. Extensive deterioration may be an indication of larger problems within the slab not visible from the surface. Cores should be taken at these locations to determine the level of deterioration. Excessive bottom-up deterioration and spalling will inhibit bonding and may lead to premature DBR failure. The DBR must be placed on sound concrete, which is a requirement for a successful and long-lasting installation. Working joints or cracks that have opened up 1 inch or more at the surface require further investigation. Areas demonstrating this bottom-up deterioration below the pavement surface should be considered as full-depth repair candidates. Areas that demonstrate heavy spalling at joints and cracks but minimal bottom-up deterioration should be repaired utilizing partial depth repairs prior to DBR installation. Corner cracking may be an indication of voids under the slabs. Further testing with ground penetrating radar or other devices may be required to determine if undersealing should be included as a part of the project. » INSTALLATION To begin, diamond saw blades mounted on a gang saw capable of forming a minimum of three slots at a time are used to saw-cut the perimeter of the slots. The slot dimensions should be based on the length and diameter of the bar being used, allowing enough room for the aggregate within the mix to move freely around the bar and chairs. The most common slot width is 2 ½ inches when using a 1 ½ inch diameter dowel bar. The slots should be placed on 1-foot centers, centered over the transverse joint or crack and parallel to the centerline with three or four slots per wheel path. Next, the team must remove the existing concrete within dowel bar slots utilizing light-weight jackhammers. To clean the slot, the team will utilize sandblasting to remove saw slurry and other debris from the slot. They then seal the existing joint or crack with a caulking compound and place the DBR assembly (bar, cap, coreboard and chair) into the slot centered over the joint or crack. Prior to backfilling, all surfaces of the slot are moistened. Non-shrink patching material is placed and consolidated into the slot and cured according to manufacturer recommendations. Diamond grinding is then used to provide a safe, smooth and quiet pavement surface followed by a joint resealing operation to prevent moisture and incompressibles from entering the repair area. For more information on DBR and diamond grinding, as well as a complete set of industry recommended specifications, please visit www.igga.net. WHERE TO CONSIDER DBR Pavements that exhibit load transfer below 60 percent. Joint and crack faulting between 1/8 to 3/4 inch. Transverse cracks that are reasonably tight with minimal spalling. If applied early, diamond grinding costs may be greatly reduced. Pavements that were constructed as non-doweled jointed pavements can have DBR applied to prevent future faulting as an effective pavement preservation treatment. WHERE NOT TO CONSIDER DBR Pavements that demonstrate extreme deterioration at the joints or cracks require coring and joint sounding to determine if the pavement has the structural integrity to support the DBR process. Pavements that exhibit severe signs of chemical deterioration such an ASR or D cracking should be examined closely before considering DBR. Under-designed pavements that are cracking due to loading may require structural enhancement through the use of an overlay. Pavements with significant base deterioration and/or erosion should be addressed with undersealing prior to applying the DBR process. » THE PROCESS: INVESTIGATION