8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
Incentives boma-doug taylor-gbf2007
1. BOMA Toronto CDM Program
Doug Taylor
Manager, BOMA Toronto CDM Program
Green Building Festival
Atlantis Pavilions, Toronto
24 October 2007
2. My Objectives Today
• Program Manager Accountabilities
• Program Features
• Eligibility
• Incentive Structure
• Program Process
• Call to Action
3. My Accountabilities as Program
Manager
• Promote Program to the Toronto market
• Track and report Program status to the
OPA and BOMA
• Facilitate Project Evaluation
• Ensure applications get through the
Program process
… my focus today
4. Program Features
• Applicant knows up front…
– Project Timetable, Financials
• Payment made immediately after
Project completion
• Industry-standard M&V protocols
uniformly applied to Measures
5. Program Benefits
• For the Applicant: solid business case,
minimum of risk, timely payment
• For the Province: auditable verifiable
results that help solve Toronto’s supply
constraint problem
6. Eligible buildings
• Are in Toronto – Office
• Are existing – not – Hotel
new construction – Retail
• Are privately owned – Mixed use
• Have a gross floor – Private Institution
area not less than (private healthcare
25,000 square feet. and education)
– Industrial Buildings
(Lighting and HVAC)
7. Non-eligible Building Types
• Multiresidential (apartments,
condominiums)
• Municipalities, Universities, Academics
Schools and Hospitals (the MUSH
MASH group)
• New construction
8. Eligible Measures
• Lighting upgrades/retrofits/controls
• HVAC re-design
• Equipment replacement
• Variable Speed Drives (Fans, Pumps, Chillers)
• Refrigeration upgrades
• Building envelope
• Building Automation Systems
• Tenant submetering
• Deep Lake Water Cooling
BUT… Not started yet!
9. Go Green Eligibility Requirement
• Online building environmental audit
• Go Green Assessment is $600 per
building
• No Program requirement to obtain
certification (extra cost)
BUT…
• Program Participants who certify are
eligible for a rebate: up to $1,000
10. CDM Program Incentives
Program provides incentives for Energy
Savings ($.05 per kWh)
Program provides incentives for Demand
Reductions ($400 per kW)
11. Electrical Load Profile - 1 Week
75,000 s.f. Office Building
500.00
A 50-KW Reduction off the
450.00 Building's year-round 8,760-
hour load profile.
400.00
350.00
Average Hourly KW
300.00
250.00
200.00
150.00
100.00
50.00
0.00
April 3, 2006 April 4, 2006 April 5, 2006 April 6, 2006 April 7, 2006 April 8, 2006 April 9, 2006
Hourly from Monday through Sunday
12. Electrical Load Profile - 1 Week
75,000 s.f. Office Building
500.00
A 50 KW Reduction off the
450.00 Building's 16-hour On-
Peak load profile
400.00
350.00
Average Hourly KW
300.00
250.00
200.00
150.00
100.00
50.00
0.00
April 3, 2006 April 4, 2006 April 5, 2006 April 6, 2006 April 7, 2006 April 8, 2006 April 9, 2006
Hourly from Monday through Sunday
13. 1 Apply The BOMA Toronto CDM
2
Program Process
PM approves
Application, PA signed
3
Applicant GoesGreen
4 PE evaluates
and audits 7
5 Applicant Initiates and completes Applicant Receives
incentive money
Project
6
PE audits finished project
14. Step 1: Apply
Download and complete an Application
Form (Excel workbook)
Write a description of what you’re
proposing
For each Measure in Project…
Describe (with support docs)
Estimate Demand and Energy for before and
after
Describe M&V Plan
15. Step 2: PM Screen
• Application to Program Management
(PM)
• PM checks for…
– Complete?
– Eligible?
– Support docs?
• Incomplete? Back to Applicant
16. Step 3: GG and PA
• Application Documentation OK?
– Applicant purchases GoGreen Tool,
submits GoGreen survey
– PM customizes Participant Agreement;
signed by applicant and BOMA
THEN…
17. Step 4: Application Approved
…PM assigns to a Project Evaluator
There are 3 PEs:
• Energy engineering firms
• Measurement & Verification experts
• Impartial
• Key to incentive payment when you
want it - at the conclusion of the Project
18. Step 4 (cont’d): Evaluate and
Audit
• Project Evaluator –
– Confirms M&V Plan
– Certifies all documents
– Checks all calculations and assumptions
– Conducts pre-Project audit
– Comes to agreement with Participant on
eligible savings
AND…
– Advance Evaluation and Incentive Report
is signed
20. Step 6: Post-Project Audit
On completion of the Project…
• Project Evaluator audits Project,
oversees M&V activities
• Non-compliant? PE writes up
variances, terms of compliance
negotiated
• Complete and in compliance? Final
Evaluation and Incentive Report is
signed
21. Step 7: Incentive Cheque OPA
to Applicants
• PM sends “Project Complete” to OPA
• OPA sends incentive cheque to
Applicant
22. What’s the Status?
• As of 1 March 2007, the BOMA Toronto
CDM Program has been receiving
applications
• 30 approved applications to date for
over 5 MW of demand reduction
• Up-to-date Program info available at
www.bomatoronto.org
23. Resources
www.bomacdm.com, for these files…
– CDM Program Application Form
– Official Program Rules
– Participant Agreement
– Frequently Asked Questions
– Measurement and Verification Procedures
– Go Green Registration Guide
– CDM Contacts
– GO Green Application
– GO Green Login
24. Audience: Please…
• Become knowledgeable about the
Program
– Get up to speed on GoGreen
– Go to BOMA’s website, download Program
guides and application form
– Communicate the Program to your
operations and financial groups – and to
your suppliers
• Review back-burnered projects
25. In conclusion…
OPA and BOMA will deliver a commercial
building incentive Program that
balances
Speed & Clarity
Against
Proven value to ratepayers