SlideShare a Scribd company logo
1 of 67
Earthquake engineering
GUJARAT TECHNOLOGICAL UNIVERSITY
A. D. PATEL INSTITUTE OF TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
Guided by: Prof. Kumarpal Trivedi
Sr. No. Team Member Enrollment No.
01. Manthan Kevadia 140010106017
02. Neel Mistry 140010106024
03. Abhi Shah 140010106050
04. Harshil Thakkar 140010106057
SUBJECT CODE: 2170612
Earthquake-resistant measures in confined masonry building
CONFINED MASONRY FOR
TWO-STOREY HOUSES
1
Horizontal ties (tie-beam) and vertical ties (tie-
column).
only tie-columns only tie-beams
Confining elements (ties)
Confining the walls is like holding a pile of books
together with a string: they can still move but
they will not fall apart.
YES
NO NO
A strong house
tie-columns
tie-columns
plinth beam
tie-beams
ring beam
window vertical
band
shear wall
lintel
band
sill band
max3
m
window vertical
reinforcement door
vertical band
All walls and openings should be confined to ensure stability during an earthquake !
Confining elements :
tie-column and tie-beams (plinth beam and ring beam)
Anchoring bands and opening reinforcement : seismic bands (lintel & sill bands) and vertical
reinforcement
Maximum ratio 1 to 3.
Free standing wall without any
tie.
Openings are too
big.
Each facade must have at least one tied wall
without openings = shear walls.
NO, THIS IS NOT CORRECT !
Shape of the house
YES, THIS IS CORRECT !
1
3
Opening is too big: Not a shear
wall !
Opening is small and outside the
diagonals: It is a shear wall !
Shear walls are walls without windows or
with a small window outside of the diagonals of the wall !
NO
YES
Full shear wall
YES
Shear walls
Minimum 10 cm
(better 45-60 cm)
YES
Seismic gap
Complex shape : WORSE
NO
Avoid complex shapes by creating seismic gaps.
Simple shape : BETTER
YES
Vertical structure
Walls must be placed
continuously one on top of the
other. From ground to the roof!
The opening is
too large.
Cantilevered
No vertical continuity between the
upper and the lower wall.
NO
YES
Vertical continuity of walls
FINDING AN
ADEQUATE LOCATION
3
Site selection: where to build
Don’t build at
the foot of a cliff.
Don’t build on stilts.
Don’t build on
fresh embankments.
YES
NO
NO
NO
NO
Don’t build too
close to a cliff.
Don’t build on
embankments.
Keep enough distance on each side
of the house.
NO
NO
Don’t build at the bottom of a canyon.
NO
Don’t build near the ocean
(due to tsunami hazard).
NO
Don’t build near a river.
Flood related hazards
Building on a slope
YES
Build between retaining walls.
NO
Don’t build against a retaining wall.
NO
Don’t build on top of a retaining wall.
Reinforced Concrete
Ties
6
NO
Types of steel rebars
Use ribbed steel for all rebars.
Only stirrups can be made of smooth steel.
For confined masonry Grade 60 should be used ! Always use standard rebars (not
sub-standard) !
Strength indication are written on the rebar :
Country of origin Producer
Grade Diameter
Do not use second hand rebars !
rebars :
min Ø 10 mm
better Ø 12 mm
Steel bar diameters
Rebars diameters (imperial and metric) :
Rebar dimensions for vertical and horizontal ties :
stirrups : min Ø 6 mm better Ø 8 mm
For rebars : For stirrups:
YES YES
YESNO
imperial inch metric rebars stirrups
#6 3/4 in. 19 mm
#5 5/8 in. 16 mm
#4 1/2 in. 12 mm
#3 3/8 in. 10 mm
- 1/3 in. 8 mm
#2 1/4 in. 6 mm
YES
YES
NO
NO
10 Ø
6 cm (rebar 6 mm)
8 cm (rebar 10 mm)
20
cm
Bend stirrup ends at 45° !
45°
If stirrups are not bent at 45°, they will open during an
earthquake !
Possible stirrup types :
Stirrups
3143
Stirrup spacing
H
H/6(better
60cm)
@20c
m
@10c
m
Rules for
stirrup spacing:
1. At the top and bottom of each
tie- column and ends
of tie-beams place the first
stirrup at 5 cm spacing, then
place stirrups at 10 cm spacing
over a
length of H/6
(better 60cm).
2. Place stirrups at 20 cm
spacing elsewhere.
Seismic
band
Plinth
beam
Tie-
beam
@20c
m
Tie-column
@10cm @20cm
first
@5cm !
first @5cm
Lap length
min 50 Ø
(lap length)
min50Ø
(lap
length)
Tie wires only hold the rebars in place. They don't
add strength to the connections !
The concrete keeps the rebars together like tight fists : the more fists we have (longer overlap)
the stronger the connection !
YES
YES
Lap length : (overlapping) 50
x Ø
(50 times the diameter)
for 10 mm rebar = 50 cm for 12 mm rebar
= 60 cm
Tie-beam : T-connection
Always :
extend hooked bars from the inside to the outside !
NONO
YES
Lap length : (overlapping) 50
x Ø
(50 times the diameter)
for 10 mm rebar = 50 cm for 12 mm rebar
= 60 cm
Connection around the inner
corner.
Connection with straight
bars.
Tie-beam : L-connection
Rebars must cross like the fingers of
a hand !
Hooked bars from inside to
inside.
Connection with straight
bars.
NO
YES
NO
Extend hooked bars
from the inside to the
outside !
Put an additional rebar
around the outer corner.
Tie-beam to Tie-column connection
If the wall ends here, bend
the vertical rebars into the
tie-beam.
One-storey building
If the wall continues,
add vertical rebars with an 50 Ø overlapp.
Two-storey building
50
Ø
50
Ø
Protection of rebar ends
Protect rebar ends with
lean concrete.
Exposed rebar
ends.
Exposed rebar ends will rust
and cannot be reused.
Protected rebar
ends.
NOYES
YES
NO
BRICKS &
BLOCKS
9
Which clay bricks to use
YES YES
Best brick :
solid burnt clay brick with frogs.
Frog
Bad brick :
vertical holes more then 50% of surface
area.
Good brick :
vertical holes less then 50% of surface
area.
Bad brick :
with horizontal holes (cannot carry
weight).
Vertical holes should be less then
50%
of the horizontal surface area !
Note : we recommend to use 10MPa bricks.
min 11 cm
(recommended 12.5-15cm)
Solid bricks are better then multiperforated ones !
NONO
Brick test
Visual test :
1. regular in form
2. uniform colour
3. not warped
4. no visible flaws or lumps
2. Resists the “3 point test” : Person standing on a
brick spanning between two other bricks.
Physical test :
1. Bricks cannot be easily scratched by a knife.
3. Bricks must give a ringing sound when struck
against each other.
NO
NO
NO
NO
Which concrete blocks to use
YES
YES
YES
YES
Best block :
15-20 cm thick, solid
block.
Satisfactory block : 15-20 cm
thick,
with 3 holes.
Best block :
15-20 cm thick,
with 4 holes.
Only if excellent quality !
20 cm thick,
with 2 holes.
web thickness min
25mm
min 15 cm thick
recommended 20 cm !!!
voids less than 50%
Note : we recommend to use 10MPa blocks.
Block test
Test blocks before buying them !
Drop 5 blocks from 1.5 m height on
hard surface ! (concrete surface)
Acceptable quality : (less than 1
broken)
Bad quality : don’t buy !
(more than 1 broken)
YES NO
Check if blocks were cured in the
shade !
Stored under plastic sheets : good !
YES
Blocks that dry in the sun : very
bad !
NO
Stored in the shade : good.
YES
1 part
cement
3/4 part clean
water
3 parts gravel (8-
10mm)
4 parts clean
sand
1. Make a pile with the gravel, the sand and
the cement but without water!
2. Mix the pile without water and move
it twice with a shovel.
Add water
only at the end !
3. Add water and mix again !
Concrete mix for blocks ( 1 : 4 : 3 )
Sand should be crushed, washed and dried.
Do not use sea beach sand !
+ ++
Cover the blocks with plastic sheets immediately!
Cure the blocks 3 times a day for minimum 7 days
and cover with plastic sheets.Store the blocks in the shade.
Fill the molds with the mixture.
To compact the concrete, hit the mold with
a shovel and a hammer.
If possible
use a
vibrating
machine !
Wait 8 days before using
the blocks !
Making the blocks
MASONRY
WALLS
10
Cement mortar mix ( 1 : 5 )
1 part
cement
5 parts clean sand
(washed and dry)
3/4 part clean
water
Add the water only at the
end !
Use 1:3 mix ratio
for 15cm or less wall thickness !
1. Make a pile with the sand and
the cement but without water!
2. Mix the pile without water and move
it twice with a shovel.
3. Add the water and mix
again.
Mix the mortar:
+ +
Cement-lime mortars
X parts
cement
Y parts lime
Cement-Lime mortar
has lower compressive strength than simple cement mortar but offers a better workability, higher
elasticity,
and it is more economical !
Mix the mortar:
Z parts clean
sand
3/4 part clean
water
Recommended mortar mix proportions :
++ +
Cement Lime Sand
x y z
preferred 1 0.5 4.5
1 1 6
minimum 1 2 9
Masonry walls height
The Width of masonry unit defines the wall height.
bricks
11cm
max:275
cm
max300
cm
H
bricks/blocks
12.5cm / 15cm / 20 cm / 24 cm
For bricks: Height smaller then 25 x wall Width
For blocks : Height max 22 x wall Width
Height = maximum 3m !
Masonry bonds
NO
Solid wall = Running bond vertical joints are not
continous.
YES
1/3 to 1/2 of block/brick
Weak wall = Stack bond vertical joints are
continuous.
Toothing 1/2 of a block : (> 1/2 of brick
length) TOO BIG !
Toothing 1/3-1/4 of a block : (max 1/2 of brick
length) GOOD !
YES
NO
Toothing
Distance from blocks or bricks :
minimum 3 cm ! (same length as
last bone of thumb).
Toothing :
min 5cm / max 13cm
Toothing options
Clay bricks (23-24 cm):
50% running bond (half of a brick)
Toothing = max 12 cm
Concrete blocks (40 cm):
33% running bond (1/3 - 2/3 of a block)
Toothing = max 13 cm
Concrete blocks (40 cm):
50% running bond (half of a block)
Break 1/3 of last block!
Toothing = min 5 cm
50% running bond toothing
50% running bond toothing
33% running bond toothing
Dowels
Although toothing is the optimal method, the use of dowels can be an
alternative.
Dowels are 6mm rebars
Place dowels :
-> 50 cm within the bed joints of the wall
-> place in pairs
every 2 layers of blocks every 4 layers of bricks
Note :
Dowels should be covered with enough mortar to protect them properly. Test if dowels can be
placed properly !
50 cm 50 cm
2 x 6 mm rebars
rebars 2 x 6
mm
Soak the blocks in water
for a while...
Preparing the masonry units
... water them with a
brush before use.
... or ...
... water all blocks together.
... or ...
Good masonry practice - 1
Use a plank as guide to ensure
the wall is in plumb and straight.
plinth beam
Joints : 10 - 15 mm
= the width of the pinky finger
!
Important : fill vertical joints with
mortar !
Stack blocks one course at a
time !
level string
Cure the concrete with water
before laying the blocks.
100 to 120 cm
(5 to 6 blocks)
Keep wall moist by pouring water on them 3 times a day for 7 days and/or by covering them with a plastic
sheet for 7 days.
Don‘t build more then 6 courses of masonry per day !
And then add a seismic band if needed.
Good masonry practice - 2
plinth beam (tie-beam)
foundation
Protect the wall in warm weather: mortar must not dry out in the
sun!
1 course
SEISMIC
REINFORCEMENT
11
Vertical reinforcement (V)
Place a vertical band on each side of every opening !
Add a horizontal reinforcement band above all openings !
max
3m
max
3m
Horizontal reinforcement (H)
Place a seismic band below and above every opening !
Don't go higher than 6 courses of blocks, don't exceed 1.20m!
max 1.2m
max 1.2m max
1.2m
max 1.2m
max 1.2m
max
3m
max
3m
Adding vertical bands
Place vertical reinforcement on each side of every opening.
Vertical bands are "half tie-columns" : add two rebars.
If a wall between openings functions as shear wall, the vertical reinforcement is identical to a tie-column :
add four rebars !
max
3m
max 4.50m
2 rebars 4 rebars 2 rebars
min 2m / max 4.50m
Vertical bands :
(for openings)
Width : 10 cm
2 Rebars : 10 mm Stirrups : 6 mm (@ 15cm)
L
H = smaller than 1.5 x L With seismic
band
H = bigger than 1.5 x L No seismic
band
Add horizontal bands to the walls if :
-> the quality of materials and construction is not ensured
-> if the Height is smaller than 1.5 of the Length
Rule :
H < 1.5 x L
NO YES
H
YES
H smaller than 1.5 x L
Adding horizontal bands
Sill band and lintel band
7.5 - 10 cm
Roughen up the top suface of
the bands to increase
bonding of the masonry
mortar.
Place a
stirrup
every 15
cm !
spacer
Seismic bands :
Height (bricks) 7.5 cm Heights (blocks)
10 cm 2 Rebars : 10 mm Stirrups : 6 mm
@15 cm
use spacers
Connect seismic band to tie-column
Hook seismic bands
reinforcement and lap with tie-
column reinforcement.
30 cm
a
b
In walls that are not shear walls, the width of the openings should not exceed half of the length of
the wall.
Rule :
b smaller than a/2
NO
Incorrect : b bigger than a/2
YES
Correct: b smaller than a/2 a
b
Size of openings
vertical door
band
plinth beam
vertical door
band
vertical door
band
horizontal door
reinforcement
30 cm
30
cm
Door reinforcement (V)
door
lintel
band
plinth beam
< 90 cm
Hook the door vertical reinforcement rebars and lap 30cm with the tie-beam rebars, under
the stirrups. Do the same with lintel band and the vertical bands.
tie-beam
30 cm
Hook the window vertical
reinforcement and lap 30 cm with the
tie-beams reinforcement, inside the
stirrups.
Do the same with the horizontal
reinforcement and the vertical bands.
vertical
window band
window horizontal
reinforcement
For windows smaller than 90 cm.
tie-beam
plinth beam
Small window reinforcement (V)
30 cm
< 90 cm
vertical window
reinforcement
plinth beam
30 cm
30 cm
Large window reinforcement (V)
90-150 cm
vertical
window band
window vertical band formwork
30 cm
For windows larger than 90 cm.
tie-beam
window lintel
min 15 cm
30 cm
window horizontal reinforcement
plinth beam
stirrups at 15 cm spacing
window lintel : reinforced seismic band.
min 15 cm
Hook the window reinforcement and lap 30 cm with the seismic band reinforcement,
inside the stirrups.
For windows smaller than 90 cm.
vertical window
reinforcement
vertical window
reinforcement
seismic band
Small window reinforcement (H)
30 cm
< 90 cm max 1.2m
sill band
30 cm
lintel band
Large window reinforcement (H)
90-150 cm
For windows larger than 90 cm.
window lintel
vertical window
reinforcement
stirrups at 15 cm spacing
vertical window
reinforcement
formwork
sill band
30 cm max 1.2m
seismic band
lintel band
30 cm
min 15cm
30 cm
window lintel :
reinforced seismic band.
min 15cm
LIGHT
ROOF
13
Good
YES
Better
YES
Better
YES
Not so good
AVOID
Roof shape
Gable wall
YES
YES
Concrete tie on top of
the gable wall.
Roof structure - Trusses
Building with planks :
AVOID
(not enough room for nails)
Building with plywood gusset :
BETTER !
Building with solid timber :
GOOD
YES
AVOID YES
Timber connections :
Put at least
3 nails in each direction !
Nails length should be twice the thickness
of the timber !
min 3 cm
min 6 cm
Keep verandas independent from main roof :
cyclones may tear off the verandas.
Closed gable wall.
Cyclones
Opened gable wall. Main roof becoming veranda.
If a veranda is part of the main roof, then a cyclone could tear off the whole
roof.
YES YES
YES
NONO
Fastening of the veranda framing
bracing
solid fastening plinth < 40 cm
straps
Fastening of the roof structure
Close the spaces between trusses with a
plank or a screen to avoid insects.
Solidly fasten the anchors or straps to
the wood framing.
rebar anchors
or straps
Bracing
Bracing :
wood planks nailed to the
trusses.
YES
YES
FUTURE
EXTENSIONS
14
Preparation
Open all corners, all rebar
connections.
Build a new solid foundation for
the new room.
Add anchor bars
Place the hooks around the vertical rebars : one on top and one under each
stirrup.
15 cm
min 50 cm
Add hooks : 10 mm rebars.
Place reinforcement
Place the 10 mm hooks and then place both the ring beams (tie-beams) and the
tie-columns.
Connect each corner the same way !
Connect the new plinth beam
to the existing one with the
hooks.
Extension of the structure
Build the masonry walls first and only after pour the concrete for the tie
columns.
The walls and tie-elements for future extensions should align with the existing structure
(existing tie-elements).
Pour concrete for the plinth beam
and fill completely the opened
corners.
References
1. www.nicee.org
2. www.eeri.org
3. www.gsdma.org
4. www.ndma.gov.in

More Related Content

What's hot

A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'Abheek Khajuria
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete aishwaryasanap
 
Chapter 10 wall finishes ( plastering,pointing &amp; painting)
Chapter 10 wall finishes ( plastering,pointing &amp; painting)Chapter 10 wall finishes ( plastering,pointing &amp; painting)
Chapter 10 wall finishes ( plastering,pointing &amp; painting)KHUSHBU SHAH
 
Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207sharad_kadbhane
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Design of columns axial load as per IS 456-2000
Design of columns  axial load as per IS 456-2000Design of columns  axial load as per IS 456-2000
Design of columns axial load as per IS 456-2000PraveenKumar Shanmugam
 
Masonry Construction Around the World
Masonry Construction Around the WorldMasonry Construction Around the World
Masonry Construction Around the WorldEERI
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential buildingK.MAHESH KUMAR
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMSagar Shah
 
Brick walling and joints
Brick walling and jointsBrick walling and joints
Brick walling and jointsSahil Pahal
 
Reports on Precast System
Reports on Precast System Reports on Precast System
Reports on Precast System Rising Sher
 
Half brick walling calculations
Half brick walling calculationsHalf brick walling calculations
Half brick walling calculationsdoogstone
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionMadan Mohan Jana
 
Earthquake collapse pattern
Earthquake collapse patternEarthquake collapse pattern
Earthquake collapse patternPakjum Nyori
 
english 1 1.5 brick thick bond
 english 1 1.5 brick thick bond english 1 1.5 brick thick bond
english 1 1.5 brick thick bondVartika khandelwal
 

What's hot (20)

A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
 
Chapter 10 wall finishes ( plastering,pointing &amp; painting)
Chapter 10 wall finishes ( plastering,pointing &amp; painting)Chapter 10 wall finishes ( plastering,pointing &amp; painting)
Chapter 10 wall finishes ( plastering,pointing &amp; painting)
 
Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Damp Proof Course
Damp Proof Course Damp Proof Course
Damp Proof Course
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Design of columns axial load as per IS 456-2000
Design of columns  axial load as per IS 456-2000Design of columns  axial load as per IS 456-2000
Design of columns axial load as per IS 456-2000
 
Partition walls
Partition walls Partition walls
Partition walls
 
Masonry Construction Around the World
Masonry Construction Around the WorldMasonry Construction Around the World
Masonry Construction Around the World
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Brick walling and joints
Brick walling and jointsBrick walling and joints
Brick walling and joints
 
Reports on Precast System
Reports on Precast System Reports on Precast System
Reports on Precast System
 
Half brick walling calculations
Half brick walling calculationsHalf brick walling calculations
Half brick walling calculations
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Earthquake collapse pattern
Earthquake collapse patternEarthquake collapse pattern
Earthquake collapse pattern
 
english 1 1.5 brick thick bond
 english 1 1.5 brick thick bond english 1 1.5 brick thick bond
english 1 1.5 brick thick bond
 

Similar to Confined Masonry Building

HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxswethaasukumar
 
Compost toilet manual
Compost toilet manualCompost toilet manual
Compost toilet manualPavel Druziak
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUISUBHENDU SAMUI
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUISubhendu Samui
 
Construction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture NotesConstruction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture NotesSHAMJITH KM
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfAbhinavSahu45
 
brickmasonry-230211140056-e3a1df36.pdf
brickmasonry-230211140056-e3a1df36.pdfbrickmasonry-230211140056-e3a1df36.pdf
brickmasonry-230211140056-e3a1df36.pdfKrupalks
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptxErankajKumar
 
wall masonary,door,paint and trusses
wall masonary,door,paint and trusseswall masonary,door,paint and trusses
wall masonary,door,paint and trusseslithakoshi
 
How To Install Cedar Shingles
How To Install Cedar ShinglesHow To Install Cedar Shingles
How To Install Cedar Shingleswildeagle
 
Timber Panels Installation
Timber Panels InstallationTimber Panels Installation
Timber Panels InstallationDeziner Panels
 
Sonal Gupta , Interior Design
Sonal Gupta , Interior DesignSonal Gupta , Interior Design
Sonal Gupta , Interior Designdezyneecole
 
Guidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporexGuidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporexPriya Raj
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkCivil 4M
 
Bricks & Plastering
Bricks & PlasteringBricks & Plastering
Bricks & PlasteringTanvir Araf
 
DIFFERENT TYPE OF BONDING SYSTEM
DIFFERENT TYPE OF BONDING SYSTEM DIFFERENT TYPE OF BONDING SYSTEM
DIFFERENT TYPE OF BONDING SYSTEM Lenin Rajat
 

Similar to Confined Masonry Building (20)

HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptx
 
Compost toilet manual
Compost toilet manualCompost toilet manual
Compost toilet manual
 
BRICK MASONRY
BRICK MASONRYBRICK MASONRY
BRICK MASONRY
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUI
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUI
 
ppt by subhendu samui
ppt by subhendu samuippt by subhendu samui
ppt by subhendu samui
 
Construction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture NotesConstruction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture Notes
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdf
 
brickmasonry-230211140056-e3a1df36.pdf
brickmasonry-230211140056-e3a1df36.pdfbrickmasonry-230211140056-e3a1df36.pdf
brickmasonry-230211140056-e3a1df36.pdf
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptx
 
wall masonary,door,paint and trusses
wall masonary,door,paint and trusseswall masonary,door,paint and trusses
wall masonary,door,paint and trusses
 
How To Install Cedar Shingles
How To Install Cedar ShinglesHow To Install Cedar Shingles
How To Install Cedar Shingles
 
Timber Panels Installation
Timber Panels InstallationTimber Panels Installation
Timber Panels Installation
 
Sonal Gupta , Interior Design
Sonal Gupta , Interior DesignSonal Gupta , Interior Design
Sonal Gupta , Interior Design
 
Guidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporexGuidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporex
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC Blockwork
 
Brick masonary
Brick masonaryBrick masonary
Brick masonary
 
Bricks & Plastering
Bricks & PlasteringBricks & Plastering
Bricks & Plastering
 
Brick work
Brick workBrick work
Brick work
 
DIFFERENT TYPE OF BONDING SYSTEM
DIFFERENT TYPE OF BONDING SYSTEM DIFFERENT TYPE OF BONDING SYSTEM
DIFFERENT TYPE OF BONDING SYSTEM
 

Recently uploaded

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 

Confined Masonry Building

  • 1. Earthquake engineering GUJARAT TECHNOLOGICAL UNIVERSITY A. D. PATEL INSTITUTE OF TECHNOLOGY CIVIL ENGINEERING DEPARTMENT Guided by: Prof. Kumarpal Trivedi Sr. No. Team Member Enrollment No. 01. Manthan Kevadia 140010106017 02. Neel Mistry 140010106024 03. Abhi Shah 140010106050 04. Harshil Thakkar 140010106057 SUBJECT CODE: 2170612 Earthquake-resistant measures in confined masonry building
  • 3. Horizontal ties (tie-beam) and vertical ties (tie- column). only tie-columns only tie-beams Confining elements (ties) Confining the walls is like holding a pile of books together with a string: they can still move but they will not fall apart. YES NO NO
  • 4. A strong house tie-columns tie-columns plinth beam tie-beams ring beam window vertical band shear wall lintel band sill band max3 m window vertical reinforcement door vertical band All walls and openings should be confined to ensure stability during an earthquake ! Confining elements : tie-column and tie-beams (plinth beam and ring beam) Anchoring bands and opening reinforcement : seismic bands (lintel & sill bands) and vertical reinforcement
  • 5. Maximum ratio 1 to 3. Free standing wall without any tie. Openings are too big. Each facade must have at least one tied wall without openings = shear walls. NO, THIS IS NOT CORRECT ! Shape of the house YES, THIS IS CORRECT ! 1 3
  • 6. Opening is too big: Not a shear wall ! Opening is small and outside the diagonals: It is a shear wall ! Shear walls are walls without windows or with a small window outside of the diagonals of the wall ! NO YES Full shear wall YES Shear walls
  • 7. Minimum 10 cm (better 45-60 cm) YES Seismic gap Complex shape : WORSE NO Avoid complex shapes by creating seismic gaps. Simple shape : BETTER YES
  • 8. Vertical structure Walls must be placed continuously one on top of the other. From ground to the roof! The opening is too large. Cantilevered No vertical continuity between the upper and the lower wall. NO YES Vertical continuity of walls
  • 10. Site selection: where to build Don’t build at the foot of a cliff. Don’t build on stilts. Don’t build on fresh embankments. YES NO NO NO NO Don’t build too close to a cliff. Don’t build on embankments. Keep enough distance on each side of the house. NO
  • 11. NO Don’t build at the bottom of a canyon. NO Don’t build near the ocean (due to tsunami hazard). NO Don’t build near a river. Flood related hazards
  • 12. Building on a slope YES Build between retaining walls. NO Don’t build against a retaining wall. NO Don’t build on top of a retaining wall.
  • 14. NO Types of steel rebars Use ribbed steel for all rebars. Only stirrups can be made of smooth steel. For confined masonry Grade 60 should be used ! Always use standard rebars (not sub-standard) ! Strength indication are written on the rebar : Country of origin Producer Grade Diameter Do not use second hand rebars !
  • 15. rebars : min Ø 10 mm better Ø 12 mm Steel bar diameters Rebars diameters (imperial and metric) : Rebar dimensions for vertical and horizontal ties : stirrups : min Ø 6 mm better Ø 8 mm For rebars : For stirrups: YES YES YESNO imperial inch metric rebars stirrups #6 3/4 in. 19 mm #5 5/8 in. 16 mm #4 1/2 in. 12 mm #3 3/8 in. 10 mm - 1/3 in. 8 mm #2 1/4 in. 6 mm
  • 16. YES YES NO NO 10 Ø 6 cm (rebar 6 mm) 8 cm (rebar 10 mm) 20 cm Bend stirrup ends at 45° ! 45° If stirrups are not bent at 45°, they will open during an earthquake ! Possible stirrup types : Stirrups 3143
  • 17. Stirrup spacing H H/6(better 60cm) @20c m @10c m Rules for stirrup spacing: 1. At the top and bottom of each tie- column and ends of tie-beams place the first stirrup at 5 cm spacing, then place stirrups at 10 cm spacing over a length of H/6 (better 60cm). 2. Place stirrups at 20 cm spacing elsewhere. Seismic band Plinth beam Tie- beam @20c m Tie-column @10cm @20cm first @5cm ! first @5cm
  • 18. Lap length min 50 Ø (lap length) min50Ø (lap length) Tie wires only hold the rebars in place. They don't add strength to the connections ! The concrete keeps the rebars together like tight fists : the more fists we have (longer overlap) the stronger the connection ! YES YES Lap length : (overlapping) 50 x Ø (50 times the diameter) for 10 mm rebar = 50 cm for 12 mm rebar = 60 cm
  • 19. Tie-beam : T-connection Always : extend hooked bars from the inside to the outside ! NONO YES Lap length : (overlapping) 50 x Ø (50 times the diameter) for 10 mm rebar = 50 cm for 12 mm rebar = 60 cm Connection around the inner corner. Connection with straight bars.
  • 20. Tie-beam : L-connection Rebars must cross like the fingers of a hand ! Hooked bars from inside to inside. Connection with straight bars. NO YES NO Extend hooked bars from the inside to the outside ! Put an additional rebar around the outer corner.
  • 21. Tie-beam to Tie-column connection If the wall ends here, bend the vertical rebars into the tie-beam. One-storey building If the wall continues, add vertical rebars with an 50 Ø overlapp. Two-storey building 50 Ø 50 Ø
  • 22. Protection of rebar ends Protect rebar ends with lean concrete. Exposed rebar ends. Exposed rebar ends will rust and cannot be reused. Protected rebar ends. NOYES YES NO
  • 24. Which clay bricks to use YES YES Best brick : solid burnt clay brick with frogs. Frog Bad brick : vertical holes more then 50% of surface area. Good brick : vertical holes less then 50% of surface area. Bad brick : with horizontal holes (cannot carry weight). Vertical holes should be less then 50% of the horizontal surface area ! Note : we recommend to use 10MPa bricks. min 11 cm (recommended 12.5-15cm) Solid bricks are better then multiperforated ones ! NONO
  • 25. Brick test Visual test : 1. regular in form 2. uniform colour 3. not warped 4. no visible flaws or lumps 2. Resists the “3 point test” : Person standing on a brick spanning between two other bricks. Physical test : 1. Bricks cannot be easily scratched by a knife. 3. Bricks must give a ringing sound when struck against each other. NO NO NO NO
  • 26. Which concrete blocks to use YES YES YES YES Best block : 15-20 cm thick, solid block. Satisfactory block : 15-20 cm thick, with 3 holes. Best block : 15-20 cm thick, with 4 holes. Only if excellent quality ! 20 cm thick, with 2 holes. web thickness min 25mm min 15 cm thick recommended 20 cm !!! voids less than 50% Note : we recommend to use 10MPa blocks.
  • 27. Block test Test blocks before buying them ! Drop 5 blocks from 1.5 m height on hard surface ! (concrete surface) Acceptable quality : (less than 1 broken) Bad quality : don’t buy ! (more than 1 broken) YES NO Check if blocks were cured in the shade ! Stored under plastic sheets : good ! YES Blocks that dry in the sun : very bad ! NO Stored in the shade : good. YES
  • 28. 1 part cement 3/4 part clean water 3 parts gravel (8- 10mm) 4 parts clean sand 1. Make a pile with the gravel, the sand and the cement but without water! 2. Mix the pile without water and move it twice with a shovel. Add water only at the end ! 3. Add water and mix again ! Concrete mix for blocks ( 1 : 4 : 3 ) Sand should be crushed, washed and dried. Do not use sea beach sand ! + ++
  • 29. Cover the blocks with plastic sheets immediately! Cure the blocks 3 times a day for minimum 7 days and cover with plastic sheets.Store the blocks in the shade. Fill the molds with the mixture. To compact the concrete, hit the mold with a shovel and a hammer. If possible use a vibrating machine ! Wait 8 days before using the blocks ! Making the blocks
  • 31. Cement mortar mix ( 1 : 5 ) 1 part cement 5 parts clean sand (washed and dry) 3/4 part clean water Add the water only at the end ! Use 1:3 mix ratio for 15cm or less wall thickness ! 1. Make a pile with the sand and the cement but without water! 2. Mix the pile without water and move it twice with a shovel. 3. Add the water and mix again. Mix the mortar: + +
  • 32. Cement-lime mortars X parts cement Y parts lime Cement-Lime mortar has lower compressive strength than simple cement mortar but offers a better workability, higher elasticity, and it is more economical ! Mix the mortar: Z parts clean sand 3/4 part clean water Recommended mortar mix proportions : ++ + Cement Lime Sand x y z preferred 1 0.5 4.5 1 1 6 minimum 1 2 9
  • 33. Masonry walls height The Width of masonry unit defines the wall height. bricks 11cm max:275 cm max300 cm H bricks/blocks 12.5cm / 15cm / 20 cm / 24 cm For bricks: Height smaller then 25 x wall Width For blocks : Height max 22 x wall Width Height = maximum 3m !
  • 34. Masonry bonds NO Solid wall = Running bond vertical joints are not continous. YES 1/3 to 1/2 of block/brick Weak wall = Stack bond vertical joints are continuous.
  • 35. Toothing 1/2 of a block : (> 1/2 of brick length) TOO BIG ! Toothing 1/3-1/4 of a block : (max 1/2 of brick length) GOOD ! YES NO Toothing Distance from blocks or bricks : minimum 3 cm ! (same length as last bone of thumb). Toothing : min 5cm / max 13cm
  • 36. Toothing options Clay bricks (23-24 cm): 50% running bond (half of a brick) Toothing = max 12 cm Concrete blocks (40 cm): 33% running bond (1/3 - 2/3 of a block) Toothing = max 13 cm Concrete blocks (40 cm): 50% running bond (half of a block) Break 1/3 of last block! Toothing = min 5 cm 50% running bond toothing 50% running bond toothing 33% running bond toothing
  • 37. Dowels Although toothing is the optimal method, the use of dowels can be an alternative. Dowels are 6mm rebars Place dowels : -> 50 cm within the bed joints of the wall -> place in pairs every 2 layers of blocks every 4 layers of bricks Note : Dowels should be covered with enough mortar to protect them properly. Test if dowels can be placed properly ! 50 cm 50 cm 2 x 6 mm rebars rebars 2 x 6 mm
  • 38. Soak the blocks in water for a while... Preparing the masonry units ... water them with a brush before use. ... or ... ... water all blocks together. ... or ...
  • 39. Good masonry practice - 1 Use a plank as guide to ensure the wall is in plumb and straight. plinth beam Joints : 10 - 15 mm = the width of the pinky finger ! Important : fill vertical joints with mortar ! Stack blocks one course at a time ! level string Cure the concrete with water before laying the blocks.
  • 40. 100 to 120 cm (5 to 6 blocks) Keep wall moist by pouring water on them 3 times a day for 7 days and/or by covering them with a plastic sheet for 7 days. Don‘t build more then 6 courses of masonry per day ! And then add a seismic band if needed. Good masonry practice - 2 plinth beam (tie-beam) foundation Protect the wall in warm weather: mortar must not dry out in the sun! 1 course
  • 42. Vertical reinforcement (V) Place a vertical band on each side of every opening ! Add a horizontal reinforcement band above all openings ! max 3m max 3m
  • 43. Horizontal reinforcement (H) Place a seismic band below and above every opening ! Don't go higher than 6 courses of blocks, don't exceed 1.20m! max 1.2m max 1.2m max 1.2m max 1.2m max 1.2m max 3m max 3m
  • 44. Adding vertical bands Place vertical reinforcement on each side of every opening. Vertical bands are "half tie-columns" : add two rebars. If a wall between openings functions as shear wall, the vertical reinforcement is identical to a tie-column : add four rebars ! max 3m max 4.50m 2 rebars 4 rebars 2 rebars min 2m / max 4.50m Vertical bands : (for openings) Width : 10 cm 2 Rebars : 10 mm Stirrups : 6 mm (@ 15cm)
  • 45. L H = smaller than 1.5 x L With seismic band H = bigger than 1.5 x L No seismic band Add horizontal bands to the walls if : -> the quality of materials and construction is not ensured -> if the Height is smaller than 1.5 of the Length Rule : H < 1.5 x L NO YES H YES H smaller than 1.5 x L Adding horizontal bands
  • 46. Sill band and lintel band 7.5 - 10 cm Roughen up the top suface of the bands to increase bonding of the masonry mortar. Place a stirrup every 15 cm ! spacer Seismic bands : Height (bricks) 7.5 cm Heights (blocks) 10 cm 2 Rebars : 10 mm Stirrups : 6 mm @15 cm use spacers
  • 47. Connect seismic band to tie-column Hook seismic bands reinforcement and lap with tie- column reinforcement. 30 cm
  • 48. a b In walls that are not shear walls, the width of the openings should not exceed half of the length of the wall. Rule : b smaller than a/2 NO Incorrect : b bigger than a/2 YES Correct: b smaller than a/2 a b Size of openings
  • 49. vertical door band plinth beam vertical door band vertical door band horizontal door reinforcement 30 cm 30 cm Door reinforcement (V) door lintel band plinth beam < 90 cm Hook the door vertical reinforcement rebars and lap 30cm with the tie-beam rebars, under the stirrups. Do the same with lintel band and the vertical bands. tie-beam 30 cm
  • 50. Hook the window vertical reinforcement and lap 30 cm with the tie-beams reinforcement, inside the stirrups. Do the same with the horizontal reinforcement and the vertical bands. vertical window band window horizontal reinforcement For windows smaller than 90 cm. tie-beam plinth beam Small window reinforcement (V) 30 cm < 90 cm vertical window reinforcement plinth beam 30 cm 30 cm
  • 51. Large window reinforcement (V) 90-150 cm vertical window band window vertical band formwork 30 cm For windows larger than 90 cm. tie-beam window lintel min 15 cm 30 cm window horizontal reinforcement plinth beam stirrups at 15 cm spacing window lintel : reinforced seismic band. min 15 cm
  • 52. Hook the window reinforcement and lap 30 cm with the seismic band reinforcement, inside the stirrups. For windows smaller than 90 cm. vertical window reinforcement vertical window reinforcement seismic band Small window reinforcement (H) 30 cm < 90 cm max 1.2m sill band 30 cm lintel band
  • 53. Large window reinforcement (H) 90-150 cm For windows larger than 90 cm. window lintel vertical window reinforcement stirrups at 15 cm spacing vertical window reinforcement formwork sill band 30 cm max 1.2m seismic band lintel band 30 cm min 15cm 30 cm window lintel : reinforced seismic band. min 15cm
  • 56. Gable wall YES YES Concrete tie on top of the gable wall.
  • 57. Roof structure - Trusses Building with planks : AVOID (not enough room for nails) Building with plywood gusset : BETTER ! Building with solid timber : GOOD YES AVOID YES Timber connections : Put at least 3 nails in each direction ! Nails length should be twice the thickness of the timber ! min 3 cm min 6 cm
  • 58. Keep verandas independent from main roof : cyclones may tear off the verandas. Closed gable wall. Cyclones Opened gable wall. Main roof becoming veranda. If a veranda is part of the main roof, then a cyclone could tear off the whole roof. YES YES YES NONO
  • 59. Fastening of the veranda framing bracing solid fastening plinth < 40 cm straps
  • 60. Fastening of the roof structure Close the spaces between trusses with a plank or a screen to avoid insects. Solidly fasten the anchors or straps to the wood framing. rebar anchors or straps
  • 61. Bracing Bracing : wood planks nailed to the trusses. YES YES
  • 63. Preparation Open all corners, all rebar connections. Build a new solid foundation for the new room.
  • 64. Add anchor bars Place the hooks around the vertical rebars : one on top and one under each stirrup. 15 cm min 50 cm Add hooks : 10 mm rebars.
  • 65. Place reinforcement Place the 10 mm hooks and then place both the ring beams (tie-beams) and the tie-columns. Connect each corner the same way ! Connect the new plinth beam to the existing one with the hooks.
  • 66. Extension of the structure Build the masonry walls first and only after pour the concrete for the tie columns. The walls and tie-elements for future extensions should align with the existing structure (existing tie-elements). Pour concrete for the plinth beam and fill completely the opened corners.
  • 67. References 1. www.nicee.org 2. www.eeri.org 3. www.gsdma.org 4. www.ndma.gov.in