SlideShare a Scribd company logo
1 of 6
REQUIREMENTS MANAGEMENT PLAN
Purpose
This document defines the systematic approach by which
Corwin Corporation manages requirements when undertaking a
new project. The requirements management system establishes
the guidelines for creating requirements documents, setting
requirements attributes, and managing traceability of the
requirements. This document also details the process by which
requirements can be changed during the project, ensuring
agreement between internal teams and customers. This
document uses established Corwin Corporation standard work to
define the Requirements Management Plan for use in the Peters
Company project.
Requirements
Requirements Planning
Initial requirements for the Peters Project were obtained
through a series of phone call interactions between Gene
Frimel, Vice-President of Engineering at Corwin Corporation
and Frank Delia, Vice-President of Marketing at the Peters
Company. The detailed requirements were provided in the
Statement of Work sent by Peters. Further requirements,
including an initial engineering test matrix, were included in the
proposal returned by Corwin. At a minimum, the remainder of
the test matrix is an outstanding requirement that will be
completed later, following the procedures laid out in this
document. Other requirements may also arise that will be added
as well.
Requirements Tracking
Because this is a research project with a short turnaround time,
it is anticipated that changes will be made rapidly, including
changes to the requirements. For this reason, it is imperative
that the requirements, and changes thereto, be tracked carefully.
To ensure all members of the team are aware of the changing
requirements, all must be documented in writing. It is
anticipated that most of the requirements will be defined by the
Statement of Work, but additional requirements or further detail
of the initial requirements must be captured in a Coordination
Memo or notes from a Requirement Change Review. Corwin
Corporation will vault these documents to its Product Lifecycle
Management (PLM) software with the appropriate revision
letter. Changes or revisions to the requirements documents must
follow the change process, detailed below. Following an
approved change, the Statement of Work will be updated, and
the Revision rolled to the next number.
Requirements Reporting
As part of this project, Corwin Corporation and Peters Company
will hold weekly meetings, wherein Status Reports will be
provided that cover any significant changes made to the
requirements. Since this is a fast-paced project and Peters will
have an on-site representative, it is recognized that
requirements may change more rapidly than on a weekly basis.
However, it is the Corwin project manager’s responsibility to
document any changes and formally report them out in the
weekly status reports. These will be submitted to Corwin and
Peters management, so the project progress can be monitored.
Configuration Management
Change Initiation
After the Statement of Work and the Project Plan have been
approved by both companies and vaulted to be stored in the
PLM, any changes to the requirements must follow the change
management process (see Figure 1). As mentioned above, the
change request must be documented in a Coordination Memo to
ensure traceability of the change.
Receive Change Request
Baseline Scope
Review Change Request
Assess Impact
Determine Decision
Update Documentation
Change Impact Analysis
The proposed change must be reviewed by the Corwin and
Peters project managers/on-site representative, as well as a
member of Corwin Corporation management. The assessment of
the impact of the change must be provided, and consider the
following factors:
· Technical impact on product formulation, material
specifications, bills of materials, technical documents, design
documents, project documents
· Technical work to be done by engineers
· Documentation to be updated
· Meetings to be conducted
· Impacts on the project schedule and other impacted tasks
· Impact on the project budget
· Quality management work to ensure change is documented and
approved
· Cost of assessing the change request
Change Authorization Levels
As stated above, the review team must include representatives
from both Corwin and Peters, as well as a member of Corwin
Corporation management. Technical changes should include Dr.
Royce, the VP of Engineering, while programmatic or financial
changes should include Gene Frimel, the VP of Marketing. The
review team must agree to change the requirements; otherwise
the requirements revert to those previously established, through
Statement of Work and/or other agreed-upon changes.
Requirements Traceability
Given the relatively high likelihood that requirements may
change, the following plan will be implemented to ensure
traceability of the changes. These procedures will vary slightly
depending on the type of item being changed.
Documents, primarily specifications, will have a revision letter
on the title page of each document. The main storage location
for specifications and other project documents will be within
the Corwin Corporation PLM system. This system has the
ability to vault and store current and former versions of each
document, so a revision history will be available following the
changes.
This project also incorporates physical items, such as test
specimens and rubber formulations. These will also require
traceability. This will be done through the use of unique part
numbersfor each formula/sample. The samples themselves will
be kept in locked storage cabinets in the laboratory so the
unique formula for each can be maintained.
The project manager shall have control over revising all
documents. Engineering staff will maintain the samples in the
engineering lab.
Requirements Prioritization Process
If a product formulation cannot be found to meet all the
requirements, it may be necessary to select a product that meets
only some. In anticipation of this scenario, all requirements
shall be prioritized based on the following model:
· Must Have – means failure to implement the requirement will
result in the failure of the entire project.
· Should Have – important requirements, but failure to
implement the requirement does not automatically imply failure
of the project.
· Nice to Have – A desirable but not extremely important
requirement
Prioritization of the requirements will be done in a collaborative
manner between Corwin and Peters. It is anticipated this will be
done in the form of an event at Corwin Corporation. The project
teams from Corwin and Peters, as well as the appropriate
members of management, shall work through the requirements
and prioritize them together. At the end of this event, all
requirements will be prioritized; changes to priority level must
go through the requirement change procedure outlined above.
Product Metrics
A significant risk in undertaking a project such as this with
incomplete requirements is the possibility of getting into an
infinite loop of design iterations. If the requirements are
changed during the design process, all the progress toward the
initial requirements will be wasted. With the project set up to a
fixed budget, Corwin Corporation is particularly sensitive to
this occurring. Therefore, the metrics to be used will be a
combination of technical metrics to the rubber formulation, and
project metrics to ensure progress toward a defined set of
requirements. These shall include the following:
· Temperature Range (degrees C
· Hardness (Shore A)
· Max Compression Set (%)
· Min Tear Resistance (kg/cm)
· Min Tensile Strength (MPa)
· Color
These are the categories for the high-level requirements for the
product. Tracking progress toward the desired ranges allows
Corwin to understand how close they are to an acceptable
formulation. Other metrics will include:
· Test iterations (25 allotted in Statement of Work)
· Labor hours invested in project (impacts budget)
· Progress to Milestones A, B, C vs schedule
· Estimated material production cost for current formulation
· Estimated production yield – failures per million parts
These metrics will track any instances of scope creep in test
iterations, budget or schedule. Additionally, these metrics are
forward-looking to the anticipated 5-year production run with
the Peters Company to ensure long-term profitability of the
design. Not only must the current project remain on schedule
and under budget, but the eventual production run must be
anticipated to be profitable or the research program was
unsuccessful.

More Related Content

Similar to REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx

Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxsmile790243
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1reddvise
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptxZiyad Zaidi
 
Essentials of Validation Project Management - Part 1
Essentials of Validation Project Management - Part 1Essentials of Validation Project Management - Part 1
Essentials of Validation Project Management - Part 1William Garvey and Associates
 
Requirements management-plan template
Requirements management-plan templateRequirements management-plan template
Requirements management-plan templateVivek Srivastava
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
Template quality management-plan2
Template quality management-plan2Template quality management-plan2
Template quality management-plan2I C
 
CaseStudy_MOC_PX_2015_LI
CaseStudy_MOC_PX_2015_LICaseStudy_MOC_PX_2015_LI
CaseStudy_MOC_PX_2015_LISean Cull
 
Software configuration management
Software configuration managementSoftware configuration management
Software configuration managementShivani Garg
 
Project qulaity initiative report
Project qulaity  initiative reportProject qulaity  initiative report
Project qulaity initiative reportAbdullaHaneefa
 
Quality_Management_Plan Template.docx
Quality_Management_Plan Template.docxQuality_Management_Plan Template.docx
Quality_Management_Plan Template.docxZiyad Zaidi
 
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...SN Panigrahi, PMP
 
www.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docxwww.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docxericbrooks84875
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measuresPavan Kumar
 

Similar to REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx (20)

Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
 
Qa qc-waste unit4
Qa qc-waste unit4Qa qc-waste unit4
Qa qc-waste unit4
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptx
 
Ray-Goodfellow.ppt
Ray-Goodfellow.pptRay-Goodfellow.ppt
Ray-Goodfellow.ppt
 
Essentials of Validation Project Management - Part 1
Essentials of Validation Project Management - Part 1Essentials of Validation Project Management - Part 1
Essentials of Validation Project Management - Part 1
 
Requirements management-plan template
Requirements management-plan templateRequirements management-plan template
Requirements management-plan template
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Template quality management-plan2
Template quality management-plan2Template quality management-plan2
Template quality management-plan2
 
CaseStudy_MOC_PX_2015_LI
CaseStudy_MOC_PX_2015_LICaseStudy_MOC_PX_2015_LI
CaseStudy_MOC_PX_2015_LI
 
Software configuration management
Software configuration managementSoftware configuration management
Software configuration management
 
Project qulaity initiative report
Project qulaity  initiative reportProject qulaity  initiative report
Project qulaity initiative report
 
Quality_Management_Plan Template.docx
Quality_Management_Plan Template.docxQuality_Management_Plan Template.docx
Quality_Management_Plan Template.docx
 
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
ETCA_4
ETCA_4ETCA_4
ETCA_4
 
How the change control process affects project quality
How the change control process affects project qualityHow the change control process affects project quality
How the change control process affects project quality
 
www.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docxwww.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docx
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measures
 

More from heunice

RequirementsMicrosoft Project is the recommended software tool f.docx
RequirementsMicrosoft Project is the recommended software tool f.docxRequirementsMicrosoft Project is the recommended software tool f.docx
RequirementsMicrosoft Project is the recommended software tool f.docxheunice
 
REQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docx
REQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docxREQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docx
REQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docxheunice
 
RequirementsOutlineIntended AudienceIdentif.docx
RequirementsOutlineIntended AudienceIdentif.docxRequirementsOutlineIntended AudienceIdentif.docx
RequirementsOutlineIntended AudienceIdentif.docxheunice
 
REQUIREMENTSIntroductionIntroduction includesthe.docx
REQUIREMENTSIntroductionIntroduction includesthe.docxREQUIREMENTSIntroductionIntroduction includesthe.docx
REQUIREMENTSIntroductionIntroduction includesthe.docxheunice
 
requirementslength-3pages longfont- 10or11space- double spacin.docx
requirementslength-3pages longfont- 10or11space- double spacin.docxrequirementslength-3pages longfont- 10or11space- double spacin.docx
requirementslength-3pages longfont- 10or11space- double spacin.docxheunice
 
REQUIREMENTSIntroductionIntroduction includesthe· P.docx
REQUIREMENTSIntroductionIntroduction includesthe· P.docxREQUIREMENTSIntroductionIntroduction includesthe· P.docx
REQUIREMENTSIntroductionIntroduction includesthe· P.docxheunice
 
RequirementsDevelop a formal Teaching Plan for a target audi.docx
RequirementsDevelop a formal Teaching Plan for a target audi.docxRequirementsDevelop a formal Teaching Plan for a target audi.docx
RequirementsDevelop a formal Teaching Plan for a target audi.docxheunice
 
RequirementsIf the student cannot attend the Intensive review, .docx
RequirementsIf the student cannot attend the Intensive review, .docxRequirementsIf the student cannot attend the Intensive review, .docx
RequirementsIf the student cannot attend the Intensive review, .docxheunice
 
RequirementsContent Craft an e-mail message that.docx
RequirementsContent    Craft an e-mail message that.docxRequirementsContent    Craft an e-mail message that.docx
RequirementsContent Craft an e-mail message that.docxheunice
 
REQUIREMENTSexternal environmentA. Natural environment.docx
REQUIREMENTSexternal environmentA. Natural environment.docxREQUIREMENTSexternal environmentA. Natural environment.docx
REQUIREMENTSexternal environmentA. Natural environment.docxheunice
 
Requirements1. Using a patient seen in their clinical setting, .docx
Requirements1. Using a patient seen in their clinical setting, .docxRequirements1. Using a patient seen in their clinical setting, .docx
Requirements1. Using a patient seen in their clinical setting, .docxheunice
 
REQUIREMENTSAs outlined in the Syllabus on Blackboard .docx
REQUIREMENTSAs outlined in the Syllabus on Blackboard .docxREQUIREMENTSAs outlined in the Syllabus on Blackboard .docx
REQUIREMENTSAs outlined in the Syllabus on Blackboard .docxheunice
 
RequirementsAll writing must be appropriate for an academi.docx
RequirementsAll writing must be appropriate for an academi.docxRequirementsAll writing must be appropriate for an academi.docx
RequirementsAll writing must be appropriate for an academi.docxheunice
 
RequirementsAllow users to login to the siteAllow users t.docx
RequirementsAllow users to login to the siteAllow users t.docxRequirementsAllow users to login to the siteAllow users t.docx
RequirementsAllow users to login to the siteAllow users t.docxheunice
 
RequirementsAfter completion of the Nurse Executive CGE Proj.docx
RequirementsAfter completion of the Nurse Executive CGE Proj.docxRequirementsAfter completion of the Nurse Executive CGE Proj.docx
RequirementsAfter completion of the Nurse Executive CGE Proj.docxheunice
 
Requirements1.Length of paper – 2 pages of content (excl.docx
Requirements1.Length of paper – 2 pages of content (excl.docxRequirements1.Length of paper – 2 pages of content (excl.docx
Requirements1.Length of paper – 2 pages of content (excl.docxheunice
 
Requirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docx
Requirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docxRequirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docx
Requirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docxheunice
 
Requirements1) Length of the paper 4-5 pages, double space.docx
Requirements1) Length of the paper 4-5 pages, double space.docxRequirements1) Length of the paper 4-5 pages, double space.docx
Requirements1) Length of the paper 4-5 pages, double space.docxheunice
 
Requirements- Combining several essays into 1 research paper.- .docx
Requirements- Combining several essays into 1 research paper.- .docxRequirements- Combining several essays into 1 research paper.- .docx
Requirements- Combining several essays into 1 research paper.- .docxheunice
 
Requirements of this assignment1) Watch a TED Talk. or an.docx
Requirements of this assignment1) Watch a TED Talk. or an.docxRequirements of this assignment1) Watch a TED Talk. or an.docx
Requirements of this assignment1) Watch a TED Talk. or an.docxheunice
 

More from heunice (20)

RequirementsMicrosoft Project is the recommended software tool f.docx
RequirementsMicrosoft Project is the recommended software tool f.docxRequirementsMicrosoft Project is the recommended software tool f.docx
RequirementsMicrosoft Project is the recommended software tool f.docx
 
REQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docx
REQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docxREQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docx
REQUIREMENTSPart 1 5-page Research paper consisting of 6 parts .docx
 
RequirementsOutlineIntended AudienceIdentif.docx
RequirementsOutlineIntended AudienceIdentif.docxRequirementsOutlineIntended AudienceIdentif.docx
RequirementsOutlineIntended AudienceIdentif.docx
 
REQUIREMENTSIntroductionIntroduction includesthe.docx
REQUIREMENTSIntroductionIntroduction includesthe.docxREQUIREMENTSIntroductionIntroduction includesthe.docx
REQUIREMENTSIntroductionIntroduction includesthe.docx
 
requirementslength-3pages longfont- 10or11space- double spacin.docx
requirementslength-3pages longfont- 10or11space- double spacin.docxrequirementslength-3pages longfont- 10or11space- double spacin.docx
requirementslength-3pages longfont- 10or11space- double spacin.docx
 
REQUIREMENTSIntroductionIntroduction includesthe· P.docx
REQUIREMENTSIntroductionIntroduction includesthe· P.docxREQUIREMENTSIntroductionIntroduction includesthe· P.docx
REQUIREMENTSIntroductionIntroduction includesthe· P.docx
 
RequirementsDevelop a formal Teaching Plan for a target audi.docx
RequirementsDevelop a formal Teaching Plan for a target audi.docxRequirementsDevelop a formal Teaching Plan for a target audi.docx
RequirementsDevelop a formal Teaching Plan for a target audi.docx
 
RequirementsIf the student cannot attend the Intensive review, .docx
RequirementsIf the student cannot attend the Intensive review, .docxRequirementsIf the student cannot attend the Intensive review, .docx
RequirementsIf the student cannot attend the Intensive review, .docx
 
RequirementsContent Craft an e-mail message that.docx
RequirementsContent    Craft an e-mail message that.docxRequirementsContent    Craft an e-mail message that.docx
RequirementsContent Craft an e-mail message that.docx
 
REQUIREMENTSexternal environmentA. Natural environment.docx
REQUIREMENTSexternal environmentA. Natural environment.docxREQUIREMENTSexternal environmentA. Natural environment.docx
REQUIREMENTSexternal environmentA. Natural environment.docx
 
Requirements1. Using a patient seen in their clinical setting, .docx
Requirements1. Using a patient seen in their clinical setting, .docxRequirements1. Using a patient seen in their clinical setting, .docx
Requirements1. Using a patient seen in their clinical setting, .docx
 
REQUIREMENTSAs outlined in the Syllabus on Blackboard .docx
REQUIREMENTSAs outlined in the Syllabus on Blackboard .docxREQUIREMENTSAs outlined in the Syllabus on Blackboard .docx
REQUIREMENTSAs outlined in the Syllabus on Blackboard .docx
 
RequirementsAll writing must be appropriate for an academi.docx
RequirementsAll writing must be appropriate for an academi.docxRequirementsAll writing must be appropriate for an academi.docx
RequirementsAll writing must be appropriate for an academi.docx
 
RequirementsAllow users to login to the siteAllow users t.docx
RequirementsAllow users to login to the siteAllow users t.docxRequirementsAllow users to login to the siteAllow users t.docx
RequirementsAllow users to login to the siteAllow users t.docx
 
RequirementsAfter completion of the Nurse Executive CGE Proj.docx
RequirementsAfter completion of the Nurse Executive CGE Proj.docxRequirementsAfter completion of the Nurse Executive CGE Proj.docx
RequirementsAfter completion of the Nurse Executive CGE Proj.docx
 
Requirements1.Length of paper – 2 pages of content (excl.docx
Requirements1.Length of paper – 2 pages of content (excl.docxRequirements1.Length of paper – 2 pages of content (excl.docx
Requirements1.Length of paper – 2 pages of content (excl.docx
 
Requirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docx
Requirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docxRequirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docx
Requirements1) Due 6 Oct2) APA 6th Ed format3) 6 Pages.docx
 
Requirements1) Length of the paper 4-5 pages, double space.docx
Requirements1) Length of the paper 4-5 pages, double space.docxRequirements1) Length of the paper 4-5 pages, double space.docx
Requirements1) Length of the paper 4-5 pages, double space.docx
 
Requirements- Combining several essays into 1 research paper.- .docx
Requirements- Combining several essays into 1 research paper.- .docxRequirements- Combining several essays into 1 research paper.- .docx
Requirements- Combining several essays into 1 research paper.- .docx
 
Requirements of this assignment1) Watch a TED Talk. or an.docx
Requirements of this assignment1) Watch a TED Talk. or an.docxRequirements of this assignment1) Watch a TED Talk. or an.docx
Requirements of this assignment1) Watch a TED Talk. or an.docx
 

Recently uploaded

BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 

Recently uploaded (20)

INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 

REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx

  • 1. REQUIREMENTS MANAGEMENT PLAN Purpose This document defines the systematic approach by which Corwin Corporation manages requirements when undertaking a new project. The requirements management system establishes the guidelines for creating requirements documents, setting requirements attributes, and managing traceability of the requirements. This document also details the process by which requirements can be changed during the project, ensuring agreement between internal teams and customers. This document uses established Corwin Corporation standard work to define the Requirements Management Plan for use in the Peters Company project. Requirements Requirements Planning Initial requirements for the Peters Project were obtained through a series of phone call interactions between Gene Frimel, Vice-President of Engineering at Corwin Corporation and Frank Delia, Vice-President of Marketing at the Peters Company. The detailed requirements were provided in the Statement of Work sent by Peters. Further requirements, including an initial engineering test matrix, were included in the proposal returned by Corwin. At a minimum, the remainder of the test matrix is an outstanding requirement that will be completed later, following the procedures laid out in this document. Other requirements may also arise that will be added as well. Requirements Tracking Because this is a research project with a short turnaround time, it is anticipated that changes will be made rapidly, including changes to the requirements. For this reason, it is imperative that the requirements, and changes thereto, be tracked carefully. To ensure all members of the team are aware of the changing
  • 2. requirements, all must be documented in writing. It is anticipated that most of the requirements will be defined by the Statement of Work, but additional requirements or further detail of the initial requirements must be captured in a Coordination Memo or notes from a Requirement Change Review. Corwin Corporation will vault these documents to its Product Lifecycle Management (PLM) software with the appropriate revision letter. Changes or revisions to the requirements documents must follow the change process, detailed below. Following an approved change, the Statement of Work will be updated, and the Revision rolled to the next number. Requirements Reporting As part of this project, Corwin Corporation and Peters Company will hold weekly meetings, wherein Status Reports will be provided that cover any significant changes made to the requirements. Since this is a fast-paced project and Peters will have an on-site representative, it is recognized that requirements may change more rapidly than on a weekly basis. However, it is the Corwin project manager’s responsibility to document any changes and formally report them out in the weekly status reports. These will be submitted to Corwin and Peters management, so the project progress can be monitored. Configuration Management Change Initiation After the Statement of Work and the Project Plan have been approved by both companies and vaulted to be stored in the PLM, any changes to the requirements must follow the change management process (see Figure 1). As mentioned above, the change request must be documented in a Coordination Memo to ensure traceability of the change.
  • 3. Receive Change Request Baseline Scope Review Change Request Assess Impact Determine Decision Update Documentation Change Impact Analysis The proposed change must be reviewed by the Corwin and Peters project managers/on-site representative, as well as a member of Corwin Corporation management. The assessment of the impact of the change must be provided, and consider the following factors: · Technical impact on product formulation, material specifications, bills of materials, technical documents, design documents, project documents · Technical work to be done by engineers · Documentation to be updated · Meetings to be conducted · Impacts on the project schedule and other impacted tasks · Impact on the project budget · Quality management work to ensure change is documented and approved · Cost of assessing the change request Change Authorization Levels As stated above, the review team must include representatives from both Corwin and Peters, as well as a member of Corwin Corporation management. Technical changes should include Dr. Royce, the VP of Engineering, while programmatic or financial changes should include Gene Frimel, the VP of Marketing. The review team must agree to change the requirements; otherwise the requirements revert to those previously established, through Statement of Work and/or other agreed-upon changes.
  • 4. Requirements Traceability Given the relatively high likelihood that requirements may change, the following plan will be implemented to ensure traceability of the changes. These procedures will vary slightly depending on the type of item being changed. Documents, primarily specifications, will have a revision letter on the title page of each document. The main storage location for specifications and other project documents will be within the Corwin Corporation PLM system. This system has the ability to vault and store current and former versions of each document, so a revision history will be available following the changes. This project also incorporates physical items, such as test specimens and rubber formulations. These will also require traceability. This will be done through the use of unique part numbersfor each formula/sample. The samples themselves will be kept in locked storage cabinets in the laboratory so the unique formula for each can be maintained. The project manager shall have control over revising all documents. Engineering staff will maintain the samples in the engineering lab. Requirements Prioritization Process If a product formulation cannot be found to meet all the requirements, it may be necessary to select a product that meets only some. In anticipation of this scenario, all requirements shall be prioritized based on the following model: · Must Have – means failure to implement the requirement will result in the failure of the entire project. · Should Have – important requirements, but failure to implement the requirement does not automatically imply failure of the project. · Nice to Have – A desirable but not extremely important requirement Prioritization of the requirements will be done in a collaborative manner between Corwin and Peters. It is anticipated this will be
  • 5. done in the form of an event at Corwin Corporation. The project teams from Corwin and Peters, as well as the appropriate members of management, shall work through the requirements and prioritize them together. At the end of this event, all requirements will be prioritized; changes to priority level must go through the requirement change procedure outlined above. Product Metrics A significant risk in undertaking a project such as this with incomplete requirements is the possibility of getting into an infinite loop of design iterations. If the requirements are changed during the design process, all the progress toward the initial requirements will be wasted. With the project set up to a fixed budget, Corwin Corporation is particularly sensitive to this occurring. Therefore, the metrics to be used will be a combination of technical metrics to the rubber formulation, and project metrics to ensure progress toward a defined set of requirements. These shall include the following: · Temperature Range (degrees C · Hardness (Shore A) · Max Compression Set (%) · Min Tear Resistance (kg/cm) · Min Tensile Strength (MPa) · Color These are the categories for the high-level requirements for the product. Tracking progress toward the desired ranges allows Corwin to understand how close they are to an acceptable formulation. Other metrics will include: · Test iterations (25 allotted in Statement of Work) · Labor hours invested in project (impacts budget) · Progress to Milestones A, B, C vs schedule · Estimated material production cost for current formulation · Estimated production yield – failures per million parts These metrics will track any instances of scope creep in test
  • 6. iterations, budget or schedule. Additionally, these metrics are forward-looking to the anticipated 5-year production run with the Peters Company to ensure long-term profitability of the design. Not only must the current project remain on schedule and under budget, but the eventual production run must be anticipated to be profitable or the research program was unsuccessful.