SlideShare a Scribd company logo
1 of 36
THE RENOVATION AND
EXTENSION OF THE
HINDUSTAN SHIVA MANDIR
NAME: ADESH RAMHARACK ID: 52748
FULL TIME
BAS.c CIVIL ENGINEERING
SUPERVISOR: Ms KAREN MEDINA
PURPOSE
• The mission for the redevelopment of the Mandir is to provide a more comfortable
gathering space, improved place for worship and increase a growing audience.
PROJECT DESCRIPTION
• The Hindustan Shiva Mandir was originally launched in 1987 and was subscribed
by Caroni 1975 Limited with the assistance of members of the community who
assembled themselves to establish the contruction of this religious organization. The
general area of study is along Hindustan road that make up the village of New
Grant, which is located along the Naparima/Mayaro Road.
Problem Statement
The Mandir does not meet current life safety codes, specifically with regard to egress
and fire protection and has suffered over the years from a lack of maintenance. The
building is becoming unfit for occupancy of any kind unless some action is taken, there
is no central air conditioning and many the windows cannot be opened for natural
ventilation. There is no legal handicap access into or within the building, the toilets do
not comply with current codes, there is no fire protection, etc. Finally, the exterior
(under ceiling) of the building have been sealed with welded wire mesh since it was
first built to prevent birds and bats from entering. Due to number of years passed,
deterioration of the wire mesh leads to birds and bats and other animals entering
through these same openings.
NEED ANALYSIS
From the data collected via the questionnaires and interview with both the members of the
Mandir and the community, various proposals were made. The data collected were evaluated
and organised into charts graphs and tables
It was observed that most of the members of the community attended the Mandir over 10
years and more, also the location of the Mandir was a greater impact on them
The chart above shows score out of 4, concerns regarding the Mandir. It can be observed that most members are
comfortable with the seating area and conduciveness to worship. Regarding the other attributes it was poorly reflected
upon. Thus work needs to be done to ensure the other attributes are met.
ALTERNATIVES
• Renovation of existing Mandir
Cost: TT$500,000.00
• Renovation of existing Mandir + Extension
Cost: TT$2,550,000.00
• Demolish and Rebuild a new Mandir
• Cost: TT$4,950,000.00
EVALUATION OF ALTERNATIVES
For selecting the best alternative, the Multi Attribute Utility Theory (MAUT) was employed. A set
of criterion were defined along with the weighting for each and a rating scale from one to five was
established, one being the least favorable and five being the most favorable. Each attribute was
ranked, the totals computed and the alternative with the highest total rank was selected.
CRITERIA
Cost weighting:
3.5
Aesthetic
weighting: 3
Structure
weighting: 2.5
Constructabilit
y weighting:2
Accessibility
weighting:1.5
Environmental
impact
weighting:1
1-Very
expensive
1-No appeal 1-Very Unsafe 1-Very difficult 1-Very difficult
1-Very high
impact
2-Expensive 2- Simple 2-Unsafe 2-Difficult
2-Difficult
2-High impact
3-Moderate 3- Moderate 3-Moderate 3-Moderate
3-Moderate 3-Medium
impact
4-Cheap
4- Good 4-Safe 4-Easy 4-Easy 4-low impact
5-Very cheap
5-
Magnificent
5-Very Safe 5-Very easy 5-Very easy
5-Very low
impact
EVALUATION OF ALTERNATIVES
ALTERNATIVE
1
ALTERNATIVE
2
ALTERNATIVE
3
CRITERIA Weighting Rank W X R Rank W X R Rank W X R
W R R R
Project Cost 3.5 3 10.5 2 7 2 7
Aesthetic
3 2 6 4 12 5 15
Structure 2.5 3 7.5 4 10 4 10
Constructability
2 4 8 3 6 2 4
Accessibility 1.5 4 6 4 6 4 6
Environmental
Impacts 1 4 4 4 4 1 1
TOTAL 42 45 43
Results of the evaluation matrix show that Alternative 2 has the highest total weighted value of 45
followed by Alternative 3 of 43 and then Alternative 1 of 42. This alternative shall therefore be
considered in further details for design purposed later in the project.
ESTIMATED CONSTRUCTION COST
SCHEDULE RATES
SITE PLAN
X-RAY VIEW OF THE MANDIR
PROJECT PLANS
COMPULSORY PLANS
• Project Management Plan
• Quality Management Plan
• Risk Management Plan
• Schedule Management Plan
• Scope Management Plan
• Stakeholder Management Plan
SUPPLEMENTAL PLANS:
• Procurement Management Plan
• Communication Management Plan
PROJECT MANAGEMENT PLAN
Initiation Fri May 27, '16 - Fri Jun 24, '16
Planning Mon Jun 27, '16 - Mon Dec 19, '16
Execution Tue Dec 20, '16 - Tue Aug 15, '17
Monitoring and control M&C for whole execution
Closing Wed Aug 16, '17 - Fri Aug 25, '17
Total duration 455 days: 1 year, 2 months, and 29
days
Start 27 May, '16
End 25 August, '17
Life cycle
Primary Stakeholders Secondary Stakeholders
Project manager Client
Contractor Operators
Design/Engineering
Consultants
Suppliers
Supervision Consultants
Schedule Variance Threshold Schedule Baseline Management
The project will be completed in 1 year, 2 months, 29
days and it is necessary to use the resources
effectively and efficiently specifically the time
resource because any delay will directly affect the cost
of the project. For the timely completion of the project
it is important that all the task are completed on their
respective deadlines.
Acceptable delay in the completion of a task depends
on its complexity, cost affect behavior and effect on
entire project. If certain task have strong impacts on
the project, then the project will be pushed back a
couple days or even a few days and the project
manager will be held responsible for the delay.
The project manager will lead the team and it will be
his responsibility to complete the tasks on time, for
this purpose the project manager will be call weekly
meetings with project team to assess their
performance. If some sort of variances are coming on
the project the project manager will look into them
and if they are out of his control then a meeting will
be called including all relevant stakeholders and all
possible solutions will be discussed including extra
time for the completion of a task, but if it is not
accepted then the project manager is authorized to
increase the working hours to meet the deadline or
replacing team members but that would be in extreme
circumstances.
Variance and Baseline Management:
Cost Variance Threshold Cost Baseline Management
The cost variance which are acceptable depend
on the nature of the task there can be
tolerance of about 10% which indicates as
yellow or cautionary. If tolerance of about 20%
then the cost status will be at a red indicator
or critical.
The cost performance baseline will be
managed by doing weekly audit reports. It will
be decided by the project manager how much
variance is acceptable for a certain task, if the
variances are large the project manager will
call an immediate meeting of the project team
members and will try to find out the reason for
such variances. Possible solution would be
increasing project funding.
Scope Variance Threshold Scope Baseline Management
The scope variance are not going to happen
more often but if they occur then the issue
must be resolve immediately because it will
directly influence the cost and schedule
variances
It will be the responsibility of the project
manager to look into the performance of the
team members and assess their tasks assigned
to verify their scope; in case of any variances
the team will be directed to change their line
of action. No such variances can be assigned
because it is an issue of serious nature
because scope variance directly affect the cost
and schedule.
QUALITY MANAGEMENT PLAN
Quality control approach
• Inspection of the processes both the project and service implementation of change
requests when there is a need.
Quality improvement approach
• Weekly meetings
• Reports on cost performance
• Resolve any dispute which may arise
No. Description Confirmed by
Project
Manager
Confirmed by
Contractor
Remarks
Sign Date Sign Date
1 Review the required excavation
depth of pile foundation as per
drawings
2 Check drawings and specification,
the number of Stirrups per the length
of rebar for pile cap, foundation and
ground beam
3 Check the quality of the mixture of
sand, cement, stones in the pile
foundation
Quality checklist for excavation
Risk management plan
SCHEDULE MANAGEMENT PLAN
Sequencing Activities
Activity sequencing was used to determine the order of work packages and assign relationships
between project activities.
Sequencing of activities performed as part of this construction project include:
1. Pre - Construction Stage
2. Start to End Construction works
3. Site Preparation
4. Substructure
5. Structural Steel Frame
6. Concrete Work
7. Roof Works
8. Walls
9. Windows/Doors
10. Floor Finish
11. Plumbing Installation
12. Electrical Installation
13. Ceiling Finishes
14. Joinery
15. Painting
16. External Works
17. Close-out Stage
Activity Duration estimate (days)
Pre - Construction Stage Mon Jun 27, '16 - Mon Dec 19, '16 (126 days)
Start to End Construction
works
Tue Dec 20, '16 - Fri Aug 18, '17 (171 days)
Site Preparation Tue Dec 20, '16 - Wed Dec 28, '16 (7 days)
Substructure Thu Dec 29, '16 - Thu Feb 9, '17 (31 days)
Structural Steel Frame Thu Feb 9, '17 - Fri Mar 3, '17 (17
days)
Concrete Work Mon Mar 6, '17 - Fri Mar 10, '17 (5 days)
Roof Works Mon Mar 13, '17 - Thu Mar 30, '17 (14 days)
Walls Fri Mar 31, '17 - Mon May 1, '17 (22 days)
Windows/Doors Tue May 2, '17 - Wed May 10, '17 (7 days)
Floor Finish Thu May 11, '17 - Fri May 26, '17 (12 days)
Plumbing Installation Fri Apr 21, '17 - Tue May 2, '17 (8
days)
Electrical Installation Mon May 29, '17 - Wed Jun 7, '17 (8 days)
Ceiling Finishes Thu Jun 8, '17 - Wed Jun 21, '17
(10 days)
Joinery Thu Jun 15, '17 - Mon Jul 17, '17 (23 days)
Painting Tue Jul 11, '17 - Tue Aug 15, '17 (26 days)
Estimating Activity Duration
Estimate Activity Duration is the process of approximating the number of work periods needed to complete
individual activities with estimated resources.
Scope Statement Development
• The project scope statement provides a detailed description of the project,
deliverables, constraints, exclusions, assumptions, and acceptance criteria.
Scope management plan
Project Assumptions
Assumptions of this Project believed to be true but unsure:
• The project will stay on or under projected budget.
• The project will be completed within given time
• Any required permits will be approved without any issue
• All equipment and material will be obtained without any complication
Scope management plan
STAKEHOLDER MANAGEMENT PLAN
Project
Stakeholder
Role in Project
Type of
Stakeholder
Strategy Project interests
Impact on
Project
Outcome
Members of
the Mandir
Client External
Project
Performance
Documentation
To receive, the
final product as
per requirements
Influencer
Parasram
Enterprises
Limited
Contractor Internal
Project
performance
feedback, RFQ
To deliver the
Project in time
and within the
approved budget
Influencer
Project Team
1
Design/Engineering
Consultants
Internal
Meeting,
Project
documentation
To perform work
as per
requirements and
collect wages
Supporter
Project Team
2
Supervision
Consultants
Internal
Project
Performance
Documentation
To check whether
the work is being
perform as per
requirement
Supporter
Adesh
Ramharack
Project Manager Internal
Official
Meetings,
Project
performance
feedback
To check whether
the work is being
perform as per
requirement
Influencer
------------- Operator External
Project
performance
feedback
To perform work
as per
requirements and
collect wages
Supporter
-------------- Supplier External
RFQ, invoices,
Payment
schedule
To deliver good
material of
approved quality
on time and
collect payments
on invoices
Supporter
PROCUREMENT MANAGEMENT PLAN
Procurement management includes the processes necessary to purchase or acquire
products, services or results needed from outside the project teams.
Selection Process and Criteria
• The suppliers will be selected on the following criteria:
• Low cost
• Quality of the Material
• Timely delivery
• Reputation in the market
Project manager Contractor
- He will look after the needs
of the project and the
materials needed to procured
- It is the responsibility of the
project manager to timely
send the request for the
procurements.
- He should procure audit
reports of the procurements.
- He should contact with the
authorized supplier and check the
availability of the materials on time.
- He should give all invoices of items
procured form the supplier to the
project manager
Roles and Responsibilities
COMMUNICATION PLAN
WHAT WHEN MEDIUM OWNER ATTENDEES OBJECTIVE
Kick off Meeting Once Face to face Project Manager
Project Team,
Stakeholder
Introduce the
project teams and
discuss the project
Project Team
Meetings
Weekly
Face to face /
Phone
Weekly Team
Leader
Project Team
Review the status
of the project
Technical Design
Meetings
As Needed
Face to face /
Presentation
Project Manager
Contractor,
Project Teams
Discuss the design
concept of the
Mandir
Monthly Project
Meetings
Monthly Face to face Project Manager Project Teams
Monthly report of
project status
Status Reports Monthly Email Team members
Project Manager
Report the status
of the project
including
activities,
progress, costs
and issues.
ANY QUESTIONS?

More Related Content

Similar to The Renovation and Extension of the Hindustan Shiva Mandir

building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTRiyaVerma238431
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1JamesMoy7
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)Pinky Chan
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxRebeccaEdwards88
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docxhyacinthshackley2629
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Minn Lwin
 
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...GoLeanSixSigma.com
 
Applied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanApplied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanNicole Heredia
 
SFK_ Resume-jobchange_dec2016
SFK_ Resume-jobchange_dec2016SFK_ Resume-jobchange_dec2016
SFK_ Resume-jobchange_dec2016Fazlullah Khan
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in constructionKartikeya Pandey
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)JamesMoy7
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...IRJET Journal
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in constructionKartikeya Pandey
 
Document 1
Document 1Document 1
Document 1Erik Ong
 

Similar to The Renovation and Extension of the Hindustan Shiva Mandir (20)

Project background
Project backgroundProject background
Project background
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)
 
ICIP2G
ICIP2GICIP2G
ICIP2G
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
 
Project Review Presentation (2)
Project Review Presentation (2)Project Review Presentation (2)
Project Review Presentation (2)
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
 
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
 
Project Name
 Project Name                                       Project Name
Project Name
 
Applied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanApplied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management Plan
 
SFK_ Resume-jobchange_dec2016
SFK_ Resume-jobchange_dec2016SFK_ Resume-jobchange_dec2016
SFK_ Resume-jobchange_dec2016
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in construction
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)
 
final ppt.pptx
final ppt.pptxfinal ppt.pptx
final ppt.pptx
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in construction
 
Document 1
Document 1Document 1
Document 1
 

Recently uploaded

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 

Recently uploaded (20)

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 

The Renovation and Extension of the Hindustan Shiva Mandir

  • 1. THE RENOVATION AND EXTENSION OF THE HINDUSTAN SHIVA MANDIR NAME: ADESH RAMHARACK ID: 52748 FULL TIME BAS.c CIVIL ENGINEERING SUPERVISOR: Ms KAREN MEDINA
  • 2. PURPOSE • The mission for the redevelopment of the Mandir is to provide a more comfortable gathering space, improved place for worship and increase a growing audience.
  • 3. PROJECT DESCRIPTION • The Hindustan Shiva Mandir was originally launched in 1987 and was subscribed by Caroni 1975 Limited with the assistance of members of the community who assembled themselves to establish the contruction of this religious organization. The general area of study is along Hindustan road that make up the village of New Grant, which is located along the Naparima/Mayaro Road.
  • 4. Problem Statement The Mandir does not meet current life safety codes, specifically with regard to egress and fire protection and has suffered over the years from a lack of maintenance. The building is becoming unfit for occupancy of any kind unless some action is taken, there is no central air conditioning and many the windows cannot be opened for natural ventilation. There is no legal handicap access into or within the building, the toilets do not comply with current codes, there is no fire protection, etc. Finally, the exterior (under ceiling) of the building have been sealed with welded wire mesh since it was first built to prevent birds and bats from entering. Due to number of years passed, deterioration of the wire mesh leads to birds and bats and other animals entering through these same openings.
  • 5. NEED ANALYSIS From the data collected via the questionnaires and interview with both the members of the Mandir and the community, various proposals were made. The data collected were evaluated and organised into charts graphs and tables It was observed that most of the members of the community attended the Mandir over 10 years and more, also the location of the Mandir was a greater impact on them
  • 6. The chart above shows score out of 4, concerns regarding the Mandir. It can be observed that most members are comfortable with the seating area and conduciveness to worship. Regarding the other attributes it was poorly reflected upon. Thus work needs to be done to ensure the other attributes are met.
  • 7. ALTERNATIVES • Renovation of existing Mandir Cost: TT$500,000.00 • Renovation of existing Mandir + Extension Cost: TT$2,550,000.00 • Demolish and Rebuild a new Mandir • Cost: TT$4,950,000.00
  • 8. EVALUATION OF ALTERNATIVES For selecting the best alternative, the Multi Attribute Utility Theory (MAUT) was employed. A set of criterion were defined along with the weighting for each and a rating scale from one to five was established, one being the least favorable and five being the most favorable. Each attribute was ranked, the totals computed and the alternative with the highest total rank was selected. CRITERIA Cost weighting: 3.5 Aesthetic weighting: 3 Structure weighting: 2.5 Constructabilit y weighting:2 Accessibility weighting:1.5 Environmental impact weighting:1 1-Very expensive 1-No appeal 1-Very Unsafe 1-Very difficult 1-Very difficult 1-Very high impact 2-Expensive 2- Simple 2-Unsafe 2-Difficult 2-Difficult 2-High impact 3-Moderate 3- Moderate 3-Moderate 3-Moderate 3-Moderate 3-Medium impact 4-Cheap 4- Good 4-Safe 4-Easy 4-Easy 4-low impact 5-Very cheap 5- Magnificent 5-Very Safe 5-Very easy 5-Very easy 5-Very low impact
  • 9. EVALUATION OF ALTERNATIVES ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3 CRITERIA Weighting Rank W X R Rank W X R Rank W X R W R R R Project Cost 3.5 3 10.5 2 7 2 7 Aesthetic 3 2 6 4 12 5 15 Structure 2.5 3 7.5 4 10 4 10 Constructability 2 4 8 3 6 2 4 Accessibility 1.5 4 6 4 6 4 6 Environmental Impacts 1 4 4 4 4 1 1 TOTAL 42 45 43 Results of the evaluation matrix show that Alternative 2 has the highest total weighted value of 45 followed by Alternative 3 of 43 and then Alternative 1 of 42. This alternative shall therefore be considered in further details for design purposed later in the project.
  • 13. X-RAY VIEW OF THE MANDIR
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19. PROJECT PLANS COMPULSORY PLANS • Project Management Plan • Quality Management Plan • Risk Management Plan • Schedule Management Plan • Scope Management Plan • Stakeholder Management Plan SUPPLEMENTAL PLANS: • Procurement Management Plan • Communication Management Plan
  • 20. PROJECT MANAGEMENT PLAN Initiation Fri May 27, '16 - Fri Jun 24, '16 Planning Mon Jun 27, '16 - Mon Dec 19, '16 Execution Tue Dec 20, '16 - Tue Aug 15, '17 Monitoring and control M&C for whole execution Closing Wed Aug 16, '17 - Fri Aug 25, '17 Total duration 455 days: 1 year, 2 months, and 29 days Start 27 May, '16 End 25 August, '17 Life cycle Primary Stakeholders Secondary Stakeholders Project manager Client Contractor Operators Design/Engineering Consultants Suppliers Supervision Consultants
  • 21. Schedule Variance Threshold Schedule Baseline Management The project will be completed in 1 year, 2 months, 29 days and it is necessary to use the resources effectively and efficiently specifically the time resource because any delay will directly affect the cost of the project. For the timely completion of the project it is important that all the task are completed on their respective deadlines. Acceptable delay in the completion of a task depends on its complexity, cost affect behavior and effect on entire project. If certain task have strong impacts on the project, then the project will be pushed back a couple days or even a few days and the project manager will be held responsible for the delay. The project manager will lead the team and it will be his responsibility to complete the tasks on time, for this purpose the project manager will be call weekly meetings with project team to assess their performance. If some sort of variances are coming on the project the project manager will look into them and if they are out of his control then a meeting will be called including all relevant stakeholders and all possible solutions will be discussed including extra time for the completion of a task, but if it is not accepted then the project manager is authorized to increase the working hours to meet the deadline or replacing team members but that would be in extreme circumstances. Variance and Baseline Management:
  • 22. Cost Variance Threshold Cost Baseline Management The cost variance which are acceptable depend on the nature of the task there can be tolerance of about 10% which indicates as yellow or cautionary. If tolerance of about 20% then the cost status will be at a red indicator or critical. The cost performance baseline will be managed by doing weekly audit reports. It will be decided by the project manager how much variance is acceptable for a certain task, if the variances are large the project manager will call an immediate meeting of the project team members and will try to find out the reason for such variances. Possible solution would be increasing project funding. Scope Variance Threshold Scope Baseline Management The scope variance are not going to happen more often but if they occur then the issue must be resolve immediately because it will directly influence the cost and schedule variances It will be the responsibility of the project manager to look into the performance of the team members and assess their tasks assigned to verify their scope; in case of any variances the team will be directed to change their line of action. No such variances can be assigned because it is an issue of serious nature because scope variance directly affect the cost and schedule.
  • 23. QUALITY MANAGEMENT PLAN Quality control approach • Inspection of the processes both the project and service implementation of change requests when there is a need. Quality improvement approach • Weekly meetings • Reports on cost performance • Resolve any dispute which may arise
  • 24. No. Description Confirmed by Project Manager Confirmed by Contractor Remarks Sign Date Sign Date 1 Review the required excavation depth of pile foundation as per drawings 2 Check drawings and specification, the number of Stirrups per the length of rebar for pile cap, foundation and ground beam 3 Check the quality of the mixture of sand, cement, stones in the pile foundation Quality checklist for excavation
  • 26.
  • 28. Sequencing Activities Activity sequencing was used to determine the order of work packages and assign relationships between project activities. Sequencing of activities performed as part of this construction project include: 1. Pre - Construction Stage 2. Start to End Construction works 3. Site Preparation 4. Substructure 5. Structural Steel Frame 6. Concrete Work 7. Roof Works 8. Walls 9. Windows/Doors 10. Floor Finish 11. Plumbing Installation 12. Electrical Installation 13. Ceiling Finishes 14. Joinery 15. Painting 16. External Works 17. Close-out Stage
  • 29. Activity Duration estimate (days) Pre - Construction Stage Mon Jun 27, '16 - Mon Dec 19, '16 (126 days) Start to End Construction works Tue Dec 20, '16 - Fri Aug 18, '17 (171 days) Site Preparation Tue Dec 20, '16 - Wed Dec 28, '16 (7 days) Substructure Thu Dec 29, '16 - Thu Feb 9, '17 (31 days) Structural Steel Frame Thu Feb 9, '17 - Fri Mar 3, '17 (17 days) Concrete Work Mon Mar 6, '17 - Fri Mar 10, '17 (5 days) Roof Works Mon Mar 13, '17 - Thu Mar 30, '17 (14 days) Walls Fri Mar 31, '17 - Mon May 1, '17 (22 days) Windows/Doors Tue May 2, '17 - Wed May 10, '17 (7 days) Floor Finish Thu May 11, '17 - Fri May 26, '17 (12 days) Plumbing Installation Fri Apr 21, '17 - Tue May 2, '17 (8 days) Electrical Installation Mon May 29, '17 - Wed Jun 7, '17 (8 days) Ceiling Finishes Thu Jun 8, '17 - Wed Jun 21, '17 (10 days) Joinery Thu Jun 15, '17 - Mon Jul 17, '17 (23 days) Painting Tue Jul 11, '17 - Tue Aug 15, '17 (26 days) Estimating Activity Duration Estimate Activity Duration is the process of approximating the number of work periods needed to complete individual activities with estimated resources.
  • 30. Scope Statement Development • The project scope statement provides a detailed description of the project, deliverables, constraints, exclusions, assumptions, and acceptance criteria. Scope management plan
  • 31. Project Assumptions Assumptions of this Project believed to be true but unsure: • The project will stay on or under projected budget. • The project will be completed within given time • Any required permits will be approved without any issue • All equipment and material will be obtained without any complication Scope management plan
  • 32. STAKEHOLDER MANAGEMENT PLAN Project Stakeholder Role in Project Type of Stakeholder Strategy Project interests Impact on Project Outcome Members of the Mandir Client External Project Performance Documentation To receive, the final product as per requirements Influencer Parasram Enterprises Limited Contractor Internal Project performance feedback, RFQ To deliver the Project in time and within the approved budget Influencer Project Team 1 Design/Engineering Consultants Internal Meeting, Project documentation To perform work as per requirements and collect wages Supporter Project Team 2 Supervision Consultants Internal Project Performance Documentation To check whether the work is being perform as per requirement Supporter Adesh Ramharack Project Manager Internal Official Meetings, Project performance feedback To check whether the work is being perform as per requirement Influencer ------------- Operator External Project performance feedback To perform work as per requirements and collect wages Supporter -------------- Supplier External RFQ, invoices, Payment schedule To deliver good material of approved quality on time and collect payments on invoices Supporter
  • 33. PROCUREMENT MANAGEMENT PLAN Procurement management includes the processes necessary to purchase or acquire products, services or results needed from outside the project teams. Selection Process and Criteria • The suppliers will be selected on the following criteria: • Low cost • Quality of the Material • Timely delivery • Reputation in the market
  • 34. Project manager Contractor - He will look after the needs of the project and the materials needed to procured - It is the responsibility of the project manager to timely send the request for the procurements. - He should procure audit reports of the procurements. - He should contact with the authorized supplier and check the availability of the materials on time. - He should give all invoices of items procured form the supplier to the project manager Roles and Responsibilities
  • 35. COMMUNICATION PLAN WHAT WHEN MEDIUM OWNER ATTENDEES OBJECTIVE Kick off Meeting Once Face to face Project Manager Project Team, Stakeholder Introduce the project teams and discuss the project Project Team Meetings Weekly Face to face / Phone Weekly Team Leader Project Team Review the status of the project Technical Design Meetings As Needed Face to face / Presentation Project Manager Contractor, Project Teams Discuss the design concept of the Mandir Monthly Project Meetings Monthly Face to face Project Manager Project Teams Monthly report of project status Status Reports Monthly Email Team members Project Manager Report the status of the project including activities, progress, costs and issues.