SlideShare a Scribd company logo
1 of 141
Download to read offline
Managing Gravel Road Maintenance
2015 NACE Conference – Daytona Beach, FL
4-22-2015
Presented by:
Ken Skorseth, Program Manager
South Dakota Local Transportation Assistance Program
South Dakota State University
Brookings, South Dakota, USA
Overview of Presentation
• Critical Issues:
–Roadway Shape or Geometry
–Gravel Quality and Quantity
–Maintenance Practices
–Training needs (if time allows)
A good resource:
The FHWA Gravel
Roads manual –
currently out of print,
but is available online
Good example of a Low Volume Rd Design Guide
Good guidance, non-
technical, accommodates
unpaved road design.
Basic Cross Section
Sketch of One Half of Roadway – Rural Section
(from center to left)
Foreslope:
recommended at 3:1
slope
A flat bottom ditch
is recommended,
hard to build at less
than eight feet.
Backslope as ROW
allows
3 ft. (example only)
The challenge is often
working in a confined R-O-W.
From AASHTO Guidelines for Geometric Design of Very
Low-Volume Local Roads (ADT < 400)
Agricultural Access Classification:
Minimum roadway width is 24 ft at 20 to
40 mph design speed, increases to 26 ft if
design speed is 50 mph
Great project, but few new gravel roads
are built
Good ditch construction and drainage
Gravel Road Rehabilitation: Often the Best
Improvement Possible
Any tool to help break sod and clumped soil is
helpful
Sometimes this is reality in confined ROW
No real cross section – You have to do
better than this!
Not many gravel surfaced roads are being built
in the US. Many existing gravel roads need
rehabilitation
Some best practice examples:
Complete rehabilitation of a county road
in Day County, SD -2013 Season
Recovery of aggregate from foreslope and
reestablishing shoulder line
Road originally constructed in 1970s
Modern tools can make the job easier
Salvage of remaining gravel
Soils in this area are weak – generally silty
clays
Done entirely with county equipment
Mixing & processing subgrade soil
Doing the best they can with what they have
Good tool
if other
compaction
equipment is
not available
Picking rocks the easy way!
Spreading the salvage gravel
Finished slopes
Finished surface
Finished shoulder line
First lift of new gravel – 2.5 inches
Project done with same process two years
earlier – road is so much easier to maintain
Another Challenge – Reverting Asphalt Surfaces
to Unpaved Surfaces:
Recycle Process
Virgin gravel
course added on
roadway prior to
recycling.
Recycle Process (Con’t)
Reshape & compaction of the material
Outstanding performance
Performance documentation
on 2-7-2013. This road had
no blade maintenance since
May, 2012. ADT is 75
Maintenance Challenges After Construction or
Rehabilitation:
10 inches average
annual rainfall
65 inches average
annual rainfall
Maintaining no crown
A crown gauge is helpful
Electronic Slope Reading
In the motorgrader cab: On-board electronics
are coming to the market very quickly
Slope Control systems on motorgraders are a
great aid in construction and rehabilitation
Poor surface drainage
Electronics only work if the operator accepts it!
Good surface drainage
Crown Example on 20 Ft Road Surface
The Next Challenge – High Shoulders!
Reasonably good cross section on low volume road
with poor horizontal and vertical alignment
Some thoughts on roads with severe horizontal
and vertical alignment problems
Drainage is critical
Just as critical is surface aggregate quality
Most of the surface is tightly bound here
Surface aggregate has good overall gradation
and relatively small top size.
Virtually no corrugation on day of observation
Recent roadway reshape is very good
Drainage run-out to carry water away from
road with erosion control – good practice.
Good culvert installation under driveway
Vertical alignment makes maintenance very
challenging – grade checked at 23.4% at one
location!
Managing Gravel Quality and Quantity
Recent validation check of material quality in SD
Gradation/PI Tests
61
List of Gravel Sources
Deuel County A
Deuel County B
Beadle County
Miner County
Hughes County
Mitchell Township
Lincoln County
Clay County
Jerauld County
Why these sites chosen?
Previous data seems inaccurate
Study contrast in local
materials used on unpaved
road
Summary
62
Source Gradation PI
Deuel County A Failed Failed (No PI)
Deuel County B Failed Failed (No PI)
Beadle County Failed Passed (5)
Miner County Failed Passed (6)
Hughes County Failed Passed (4)
Mitchell Township Failed Failed (No PI)
Lincoln County Passed Failed (no PI)
Clay County Failed Passed (7)
Jerauld County Failed Passed (4)
Gravel Quality Issues
• Gradation problems generally confined to small
percentage retained on 1 in. sieve (SDDOT Gravel
surfacing spec requires 100% passing 3/4 in. sieve.
• Generally good on the split between coarse and fine
aggregate on the #4 sieve.
• SDDOT Standard Specification requires minimum
plasticity index (PI) of 4 and maximum of 12
– Only five of nine samples had PI.
– Maximum PI tested was 7.
Part of the problem in not getting plasticity:
Managing Layer Thickness: Coring a Gravel Road:
Over two inches of thickness deviation
Example of test pit in existing gravel road
Calculate spread
rates on gravel
projects
It requires 407 cubic yards (570 tons) to place
one inch of gravel on a one mile 20 ft wide.
A 25-ton load of gravel covers only 320 linear ft to
place one inch of gravel on one mile 20 ft wide.
Nice job of processing and placing gravel
The skilled
operator is the key
to controlling
gravel road shape
and placing gravel.
Note: this is an adequate layer for maintenance,
but not adequate thickness to carry legal loads
in all conditions!
Deep Layer Needed to Carry Heavy Loads
14.5 inches of gravel needed
to carry 25 to 50 trucks per
day over weak subgrade!
From SDDOT Rural Road Design, Maint, & Rehab Guide
77
More on Gravel Quality
Same operator
Same road
Same day
Different gravel
Updates From the SDDOT/SDLTAP
Surface Gravel Study Project
Brookings Site Constructed in 2011
Reason for Project
• More than 50% of local roads in SD are unpaved –
managing them is a challenge!
• Biggest complaints from public are: rough condition
(generally from corrugation or “washboard” in
surface) and too much loose aggregate on the
surface makes it hard to control a vehicle.
• How critical is gravel quality to this and how does it
affect total cost of maintenance?
• Primary focus is on effect of gravel quality on
life-cycle cost of gravel road maintenance
• Three types of gravel used in study:
1. Substandard but commonly used – meets no
spec except top size control – one inch minus.
2. Barely meets SDDOT Gravel Surfacing Spec –
percent passing #200 sieve is low and/or
plasticity index (PI) at bottom of range at 4
3. Modified SDDOT Spec – higher minimums of
10% passing #200 sieve and PI at 7.
Focus of Test Project
Substandard
Gravel
SD Standard
Specification
Modified
Specification
Compacted and
Uncompacted
Sections
Compacted and
Uncompacted
Sections
Buffer Sections
One of the biggest challenges was finding
gravel that meets the modified SDDOT
Specification: “Shall have minimum plasticity
index (PI) of seven”. (Even higher minimum
was considered in project planning)
One way to meet modified spec – blend
different material from separate sources
This was done on one
section in Brookings Co
and one section in
Custer Co
Is this the future? More blending or “manufacturing” to
get high quality gravel – processing from a natural clay
source here:
Road mixing natural clay to get a high quality
surface gravel
Please
note this
area
Current Status of Project
• SDLTAP has accumulated photo documentation
on all sections over the past two years.
• Measurement and documentation has been done
on these distress types in 2012 & 2013:
1. Accumulation of loose aggregate (float)
2. Changes in top width from time of construction
3. Presence of corrugation (washboard) on surface
4. Change in roadway crown
The float test (loose aggregate)
Simply remove
loose aggregate
from a 10 inch
cross section,
weigh it and
convert that to a
one-mile section
Change in top-width is measured on traveled
way – hinge point to hinge point
XX ft.
Corrugation (washboard):
Hard to quantify in extent,
fairly easy to measure severity
Brookings Section – Loose Aggregate 2012
(Tons per mile)
Substandard
Compacted Uncompacted
Standard Spec
Uncompacted Compacted
Modified
Spec
405 tons
71 tons
Cooler, wetter season in
2013 – 2.94 inches of rain in
previous 20 days – most of
that in three days prior to
the last test.
Difference in 2012 & 2013 maintenance seasons:
Brooking Section – Loose aggregate 2013
0
20
40
60
80
100
120
140
160
180
200
Tons per mile (October 2013)
Tons per mile
(October 2013)
186 tons
16 tons
Loose aggregate comparison 2013 & 2012
0
50
100
150
200
250
300
350
400
450
Tons per mile
(October 2013)
Tons per mile
(October 2012)
2014 Spring Measurement of Loose Aggregate
0
50
100
150
200
250
300
350
Substandard C Substandard UC Standard UC Standard C Modified C
6/20/2014 Measurements
Substandard
Compacted Uncompacted
Standard Spec
Uncompacted Compacted
Modified
Spec
44 tons
310 tons
118 tons
Corrugation (Washboard)
• No corrugation observed on any sections
meeting at least minimum standard
specification.
• However, substandard section had the
beginning of light corrugation only two days
after blade maintenance after nearly three
inches of rain.
Change in Roadway Surface Width
Constructed Width – 21.5 ft on all sections
Constructed Width – Modified Section
Current Width – Oct 2013
Constructed Width – Standard Spec Section
Current Width – Oct 2013
Constructed Width – Substandard Section
Current Width – Oct 2013
Current width ranges from 22 ft on modified section (top
bar) to 25.25 ft on substandard section (bottom bar)
Substandard section – aggregate has moved
outward over 4 ft since construction
Modified section has moved outward only six
inches since construction
View of Substandard section – 10-18-13
View of Modified section – 10-18-13
Does the modified section rut in wet weather?
No, virtually no rutting observed.
Any traffic on
this road?
Concluding Points
• Meeting basic SDDOT standard surface gravel
specification reduces loose aggregate by 1/3 to 1/2.
• Widest differential was in Brookings County near end
of corn harvest in 2012 with 405 tons of loose
aggregate on substandard section to only 71 tons on
modified section.
• No corrugation ever observed on standard or modified
material.
• Most interesting fact thus far: Brookings has done
blade maintenance up to four times on substandard
section to only once on modified!
• A negative aspect: we are getting a lot of push-back
from aggregate producers who would prefer to
produce as they always have – no close control of %
passing the #200 sieve and plasticity index.
Concluding Points (Con’t)
Feasibility of Dust Control
or Stabilization
$-
$20,000.00
$40,000.00
$60,000.00
$80,000.00
$100,000.00
$120,000.00
$140,000.00
$160,000.00
0 200 400 600 800 1000
ADT
AgencyCost($)
HMA
Blotter
Gravel
Linear (HMA)
Linear (Blotter)
Linear (Gravel)
Gravel Blotter HMA
Summary of gravel, AST and HMA surface
life cycle costs related to ADT – SDDOT Surface
Selection Criteria Study
Gravel – cost
effective to 150 ADT
AST (Blotter) – cost
effective to 650 ADT
HMA Pavement – cost
effective above 650 ADT
109
Cass County, ND Cement Treated Gravel
Excellent stability in the gravel layer
May 15, 2014 – cold, late spring in a slough area
Remarkable success with stabilized gravel in SD
A Chloride Stabilized Road Since 1998!
112
Portland Cement Railcar Offloading Facility
113
Less than 200 tons of gravel replaced in 14 yrs!
Carries up to 80 portland cement haulers
per day in addition to regular traffic.
114
Brief Coverage of Chloride Treatment Process
• Must have good surface gravel in place:
– Needs to meet surface specification (ND Class 13 or SD
Gravel Surfacing Specification)
– Prefer minimum four inches thickness on good base
• Gravel must be prepared well:
– Loosen the top one to two inches uniformly across the
surface.
– Gravel must be in a moist condition while preparing and
just prior to treatment.
• Apply chloride evenly and uniformly.
• Don’t use rollers too soon! (Sometimes not at all)
Bit-type cutting edges are excellent for
preparing surface
Excellent example – surface is loose and open
in moist condition
Don’t apply too much chloride in one pass –
watch for absorption
Second application being made after complete
absorption of first application
Case Study from Meade County, SD
Experience with Alternatives to
Paving
Information from:
Mr. Ken McGirr
Meade County Highway Supt
Sturgis, SD
• Elk Vale Road
– Located directly east and north of Rapid City
– Serves a growing area just off of exit 61 on
Interstate Highway 90
– Classification: Rural Major Collector
– Became impossible to maintain as gravel surface
121
Recent Traffic Count Breakdown
• Northbound
– 12/04/2012 299 total vehicles 22 trucks
– 12/05/2012 319 total vehicles 28 trucks
– 12/06/2012 317 total vehicles 22 trucks
• Southbound
– 12/04/2012 331 total vehicles 69 trucks
– 12/05/2012 339 total vehicles 92 trucks
– 12/06/2012 319 total vehicles 76 trucks
• Total*
– 12/04/2012 610 total vehicles 91 trucks
– 12/05/2012 658 total vehicles 120 trucks
– 12/06/2012 636 total vehicles 98 trucks
*Meade County count tallied over 700 vehicles in earlier count with 25% trucks
122
Average 635 vehicles per day and average 103
trucks per day (16% of total volume)
A difficult area for road management
Originally constructed in May, 2011
Excellent performance after first year
124
Close-up view of stabilized surface
125
Stabilization was done with .75 gal of liquid MgCl2
per sq yd mixed into top three inches (75 mm) of
good quality surface gravel layer
126
No significant loose aggregate and no
corrugation even on 7% grade.
127
No blade maintenance was done
between construction in summer
of 2011 and surface retreatment
in summer of 2012!
128
Phone call from citizen – “If you had
enough money to pave this road, why
didn’t you save enough to put striping
on it”
129
End of season condition assessment 10-24-13
Skid marks from recent incident
Observation– 2-29-14
Treatment done in May, 2013
A little about training
• A great need in our industry
–Management level
–Field supervisors
–Operators
Management Training
• Clear communication on expectations must
be conveyed to field staff.
• Does everyone have the same goals?
• Is management too preoccupied with the
primary roads?
• Gravel roads become very low priority and
consequently reach failed or near failed
condition before work is done?
Field Supervisor Training
• May not understand the right geometry needed
on a gravel road (different than pavement).
• Consequently do not know how to convey to
operators (in-house or out sourced) what is
needed for good maintenance.
• Supervisors and operators develop adversarial
relationship – the team breaks down!
Operator Training
• Too often no training given on desired
roadway shape (geometry) and bad habits
are developed.
• Little or no mentoring by skilled operators
who could communicate what they know.
• Great lack of training in our technical colleges
or trades training centers for this field.
• No recognition for doing a good job!
SD Recent Training Efforts
Administrative and Field Supervisor Training
Operator Training
Results:
• Positive Outcomes:
– Excellent attendance and participation
– Significant request for more training
– Operators and supervisors understand each other’s
positions much better
• Challenges:
– Lack of good training material
– Agencies want training very condensed and fast
– Very hard to find good trainers, especially for
operator level
– Hands-on field training is expensive
A new education
resource in the
US:
The Gravel Roads
Academy
Easy to find online
by doing a simple
search
Get ready to face the challenges of
maintaining gravel roads in the future!
Good Luck and Thank You!

More Related Content

What's hot

Pavement skid resistance
Pavement skid resistancePavement skid resistance
Pavement skid resistanceHai Vo
 
L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1  L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1 Sachin PatiL
 
Corrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in railsCorrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in railsSagar Kaptan
 
Ce2026 traffic engineering and management notes
Ce2026 traffic engineering and management notesCe2026 traffic engineering and management notes
Ce2026 traffic engineering and management notesNayana 54321
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road constructionAnitha Jacob
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume StudiesMd Tanvir Alam
 
Traffic volume-study
Traffic volume-studyTraffic volume-study
Traffic volume-studyStone Rayhan
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineeringtirath prajapati
 
Hill roads and Drainage
Hill roads and DrainageHill roads and Drainage
Hill roads and Drainageholegajendra
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional ElementsAkshathaBhandary
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distanceAglaia Connect
 
Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Pankti Jethi
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic EngineeringLatif Hyder Wadho
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railwayRAMPRASAD KUMAWAT
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian uitm pulau pinang
 
INTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERINGINTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERINGjagadeesh prasad
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentationPawan Kumar
 

What's hot (20)

Pavement skid resistance
Pavement skid resistancePavement skid resistance
Pavement skid resistance
 
L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1  L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1
 
Corrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in railsCorrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in rails
 
Ce2026 traffic engineering and management notes
Ce2026 traffic engineering and management notesCe2026 traffic engineering and management notes
Ce2026 traffic engineering and management notes
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
 
Traffic volume-study
Traffic volume-studyTraffic volume-study
Traffic volume-study
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineering
 
Hill roads and Drainage
Hill roads and DrainageHill roads and Drainage
Hill roads and Drainage
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distance
 
Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic Engineering
 
3. earthen roads 30 aug
3. earthen roads 30 aug3. earthen roads 30 aug
3. earthen roads 30 aug
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian
 
INTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERINGINTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERING
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 

Similar to Managing gravel road maintenance and rehabilitation

Gravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the StateGravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the StateUGPTI
 
Webinar_Full_Depth_Reclamation_2_3_2022.pptx
Webinar_Full_Depth_Reclamation_2_3_2022.pptxWebinar_Full_Depth_Reclamation_2_3_2022.pptx
Webinar_Full_Depth_Reclamation_2_3_2022.pptxgamalelmostafa
 
New ppt on road construction
New ppt on road construction New ppt on road construction
New ppt on road construction Kuldeep317348
 
Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportUGPTI
 
LTCP meeting 02-10-05
LTCP meeting 02-10-05LTCP meeting 02-10-05
LTCP meeting 02-10-05HartTWI
 
Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...UGPTI
 
Proper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete PavementsProper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete PavementsJill Reeves
 
Rehabilitation of Flexible Pavements.pptx
Rehabilitation of Flexible Pavements.pptxRehabilitation of Flexible Pavements.pptx
Rehabilitation of Flexible Pavements.pptxGhulam Mehdi Sahito
 
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...UGPTI
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Malyar Talash
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete RoadwaysJill Reeves
 
PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forVishalshukla347388
 
CV530_04_Pavement-Design.pdf
CV530_04_Pavement-Design.pdfCV530_04_Pavement-Design.pdf
CV530_04_Pavement-Design.pdfssuser3f175e
 
CE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvu
CE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvuCE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvu
CE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvussuserb923e1
 

Similar to Managing gravel road maintenance and rehabilitation (20)

Gravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the StateGravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the State
 
Webinar_Full_Depth_Reclamation_2_3_2022.pptx
Webinar_Full_Depth_Reclamation_2_3_2022.pptxWebinar_Full_Depth_Reclamation_2_3_2022.pptx
Webinar_Full_Depth_Reclamation_2_3_2022.pptx
 
Pavement
PavementPavement
Pavement
 
New ppt on road construction
New ppt on road construction New ppt on road construction
New ppt on road construction
 
Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status Report
 
LTCP meeting 02-10-05
LTCP meeting 02-10-05LTCP meeting 02-10-05
LTCP meeting 02-10-05
 
final ppt.pptx
final ppt.pptxfinal ppt.pptx
final ppt.pptx
 
Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota's County, Township, & Tribal Roads & Bridg...
 
Proper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete PavementsProper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete Pavements
 
Rehabilitation of Flexible Pavements.pptx
Rehabilitation of Flexible Pavements.pptxRehabilitation of Flexible Pavements.pptx
Rehabilitation of Flexible Pavements.pptx
 
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
2016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-162016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-16
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete Roadways
 
PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx for
 
CV530_04_Pavement-Design.pdf
CV530_04_Pavement-Design.pdfCV530_04_Pavement-Design.pdf
CV530_04_Pavement-Design.pdf
 
CE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvu
CE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvuCE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvu
CE3030igbyugfvtukfctrkryjcrycdftykfvtuljuvyuvu
 
Ada resurface apwa_2016_presentation
Ada resurface apwa_2016_presentationAda resurface apwa_2016_presentation
Ada resurface apwa_2016_presentation
 
pothole repairs
pothole repairspothole repairs
pothole repairs
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 

More from Florida Public Works Expo

More from Florida Public Works Expo (6)

Nace 2015 presentation roadsoft
Nace 2015 presentation    roadsoftNace 2015 presentation    roadsoft
Nace 2015 presentation roadsoft
 
Nace barker presentation
Nace barker presentationNace barker presentation
Nace barker presentation
 
Making the successful single stream leap
Making the successful single stream leapMaking the successful single stream leap
Making the successful single stream leap
 
Golf lesson slides 040215
Golf lesson slides 040215Golf lesson slides 040215
Golf lesson slides 040215
 
2015 nace daytona_gsp
2015 nace daytona_gsp2015 nace daytona_gsp
2015 nace daytona_gsp
 
Uninterrupted lift station operation using by pass pump
Uninterrupted lift station operation using by pass pumpUninterrupted lift station operation using by pass pump
Uninterrupted lift station operation using by pass pump
 

Recently uploaded

ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 

Recently uploaded (20)

ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 

Managing gravel road maintenance and rehabilitation

  • 1. Managing Gravel Road Maintenance 2015 NACE Conference – Daytona Beach, FL 4-22-2015 Presented by: Ken Skorseth, Program Manager South Dakota Local Transportation Assistance Program South Dakota State University Brookings, South Dakota, USA
  • 2. Overview of Presentation • Critical Issues: –Roadway Shape or Geometry –Gravel Quality and Quantity –Maintenance Practices –Training needs (if time allows)
  • 3. A good resource: The FHWA Gravel Roads manual – currently out of print, but is available online
  • 4. Good example of a Low Volume Rd Design Guide Good guidance, non- technical, accommodates unpaved road design.
  • 6. Sketch of One Half of Roadway – Rural Section (from center to left) Foreslope: recommended at 3:1 slope A flat bottom ditch is recommended, hard to build at less than eight feet. Backslope as ROW allows 3 ft. (example only) The challenge is often working in a confined R-O-W.
  • 7. From AASHTO Guidelines for Geometric Design of Very Low-Volume Local Roads (ADT < 400) Agricultural Access Classification: Minimum roadway width is 24 ft at 20 to 40 mph design speed, increases to 26 ft if design speed is 50 mph
  • 8. Great project, but few new gravel roads are built
  • 9. Good ditch construction and drainage
  • 10. Gravel Road Rehabilitation: Often the Best Improvement Possible
  • 11. Any tool to help break sod and clumped soil is helpful
  • 12. Sometimes this is reality in confined ROW
  • 13. No real cross section – You have to do better than this!
  • 14. Not many gravel surfaced roads are being built in the US. Many existing gravel roads need rehabilitation Some best practice examples:
  • 15. Complete rehabilitation of a county road in Day County, SD -2013 Season
  • 16. Recovery of aggregate from foreslope and reestablishing shoulder line Road originally constructed in 1970s
  • 17. Modern tools can make the job easier
  • 19. Soils in this area are weak – generally silty clays
  • 20. Done entirely with county equipment
  • 21.
  • 22. Mixing & processing subgrade soil
  • 23. Doing the best they can with what they have
  • 25. Picking rocks the easy way!
  • 30. First lift of new gravel – 2.5 inches
  • 31. Project done with same process two years earlier – road is so much easier to maintain
  • 32. Another Challenge – Reverting Asphalt Surfaces to Unpaved Surfaces:
  • 33. Recycle Process Virgin gravel course added on roadway prior to recycling.
  • 35. Reshape & compaction of the material
  • 36. Outstanding performance Performance documentation on 2-7-2013. This road had no blade maintenance since May, 2012. ADT is 75
  • 37. Maintenance Challenges After Construction or Rehabilitation:
  • 38. 10 inches average annual rainfall 65 inches average annual rainfall
  • 40. A crown gauge is helpful
  • 41. Electronic Slope Reading In the motorgrader cab: On-board electronics are coming to the market very quickly
  • 42. Slope Control systems on motorgraders are a great aid in construction and rehabilitation
  • 43. Poor surface drainage Electronics only work if the operator accepts it!
  • 45. Crown Example on 20 Ft Road Surface
  • 46. The Next Challenge – High Shoulders!
  • 47. Reasonably good cross section on low volume road with poor horizontal and vertical alignment
  • 48. Some thoughts on roads with severe horizontal and vertical alignment problems
  • 50. Just as critical is surface aggregate quality
  • 51. Most of the surface is tightly bound here
  • 52. Surface aggregate has good overall gradation and relatively small top size.
  • 53. Virtually no corrugation on day of observation
  • 54. Recent roadway reshape is very good
  • 55. Drainage run-out to carry water away from road with erosion control – good practice.
  • 56. Good culvert installation under driveway
  • 57. Vertical alignment makes maintenance very challenging – grade checked at 23.4% at one location!
  • 58. Managing Gravel Quality and Quantity
  • 59.
  • 60. Recent validation check of material quality in SD
  • 61. Gradation/PI Tests 61 List of Gravel Sources Deuel County A Deuel County B Beadle County Miner County Hughes County Mitchell Township Lincoln County Clay County Jerauld County Why these sites chosen? Previous data seems inaccurate Study contrast in local materials used on unpaved road
  • 62. Summary 62 Source Gradation PI Deuel County A Failed Failed (No PI) Deuel County B Failed Failed (No PI) Beadle County Failed Passed (5) Miner County Failed Passed (6) Hughes County Failed Passed (4) Mitchell Township Failed Failed (No PI) Lincoln County Passed Failed (no PI) Clay County Failed Passed (7) Jerauld County Failed Passed (4)
  • 63. Gravel Quality Issues • Gradation problems generally confined to small percentage retained on 1 in. sieve (SDDOT Gravel surfacing spec requires 100% passing 3/4 in. sieve. • Generally good on the split between coarse and fine aggregate on the #4 sieve. • SDDOT Standard Specification requires minimum plasticity index (PI) of 4 and maximum of 12 – Only five of nine samples had PI. – Maximum PI tested was 7.
  • 64. Part of the problem in not getting plasticity:
  • 65. Managing Layer Thickness: Coring a Gravel Road:
  • 66.
  • 67.
  • 68. Over two inches of thickness deviation
  • 69. Example of test pit in existing gravel road
  • 70. Calculate spread rates on gravel projects
  • 71. It requires 407 cubic yards (570 tons) to place one inch of gravel on a one mile 20 ft wide.
  • 72. A 25-ton load of gravel covers only 320 linear ft to place one inch of gravel on one mile 20 ft wide.
  • 73. Nice job of processing and placing gravel
  • 74.
  • 75. The skilled operator is the key to controlling gravel road shape and placing gravel.
  • 76. Note: this is an adequate layer for maintenance, but not adequate thickness to carry legal loads in all conditions!
  • 77. Deep Layer Needed to Carry Heavy Loads 14.5 inches of gravel needed to carry 25 to 50 trucks per day over weak subgrade! From SDDOT Rural Road Design, Maint, & Rehab Guide 77
  • 78. More on Gravel Quality Same operator Same road Same day Different gravel
  • 79. Updates From the SDDOT/SDLTAP Surface Gravel Study Project Brookings Site Constructed in 2011
  • 80. Reason for Project • More than 50% of local roads in SD are unpaved – managing them is a challenge! • Biggest complaints from public are: rough condition (generally from corrugation or “washboard” in surface) and too much loose aggregate on the surface makes it hard to control a vehicle. • How critical is gravel quality to this and how does it affect total cost of maintenance?
  • 81. • Primary focus is on effect of gravel quality on life-cycle cost of gravel road maintenance • Three types of gravel used in study: 1. Substandard but commonly used – meets no spec except top size control – one inch minus. 2. Barely meets SDDOT Gravel Surfacing Spec – percent passing #200 sieve is low and/or plasticity index (PI) at bottom of range at 4 3. Modified SDDOT Spec – higher minimums of 10% passing #200 sieve and PI at 7. Focus of Test Project
  • 83. One of the biggest challenges was finding gravel that meets the modified SDDOT Specification: “Shall have minimum plasticity index (PI) of seven”. (Even higher minimum was considered in project planning)
  • 84. One way to meet modified spec – blend different material from separate sources This was done on one section in Brookings Co and one section in Custer Co
  • 85. Is this the future? More blending or “manufacturing” to get high quality gravel – processing from a natural clay source here:
  • 86. Road mixing natural clay to get a high quality surface gravel
  • 88. Current Status of Project • SDLTAP has accumulated photo documentation on all sections over the past two years. • Measurement and documentation has been done on these distress types in 2012 & 2013: 1. Accumulation of loose aggregate (float) 2. Changes in top width from time of construction 3. Presence of corrugation (washboard) on surface 4. Change in roadway crown
  • 89. The float test (loose aggregate)
  • 90. Simply remove loose aggregate from a 10 inch cross section, weigh it and convert that to a one-mile section
  • 91. Change in top-width is measured on traveled way – hinge point to hinge point XX ft.
  • 92. Corrugation (washboard): Hard to quantify in extent, fairly easy to measure severity
  • 93. Brookings Section – Loose Aggregate 2012 (Tons per mile) Substandard Compacted Uncompacted Standard Spec Uncompacted Compacted Modified Spec 405 tons 71 tons
  • 94. Cooler, wetter season in 2013 – 2.94 inches of rain in previous 20 days – most of that in three days prior to the last test. Difference in 2012 & 2013 maintenance seasons:
  • 95. Brooking Section – Loose aggregate 2013 0 20 40 60 80 100 120 140 160 180 200 Tons per mile (October 2013) Tons per mile (October 2013) 186 tons 16 tons
  • 96. Loose aggregate comparison 2013 & 2012 0 50 100 150 200 250 300 350 400 450 Tons per mile (October 2013) Tons per mile (October 2012)
  • 97. 2014 Spring Measurement of Loose Aggregate 0 50 100 150 200 250 300 350 Substandard C Substandard UC Standard UC Standard C Modified C 6/20/2014 Measurements Substandard Compacted Uncompacted Standard Spec Uncompacted Compacted Modified Spec 44 tons 310 tons 118 tons
  • 98. Corrugation (Washboard) • No corrugation observed on any sections meeting at least minimum standard specification. • However, substandard section had the beginning of light corrugation only two days after blade maintenance after nearly three inches of rain.
  • 99. Change in Roadway Surface Width Constructed Width – 21.5 ft on all sections Constructed Width – Modified Section Current Width – Oct 2013 Constructed Width – Standard Spec Section Current Width – Oct 2013 Constructed Width – Substandard Section Current Width – Oct 2013 Current width ranges from 22 ft on modified section (top bar) to 25.25 ft on substandard section (bottom bar)
  • 100. Substandard section – aggregate has moved outward over 4 ft since construction
  • 101. Modified section has moved outward only six inches since construction
  • 102. View of Substandard section – 10-18-13
  • 103. View of Modified section – 10-18-13
  • 104. Does the modified section rut in wet weather? No, virtually no rutting observed.
  • 106. Concluding Points • Meeting basic SDDOT standard surface gravel specification reduces loose aggregate by 1/3 to 1/2. • Widest differential was in Brookings County near end of corn harvest in 2012 with 405 tons of loose aggregate on substandard section to only 71 tons on modified section. • No corrugation ever observed on standard or modified material.
  • 107. • Most interesting fact thus far: Brookings has done blade maintenance up to four times on substandard section to only once on modified! • A negative aspect: we are getting a lot of push-back from aggregate producers who would prefer to produce as they always have – no close control of % passing the #200 sieve and plasticity index. Concluding Points (Con’t)
  • 108. Feasibility of Dust Control or Stabilization
  • 109. $- $20,000.00 $40,000.00 $60,000.00 $80,000.00 $100,000.00 $120,000.00 $140,000.00 $160,000.00 0 200 400 600 800 1000 ADT AgencyCost($) HMA Blotter Gravel Linear (HMA) Linear (Blotter) Linear (Gravel) Gravel Blotter HMA Summary of gravel, AST and HMA surface life cycle costs related to ADT – SDDOT Surface Selection Criteria Study Gravel – cost effective to 150 ADT AST (Blotter) – cost effective to 650 ADT HMA Pavement – cost effective above 650 ADT 109
  • 110. Cass County, ND Cement Treated Gravel
  • 111. Excellent stability in the gravel layer May 15, 2014 – cold, late spring in a slough area
  • 112. Remarkable success with stabilized gravel in SD A Chloride Stabilized Road Since 1998! 112
  • 113. Portland Cement Railcar Offloading Facility 113
  • 114. Less than 200 tons of gravel replaced in 14 yrs! Carries up to 80 portland cement haulers per day in addition to regular traffic. 114
  • 115. Brief Coverage of Chloride Treatment Process • Must have good surface gravel in place: – Needs to meet surface specification (ND Class 13 or SD Gravel Surfacing Specification) – Prefer minimum four inches thickness on good base • Gravel must be prepared well: – Loosen the top one to two inches uniformly across the surface. – Gravel must be in a moist condition while preparing and just prior to treatment. • Apply chloride evenly and uniformly. • Don’t use rollers too soon! (Sometimes not at all)
  • 116. Bit-type cutting edges are excellent for preparing surface
  • 117. Excellent example – surface is loose and open in moist condition
  • 118. Don’t apply too much chloride in one pass – watch for absorption
  • 119. Second application being made after complete absorption of first application
  • 120. Case Study from Meade County, SD Experience with Alternatives to Paving Information from: Mr. Ken McGirr Meade County Highway Supt Sturgis, SD
  • 121. • Elk Vale Road – Located directly east and north of Rapid City – Serves a growing area just off of exit 61 on Interstate Highway 90 – Classification: Rural Major Collector – Became impossible to maintain as gravel surface 121
  • 122. Recent Traffic Count Breakdown • Northbound – 12/04/2012 299 total vehicles 22 trucks – 12/05/2012 319 total vehicles 28 trucks – 12/06/2012 317 total vehicles 22 trucks • Southbound – 12/04/2012 331 total vehicles 69 trucks – 12/05/2012 339 total vehicles 92 trucks – 12/06/2012 319 total vehicles 76 trucks • Total* – 12/04/2012 610 total vehicles 91 trucks – 12/05/2012 658 total vehicles 120 trucks – 12/06/2012 636 total vehicles 98 trucks *Meade County count tallied over 700 vehicles in earlier count with 25% trucks 122 Average 635 vehicles per day and average 103 trucks per day (16% of total volume)
  • 123. A difficult area for road management
  • 124. Originally constructed in May, 2011 Excellent performance after first year 124
  • 125. Close-up view of stabilized surface 125
  • 126. Stabilization was done with .75 gal of liquid MgCl2 per sq yd mixed into top three inches (75 mm) of good quality surface gravel layer 126
  • 127. No significant loose aggregate and no corrugation even on 7% grade. 127
  • 128. No blade maintenance was done between construction in summer of 2011 and surface retreatment in summer of 2012! 128
  • 129. Phone call from citizen – “If you had enough money to pave this road, why didn’t you save enough to put striping on it” 129
  • 130. End of season condition assessment 10-24-13
  • 131. Skid marks from recent incident
  • 133. A little about training • A great need in our industry –Management level –Field supervisors –Operators
  • 134. Management Training • Clear communication on expectations must be conveyed to field staff. • Does everyone have the same goals? • Is management too preoccupied with the primary roads? • Gravel roads become very low priority and consequently reach failed or near failed condition before work is done?
  • 135. Field Supervisor Training • May not understand the right geometry needed on a gravel road (different than pavement). • Consequently do not know how to convey to operators (in-house or out sourced) what is needed for good maintenance. • Supervisors and operators develop adversarial relationship – the team breaks down!
  • 136. Operator Training • Too often no training given on desired roadway shape (geometry) and bad habits are developed. • Little or no mentoring by skilled operators who could communicate what they know. • Great lack of training in our technical colleges or trades training centers for this field. • No recognition for doing a good job!
  • 137. SD Recent Training Efforts Administrative and Field Supervisor Training
  • 139. Results: • Positive Outcomes: – Excellent attendance and participation – Significant request for more training – Operators and supervisors understand each other’s positions much better • Challenges: – Lack of good training material – Agencies want training very condensed and fast – Very hard to find good trainers, especially for operator level – Hands-on field training is expensive
  • 140. A new education resource in the US: The Gravel Roads Academy Easy to find online by doing a simple search
  • 141. Get ready to face the challenges of maintaining gravel roads in the future! Good Luck and Thank You!