SB-10 – THE ENVELOPE ULTIMATUMGreen Building Festival12 October 2012
Energy EfficientEnclosures & SB-10            SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Why does it matter? • Codes demand it • Substantial portion of construction budget – 20% range • Integration with HVAC req...
Why does it matter?1210                     Performance                     Gap 8 6                         Mechanical    ...
Why does it matter?$90,000.00$80,000.00$70,000.00$60,000.00$50,000.00$40,000.00$30,000.00$20,000.00$10,000.00       $-    ...
Enclosure FailureEnergy & Durability                      SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Enclosure FailureIndoor Environmental Quality                               SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Energy Code Trends                     SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Achieving SB-10           SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
OBC and SB-10Design Considerations       • Meet ASHRAE 90.1-2010 + SB-10 Envelope         Values (i.e. ASHRAE 189)        ...
SB-10 Envelope Values    Zone Comparison                                                                    Zone          ...
Achieving SB-10Solid Opaque Walls                     SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Achieving SB-10Fenestration                  SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
OBC and SB-10Design Considerations       • Meet ASHRAE 90.1-2010 + SB-10 Envelope         Values (i.e. ASHRAE 189)        ...
Accurate Performance     Prediction (Energy Modeling that Works)                     SB-10 – THE ENVELOPE ULTIMATUM | 12 O...
Energy Modeling That Works                   SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Energy Modeling That Works                   SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
High Performance   Enclosures           SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
High-Performance EnclosuresBuilding-Integrated PV                         SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
High-Performance EnclosuresExternal Shading                   SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
High-Performance EnclosuresVegetated Green Walls                        SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Analyzing SystemsFenestration                                               © Kawneer.com                    SB-10 – THE E...
Delivering QualityEnclosure Commissioning                          SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Verifying PerformanceEnclosure Commissioning                          SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
Scott R Armstrong         Dipl. Arch. Tech., A.Sc.T., LEED AP BD+CManager, Building Science & SustainabilityAssociateMMM G...
Communities                                                             Transportation                                    ...
Upcoming SlideShare
Loading in …5
×

SB-10: The Envelope Ultimatum

692 views

Published on

Scott Armstrong
Design considerations in achieving SB-10 – high performance enclosures, analyzing systems, delivering quality, and verifying performance

Published in: Design
  • Be the first to comment

  • Be the first to like this

SB-10: The Envelope Ultimatum

  1. 1. SB-10 – THE ENVELOPE ULTIMATUMGreen Building Festival12 October 2012
  2. 2. Energy EfficientEnclosures & SB-10 SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  3. 3. Why does it matter? • Codes demand it • Substantial portion of construction budget – 20% range • Integration with HVAC requires that the building envelope perform • Sustainable buildings often incorporate innovative assemblies and materials • Envelope failure can require costly repairs to re-establish the design intent • Envelopes are complex systems with shared responsibilities and are not typically commissioned SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  4. 4. Why does it matter?1210 Performance Gap 8 6 Mechanical Envelope Extract from NCBC 2010 Seminar “Successful Exterior Enclosure Commissioning” 4 2 0 1 2 SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  5. 5. Why does it matter?$90,000.00$80,000.00$70,000.00$60,000.00$50,000.00$40,000.00$30,000.00$20,000.00$10,000.00 $- 1 2 3 4 5 6 7 8 9 10 Code Building based on 3% annual inflation 25% Better over 10 years SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  6. 6. Enclosure FailureEnergy & Durability SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  7. 7. Enclosure FailureIndoor Environmental Quality SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  8. 8. Energy Code Trends SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  9. 9. Achieving SB-10 SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  10. 10. OBC and SB-10Design Considerations • Meet ASHRAE 90.1-2010 + SB-10 Envelope Values (i.e. ASHRAE 189) Prescriptive • Exceed ASHRAE 90.1-2010 by minimum 5% Modeled • Exceed MNECB (1997) by minimum 25% Modeled • 40% maximum fenestration-to-wall ratio LEED NC 2009 prerequisite equivalent SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  11. 11. SB-10 Envelope Values Zone Comparison Zone 5 6 7 Max U-value Min. R-Value Max U-value Min. R-Value Max U-value Min. R-Value 2 2 2Assembly (w/m K) (w/m K) (w/m K)Roof 0.22 R-25 ci 0.18 R-30 ci 0.16 R-35 ciMass Walls 0.45 R-13.3 ci 0.40 R-15.2 ci 0.34 R-20 ciMetal Building 0.30 R-13 + R-13 ci 0.30 R-13 + R-13 ci 0.30 R-13 + R-13 ciSteel Framed 0.31 R-13 + R-10 ci 0.31 R-13 + R-13 ci 0.31 R-13 + R-10 ciMetal framed 1.99 0.35 SHGC 1.99 0.40 SHGC 1.70 0.45 SHGCfenestration (max40%) SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  12. 12. Achieving SB-10Solid Opaque Walls SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  13. 13. Achieving SB-10Fenestration SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  14. 14. OBC and SB-10Design Considerations • Meet ASHRAE 90.1-2010 + SB-10 Envelope Values (i.e. ASHRAE 189) Prescriptive • Exceed ASHRAE 90.1-2010 by minimum 5% Modeled • Exceed MNECB (1997) by minimum 25% Modeled • 40% maximum fenestration-to-wall ratio LEED NC 2009 prerequisite equivalent SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  15. 15. Accurate Performance Prediction (Energy Modeling that Works) SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  16. 16. Energy Modeling That Works SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  17. 17. Energy Modeling That Works SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  18. 18. High Performance Enclosures SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  19. 19. High-Performance EnclosuresBuilding-Integrated PV SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  20. 20. High-Performance EnclosuresExternal Shading SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  21. 21. High-Performance EnclosuresVegetated Green Walls SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  22. 22. Analyzing SystemsFenestration © Kawneer.com SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  23. 23. Delivering QualityEnclosure Commissioning SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  24. 24. Verifying PerformanceEnclosure Commissioning SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  25. 25. Scott R Armstrong Dipl. Arch. Tech., A.Sc.T., LEED AP BD+CManager, Building Science & SustainabilityAssociateMMM Group Limited100 Commerce Valley Drive WestThornhill ON L3T 0A1ArmstrongS@mmm.ca | m: 647.923.9053 | t: 905.882.4211 xt. 6864 | www.mmm.ca SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012
  26. 26. Communities Transportation Buildings InfrastructurePROJECT EXPERTISE& RESOURCES Green Buildings & LEED Building Science Consulting SB-10 – THE ENVELOPE ULTIMATUM | 12 OCT 2012

×