The purpose of this class is to provide you with an overall
foundation of knowledge pertaining to Cranes and Crane
Safety.
Upon completion of this course, students will be able to
identify types of cranes and their basic components,
recognize hazards associated with cranes and understand safe
operating practices based on guidelines established by OSHA.
3
• Describe maintenance, inspection and certification requirements of cranes
• Understand load capacities, limits and lifting principles
• Describe safe assembly/disassembly activities
• Understand hand signals
• Describe hazards and most common causes of crane accidents
• Recognize types of cranes, basic components as well as rigging equipment
• Summarize OSHA standards pertaining to cranes
• Understand the roles and responsibilities of lifting personnel
Objectives
4
Types of Cranes
• Mobile Telescopic
• Crawler Lattice
• Side Lift
• All Terrain
• Truck Mounted
• Articulating
• Barge/Floating/Ship
• Railroad
• Aerial/Helicopter
• Overhead Traveling
• Wall
• Gantry
• Semi-Gantry
• Cantilever
• Straddle/Mobile Gantry
• Tower/Derrick Hammer Head
• Stiff-leg Derrick
5
Most Common Types of
Cranes in Construction
6 6
Crawler Lattice
7 7
Wheel-Mounted Telescoping
8 8
Tower Crane
9
Construction - Cranes & Rigging
• 1926.1400-1442 - Cranes Subpart CC
• 1926.251 - Rigging equipment for material handling
Marine Terminals - Cargo Handling Gear and Equipment
• 1917.45 - Cranes and derricks (see also 1917.50)
• 1917.50 - Certification of marine terminal material handling devices
General Industry - 1910 Subpart N - Materials Handling and Storage
• 1910.179 - Overhead and gantry cranes
• 1910.180 - Crawler locomotive and truck cranes
• 1910.181 - Derricks
• 1910.183 - Helicopters
• 1910.184 - Slings
OSHA Crane Standards
10
Wind Speed Incorporated by DOE Reference?
DOE STANDARD, HOISTING AND RIGGING
(Formerly Hoisting and Rigging Manual)
DOE-STD-1090-99
9.5.1 Conduct of Operator
v. In the absence of crane manufacturer’s instructions regarding maximum wind speeds for
operation, operations undertaken at wind speeds in excess of 25 mph should be evaluated by a
qualified person to determine if the size, shape and weight of the load can be safely lifted.
15.5.2 Mobile Cranes/Boom Trucks
7. In the absence of crane manufacturer’s instructions regarding maximum wind speeds for
operation, operations undertaken at wind speeds in excess of 25 mph should be evaluated by a
qualified person to determine if the size, shape and weight of the load can be safely lifted.
4.1 General
22. Personnel platforms should not be used in winds greater than 15 mph (25 km/h), electric storms,
snow, ice, sleet, or other adverse weather conditions that could affect the safety of personnel.
10
11 11
Option Description Portable Valid
1 Certification by an accredited crane operator
testing organization
Y 5
2 Qualification by an audited employer program
Developed by an accredited crane operator
testing organization or Approved by an auditor
in accordance with CFR.
N 5
3 Qualification by the U.S. military N Infinity
4 Licensing by a government entity N 5 or less
Operator Qualification Certification 1427 & 1428
Should have taken effect November 10, 2014 but will now go into effect November 10, 2017.
12
Feb. 7, 2014
Contact: Office of Communications
Phone: 202-693-1999
OSHA issues proposed rule to extend compliance date for crane operator
certification requirements
WASHINGTON – The Occupational Safety and Health Administration today issued a proposed rule to extend the compliance date
for the crane operator certification requirement by three years to Nov. 10, 2017. The proposal would also extend to the same
date the existing phase-in requirement that employers ensure that their operators are qualified to operate the equipment.
OSHA issued a final standard on requirements for cranes and derricks in construction work on Aug. 9, 2010. The standard
requires crane operators on construction sites to meet one of four qualification/certification options by Nov. 10, 2014. After
OSHA issued the standard, a number of parties raised concerns about the qualification/certification requirements. After
conducting several public meetings, OSHA decided to extend the enforcement date so that the certification requirements do not
take effect during potential rulemaking or cause disruption to the construction industry.
Comments may submitted electronically at http://www.regulations.gov, the Federal e-Rulemaking Portal or by facsimile or mail.
See the Federal Register notice for submission details and additional information about this proposed rule. Comments must be
submitted by March 12, 2014.
OSHA held three stakeholder meetings on operator certification/qualification issues in April 2013 and posted detailed notes of
the meetings at http://www.osha.gov/cranes-derricks/stakeholders.html, a Web page devoted to the stakeholder meeting. A list
of frequently asked questions are also posted on OSHA's Cranes and Derricks in Construction Web page to provide additional
clarification and address some comments and concerns raised by stakeholders.
Under the Occupational Safety and Health Act of 1970, employers are responsible for providing safe and healthful workplaces
for their employees. OSHA's role is to ensure these conditions for America's working men and women by setting and enforcing
standards, and providing training, education and assistance. For more information, visit http://www.osha.gov.
12
13 13
Definitions
• Crane – Consists of a rotating structure for lifting and lowering
horizontally on rubber tires or crawler treads
• Hoist – Used to lift and lower load
• Boom – An inclined spar, strut, or other long member supporting the
hoisting tackle
• Boom stops – A device used to limit the angle of the boom at its highest
position
• Brake – To slow or stop motion by friction or power
• Block – Sheaves or grooved pulleys in a frame with hook, eye and strap
• Jib – Extension attached to the boom point to provide added boom length
for lifting specified loads
14 14
Crane
Parts
15
OSHA Competent Person vs. Qualified Person
• This is in response to your memorandum of January 28, on the above subject.
• 29 CFR 1926.32(f) states: "Competent person" means on who is capable of identifying existing and predictable
hazards in the surroundings or working conditions, which are unsanitary, hazardous, or dangerous to employees,
and who has authorization to take prompt corrective measures to eliminate them.
• 29 CFR 1926.32(l) states: "Qualified" means one who, by possession of a recognized degree, certificate, or profess-
ional standing, or who by extensive knowledge, training and experience, has successfully demonstrated his ability to
solve or resolve problems relating to the subject matter, the work, or the project.
• These definitions provide that a competent person must have authority to take prompt measures to eliminate
hazards at the work site and have the experience to be capable of identifying these hazards. This is the reason a
competent person is required under inspection requirements in 29 CFR 1926.650 and 29 CFR 1926.651.
• The definitions provide that a qualified person must have a recognized degree, certificate, etc., or extensive
experience and ability to solve the subject problems, at the worksite. This is the reason why 29 CFR 1926.651(f)
requires that supporting systems design shall be by a qualified person. There may be a requirement for more
technical or engineering knowledge here.
• Each excavation job as in any other case, must be evaluated as to the facts relating to the needs of a competent
person, and qualified person.
• The professional judgment of OSHA must come into play by using our construction regulations where they apply
• Please advise if we can be of further assistance.
15
16
Qualified Operator
Any person engaged in a construction activity who is operating a crane
covered by the new cranes and derricks rule, except:
• Sideboom cranes
• Derricks
• Equipment with a rated hoisting/lifting capacity of 2,000 pounds or less
Operators of listed equipment must meet the criteria for minimum expertise
described in the applicable section in subpart CC 1926.1427
* A Certified Operator is currently recommended and expected to be required on
November 10, 2017.
Who needs to be certified or qualified?
17
When is a qualified rigger required?
Employers must use qualified riggers during hoisting
activities for assembly and disassembly work
(1926.1404(r)(1)). Additionally, qualified riggers are required
whenever workers are within the fall zone and hooking,
unhooking, or guiding a load, or doing the initial connection
of a load to a component or structure (1926.1425(c)).
Qualified Operator
18
Qualified Signal Person
When is a signal person required?
A signal person is required when: The point of operation is
not in full view of the operator (1926.1419(a)), the
operator’s view is obstructed in the direction the equipment
is traveling, or either the operator or the person handling
the load determines that a signal person is needed because
of site-specific safety concerns.
19
Subpart CC – Cranes and Derricks in
Construction: Assembly/Disassembly
Employers must comply with all manufacturer prohibitions regarding assembly
and disassembly.
The OSHA standard generally allows employers to choose between the
manufacturer’s procedures or their own, any the most stringent must be
followed.
Employer procedures must be developed by a “qualified person” and must
satisfy a number of specified requirements, such as providing adequate
support and stability for all parts of the equipment, and positioning employees
involved to minimize exposure to any unintended movement or collapse.
20
Assembly/Disassembly Responsibilities
• The rule requires the work to be directed by an Assembly/Disassembly
(A/D) director. The A/D director must meet the criteria for both a
“competent person” and a “qualified person,” which are terms defined in
this rule, or must be a “competent person” assisted by a “qualified person.”
• The A/D director must understand the applicable procedures.
• The A/D director must review the procedures immediately prior to
beginning work unless he or she understands the procedures and has used
them before for that equipment type and configuration.
• The A/D director must ensure that each member of the crew understands
his or her tasks, the hazards of the tasks, and any hazardous positions or
locations to avoid.
21
• The A/D director must verify all capacities of any equipment used,
including rigging, lifting lugs, etc.
• The A/D director must also address hazards associated with the
operation, including 12 specified areas of concern:
Assembly/Disassembly Responsibilities (cont.)
• Site and ground conditions
• Blocking material
• Proper location of blocking
• Verifying assist crane loads
• Boom & jib pick points
• Center of gravity
• Stability upon pin removal
• Stability upon pin removal
• Snagging
• Struck by counterweights
• Boom hoist brake failure
• Loss of backward stability
• Wind speed and weather
22
A/D General Requirements
• A crew member who moves out of the operator’s view to a location where the
crew member could be injured by movement of the equipment (or load) MUST
inform the operator before going to that location. The operator must not move
the equipment until that crew member informs the operator that he or she
has relocated to a safe position.
• Employees must never be under the boom or jib when pins (or similar devices)
are being removed, unless it is required by site constraints and the A/D
director has implemented procedures that minimize the risk of unintended
movement and the duration and extent of exposure under the boom.
23
• Component weights must be readily available for all components to
be assembled.
• All rigging must be done by a “qualified rigger.”
• Pins may not be removed during disassembly when the pendants
are in tension.
• Booms supported only by cantilevering must not exceed
manufacturer limitations or RPE (Registered Professional Engineer)
limitations, as applicable.
• Component selection and equipment configuration that affects the
capacity or safe operation of the equipment must be in accordance
with manufacturer requirements and limits or RPE requirements and
limits, as applicable.
A/D General Requirements (cont.)
24
A/D Outriggers and Stabilizers
When outriggers or stabilizers are used or are necessary in light of the load to be
handled and the operating radius:
• Outriggers and stabilizers must be fully extended or, if permitted by manufacturer
procedures, deployed is specified in the load chart.
• Outriggers must be set to remove equipment weight from the wheels, except for
locomotive cranes.
• Outrigger floats, if used, must be attached to the outriggers; stabilizer floats, if
used, must be attached to the stabilizers.
• Each outrigger or stabilizer must be visible to the operator or to a signal person
during extension and setting.
• Outrigger and stabilizer blocking must be placed under the float/pad of the jack or,
if there is no jack, under the outer bearing surface of the outrigger or stabilizer
beam. Blocking must also be sufficient to sustain the loads and maintain stability
and must be properly placed.
25 25
• Contact with power lines
• Overturns
• Falls
• Mechanical failures
• Moving parts
• Improper load rating
• Excessive speeds
• No hand signals
• Inadequate inspection and maintenance
Crane Hazards
26 26
• Unguarded parts
• Unguarded swing radius
• Working too close to power lines
• Improper exhaust system
• Shattered windows
• No steps/guardrails walkways
• No boom angle indicator
• Not using outriggers
Crane Hazards (cont.)
27
OSHA-Identified Crane Hazards
OSHA's analysis identified the major causes of crane accidents to include:
• Boom or crane contact with energized power lines (nearly 45% of the cases)
• Under the hook lifting device
• Overturned cranes
• Dropped loads
• Boom collapse
• Crushing by the counter weight
• Outrigger use
• Falls
• Rigging failures
28 28
Who is at Risk?
• Operators
• Persons at Crane Site
29 29
Power Lines
The greatest risk for cranes is contacting power lines.
30 30
Stay clear from power lines
at least 10 feet under 50kv.
If the voltage of the power
lines is unknown, stay at
least 20 feet away or more
and immediately contact
your employer so that they
may contact the utility
provider to determine
voltage of the power lines.
Warning: Power lines can
carry 50kv, 250kv, 350kv,
500kv or more. The higher
the kv the greater the risk of
arcing and employee injury
and property damage.
Power Lines
31 31
Improper Load
Improper loads or speeds can result
in the tipping of the crane.
32 32
Improper Load
33 33
Improper Load
34 34
Guard Moving Parts
Unguarded
Chain Drive
Guard moving parts such as gears or belts.
35 35
Swing Radius
Stay out of the swing radius of the crane –
make sure there are barrier guards showing swing radius.
36 36
Operator Visibility
Broken
Window
Make sure broken
windows or other
obstructions do not
prevent the operator
from seeing.
37 37
Ladders
Ladder
Use ladders to get to the upper portion of the cab.
38 38
Guardrails
Runways and
steps need to have
guardrails,
handholds and slip
resistant surfaces.
39 39
Planning Before Start-Up
• Level the crane and ensure support surface is firm and able to support the load.
• Contact power line owners and determine precautions. Know the location and
voltage of overhead power lines.
• Know the basic crane capacities, limitations, and job site restrictions, such as
the location of power lines, unstable soil, or high winds.
• Make other personnel aware of hoisting activities.
• Barricade areas within swing radius.
• Ensure proper maintenance and inspections.
• Determine safe areas to store materials and place machinery.
40 40
Suspended Loads
Don’t stand under
suspended loads.
41 41
• Instability – unsecured load, load capacity exceeded, or
ground not level or too soft
• Lack of communication – the point of operation is a distance
from the crane operator or not in full view of the operator
• Lack of training – inadequate maintenance or inspection
Common Reasons Accidents Occur
42 42
Competent Person
The competent person must
inspect all machinery and
equipment prior to each use,
and during use, to make sure it
is in safe operating condition.
If it needs fixing, take it out of
service and don’t use it until it
is fixed.
Broken Track
43 43
Load Capacity - Speed - Warnings
• Make sure the crane
operator can see the:
• Rated Load Capacities
• Operating Speeds
• Special Hazard
Warning or Instruction
Load Rating Chart
44 44
Boom Angle Indicator
A boom angle indicator must be on the crane
45 45
Know the Weight of the Load
• Refer to shipping ticket or other documentation
• Ensure lift calculations are correct
• Ensure load is within load chart rating for boom length and
load radius of crane
• Crane is rated by the maximum weight it will lift at a
minimum radius and minimum boom length – the further
from its centerpoint, the less it will lift
46 46
Load-Limiting Factors
• Not level
• Wind
• Side loads
• On its wheels
• Lifting over the side
• Use of extensions, jibs and other attachments
• Limits of wire rope, slings and lifting devices
47 47
Mobile Cranes – Lifting Principles
• Center of gravity
• Leverage
• Stability
• Structural integrity
48 48
Load Example – 30 Ton Crane
• Will lift 60,000 pounds at 10 feet from the
center pin of the crane
• Based on level surface, no wind, and outriggers
fully extended
• At 25 feet from the center pin with an 80 foot
boom, the capacity is only 14,950 pounds
• At 74 feet from the center pin, the capacity is
only 4,800 pounds
49
Communication is Key
50
Hand Signals
51
Standard and Alternative Signals
Hand signal charts must be either posted on the equipment or
conspicuously posted in the vicinity of the hoisting operations.
When using non-standard hand signals, the signal person, operator, and
lift director (where there is one) must contact each other prior to the
operation and agree on the non-standard hand signals that will be used.
Hand signal charts must be either posted on the equipment or
conspicuously posted in the vicinity of the hoisting operation.
52
Maintenance, Inspection and
Crane Certification
53
A competent person must begin a visual inspection prior to
each shift the equipment will be used.
The inspection must consist of observation for apparent deficiencies.
Taking apart equipment components and booming down is not required
as part of this inspection unless the results of the visual inspection or trial
operation indicate that further investigation is necessary. Determinations
made in the inspection must be reassessed in light of observations made
during operation. At a minimum the inspection must include all of the
following:
Inspections - Each Shift
54
• Control mechanisms for maladjustments interfering with proper operation.
Control and drive mechanisms for apparent excessive wear of components
and contamination by lubricants, water or other foreign matter.
• Air, hydraulic, and other pressurized lines for deterioration or leakage,
particularly those which flex in normal operation.
• Hydraulic system for proper fluid level.
• Hooks and latches for deformation, cracks, excessive wear, or damage
such as from chemicals or heat.
• Wire rope reeving for compliance with the manufacturer's specifications.
• Wire rope, in accordance with §1926.1413(a).
• Electrical apparatus for malfunctioning, signs of apparent excessive
deterioration, dirt or moisture accumulation.
55
• Tires (when in use) for proper inflation and condition.
• Ground conditions around the equipment for proper support, including
ground settling under and around outriggers/stabilizers and supporting
foundations, ground water accumulation, or similar conditions.
• The equipment for level position within the tolerances specified by the
equipment manufacturer's recommendations, both before each shift and
after each move and setup.
• Operator cab windows for significant cracks, breaks, or other deficiencies
that would hamper the operator's view.
• Rails, rail stops, rail clamps and supporting surfaces when the equipment
has rail traveling.
• Safety devices and operational aids for proper operation.
56
Monthly Inspections
Each month the equipment is in service it must be inspected and
records must be kept for at least 3 months.
Annual/Comprehensive Inspections
At least every 12 months the equipment must be inspected by a
qualified person in accordance with 1926.1412(f).
57
Review
• Is anyone allowed to operate a crane?
• MUST a crew member inform the operator before going to that
location behind a crane or blind spot?
• Is the greatest risk for cranes coming into contacting power lines?
• When should crane be inspected?
58
Review
• Is anyone allowed to operate a crane?
No, only qualified operators.
• MUST a crew member inform the operator before going to that
location behind a crane or blind spot?
Yes, always.
• Is the greatest risk for cranes coming into contacting power lines?
Yes, and being struck by a crane or falling load are also great risks.
• When should crane be inspected?
At the beginning of every shift, monthly and annually.

More Related Content

What's hot (20)

Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Lifting Sling Safety
Lifting Sling SafetyLifting Sling Safety
Lifting Sling Safety
 
Crane Rigging Safety by HF & C
Crane Rigging Safety by HF & CCrane Rigging Safety by HF & C
Crane Rigging Safety by HF & C
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Crane safety
Crane safetyCrane safety
Crane safety
 
Operating practices
Operating practicesOperating practices
Operating practices
 
Lifting & procedure
Lifting & procedureLifting & procedure
Lifting & procedure
 
Industrial safetY of height works
Industrial safetY of height worksIndustrial safetY of height works
Industrial safetY of height works
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
 
Gi 2016 industrial rigging safety
Gi 2016 industrial rigging safetyGi 2016 industrial rigging safety
Gi 2016 industrial rigging safety
 
Cranes ppt
Cranes pptCranes ppt
Cranes ppt
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Lifting & Rigging by NEIS
Lifting & Rigging by NEISLifting & Rigging by NEIS
Lifting & Rigging by NEIS
 
Liftingproedure
LiftingproedureLiftingproedure
Liftingproedure
 
Work At Height
Work At HeightWork At Height
Work At Height
 
Working at heights
Working at heightsWorking at heights
Working at heights
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
 

Similar to Crane Safety Awareness by University of Texas Arlington

Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationComplianceSigns, LLC
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).pptRonald Aranha
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdfdinesh622857
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10vtsiri
 
Powered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptxPowered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptxFarizSafarulla1
 
Lifting plan
Lifting planLifting plan
Lifting plantnsv22
 
cranes_derricks9-30-10-2.ppt
cranes_derricks9-30-10-2.pptcranes_derricks9-30-10-2.ppt
cranes_derricks9-30-10-2.pptRickBellew1
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brownBill Brown
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2Sergio Augusto Esteves
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docYasserAbdulkareem1
 
Bletconductor certificatio nv14c blet2
Bletconductor certificatio nv14c blet2Bletconductor certificatio nv14c blet2
Bletconductor certificatio nv14c blet2John Passi
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxVikasMore37
 

Similar to Crane Safety Awareness by University of Texas Arlington (20)

2015 CRW - New Crane Rules = New Compliance Directives
 2015 CRW - New Crane Rules = New Compliance Directives 2015 CRW - New Crane Rules = New Compliance Directives
2015 CRW - New Crane Rules = New Compliance Directives
 
UTA_AST-Rigging.pptx
UTA_AST-Rigging.pptxUTA_AST-Rigging.pptx
UTA_AST-Rigging.pptx
 
2014 CRW - The Key to Hiring the Right Lift Director
2014 CRW - The Key to Hiring the Right Lift Director2014 CRW - The Key to Hiring the Right Lift Director
2014 CRW - The Key to Hiring the Right Lift Director
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane Operation
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).ppt
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
 
Powered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptxPowered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptx
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Scaffold Safety (2).ppt
Scaffold Safety (2).pptScaffold Safety (2).ppt
Scaffold Safety (2).ppt
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
cranes_derricks9-30-10-2.ppt
cranes_derricks9-30-10-2.pptcranes_derricks9-30-10-2.ppt
cranes_derricks9-30-10-2.ppt
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brown
 
Standards Regulations
Standards RegulationsStandards Regulations
Standards Regulations
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.doc
 
Bletconductor certificatio nv14c blet2
Bletconductor certificatio nv14c blet2Bletconductor certificatio nv14c blet2
Bletconductor certificatio nv14c blet2
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptx
 

More from Atlantic Training, LLC.

Stress and Worker Safety by Pennsylvania L&I
Stress and Worker Safety by Pennsylvania L&IStress and Worker Safety by Pennsylvania L&I
Stress and Worker Safety by Pennsylvania L&IAtlantic Training, LLC.
 
Workplace Harassment Prevention by UT EAP
Workplace Harassment Prevention by  UT EAPWorkplace Harassment Prevention by  UT EAP
Workplace Harassment Prevention by UT EAPAtlantic Training, LLC.
 
Preventing Falls, Slips and Trips by MGSU
Preventing Falls, Slips and Trips by MGSUPreventing Falls, Slips and Trips by MGSU
Preventing Falls, Slips and Trips by MGSUAtlantic Training, LLC.
 
Preventing Workplace Harassment by Pennsylvania L&I
Preventing Workplace Harassment by Pennsylvania L&IPreventing Workplace Harassment by Pennsylvania L&I
Preventing Workplace Harassment by Pennsylvania L&IAtlantic Training, LLC.
 
Warehouses In Emergencies by WFP Logistics
Warehouses In Emergencies by WFP LogisticsWarehouses In Emergencies by WFP Logistics
Warehouses In Emergencies by WFP LogisticsAtlantic Training, LLC.
 
Sexual Harassment in the Workplace Training by Shumaker
Sexual Harassment in the Workplace Training by ShumakerSexual Harassment in the Workplace Training by Shumaker
Sexual Harassment in the Workplace Training by ShumakerAtlantic Training, LLC.
 
New Employee Safety Orientation by Oregon State University
New Employee Safety Orientation by Oregon State UniversityNew Employee Safety Orientation by Oregon State University
New Employee Safety Orientation by Oregon State UniversityAtlantic Training, LLC.
 

More from Atlantic Training, LLC. (20)

Wellness for Supervisors by SWOSU
Wellness for Supervisors by SWOSUWellness for Supervisors by SWOSU
Wellness for Supervisors by SWOSU
 
Workplace Wellness by PHA
Workplace Wellness by PHAWorkplace Wellness by PHA
Workplace Wellness by PHA
 
Stress Management Training by SG
Stress Management Training by  SGStress Management Training by  SG
Stress Management Training by SG
 
Stress Management Training by SW
Stress Management Training by SWStress Management Training by SW
Stress Management Training by SW
 
Stress and Worker Safety by Pennsylvania L&I
Stress and Worker Safety by Pennsylvania L&IStress and Worker Safety by Pennsylvania L&I
Stress and Worker Safety by Pennsylvania L&I
 
Respectful Workplace by RDTC
Respectful Workplace by RDTCRespectful Workplace by RDTC
Respectful Workplace by RDTC
 
Workplace Harassment by CLGW
Workplace Harassment by CLGWWorkplace Harassment by CLGW
Workplace Harassment by CLGW
 
Workplace Harassment Prevention by UT EAP
Workplace Harassment Prevention by  UT EAPWorkplace Harassment Prevention by  UT EAP
Workplace Harassment Prevention by UT EAP
 
Welding Safety by Pennsylvania L&I
Welding Safety by Pennsylvania L&IWelding Safety by Pennsylvania L&I
Welding Safety by Pennsylvania L&I
 
Slips Trips & Falls Training by Signal
Slips Trips & Falls Training by SignalSlips Trips & Falls Training by Signal
Slips Trips & Falls Training by Signal
 
Preventing Falls, Slips and Trips by MGSU
Preventing Falls, Slips and Trips by MGSUPreventing Falls, Slips and Trips by MGSU
Preventing Falls, Slips and Trips by MGSU
 
Preventing Workplace Harassment by Pennsylvania L&I
Preventing Workplace Harassment by Pennsylvania L&IPreventing Workplace Harassment by Pennsylvania L&I
Preventing Workplace Harassment by Pennsylvania L&I
 
Warehouses In Emergencies by WFP Logistics
Warehouses In Emergencies by WFP LogisticsWarehouses In Emergencies by WFP Logistics
Warehouses In Emergencies by WFP Logistics
 
Prevention of Sexual Harassment by USMC
Prevention of Sexual Harassment by USMCPrevention of Sexual Harassment by USMC
Prevention of Sexual Harassment by USMC
 
Sexual Harassment by DEOMI
Sexual Harassment by DEOMISexual Harassment by DEOMI
Sexual Harassment by DEOMI
 
Sexual Harassment in the Workplace Training by Shumaker
Sexual Harassment in the Workplace Training by ShumakerSexual Harassment in the Workplace Training by Shumaker
Sexual Harassment in the Workplace Training by Shumaker
 
Sexual Harassment Training by NAP
Sexual Harassment Training by NAPSexual Harassment Training by NAP
Sexual Harassment Training by NAP
 
Scaffolds Training by Pennsylvania L&I
Scaffolds Training by Pennsylvania L&IScaffolds Training by Pennsylvania L&I
Scaffolds Training by Pennsylvania L&I
 
Supervision
SupervisionSupervision
Supervision
 
New Employee Safety Orientation by Oregon State University
New Employee Safety Orientation by Oregon State UniversityNew Employee Safety Orientation by Oregon State University
New Employee Safety Orientation by Oregon State University
 

Recently uploaded

The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 

Recently uploaded (20)

The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 

Crane Safety Awareness by University of Texas Arlington

  • 2. 2 The purpose of this class is to provide you with an overall foundation of knowledge pertaining to Cranes and Crane Safety. Upon completion of this course, students will be able to identify types of cranes and their basic components, recognize hazards associated with cranes and understand safe operating practices based on guidelines established by OSHA.
  • 3. 3 • Describe maintenance, inspection and certification requirements of cranes • Understand load capacities, limits and lifting principles • Describe safe assembly/disassembly activities • Understand hand signals • Describe hazards and most common causes of crane accidents • Recognize types of cranes, basic components as well as rigging equipment • Summarize OSHA standards pertaining to cranes • Understand the roles and responsibilities of lifting personnel Objectives
  • 4. 4 Types of Cranes • Mobile Telescopic • Crawler Lattice • Side Lift • All Terrain • Truck Mounted • Articulating • Barge/Floating/Ship • Railroad • Aerial/Helicopter • Overhead Traveling • Wall • Gantry • Semi-Gantry • Cantilever • Straddle/Mobile Gantry • Tower/Derrick Hammer Head • Stiff-leg Derrick
  • 5. 5 Most Common Types of Cranes in Construction
  • 9. 9 Construction - Cranes & Rigging • 1926.1400-1442 - Cranes Subpart CC • 1926.251 - Rigging equipment for material handling Marine Terminals - Cargo Handling Gear and Equipment • 1917.45 - Cranes and derricks (see also 1917.50) • 1917.50 - Certification of marine terminal material handling devices General Industry - 1910 Subpart N - Materials Handling and Storage • 1910.179 - Overhead and gantry cranes • 1910.180 - Crawler locomotive and truck cranes • 1910.181 - Derricks • 1910.183 - Helicopters • 1910.184 - Slings OSHA Crane Standards
  • 10. 10 Wind Speed Incorporated by DOE Reference? DOE STANDARD, HOISTING AND RIGGING (Formerly Hoisting and Rigging Manual) DOE-STD-1090-99 9.5.1 Conduct of Operator v. In the absence of crane manufacturer’s instructions regarding maximum wind speeds for operation, operations undertaken at wind speeds in excess of 25 mph should be evaluated by a qualified person to determine if the size, shape and weight of the load can be safely lifted. 15.5.2 Mobile Cranes/Boom Trucks 7. In the absence of crane manufacturer’s instructions regarding maximum wind speeds for operation, operations undertaken at wind speeds in excess of 25 mph should be evaluated by a qualified person to determine if the size, shape and weight of the load can be safely lifted. 4.1 General 22. Personnel platforms should not be used in winds greater than 15 mph (25 km/h), electric storms, snow, ice, sleet, or other adverse weather conditions that could affect the safety of personnel. 10
  • 11. 11 11 Option Description Portable Valid 1 Certification by an accredited crane operator testing organization Y 5 2 Qualification by an audited employer program Developed by an accredited crane operator testing organization or Approved by an auditor in accordance with CFR. N 5 3 Qualification by the U.S. military N Infinity 4 Licensing by a government entity N 5 or less Operator Qualification Certification 1427 & 1428 Should have taken effect November 10, 2014 but will now go into effect November 10, 2017.
  • 12. 12 Feb. 7, 2014 Contact: Office of Communications Phone: 202-693-1999 OSHA issues proposed rule to extend compliance date for crane operator certification requirements WASHINGTON – The Occupational Safety and Health Administration today issued a proposed rule to extend the compliance date for the crane operator certification requirement by three years to Nov. 10, 2017. The proposal would also extend to the same date the existing phase-in requirement that employers ensure that their operators are qualified to operate the equipment. OSHA issued a final standard on requirements for cranes and derricks in construction work on Aug. 9, 2010. The standard requires crane operators on construction sites to meet one of four qualification/certification options by Nov. 10, 2014. After OSHA issued the standard, a number of parties raised concerns about the qualification/certification requirements. After conducting several public meetings, OSHA decided to extend the enforcement date so that the certification requirements do not take effect during potential rulemaking or cause disruption to the construction industry. Comments may submitted electronically at http://www.regulations.gov, the Federal e-Rulemaking Portal or by facsimile or mail. See the Federal Register notice for submission details and additional information about this proposed rule. Comments must be submitted by March 12, 2014. OSHA held three stakeholder meetings on operator certification/qualification issues in April 2013 and posted detailed notes of the meetings at http://www.osha.gov/cranes-derricks/stakeholders.html, a Web page devoted to the stakeholder meeting. A list of frequently asked questions are also posted on OSHA's Cranes and Derricks in Construction Web page to provide additional clarification and address some comments and concerns raised by stakeholders. Under the Occupational Safety and Health Act of 1970, employers are responsible for providing safe and healthful workplaces for their employees. OSHA's role is to ensure these conditions for America's working men and women by setting and enforcing standards, and providing training, education and assistance. For more information, visit http://www.osha.gov. 12
  • 13. 13 13 Definitions • Crane – Consists of a rotating structure for lifting and lowering horizontally on rubber tires or crawler treads • Hoist – Used to lift and lower load • Boom – An inclined spar, strut, or other long member supporting the hoisting tackle • Boom stops – A device used to limit the angle of the boom at its highest position • Brake – To slow or stop motion by friction or power • Block – Sheaves or grooved pulleys in a frame with hook, eye and strap • Jib – Extension attached to the boom point to provide added boom length for lifting specified loads
  • 15. 15 OSHA Competent Person vs. Qualified Person • This is in response to your memorandum of January 28, on the above subject. • 29 CFR 1926.32(f) states: "Competent person" means on who is capable of identifying existing and predictable hazards in the surroundings or working conditions, which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them. • 29 CFR 1926.32(l) states: "Qualified" means one who, by possession of a recognized degree, certificate, or profess- ional standing, or who by extensive knowledge, training and experience, has successfully demonstrated his ability to solve or resolve problems relating to the subject matter, the work, or the project. • These definitions provide that a competent person must have authority to take prompt measures to eliminate hazards at the work site and have the experience to be capable of identifying these hazards. This is the reason a competent person is required under inspection requirements in 29 CFR 1926.650 and 29 CFR 1926.651. • The definitions provide that a qualified person must have a recognized degree, certificate, etc., or extensive experience and ability to solve the subject problems, at the worksite. This is the reason why 29 CFR 1926.651(f) requires that supporting systems design shall be by a qualified person. There may be a requirement for more technical or engineering knowledge here. • Each excavation job as in any other case, must be evaluated as to the facts relating to the needs of a competent person, and qualified person. • The professional judgment of OSHA must come into play by using our construction regulations where they apply • Please advise if we can be of further assistance. 15
  • 16. 16 Qualified Operator Any person engaged in a construction activity who is operating a crane covered by the new cranes and derricks rule, except: • Sideboom cranes • Derricks • Equipment with a rated hoisting/lifting capacity of 2,000 pounds or less Operators of listed equipment must meet the criteria for minimum expertise described in the applicable section in subpart CC 1926.1427 * A Certified Operator is currently recommended and expected to be required on November 10, 2017. Who needs to be certified or qualified?
  • 17. 17 When is a qualified rigger required? Employers must use qualified riggers during hoisting activities for assembly and disassembly work (1926.1404(r)(1)). Additionally, qualified riggers are required whenever workers are within the fall zone and hooking, unhooking, or guiding a load, or doing the initial connection of a load to a component or structure (1926.1425(c)). Qualified Operator
  • 18. 18 Qualified Signal Person When is a signal person required? A signal person is required when: The point of operation is not in full view of the operator (1926.1419(a)), the operator’s view is obstructed in the direction the equipment is traveling, or either the operator or the person handling the load determines that a signal person is needed because of site-specific safety concerns.
  • 19. 19 Subpart CC – Cranes and Derricks in Construction: Assembly/Disassembly Employers must comply with all manufacturer prohibitions regarding assembly and disassembly. The OSHA standard generally allows employers to choose between the manufacturer’s procedures or their own, any the most stringent must be followed. Employer procedures must be developed by a “qualified person” and must satisfy a number of specified requirements, such as providing adequate support and stability for all parts of the equipment, and positioning employees involved to minimize exposure to any unintended movement or collapse.
  • 20. 20 Assembly/Disassembly Responsibilities • The rule requires the work to be directed by an Assembly/Disassembly (A/D) director. The A/D director must meet the criteria for both a “competent person” and a “qualified person,” which are terms defined in this rule, or must be a “competent person” assisted by a “qualified person.” • The A/D director must understand the applicable procedures. • The A/D director must review the procedures immediately prior to beginning work unless he or she understands the procedures and has used them before for that equipment type and configuration. • The A/D director must ensure that each member of the crew understands his or her tasks, the hazards of the tasks, and any hazardous positions or locations to avoid.
  • 21. 21 • The A/D director must verify all capacities of any equipment used, including rigging, lifting lugs, etc. • The A/D director must also address hazards associated with the operation, including 12 specified areas of concern: Assembly/Disassembly Responsibilities (cont.) • Site and ground conditions • Blocking material • Proper location of blocking • Verifying assist crane loads • Boom & jib pick points • Center of gravity • Stability upon pin removal • Stability upon pin removal • Snagging • Struck by counterweights • Boom hoist brake failure • Loss of backward stability • Wind speed and weather
  • 22. 22 A/D General Requirements • A crew member who moves out of the operator’s view to a location where the crew member could be injured by movement of the equipment (or load) MUST inform the operator before going to that location. The operator must not move the equipment until that crew member informs the operator that he or she has relocated to a safe position. • Employees must never be under the boom or jib when pins (or similar devices) are being removed, unless it is required by site constraints and the A/D director has implemented procedures that minimize the risk of unintended movement and the duration and extent of exposure under the boom.
  • 23. 23 • Component weights must be readily available for all components to be assembled. • All rigging must be done by a “qualified rigger.” • Pins may not be removed during disassembly when the pendants are in tension. • Booms supported only by cantilevering must not exceed manufacturer limitations or RPE (Registered Professional Engineer) limitations, as applicable. • Component selection and equipment configuration that affects the capacity or safe operation of the equipment must be in accordance with manufacturer requirements and limits or RPE requirements and limits, as applicable. A/D General Requirements (cont.)
  • 24. 24 A/D Outriggers and Stabilizers When outriggers or stabilizers are used or are necessary in light of the load to be handled and the operating radius: • Outriggers and stabilizers must be fully extended or, if permitted by manufacturer procedures, deployed is specified in the load chart. • Outriggers must be set to remove equipment weight from the wheels, except for locomotive cranes. • Outrigger floats, if used, must be attached to the outriggers; stabilizer floats, if used, must be attached to the stabilizers. • Each outrigger or stabilizer must be visible to the operator or to a signal person during extension and setting. • Outrigger and stabilizer blocking must be placed under the float/pad of the jack or, if there is no jack, under the outer bearing surface of the outrigger or stabilizer beam. Blocking must also be sufficient to sustain the loads and maintain stability and must be properly placed.
  • 25. 25 25 • Contact with power lines • Overturns • Falls • Mechanical failures • Moving parts • Improper load rating • Excessive speeds • No hand signals • Inadequate inspection and maintenance Crane Hazards
  • 26. 26 26 • Unguarded parts • Unguarded swing radius • Working too close to power lines • Improper exhaust system • Shattered windows • No steps/guardrails walkways • No boom angle indicator • Not using outriggers Crane Hazards (cont.)
  • 27. 27 OSHA-Identified Crane Hazards OSHA's analysis identified the major causes of crane accidents to include: • Boom or crane contact with energized power lines (nearly 45% of the cases) • Under the hook lifting device • Overturned cranes • Dropped loads • Boom collapse • Crushing by the counter weight • Outrigger use • Falls • Rigging failures
  • 28. 28 28 Who is at Risk? • Operators • Persons at Crane Site
  • 29. 29 29 Power Lines The greatest risk for cranes is contacting power lines.
  • 30. 30 30 Stay clear from power lines at least 10 feet under 50kv. If the voltage of the power lines is unknown, stay at least 20 feet away or more and immediately contact your employer so that they may contact the utility provider to determine voltage of the power lines. Warning: Power lines can carry 50kv, 250kv, 350kv, 500kv or more. The higher the kv the greater the risk of arcing and employee injury and property damage. Power Lines
  • 31. 31 31 Improper Load Improper loads or speeds can result in the tipping of the crane.
  • 34. 34 34 Guard Moving Parts Unguarded Chain Drive Guard moving parts such as gears or belts.
  • 35. 35 35 Swing Radius Stay out of the swing radius of the crane – make sure there are barrier guards showing swing radius.
  • 36. 36 36 Operator Visibility Broken Window Make sure broken windows or other obstructions do not prevent the operator from seeing.
  • 37. 37 37 Ladders Ladder Use ladders to get to the upper portion of the cab.
  • 38. 38 38 Guardrails Runways and steps need to have guardrails, handholds and slip resistant surfaces.
  • 39. 39 39 Planning Before Start-Up • Level the crane and ensure support surface is firm and able to support the load. • Contact power line owners and determine precautions. Know the location and voltage of overhead power lines. • Know the basic crane capacities, limitations, and job site restrictions, such as the location of power lines, unstable soil, or high winds. • Make other personnel aware of hoisting activities. • Barricade areas within swing radius. • Ensure proper maintenance and inspections. • Determine safe areas to store materials and place machinery.
  • 40. 40 40 Suspended Loads Don’t stand under suspended loads.
  • 41. 41 41 • Instability – unsecured load, load capacity exceeded, or ground not level or too soft • Lack of communication – the point of operation is a distance from the crane operator or not in full view of the operator • Lack of training – inadequate maintenance or inspection Common Reasons Accidents Occur
  • 42. 42 42 Competent Person The competent person must inspect all machinery and equipment prior to each use, and during use, to make sure it is in safe operating condition. If it needs fixing, take it out of service and don’t use it until it is fixed. Broken Track
  • 43. 43 43 Load Capacity - Speed - Warnings • Make sure the crane operator can see the: • Rated Load Capacities • Operating Speeds • Special Hazard Warning or Instruction Load Rating Chart
  • 44. 44 44 Boom Angle Indicator A boom angle indicator must be on the crane
  • 45. 45 45 Know the Weight of the Load • Refer to shipping ticket or other documentation • Ensure lift calculations are correct • Ensure load is within load chart rating for boom length and load radius of crane • Crane is rated by the maximum weight it will lift at a minimum radius and minimum boom length – the further from its centerpoint, the less it will lift
  • 46. 46 46 Load-Limiting Factors • Not level • Wind • Side loads • On its wheels • Lifting over the side • Use of extensions, jibs and other attachments • Limits of wire rope, slings and lifting devices
  • 47. 47 47 Mobile Cranes – Lifting Principles • Center of gravity • Leverage • Stability • Structural integrity
  • 48. 48 48 Load Example – 30 Ton Crane • Will lift 60,000 pounds at 10 feet from the center pin of the crane • Based on level surface, no wind, and outriggers fully extended • At 25 feet from the center pin with an 80 foot boom, the capacity is only 14,950 pounds • At 74 feet from the center pin, the capacity is only 4,800 pounds
  • 51. 51 Standard and Alternative Signals Hand signal charts must be either posted on the equipment or conspicuously posted in the vicinity of the hoisting operations. When using non-standard hand signals, the signal person, operator, and lift director (where there is one) must contact each other prior to the operation and agree on the non-standard hand signals that will be used. Hand signal charts must be either posted on the equipment or conspicuously posted in the vicinity of the hoisting operation.
  • 53. 53 A competent person must begin a visual inspection prior to each shift the equipment will be used. The inspection must consist of observation for apparent deficiencies. Taking apart equipment components and booming down is not required as part of this inspection unless the results of the visual inspection or trial operation indicate that further investigation is necessary. Determinations made in the inspection must be reassessed in light of observations made during operation. At a minimum the inspection must include all of the following: Inspections - Each Shift
  • 54. 54 • Control mechanisms for maladjustments interfering with proper operation. Control and drive mechanisms for apparent excessive wear of components and contamination by lubricants, water or other foreign matter. • Air, hydraulic, and other pressurized lines for deterioration or leakage, particularly those which flex in normal operation. • Hydraulic system for proper fluid level. • Hooks and latches for deformation, cracks, excessive wear, or damage such as from chemicals or heat. • Wire rope reeving for compliance with the manufacturer's specifications. • Wire rope, in accordance with §1926.1413(a). • Electrical apparatus for malfunctioning, signs of apparent excessive deterioration, dirt or moisture accumulation.
  • 55. 55 • Tires (when in use) for proper inflation and condition. • Ground conditions around the equipment for proper support, including ground settling under and around outriggers/stabilizers and supporting foundations, ground water accumulation, or similar conditions. • The equipment for level position within the tolerances specified by the equipment manufacturer's recommendations, both before each shift and after each move and setup. • Operator cab windows for significant cracks, breaks, or other deficiencies that would hamper the operator's view. • Rails, rail stops, rail clamps and supporting surfaces when the equipment has rail traveling. • Safety devices and operational aids for proper operation.
  • 56. 56 Monthly Inspections Each month the equipment is in service it must be inspected and records must be kept for at least 3 months. Annual/Comprehensive Inspections At least every 12 months the equipment must be inspected by a qualified person in accordance with 1926.1412(f).
  • 57. 57 Review • Is anyone allowed to operate a crane? • MUST a crew member inform the operator before going to that location behind a crane or blind spot? • Is the greatest risk for cranes coming into contacting power lines? • When should crane be inspected?
  • 58. 58 Review • Is anyone allowed to operate a crane? No, only qualified operators. • MUST a crew member inform the operator before going to that location behind a crane or blind spot? Yes, always. • Is the greatest risk for cranes coming into contacting power lines? Yes, and being struck by a crane or falling load are also great risks. • When should crane be inspected? At the beginning of every shift, monthly and annually.