SlideShare a Scribd company logo
1 of 12
PRODUCTIVITY
IMPROVEMENT
OF PRE-TREATMENT &
POWDER COATING
PROCESS.
Department of Engineering & Technology.
Manufacturing Engineering Foundation Degree.
WORKED - BASED PROJECT (BMCF507)
BY RAHEEM ARIF
27/05/2018
Objective
 In the following table we have presented designed capacity and
production with efficiency of 85% & 90%. The designed capacity is based
on individual process time of the workstations. In these workstations we
have deleted on line inspection work stations because of their higher
capacity.
Workstation Coiling &
powder
coating
processes
Designed
capacity
Production
with 85%
efficiency
Production
with 90%
efficiency
Average
Ws2 Cold coiling 468000 397800 421200 4.1
Ws3 Stress relief 409500 348075 368550 3.6
Ws4 Warm
peening
468000 397800 421200 4.1
Ws5 Pre-setting 468000 397800 421200 4.1
Ws6 Stress
peening
468000 397800 421200 4.1
Ws7 Laser
marking
468000 397800 421200 4.1
Ws9 Pre-
treatment
234000 198900 210600 2.0
Ws10 Powder
coating
234000 198900 210600 2.0
Ws11 Sc ragging 468000 379800 421200 4.1
Ws12 Colour
marking
468000 379800 421200 4.1
Table 5.3 the production capacity of workstations per month
 The average production at 87.5% efficiency is taken for presentation. In the
last column we observed that the production capacity of workstation
except pre-treatment and powder coating is higher than the consolidated
demand of 330.000 per month. Therefore we needed to improve the
capacity of these two workstation in order to improve the whole line. The
following figure shows production capacity and demand line. To fulfil the
shortfall we have proposed improvement in these two bottleneck
workstation. We have already started that there are 14 workstations in the
suspension spring line. Out of these 4 devoted for inspection which is
carried out on line. In the remaining 10 workstation the production of 8
stations at 87.5% efficiency is more than demand. Only two workstations
namely WS9: pre-treatment and WS10: powder coating are bottleneck.
Therefore our scope is limited to the improvement in the process related
to these two bottleneck workstation. In this project we are going to
change the design of the hangers in order to accommodate more jobs.
 Method:
 Examine and observe the functioning of the modified process for one
month, record data mainly production schedules and consumptions that
have been used.
 To implement the recommendations in the periods of one month after
approval of production before and after.
 Data, resources, equipment, materials & software that we will be using.
 Welding, cutting & bending- For spacer bar, end cap, hanger rod is carried
out. Final drawing of new hanger with details
 Obtaining material required for hangers.
 3 processes will be required Cutting, Bending & Welding.
 Arc welding, tools & machinery
 Alignment for spray guns for new hangers
 Each recommendation will be explained in detail. The following primary data is
maintained for the purpose of the project
 Primary data-
 Consumption of electricity, LPG, Demineralized water and industrial water after
implementation of project. (as this could increase)
 Production of suspension springs after modification.
 Secondary data:
 We have collected this data from the company for this. The following
secondary data has been incorporated in this project.
 Secondary data-
 Workstation capacity
 Production in three shifts and net available time for production (production
department).
 Present and future demand of the suspension springs.
 Production scenario for the period of 10 month i.e. from April 2017 to Jan
2018.
Achievements:
 Test procedure
 At first the trial on eight modified hangers has been carried out. After
inspecting quality of the powder coating it is then extended to all hangers.
This project doesn’t increase the speed of the powder coating or
additional unit. It proposes design of the existing system to some extent.
The additional unit will costly affair and it is beyond scope of this project.
However it revisits existing process parameters for improving effectiveness
is considered in this project. Instead of 4 jobs now the line is 8 jobs at a
time accordingly some modification in the parameters such as speed,
phosphating and nozzles are necessary. Necessary trial and errors of the
same have been conducted to make a final decision.
 The powder coating process is now carrying out in three shifts every day.
The net times available for the production is 1170 minutes as before. We
have not worked on improving the idle time. The improvements in the
input level in a specific time (cycle time) has brought the result. In the first
and second shift about same quantity of jobs are processed: Where as in
third shift 80% jobs are processed. In the may2018 we have produced
328000 springs are produced. This is about 12600 springs are processed
per day. The plant is operating for 26 days in this month. Now here we are
presenting consumption of resources for the powder coating both before
and after implementation of project. Various resources are electricity, LPG
(Kg), Demineralized water (Kilo litre), Industrial water (Kilo Litre) and
chemicals (in litre). This is presented to analyse the consumption of their
resources (consumables). Here we are going to present summary of the
data before and after implementation of the project. However it is noticed
that the consumption of all these resources are increased in the
production level.
Date Working Days Electricity LPG(Kg) DM water-KL Industrial water-KL
Mar-18 27 146293 4760 170.9 124.2
Apr-18 25 136294 4378 159.3 114.2
May-18 26 139841 4555 166.2 119.5
Consumption of process resources (After)
Date Working days Electricity (Kwh) LPG(Kg) DM water-KL Industrial water-KL
Apr-17 26 124835 3730 125.4 84.4
May-17 25 122923 3726 124.5 82.7
June-17 26 128546 3883 130 87.7
July -17 27 134515 4025 134.4 90.9
Aug-17 26 129877 3898 130 88.2
Sep-17 26 123555 3738 134.4 85.5
Oct-17 27 132555 4046 130.2 90.6
Nov-17 25 132633 3737 124.5 83.6
Dec-17 27 132975 4071 134.4 90.9
Average 128315 3873 129.1 87.2
Consumption of process resources (Before)
 On the job training is given to operators especially for loading and
unloading purposes. The unloading spring rate is now increased by 65%of
the previous. The operator has to unload double springs in 20% more time
of the previous. Similar synchronization of loading by first and second
operator is also important. The conveyor speed cannot be changed or
stopped for loading and unloading purposes. Two operator are moving to
the entire length to and from for observing the powder coating process.
They are informed about changed parameters and the logic behind it. No
one is allowed to change the setting without permission. The consumption
of chemical, epoxy powder, coverage of area and monitoring on
consumption are informed. The in charge of powder coating line was part
of the hence he is also involved in training. New sufficient to them for
working according to revised instructions.
 Final Evaluation
 In this section we have described how we have monitored the overall
process of execution of project, our five members have acted alternatively
on the supervision of the progress. Maintained, production, store
department and quality personnel were involved in the project. Duties of
each member were well defined previously and approved. The time for
execution. Of the project and activities needed to be carried out are
mentioned in the project. I was responsible for data collection, analysis
supervision on carrying out correctives actions.
 After positive results of the quality department our work started
confidently. The responsibility of the powder coating in-line charge to
monitor the process whether it is running as per present norms or not.
quality department checks quality of the coating which is an indication of
the process is under control. The training is given to six employee
out observation of the process throughout the line and responsible for
setting.
Thank you for listening.

More Related Content

What's hot

Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)Ashok Yadav
 
20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelec20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelecSirris
 
Girouard.joseph.resume.v5
Girouard.joseph.resume.v5Girouard.joseph.resume.v5
Girouard.joseph.resume.v5Joseph Girouard
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plantNihar Routray
 
Case Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsCase Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsKoch Modular Process Systems, LLC.
 
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
 
Sr. Ammonia Process Engineer's CV
Sr. Ammonia Process Engineer's CVSr. Ammonia Process Engineer's CV
Sr. Ammonia Process Engineer's CVMohamed Abosereei
 
Cfd03 thermal analysis-of-automotive-lumax
Cfd03 thermal analysis-of-automotive-lumaxCfd03 thermal analysis-of-automotive-lumax
Cfd03 thermal analysis-of-automotive-lumaxAnand Kumar Chinni
 
A-Umar Saeed-Nestle Summer Associate Program-2014
A-Umar Saeed-Nestle Summer Associate Program-2014A-Umar Saeed-Nestle Summer Associate Program-2014
A-Umar Saeed-Nestle Summer Associate Program-2014Umar Saeed
 
Koch Modular's CURT (Construction Users Round Table) Presentation
Koch Modular's CURT (Construction Users Round Table) PresentationKoch Modular's CURT (Construction Users Round Table) Presentation
Koch Modular's CURT (Construction Users Round Table) PresentationKoch Modular Process Systems, LLC.
 

What's hot (20)

NEW MRP CV 2016
NEW MRP CV 2016NEW MRP CV 2016
NEW MRP CV 2016
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
 
Purushothaman K 3+ years exp. In QMS
Purushothaman K 3+ years exp. In QMSPurushothaman K 3+ years exp. In QMS
Purushothaman K 3+ years exp. In QMS
 
crkline_resume
crkline_resumecrkline_resume
crkline_resume
 
20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelec20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelec
 
Analytical Balance by ACMAS Technologies Pvt Ltd.
Analytical Balance by ACMAS Technologies Pvt Ltd.Analytical Balance by ACMAS Technologies Pvt Ltd.
Analytical Balance by ACMAS Technologies Pvt Ltd.
 
Final TEAM SLIDE PRESENTATION (1)
Final TEAM  SLIDE PRESENTATION (1)Final TEAM  SLIDE PRESENTATION (1)
Final TEAM SLIDE PRESENTATION (1)
 
Mohit chaudhary link
Mohit chaudhary linkMohit chaudhary link
Mohit chaudhary link
 
Girouard.joseph.resume.v5
Girouard.joseph.resume.v5Girouard.joseph.resume.v5
Girouard.joseph.resume.v5
 
khaled-2
khaled-2khaled-2
khaled-2
 
DKSHAH RESUME
DKSHAH RESUMEDKSHAH RESUME
DKSHAH RESUME
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plant
 
Case Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsCase Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent Solvents
 
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
 
Sr. Ammonia Process Engineer's CV
Sr. Ammonia Process Engineer's CVSr. Ammonia Process Engineer's CV
Sr. Ammonia Process Engineer's CV
 
Cfd03 thermal analysis-of-automotive-lumax
Cfd03 thermal analysis-of-automotive-lumaxCfd03 thermal analysis-of-automotive-lumax
Cfd03 thermal analysis-of-automotive-lumax
 
Mohammed vasil k.
Mohammed vasil k.Mohammed vasil k.
Mohammed vasil k.
 
A-Umar Saeed-Nestle Summer Associate Program-2014
A-Umar Saeed-Nestle Summer Associate Program-2014A-Umar Saeed-Nestle Summer Associate Program-2014
A-Umar Saeed-Nestle Summer Associate Program-2014
 
Ravi-LPG
Ravi-LPGRavi-LPG
Ravi-LPG
 
Koch Modular's CURT (Construction Users Round Table) Presentation
Koch Modular's CURT (Construction Users Round Table) PresentationKoch Modular's CURT (Construction Users Round Table) Presentation
Koch Modular's CURT (Construction Users Round Table) Presentation
 

Similar to PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.

Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industryGanesh TN
 
Presntation (MNIT).pptx
Presntation (MNIT).pptxPresntation (MNIT).pptx
Presntation (MNIT).pptxrajtashee725
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET Journal
 
updated resume yathesh 18.09.2016
updated resume yathesh 18.09.2016updated resume yathesh 18.09.2016
updated resume yathesh 18.09.2016Yatheesh J R
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternIRJET Journal
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET Journal
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringIJECSJournal
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation ProjectChawal Ukesh
 
project report - COMPLETE
project report - COMPLETEproject report - COMPLETE
project report - COMPLETEAmit Verma
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...IRJET Journal
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docxhyacinthshackley2629
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
 

Similar to PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS. (20)

Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Presntation (MNIT).pptx
Presntation (MNIT).pptxPresntation (MNIT).pptx
Presntation (MNIT).pptx
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
 
updated resume yathesh 18.09.2016
updated resume yathesh 18.09.2016updated resume yathesh 18.09.2016
updated resume yathesh 18.09.2016
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and Pattern
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
 
Rajesh mba resume - dubai
Rajesh mba resume - dubaiRajesh mba resume - dubai
Rajesh mba resume - dubai
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation Project
 
CV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMACV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMA
 
project report - COMPLETE
project report - COMPLETEproject report - COMPLETE
project report - COMPLETE
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Steve Mutch
Steve MutchSteve Mutch
Steve Mutch
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
vijay cv
vijay cvvijay cv
vijay cv
 
CV-cassidy
CV-cassidyCV-cassidy
CV-cassidy
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
 
Resume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnamResume rahul iyer jan 2014 vietnam
Resume rahul iyer jan 2014 vietnam
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 

Recently uploaded

Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 

Recently uploaded (20)

Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 

PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.

  • 1. PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENT & POWDER COATING PROCESS. Department of Engineering & Technology. Manufacturing Engineering Foundation Degree. WORKED - BASED PROJECT (BMCF507) BY RAHEEM ARIF 27/05/2018
  • 2. Objective  In the following table we have presented designed capacity and production with efficiency of 85% & 90%. The designed capacity is based on individual process time of the workstations. In these workstations we have deleted on line inspection work stations because of their higher capacity.
  • 3. Workstation Coiling & powder coating processes Designed capacity Production with 85% efficiency Production with 90% efficiency Average Ws2 Cold coiling 468000 397800 421200 4.1 Ws3 Stress relief 409500 348075 368550 3.6 Ws4 Warm peening 468000 397800 421200 4.1 Ws5 Pre-setting 468000 397800 421200 4.1 Ws6 Stress peening 468000 397800 421200 4.1 Ws7 Laser marking 468000 397800 421200 4.1 Ws9 Pre- treatment 234000 198900 210600 2.0 Ws10 Powder coating 234000 198900 210600 2.0 Ws11 Sc ragging 468000 379800 421200 4.1 Ws12 Colour marking 468000 379800 421200 4.1 Table 5.3 the production capacity of workstations per month
  • 4.  The average production at 87.5% efficiency is taken for presentation. In the last column we observed that the production capacity of workstation except pre-treatment and powder coating is higher than the consolidated demand of 330.000 per month. Therefore we needed to improve the capacity of these two workstation in order to improve the whole line. The following figure shows production capacity and demand line. To fulfil the shortfall we have proposed improvement in these two bottleneck workstation. We have already started that there are 14 workstations in the suspension spring line. Out of these 4 devoted for inspection which is carried out on line. In the remaining 10 workstation the production of 8 stations at 87.5% efficiency is more than demand. Only two workstations namely WS9: pre-treatment and WS10: powder coating are bottleneck. Therefore our scope is limited to the improvement in the process related to these two bottleneck workstation. In this project we are going to change the design of the hangers in order to accommodate more jobs.
  • 5.  Method:  Examine and observe the functioning of the modified process for one month, record data mainly production schedules and consumptions that have been used.  To implement the recommendations in the periods of one month after approval of production before and after.  Data, resources, equipment, materials & software that we will be using.  Welding, cutting & bending- For spacer bar, end cap, hanger rod is carried out. Final drawing of new hanger with details  Obtaining material required for hangers.  3 processes will be required Cutting, Bending & Welding.  Arc welding, tools & machinery  Alignment for spray guns for new hangers
  • 6.  Each recommendation will be explained in detail. The following primary data is maintained for the purpose of the project  Primary data-  Consumption of electricity, LPG, Demineralized water and industrial water after implementation of project. (as this could increase)  Production of suspension springs after modification.  Secondary data:  We have collected this data from the company for this. The following secondary data has been incorporated in this project.  Secondary data-  Workstation capacity  Production in three shifts and net available time for production (production department).  Present and future demand of the suspension springs.  Production scenario for the period of 10 month i.e. from April 2017 to Jan 2018.
  • 7. Achievements:  Test procedure  At first the trial on eight modified hangers has been carried out. After inspecting quality of the powder coating it is then extended to all hangers. This project doesn’t increase the speed of the powder coating or additional unit. It proposes design of the existing system to some extent. The additional unit will costly affair and it is beyond scope of this project. However it revisits existing process parameters for improving effectiveness is considered in this project. Instead of 4 jobs now the line is 8 jobs at a time accordingly some modification in the parameters such as speed, phosphating and nozzles are necessary. Necessary trial and errors of the same have been conducted to make a final decision.
  • 8.  The powder coating process is now carrying out in three shifts every day. The net times available for the production is 1170 minutes as before. We have not worked on improving the idle time. The improvements in the input level in a specific time (cycle time) has brought the result. In the first and second shift about same quantity of jobs are processed: Where as in third shift 80% jobs are processed. In the may2018 we have produced 328000 springs are produced. This is about 12600 springs are processed per day. The plant is operating for 26 days in this month. Now here we are presenting consumption of resources for the powder coating both before and after implementation of project. Various resources are electricity, LPG (Kg), Demineralized water (Kilo litre), Industrial water (Kilo Litre) and chemicals (in litre). This is presented to analyse the consumption of their resources (consumables). Here we are going to present summary of the data before and after implementation of the project. However it is noticed that the consumption of all these resources are increased in the production level.
  • 9. Date Working Days Electricity LPG(Kg) DM water-KL Industrial water-KL Mar-18 27 146293 4760 170.9 124.2 Apr-18 25 136294 4378 159.3 114.2 May-18 26 139841 4555 166.2 119.5 Consumption of process resources (After) Date Working days Electricity (Kwh) LPG(Kg) DM water-KL Industrial water-KL Apr-17 26 124835 3730 125.4 84.4 May-17 25 122923 3726 124.5 82.7 June-17 26 128546 3883 130 87.7 July -17 27 134515 4025 134.4 90.9 Aug-17 26 129877 3898 130 88.2 Sep-17 26 123555 3738 134.4 85.5 Oct-17 27 132555 4046 130.2 90.6 Nov-17 25 132633 3737 124.5 83.6 Dec-17 27 132975 4071 134.4 90.9 Average 128315 3873 129.1 87.2 Consumption of process resources (Before)
  • 10.  On the job training is given to operators especially for loading and unloading purposes. The unloading spring rate is now increased by 65%of the previous. The operator has to unload double springs in 20% more time of the previous. Similar synchronization of loading by first and second operator is also important. The conveyor speed cannot be changed or stopped for loading and unloading purposes. Two operator are moving to the entire length to and from for observing the powder coating process. They are informed about changed parameters and the logic behind it. No one is allowed to change the setting without permission. The consumption of chemical, epoxy powder, coverage of area and monitoring on consumption are informed. The in charge of powder coating line was part of the hence he is also involved in training. New sufficient to them for working according to revised instructions.
  • 11.  Final Evaluation  In this section we have described how we have monitored the overall process of execution of project, our five members have acted alternatively on the supervision of the progress. Maintained, production, store department and quality personnel were involved in the project. Duties of each member were well defined previously and approved. The time for execution. Of the project and activities needed to be carried out are mentioned in the project. I was responsible for data collection, analysis supervision on carrying out correctives actions.  After positive results of the quality department our work started confidently. The responsibility of the powder coating in-line charge to monitor the process whether it is running as per present norms or not. quality department checks quality of the coating which is an indication of the process is under control. The training is given to six employee out observation of the process throughout the line and responsible for setting.
  • 12. Thank you for listening.