1. Construction	Area	
i) Construction	Area	Ground	Floor		 =	305.5m2
	
ii) Construction	Area	1st
	Floor		 	 =	305.5m2
	
iii) Construction	Area	2nd
	Floor		 	 =	305.5m2
	
iv) Construction	Roof	Area			 	 =	362.29m2
	
Total	Construction	Area		 	 =	1278.80m2	
	
2. Structural	System	
i) Beams	 	 =	Precast	Concrete	Beams	
ii) Columns	 =	Precast	Concrete	Columns	
iii) Floor	Slab	 =	Precast	Hollow	Core	Slab	
iv) Roof	Truss	 =	Prefabricated	Steel	Roof	Truss		
	
3. Wall	System		
i) External	Wall	 	 =	Precast	Concrete	Panel	Wall	
ii) Internal	Wall		 	 =	Dry	Wall	System		
	
4. Other	Simplified	Construction	Solutions	
i) Beams	 	 =	100	%	complies	with	MS	1064	Part	10:2001	
Columns		 =	100	%	complies	with	MS	1064	Part	10:2001	
Walls	 	 =	100	%	complies	with	MS	1064	Part	10:2001	
Slabs	 	 =	100	%	complies	with	MS	1064	Part	10:2001	
Doors	 	 =	87.5	%	complies	with	MS	1064	Part	4:2001	
Windows	 =	0	%	complies	with	MS	1064	Part	5:2001	
ii) Repetition	of	floor	to	floor	height		 	 =	100%		
Vertical	repetition	of	structural	floor	layout		 =	100%	
Horizontal	repetition	of	structural	floor	layout		 =	100%
Total	of	Part	3		 26	
IBS	Content	Score	Of	Project	(Part	1	+	Part	2	+	Part	3)	 96	
	
	
	
ELEMENTS	 AREA	(m2
)	OR	LENGTH	
(m)	
IBS	
FACTOR	
COVERAGE		 IBS	SCORE		
Part	1:	Structural	
Elements		
	
	 	 	
Precast	Beams	+	Precast	
Columns	+	Precast	Floor	
Slab	(2	units	+	Corridor)		
305.5m2
	 1.0	 (916.5/1278.8)	
=	0.72	
0.72	x	1.0	x	50	
=	36	
Prefabrication	Steel	Roof	
Truss			
362.29	m2
	 1.0	 (362.29/1278.8)	
=	0.28	
0.28	x	1.0	x	50	
=	14	
Total	of	Part	1	(3	floors	
+	roof)		
1278.8	m2	
	 1.0	 50	
Part	2:	Wall	System	 	 	 	 	
External	Wall:	
Precast	Concrete	Panel		
71.44m	 1.0	 (71.44/97.19)	
=	0.74	
0.74	x	1.0	x	20	
=	14.8	
Internal	Wall:		
Dry	Wall	System		
25.75m	 1.0	 (25.75/97.19)	
=	0.26	
0.26	x	1.0	x	20	
=	5.2		
Total	of	Part	2	 97.19m	 	 1.0	 20	
Part	3:	Other	Simplified	
Construction	Solutions		
	 	 	 	
100	%	beams	sizes	
follow	MS	1064	Part	
10:2001	
	 	 100%	 4	
100	%	columns	sizes	
follow	MS	1064	Part	
10:2001	
	 	 100%	 4	
100	%	wall	thickness	
sizes	follow	MS	1064	
Part	10:2001	
	 	 100%	 4	
100	%	slab	thickness	
follow	MS	1064	Part	
10:2001	
	 	 100%	 4	
87.5	%	door	sizes	follow	
MS	1064	Part	4:2001	
	 	 87.5%	 4	
0	%	window	sizes	follow	
MS	1064	Part	5:2001	
	 	 0%	 0	
100%	Repetition	of	floor	
to	floor	height	
	 	 100%	 2	
100%	Vertical	repetition	
of	structural	floor	layout	
	 	 100%	 2	
100%	Horizontal	
repetition	of	structural	
floor	layout	
	 	 100%	 2
Precast	Foundation		
TYPE		 FOOTING(mm)	 COLUMN	STUMP	(mm)	 QUANTITY		
LENGTH		 WIDTH		 HEIGHT		 LENGTH		 WIDTH		 HEIGHT		 	
20	F1		 500	 500	 300		 300	 300	 800	
	
Precast	Beams	
TYPE		 LENGTH	(mm)		 HEIGHT	(mm)		 THICKNESS	(mm)		 QUANTITY		
B1	 4350	 	
	
	
	
400	
	
	
	
	
	
300	
12	
B2	 7100	 18	
B3	 4700	 24	
B4	 3300	 18	
B5	 6075	 9	
B6	 11500	 6	
B7	 1750	 12	
B8	 2800	 12	
D9	 5000	 12	
	
Precast	Columns		
TYPE		 POLE	(mm)	 CORBEL	(mm)		 QUANTITY	
LENGTH		 WIDTH		 HEIGHT		 LENGTH		 WIDTH		 HEIGHT		 QUANTITY	
C1	 300	 300	 3800	 350	 200	 300	 4	 24	
C2	 300	 300	 3800	 350	 200	 300	 2	 30	
C3		 300	 300	 3800	 350	 200	 300	 3	 6	
	
Precast	Walls	
TYPE		 LENGTH	(mm)		 HEIGHT	(mm)		 THICKNESS	(mm)		 QUANTITY		
W1		 3750	 	
	
	
3300	
	
	
	
150	
	
	
6	
W2	 4400	 6	
W3	 3300	 6	
W4	 2000	 12	
W5	 3000	 6	
W6	 1500	 12	
W7	 6075	 3	
	
Precast	Walls	With	Doors	
TYPE		 LENGTH	(mm)		 HEIGHT	(mm)	 THICKNESS	(mm)		 QUANTITY		
WD1	 3750	 	
	
	
3300	
	
	
	
150	
6	
WD2	 3800	 6	
WD3	 2800	 6	
WD4	 6800	 12	
WD5	 1500	 12	
WD6	 6075	 1	
WD7		 4400	 6
Precast	Walls	With	Windows	
TYPE	 LENGTH	(mm)	 HEIGHT	(mm)	 THICKNESS	(mm)		 QUANTITY		
WW1	 3750	 	
3300	
	
150	
12	
WW2	 6800	 6	
WW3	 3300	 6	
	
Precast	Staircase		
TYPE	 RISER	(mm)	 THREAT	(mm)	 TOTAL	
HEIGHT		
TOTAL	
WIDTH		LENGTH		 WIDTH		 QUANTITY		 LENGTH		 WIDTH		 QUANTITY		
ST	1		 1600	 200	 19	 1600	 250	 19	 3800	 3350	
	
Precast	Concrete	Hollow	Walls	
TYPE		 LENGTH	(mm)	 WIDTH	(mm)	 THICKNESS	(mm)	 QUANTITY		
S1	 4600	 	
1800	
	
	
150	
14	
S2	 3500	 12	
S3	 6500	 3	
S4		 1800	 10	
	
Dry	Wall	Toilet	Pod	
TYPE		 LENGTH	(mm)	 WIDTH	(mm)	 HEIGHT	(mm)		 THICKNESS	(mm)	 QUANTITY		
TP1	 2700	 1300	 3300	 120	 12	
	
Prefab	Purlin		
TYPE		 LENGTH	(mm)		 WIDTH	(mm)		 HEIGHT	(mm)		 QUANTITY		
P1		 23000	 150	 150	 15	
	
Prefab	Truss	
TYPE		 LENGTH	(mm)		 WIDTH	(mm)		 HEIGHT	(mm)	 QUANTITY		
T1	 21200	 150	 1250	 15	
	
Precast	Balcony	
TYPE		 LENGTH	(mm)		 WIDTH	(mm)		 THICKNESS	(mm)		 QUANTITY		
BC1	 4850	 2000	 150	 6	
	
Precast	Planter		
TYPE		 LENGTH	(mm)		 WIDTH	(mm)		 HEIGHT	(mm)	 QUANTITY		
PT1		 4850	 1000	 600	 6

More Related Content

What's hot

Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows마 이환
 
Timber - A Construction Material
Timber - A Construction MaterialTimber - A Construction Material
Timber - A Construction MaterialAadîl Khåñ
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Confined Masonry Building
Confined Masonry BuildingConfined Masonry Building
Confined Masonry BuildingManthan Kevadia
 
Quantity notes pdf
Quantity notes pdfQuantity notes pdf
Quantity notes pdfSaqib Imran
 
Mat foundation
Mat foundationMat foundation
Mat foundationJNTUK
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQashleyyeap
 
Earth retaining structures
Earth retaining structuresEarth retaining structures
Earth retaining structuresJNTUK
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)ahsanrabbani
 
Design of staircase_practical_example
Design of staircase_practical_exampleDesign of staircase_practical_example
Design of staircase_practical_examplePralhad Kore
 
Chapter 8 floorings
Chapter 8 flooringsChapter 8 floorings
Chapter 8 flooringsKHUSHBU SHAH
 
Construction technology ii report
Construction technology ii   reportConstruction technology ii   report
Construction technology ii report마 이환
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 

What's hot (20)

Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows
 
Stairs
StairsStairs
Stairs
 
Slab
SlabSlab
Slab
 
Timber - A Construction Material
Timber - A Construction MaterialTimber - A Construction Material
Timber - A Construction Material
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Confined Masonry Building
Confined Masonry BuildingConfined Masonry Building
Confined Masonry Building
 
7. building components
7. building components7. building components
7. building components
 
Quantity notes pdf
Quantity notes pdfQuantity notes pdf
Quantity notes pdf
 
Steel
SteelSteel
Steel
 
Steel buildings
Steel buildings  Steel buildings
Steel buildings
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQ
 
Earth retaining structures
Earth retaining structuresEarth retaining structures
Earth retaining structures
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
Bar bending schedule
Bar bending scheduleBar bending schedule
Bar bending schedule
 
Design of staircase_practical_example
Design of staircase_practical_exampleDesign of staircase_practical_example
Design of staircase_practical_example
 
Brick Masonry
Brick MasonryBrick Masonry
Brick Masonry
 
Chapter 8 floorings
Chapter 8 flooringsChapter 8 floorings
Chapter 8 floorings
 
Construction technology ii report
Construction technology ii   reportConstruction technology ii   report
Construction technology ii report
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 

Similar to IBS Score

IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartmentJy Chong
 
Building Technology I
Building Technology IBuilding Technology I
Building Technology IOng Shi Hui
 
Killeshin building it carlow
Killeshin building it carlowKilleshin building it carlow
Killeshin building it carlowTej Raj Upreti
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project reportPraba Haran
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure CentreEdel Fox
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Blockjeyanthi4
 
SL020 & SL022 - sections
SL020 & SL022 - sectionsSL020 & SL022 - sections
SL020 & SL022 - sectionssamson oakley
 
Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...
Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...
Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...Nystrom Building Products
 
Lewis Flooring Presentation Short Version
Lewis Flooring Presentation Short VersionLewis Flooring Presentation Short Version
Lewis Flooring Presentation Short Versionphilwdm
 
Lewis Flooring Presentation Short Version
Lewis Flooring Presentation Short VersionLewis Flooring Presentation Short Version
Lewis Flooring Presentation Short Versionphilwdm
 
NJI Portfolio Short
NJI Portfolio ShortNJI Portfolio Short
NJI Portfolio ShortNick Ivill
 

Similar to IBS Score (18)

IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 
Building Technology I
Building Technology IBuilding Technology I
Building Technology I
 
Killeshin building it carlow
Killeshin building it carlowKilleshin building it carlow
Killeshin building it carlow
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project report
 
5th batch.pptx
5th batch.pptx5th batch.pptx
5th batch.pptx
 
The specs of container house
The specs of container houseThe specs of container house
The specs of container house
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
Partitions
PartitionsPartitions
Partitions
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Block
 
Event domes
Event domesEvent domes
Event domes
 
SL020 & SL022 - sections
SL020 & SL022 - sectionsSL020 & SL022 - sections
SL020 & SL022 - sections
 
Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...
Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...
Nystrom CE Course-INY07A Managing Building Movement with Joints_In-Person_Sli...
 
Glass beams
Glass beamsGlass beams
Glass beams
 
Lewis Flooring Presentation Short Version
Lewis Flooring Presentation Short VersionLewis Flooring Presentation Short Version
Lewis Flooring Presentation Short Version
 
Lewis Flooring Presentation Short Version
Lewis Flooring Presentation Short VersionLewis Flooring Presentation Short Version
Lewis Flooring Presentation Short Version
 
NJI Portfolio Short
NJI Portfolio ShortNJI Portfolio Short
NJI Portfolio Short
 
foundation
foundationfoundation
foundation
 

More from jinlieww

Urban Theories Summaries
Urban Theories SummariesUrban Theories Summaries
Urban Theories Summariesjinlieww
 
Urban Theories Summaries
Urban Theories SummariesUrban Theories Summaries
Urban Theories Summariesjinlieww
 
Presentation board stuidio final
Presentation board stuidio finalPresentation board stuidio final
Presentation board stuidio finaljinlieww
 
Building construction-ii
Building construction-iiBuilding construction-ii
Building construction-iijinlieww
 
Building science 1
Building science 1Building science 1
Building science 1jinlieww
 
SSSY Report
SSSY ReportSSSY Report
SSSY Reportjinlieww
 
Culture History 2
Culture History 2Culture History 2
Culture History 2jinlieww
 
Cl f inal project report
Cl f inal project reportCl f inal project report
Cl f inal project reportjinlieww
 
Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)jinlieww
 
Ici magazine (latest)
Ici magazine (latest)Ici magazine (latest)
Ici magazine (latest)jinlieww
 
ENBE FP - REPORT
ENBE FP - REPORT ENBE FP - REPORT
ENBE FP - REPORT jinlieww
 

More from jinlieww (11)

Urban Theories Summaries
Urban Theories SummariesUrban Theories Summaries
Urban Theories Summaries
 
Urban Theories Summaries
Urban Theories SummariesUrban Theories Summaries
Urban Theories Summaries
 
Presentation board stuidio final
Presentation board stuidio finalPresentation board stuidio final
Presentation board stuidio final
 
Building construction-ii
Building construction-iiBuilding construction-ii
Building construction-ii
 
Building science 1
Building science 1Building science 1
Building science 1
 
SSSY Report
SSSY ReportSSSY Report
SSSY Report
 
Culture History 2
Culture History 2Culture History 2
Culture History 2
 
Cl f inal project report
Cl f inal project reportCl f inal project report
Cl f inal project report
 
Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)
 
Ici magazine (latest)
Ici magazine (latest)Ici magazine (latest)
Ici magazine (latest)
 
ENBE FP - REPORT
ENBE FP - REPORT ENBE FP - REPORT
ENBE FP - REPORT
 

Recently uploaded

A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 

Recently uploaded (20)

A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 

IBS Score

  • 1. 1. Construction Area i) Construction Area Ground Floor = 305.5m2 ii) Construction Area 1st Floor = 305.5m2 iii) Construction Area 2nd Floor = 305.5m2 iv) Construction Roof Area = 362.29m2 Total Construction Area = 1278.80m2 2. Structural System i) Beams = Precast Concrete Beams ii) Columns = Precast Concrete Columns iii) Floor Slab = Precast Hollow Core Slab iv) Roof Truss = Prefabricated Steel Roof Truss 3. Wall System i) External Wall = Precast Concrete Panel Wall ii) Internal Wall = Dry Wall System 4. Other Simplified Construction Solutions i) Beams = 100 % complies with MS 1064 Part 10:2001 Columns = 100 % complies with MS 1064 Part 10:2001 Walls = 100 % complies with MS 1064 Part 10:2001 Slabs = 100 % complies with MS 1064 Part 10:2001 Doors = 87.5 % complies with MS 1064 Part 4:2001 Windows = 0 % complies with MS 1064 Part 5:2001 ii) Repetition of floor to floor height = 100% Vertical repetition of structural floor layout = 100% Horizontal repetition of structural floor layout = 100%
  • 2. Total of Part 3 26 IBS Content Score Of Project (Part 1 + Part 2 + Part 3) 96 ELEMENTS AREA (m2 ) OR LENGTH (m) IBS FACTOR COVERAGE IBS SCORE Part 1: Structural Elements Precast Beams + Precast Columns + Precast Floor Slab (2 units + Corridor) 305.5m2 1.0 (916.5/1278.8) = 0.72 0.72 x 1.0 x 50 = 36 Prefabrication Steel Roof Truss 362.29 m2 1.0 (362.29/1278.8) = 0.28 0.28 x 1.0 x 50 = 14 Total of Part 1 (3 floors + roof) 1278.8 m2 1.0 50 Part 2: Wall System External Wall: Precast Concrete Panel 71.44m 1.0 (71.44/97.19) = 0.74 0.74 x 1.0 x 20 = 14.8 Internal Wall: Dry Wall System 25.75m 1.0 (25.75/97.19) = 0.26 0.26 x 1.0 x 20 = 5.2 Total of Part 2 97.19m 1.0 20 Part 3: Other Simplified Construction Solutions 100 % beams sizes follow MS 1064 Part 10:2001 100% 4 100 % columns sizes follow MS 1064 Part 10:2001 100% 4 100 % wall thickness sizes follow MS 1064 Part 10:2001 100% 4 100 % slab thickness follow MS 1064 Part 10:2001 100% 4 87.5 % door sizes follow MS 1064 Part 4:2001 87.5% 4 0 % window sizes follow MS 1064 Part 5:2001 0% 0 100% Repetition of floor to floor height 100% 2 100% Vertical repetition of structural floor layout 100% 2 100% Horizontal repetition of structural floor layout 100% 2
  • 3. Precast Foundation TYPE FOOTING(mm) COLUMN STUMP (mm) QUANTITY LENGTH WIDTH HEIGHT LENGTH WIDTH HEIGHT 20 F1 500 500 300 300 300 800 Precast Beams TYPE LENGTH (mm) HEIGHT (mm) THICKNESS (mm) QUANTITY B1 4350 400 300 12 B2 7100 18 B3 4700 24 B4 3300 18 B5 6075 9 B6 11500 6 B7 1750 12 B8 2800 12 D9 5000 12 Precast Columns TYPE POLE (mm) CORBEL (mm) QUANTITY LENGTH WIDTH HEIGHT LENGTH WIDTH HEIGHT QUANTITY C1 300 300 3800 350 200 300 4 24 C2 300 300 3800 350 200 300 2 30 C3 300 300 3800 350 200 300 3 6 Precast Walls TYPE LENGTH (mm) HEIGHT (mm) THICKNESS (mm) QUANTITY W1 3750 3300 150 6 W2 4400 6 W3 3300 6 W4 2000 12 W5 3000 6 W6 1500 12 W7 6075 3 Precast Walls With Doors TYPE LENGTH (mm) HEIGHT (mm) THICKNESS (mm) QUANTITY WD1 3750 3300 150 6 WD2 3800 6 WD3 2800 6 WD4 6800 12 WD5 1500 12 WD6 6075 1 WD7 4400 6
  • 4. Precast Walls With Windows TYPE LENGTH (mm) HEIGHT (mm) THICKNESS (mm) QUANTITY WW1 3750 3300 150 12 WW2 6800 6 WW3 3300 6 Precast Staircase TYPE RISER (mm) THREAT (mm) TOTAL HEIGHT TOTAL WIDTH LENGTH WIDTH QUANTITY LENGTH WIDTH QUANTITY ST 1 1600 200 19 1600 250 19 3800 3350 Precast Concrete Hollow Walls TYPE LENGTH (mm) WIDTH (mm) THICKNESS (mm) QUANTITY S1 4600 1800 150 14 S2 3500 12 S3 6500 3 S4 1800 10 Dry Wall Toilet Pod TYPE LENGTH (mm) WIDTH (mm) HEIGHT (mm) THICKNESS (mm) QUANTITY TP1 2700 1300 3300 120 12 Prefab Purlin TYPE LENGTH (mm) WIDTH (mm) HEIGHT (mm) QUANTITY P1 23000 150 150 15 Prefab Truss TYPE LENGTH (mm) WIDTH (mm) HEIGHT (mm) QUANTITY T1 21200 150 1250 15 Precast Balcony TYPE LENGTH (mm) WIDTH (mm) THICKNESS (mm) QUANTITY BC1 4850 2000 150 6 Precast Planter TYPE LENGTH (mm) WIDTH (mm) HEIGHT (mm) QUANTITY PT1 4850 1000 600 6