SlideShare a Scribd company logo
1 of 32
Download to read offline
DOOSAN
1 -
Introduction of
Boiler General Arrangement (G/A)
Mong Duong II TPP (2 x 560MW)
15
3
23
25
9
13
1
22
19
4
20
26
24
5
14
21
16
17
18
2
611
12
87
27
28
29
30
10
31
26A
21A
26B
27A
DOOSAN
Contents
2. Work Boundaries
1. Definition & Mission
2 -
4. Layout Considerations
3. Design Objectives
5. Understanding of G/A Drawing
6. Introduction of G/A for MD II
7. Appendix
DOOSAN
3 -1. Definition & Mission
• The General Arrangement drawing is a basic document which shows
the arrangement of the Boiler, Steel Structure, Auxiliary equipments,
Air & Gas ducts and Major Piping etc. relative to each other in the
Proper area specified by Customer.
• The G/A drawing visualizes the actual size of the various equipments
and represents them in a scaled down manner in both elevation and
plan views.
G/A drawing is just for indicating the general information, but all the more information of actual
platform area, partial platform elevation and local stair/ladder location etc. refer to the relevant
steelwork drawings.
• The mission of G/A drawing
 To ensure optimum arrangement/position of the various equipments
within the available space. (Economical efficiency)
 To ensure easy access and maintenance.
 To co-ordinate between detailed design and Aux. equipments.
DOOSAN
4 -2. Work Boundaries
TBN/GEN BOPBOP BOILER
DOOSAN
3. Objectives
- Cost estimation
- Presentation in the proposal
- Guiding contract drafting
• For Proposal Stage
- Client approval and erection.
- Facilitate detailed design engineers on the relative arrangement / location of the
various boiler components and guides them during detail engineering.
- Provide information for basic design of Steel Structure, Piping & Duct Layout.
- Provide knowledge on the location, access, space availability, handling facilities
to plan maintenance activities.(To help O&M personnel)
- Provide information on interface details with other’s scope of work.
(To avoid interference between equipments, steel structure, piping etc.)
• For Contract Stage
5 -
DOOSAN
6 -4. Boiler G/A Considerations (1/3)
- Plant Elevation (ex, Mean Sea Level)
- Boiler Specification
• General Information
- Equipment Maintenance Space
- Boiler(Furnace) Envelope Dimensions & Instrument Connection Location
- Furnace & Back-pass Opening Location
(Soot blower, CCTV, Observation Door, Access Door etc.)
• Boiler Proper
- Buckstay Elevation
- Interface & Terminal Point
- Thermal Expansion Movement
DOOSAN
7 -
- Fans (F.D Fan, I.D Fan, P.A Fan, Seal Air Fan)
• Major Equipments (Location, Dimension & Shape)
- GAPH (Gas Air Preheater)
- SCAH (Steam Coil Air Heater)
- Environmental Equipments (FGD, SCR, ESP)
- Equipment Handling Device (Monorail Hoist, Crane, etc)
- Elevator (Passenger)
4. Boiler G/A Considerations (2/3)
DOOSAN
8 -
- Duct Configuration Including Size & Shape
• Air & Flue Gas System
- Column Location and Main Staircase Location
• Structural Steel
- Maintenance & Access Platform Elevations
- Damper, Expansion Joint & Access Door Location
- Major Pipe Runs, Pipe Size & Elevations (MS, HR, CR & FW)
• Piping
- Large Valve Locations (MOV. S/V)
- Instrument Connection Location
4. Boiler G/A Considerations (3/3)
DOOSAN
9 -
- Key Plan Drawing
• Kind of G/A Drawings
5. Understanding of Boiler G/A Drawing
- Plan View Drawing (Floor Plan)
- Side & Front/Rear Elevation View Drawing
- 3-Dimensional View (by PDS)
• Basic Knowledge to Reading the G/A
- Unit Quantity (Number)
- North Direction & Plant Elevation
- Kind of Equipments & Future Facilities
- General Notes in Drawing
- Legend & Abbreviation etc. in Drawing
DOOSAN
10 -6. Introduction of G/A for MD II
- Key Plan & Each Plan View
- Side Elevation View
- Front & Rear Elevation View
- Reference Picture
• Unit Description
• General Layout Graphic
• Heating Surface & Steam Circuit
• Water Circuit (Economizer)
• Lifting Device for Equipment Maintenance
• Access Door Location in Boiler Pressure Part
• G/A Drawings
DOOSAN
11 -
Name of Plant Mong Duong II TPP
Generation (MWe) 560MW x 2 units
Evaporation 1.912 ton/hr
Type of boiler
Subcritical,
Drum Type and Natural
Circulation
Balanced Draft, Semi-Outdoor
Firing Type
Slot Burners
(Downshot Firing System)
Total 36ea Burners
(Slot Burner 24 + Wall Burner 12)
Fuel Anthracite Coal
Boiler Size (m)
Furnace Width : 28.520
Furnace Depth : 22.712
Furnace Height : 55.217
Executing
• Design :
DOOSAN Babcock & DOOSAN
Co-work
• Manufacturing :
DOOSAN Changwon Factory
• Commissioning :
DOOSAN Babcock & DOOSAN
Co-work
Unit Description
15.0°
PLATEN SH
600
F W
F W
ECONOMISER
FINAL SH
PRI RH 1st BANK
PRI RH 3rd BANK
PRI RH 2nd BANK
PRI SH 1st BANK
PRI SH 3rd BANK
PRI SH 2nd BANK
FINAL RH
DOOSAN
12-General Layout Graphic
15
3
23
25
9
13
1
22
19
4
20
26
24
5
14
21
16
17
18
2
611
12
87
27
28
29
30
10
31
26A
21A
26B
27A
Air Duct System ;
Cold air supplied from FD fan is
after heated by hot gas in the
GAPH. and hot air is transported
through wind box into the burner.
for combustion.
Gas Duct System ;
After recovering heat from hot
flue gas at the furnace and
through to the SCR, GAPH,
EP, IDF, FGD(or FGD bypass)
and stack and exhausted to
atmosphere.
Electrostatic
Precipitator
DESCRIPTION OF COMPONENTS
Cold Reheater Pipe
Main Steam Pipe
Final
Superheater
Platen Superheater
Primary Superheater
Downcomers
Steam Drum
Economizer
Feed Water Pipe
Furnace Water Wall
Silencer
Blow Down Tank
Hot Reheater Pipe
Final Reheater
Wall Burner
Slot Burner Set
Gas Air Preheater
Steam Coil Air Heater
Forced Draft Fan
Seal Air Fan
Primary Air Fan
Coal Feeder
Coal Silo
Coal Tripper
Tube Mill
S.C.R
C.I.D Fan
Stack
Primary Reheater
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
21A
22
23
Mixed P.A Duct
24
25
26
26A
26B
Classifiers
Coal Pipes
27
27A Bias Damper
28
29
30
31
SCC Bottom Ash
Sys
DOOSAN
15.0°
PLATEN SH
600
F W
F W
ECONOMISER
FINAL SH
PRI RH 1st BANK
PRI RH 3rd BANK
PRI RH 2nd BANK
PRI SH 1st BANK
PRI SH 3rd BANK
PRI SH 2nd BANK
FINAL RH
13 -Heating Surface Arrangement & Steam Circuit
RH Inlet Header
SH Outlet Header
High Gas
Temperature
RH Outlet Header
Final Superheater
Pass
Tertiary Burners
Slot Burner Sets
Economizer
Steam Drum
Reheater Pass
Superheater Pass
Wind box
DOOSAN
14 -Water Circuit (Economizer)
Eco. Inlet Header
Steam Drum
DOOSAN
15 -
The boiler pressure parts have been
designed / selected to ensure both
ready access and long term reliability.
: Access Door
Access Door Location in Boiler Pressure Part
- Size 500 x 500 in Tube walls
- Size 500 x 900 in Furnace hopper
: Observation Door
DOOSAN
16 -Equipment Maintenance
- Boiler, Equipment Location & Duct Layout
Lifting Device Supply List /Per Boiler
Equipment
Capacity
x Q’ty
Type
Location
in G/A Dwg.
Remarks
1 F.D Fan (Motor) 20 Ton x 2 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 10m
2 F.D Fan (Rotor) 5 Ton x 2 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 10m
3 P.A Fan (Motor) 16 Ton x 1 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 08m
4 P.A Fan (Rotor) 5 Ton x 1 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 08m
5 I.D Fan (Motor) 29 Ton x 2 Sets Motor Driven, Monorail Hoist -310013/310014 Lifting Height 12m
6 I.D Fan (Rotor) 10 Ton x 1 Sets Motor Driven, Monorail Hoist -310013/310014 Lifting Height 12m
7 Scanner Cooling Air Fan Motor 2 Ton x 1 Set Motor Driven, Monorail Hoist -310005 Lifting Height 08m
8 Gas Air Preheater Basket 2 Ton x 2 Sets Motor Driven, Monorail Hoist -310005 Lifting Height 28m
9 Pulverizer (Motor) 30 Ton x 6 Sets Motor Driven, Monorail Hoist -310004 Lifting Height 14m
10 Pulverizer Ball Charge 2 Ton x 1 Sets Motor Driven, Monorail Hoist -310004 Lifting Height 20m
11
Common Chain Block W/ Geared
Trolley
3.5 Ton x
24Sets
Manual Not Specified Lifting Height 7m
12 Common Chain Block 2 Ton x 2 Sets Manual Not Specified Lifting Height 5m
13
14
15
16
DOOSAN
17 -G/A Drawing - (Key plan)
DOOSAN
18 -G/A Drawing - (Side View)
DOOSAN
19 -G/A Drawing - (Front View)
DOOSAN
20 -G/A Drawing - (Rear View)
DOOSAN
21 -G/A Drawing – (Ground floor Plan View)
DOOSAN
22 -G/A Drawing - (Plan View “04-04”)
DOOSAN
23 -G/A Drawing - (Top Plan View)
DOOSAN
Boiler Instrument Insert Location- (Connection Insert list)
DOOSAN
Boiler Instrument Insert Location- (Connection Detail)
DOOSAN
Boiler Instrument Insert Location- (Side Elevation View)
DOOSAN
Boiler Instrument Insert Location- (Plan Section View)
DOOSAN
Support Steel For Ret. Sootblowers (1/2)
DOOSAN
Support Steel For Ret. Sootblowers (2/2)
DOOSAN
24 -G/A Drawing - (Reference Picture)
Furnace Wall
Lance Tube
Axial Type Fan (F.D fan & I.D fan) Centrifugal Type Fan (G.R fan)
Long Retractable Soot Blower
DOOSAN
26 -
3D Animation
7. Appendix
DOOSAN
27 -
E.O.D
THANK YOU !

More Related Content

What's hot

Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plants
SHIVAJI CHOUDHURY
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
SHIVAJI CHOUDHURY
 

What's hot (20)

Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdown
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plants
 
An introduction to Fired Heaters.pdf
An introduction to Fired Heaters.pdfAn introduction to Fired Heaters.pdf
An introduction to Fired Heaters.pdf
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
Power plant performance_efficiency
Power plant performance_efficiencyPower plant performance_efficiency
Power plant performance_efficiency
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Boiler feed and pump sizing c-b and grundfos july 2016(1)
Boiler feed and pump sizing   c-b and grundfos july 2016(1)Boiler feed and pump sizing   c-b and grundfos july 2016(1)
Boiler feed and pump sizing c-b and grundfos july 2016(1)
 
Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
 
Introduction of Fired heaters
Introduction of Fired heatersIntroduction of Fired heaters
Introduction of Fired heaters
 
High pressure boiler
High pressure boilerHigh pressure boiler
High pressure boiler
 
Deaerator
DeaeratorDeaerator
Deaerator
 
Study and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boilerStudy and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boiler
 
Cfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenanceCfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenance
 
Combustion in a CFBC Boiler
Combustion in a CFBC BoilerCombustion in a CFBC Boiler
Combustion in a CFBC Boiler
 
Boiler Water Circulation Pumps
Boiler Water Circulation PumpsBoiler Water Circulation Pumps
Boiler Water Circulation Pumps
 
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGCOAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
 

Similar to Training manual boiler general arrangement_mongduong ii

Project Report ME-494
Project Report ME-494Project Report ME-494
Project Report ME-494
Hassaan Ahmad
 
48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrier48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrier
Rios Luis
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
coderweb
 
Safavi-C V-English-03
Safavi-C V-English-03Safavi-C V-English-03
Safavi-C V-English-03
Sahand Safavi
 
PRESTIGE LTST 2O16 - Copy
PRESTIGE LTST 2O16 - CopyPRESTIGE LTST 2O16 - Copy
PRESTIGE LTST 2O16 - Copy
anil prashanth
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011
abughaws
 

Similar to Training manual boiler general arrangement_mongduong ii (20)

project
projectproject
project
 
fired heater design , fired heater design
fired heater design , fired heater designfired heater design , fired heater design
fired heater design , fired heater design
 
Solutions Manual for Analysis Synthesis And Design Of Chemical Processes 3rd ...
Solutions Manual for Analysis Synthesis And Design Of Chemical Processes 3rd ...Solutions Manual for Analysis Synthesis And Design Of Chemical Processes 3rd ...
Solutions Manual for Analysis Synthesis And Design Of Chemical Processes 3rd ...
 
Project Report ME-494
Project Report ME-494Project Report ME-494
Project Report ME-494
 
Projects executed
Projects executedProjects executed
Projects executed
 
48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrier48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrier
 
Power-Plant-Simulator-Designer-Presentation.pdf
Power-Plant-Simulator-Designer-Presentation.pdfPower-Plant-Simulator-Designer-Presentation.pdf
Power-Plant-Simulator-Designer-Presentation.pdf
 
Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
Safavi-C V-English-03
Safavi-C V-English-03Safavi-C V-English-03
Safavi-C V-English-03
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 
Company frofile 2015 (wooil)
Company frofile 2015 (wooil)Company frofile 2015 (wooil)
Company frofile 2015 (wooil)
 
PRESTIGE LTST 2O16 - Copy
PRESTIGE LTST 2O16 - CopyPRESTIGE LTST 2O16 - Copy
PRESTIGE LTST 2O16 - Copy
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
Operations ETI-DLH
Operations ETI-DLHOperations ETI-DLH
Operations ETI-DLH
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011
 
project ppt
project pptproject ppt
project ppt
 
500 mw utility boiler ppt
500 mw utility boiler ppt500 mw utility boiler ppt
500 mw utility boiler ppt
 
Design and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure AccumulatorDesign and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure Accumulator
 
Boiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plantBoiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plant
 

Recently uploaded

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 

Recently uploaded (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Training manual boiler general arrangement_mongduong ii

  • 1. DOOSAN 1 - Introduction of Boiler General Arrangement (G/A) Mong Duong II TPP (2 x 560MW) 15 3 23 25 9 13 1 22 19 4 20 26 24 5 14 21 16 17 18 2 611 12 87 27 28 29 30 10 31 26A 21A 26B 27A
  • 2. DOOSAN Contents 2. Work Boundaries 1. Definition & Mission 2 - 4. Layout Considerations 3. Design Objectives 5. Understanding of G/A Drawing 6. Introduction of G/A for MD II 7. Appendix
  • 3. DOOSAN 3 -1. Definition & Mission • The General Arrangement drawing is a basic document which shows the arrangement of the Boiler, Steel Structure, Auxiliary equipments, Air & Gas ducts and Major Piping etc. relative to each other in the Proper area specified by Customer. • The G/A drawing visualizes the actual size of the various equipments and represents them in a scaled down manner in both elevation and plan views. G/A drawing is just for indicating the general information, but all the more information of actual platform area, partial platform elevation and local stair/ladder location etc. refer to the relevant steelwork drawings. • The mission of G/A drawing  To ensure optimum arrangement/position of the various equipments within the available space. (Economical efficiency)  To ensure easy access and maintenance.  To co-ordinate between detailed design and Aux. equipments.
  • 4. DOOSAN 4 -2. Work Boundaries TBN/GEN BOPBOP BOILER
  • 5. DOOSAN 3. Objectives - Cost estimation - Presentation in the proposal - Guiding contract drafting • For Proposal Stage - Client approval and erection. - Facilitate detailed design engineers on the relative arrangement / location of the various boiler components and guides them during detail engineering. - Provide information for basic design of Steel Structure, Piping & Duct Layout. - Provide knowledge on the location, access, space availability, handling facilities to plan maintenance activities.(To help O&M personnel) - Provide information on interface details with other’s scope of work. (To avoid interference between equipments, steel structure, piping etc.) • For Contract Stage 5 -
  • 6. DOOSAN 6 -4. Boiler G/A Considerations (1/3) - Plant Elevation (ex, Mean Sea Level) - Boiler Specification • General Information - Equipment Maintenance Space - Boiler(Furnace) Envelope Dimensions & Instrument Connection Location - Furnace & Back-pass Opening Location (Soot blower, CCTV, Observation Door, Access Door etc.) • Boiler Proper - Buckstay Elevation - Interface & Terminal Point - Thermal Expansion Movement
  • 7. DOOSAN 7 - - Fans (F.D Fan, I.D Fan, P.A Fan, Seal Air Fan) • Major Equipments (Location, Dimension & Shape) - GAPH (Gas Air Preheater) - SCAH (Steam Coil Air Heater) - Environmental Equipments (FGD, SCR, ESP) - Equipment Handling Device (Monorail Hoist, Crane, etc) - Elevator (Passenger) 4. Boiler G/A Considerations (2/3)
  • 8. DOOSAN 8 - - Duct Configuration Including Size & Shape • Air & Flue Gas System - Column Location and Main Staircase Location • Structural Steel - Maintenance & Access Platform Elevations - Damper, Expansion Joint & Access Door Location - Major Pipe Runs, Pipe Size & Elevations (MS, HR, CR & FW) • Piping - Large Valve Locations (MOV. S/V) - Instrument Connection Location 4. Boiler G/A Considerations (3/3)
  • 9. DOOSAN 9 - - Key Plan Drawing • Kind of G/A Drawings 5. Understanding of Boiler G/A Drawing - Plan View Drawing (Floor Plan) - Side & Front/Rear Elevation View Drawing - 3-Dimensional View (by PDS) • Basic Knowledge to Reading the G/A - Unit Quantity (Number) - North Direction & Plant Elevation - Kind of Equipments & Future Facilities - General Notes in Drawing - Legend & Abbreviation etc. in Drawing
  • 10. DOOSAN 10 -6. Introduction of G/A for MD II - Key Plan & Each Plan View - Side Elevation View - Front & Rear Elevation View - Reference Picture • Unit Description • General Layout Graphic • Heating Surface & Steam Circuit • Water Circuit (Economizer) • Lifting Device for Equipment Maintenance • Access Door Location in Boiler Pressure Part • G/A Drawings
  • 11. DOOSAN 11 - Name of Plant Mong Duong II TPP Generation (MWe) 560MW x 2 units Evaporation 1.912 ton/hr Type of boiler Subcritical, Drum Type and Natural Circulation Balanced Draft, Semi-Outdoor Firing Type Slot Burners (Downshot Firing System) Total 36ea Burners (Slot Burner 24 + Wall Burner 12) Fuel Anthracite Coal Boiler Size (m) Furnace Width : 28.520 Furnace Depth : 22.712 Furnace Height : 55.217 Executing • Design : DOOSAN Babcock & DOOSAN Co-work • Manufacturing : DOOSAN Changwon Factory • Commissioning : DOOSAN Babcock & DOOSAN Co-work Unit Description 15.0° PLATEN SH 600 F W F W ECONOMISER FINAL SH PRI RH 1st BANK PRI RH 3rd BANK PRI RH 2nd BANK PRI SH 1st BANK PRI SH 3rd BANK PRI SH 2nd BANK FINAL RH
  • 12. DOOSAN 12-General Layout Graphic 15 3 23 25 9 13 1 22 19 4 20 26 24 5 14 21 16 17 18 2 611 12 87 27 28 29 30 10 31 26A 21A 26B 27A Air Duct System ; Cold air supplied from FD fan is after heated by hot gas in the GAPH. and hot air is transported through wind box into the burner. for combustion. Gas Duct System ; After recovering heat from hot flue gas at the furnace and through to the SCR, GAPH, EP, IDF, FGD(or FGD bypass) and stack and exhausted to atmosphere. Electrostatic Precipitator DESCRIPTION OF COMPONENTS Cold Reheater Pipe Main Steam Pipe Final Superheater Platen Superheater Primary Superheater Downcomers Steam Drum Economizer Feed Water Pipe Furnace Water Wall Silencer Blow Down Tank Hot Reheater Pipe Final Reheater Wall Burner Slot Burner Set Gas Air Preheater Steam Coil Air Heater Forced Draft Fan Seal Air Fan Primary Air Fan Coal Feeder Coal Silo Coal Tripper Tube Mill S.C.R C.I.D Fan Stack Primary Reheater 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 21A 22 23 Mixed P.A Duct 24 25 26 26A 26B Classifiers Coal Pipes 27 27A Bias Damper 28 29 30 31 SCC Bottom Ash Sys
  • 13. DOOSAN 15.0° PLATEN SH 600 F W F W ECONOMISER FINAL SH PRI RH 1st BANK PRI RH 3rd BANK PRI RH 2nd BANK PRI SH 1st BANK PRI SH 3rd BANK PRI SH 2nd BANK FINAL RH 13 -Heating Surface Arrangement & Steam Circuit RH Inlet Header SH Outlet Header High Gas Temperature RH Outlet Header Final Superheater Pass Tertiary Burners Slot Burner Sets Economizer Steam Drum Reheater Pass Superheater Pass Wind box
  • 14. DOOSAN 14 -Water Circuit (Economizer) Eco. Inlet Header Steam Drum
  • 15. DOOSAN 15 - The boiler pressure parts have been designed / selected to ensure both ready access and long term reliability. : Access Door Access Door Location in Boiler Pressure Part - Size 500 x 500 in Tube walls - Size 500 x 900 in Furnace hopper : Observation Door
  • 16. DOOSAN 16 -Equipment Maintenance - Boiler, Equipment Location & Duct Layout Lifting Device Supply List /Per Boiler Equipment Capacity x Q’ty Type Location in G/A Dwg. Remarks 1 F.D Fan (Motor) 20 Ton x 2 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 10m 2 F.D Fan (Rotor) 5 Ton x 2 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 10m 3 P.A Fan (Motor) 16 Ton x 1 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 08m 4 P.A Fan (Rotor) 5 Ton x 1 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 08m 5 I.D Fan (Motor) 29 Ton x 2 Sets Motor Driven, Monorail Hoist -310013/310014 Lifting Height 12m 6 I.D Fan (Rotor) 10 Ton x 1 Sets Motor Driven, Monorail Hoist -310013/310014 Lifting Height 12m 7 Scanner Cooling Air Fan Motor 2 Ton x 1 Set Motor Driven, Monorail Hoist -310005 Lifting Height 08m 8 Gas Air Preheater Basket 2 Ton x 2 Sets Motor Driven, Monorail Hoist -310005 Lifting Height 28m 9 Pulverizer (Motor) 30 Ton x 6 Sets Motor Driven, Monorail Hoist -310004 Lifting Height 14m 10 Pulverizer Ball Charge 2 Ton x 1 Sets Motor Driven, Monorail Hoist -310004 Lifting Height 20m 11 Common Chain Block W/ Geared Trolley 3.5 Ton x 24Sets Manual Not Specified Lifting Height 7m 12 Common Chain Block 2 Ton x 2 Sets Manual Not Specified Lifting Height 5m 13 14 15 16
  • 17. DOOSAN 17 -G/A Drawing - (Key plan)
  • 18. DOOSAN 18 -G/A Drawing - (Side View)
  • 19. DOOSAN 19 -G/A Drawing - (Front View)
  • 20. DOOSAN 20 -G/A Drawing - (Rear View)
  • 21. DOOSAN 21 -G/A Drawing – (Ground floor Plan View)
  • 22. DOOSAN 22 -G/A Drawing - (Plan View “04-04”)
  • 23. DOOSAN 23 -G/A Drawing - (Top Plan View)
  • 24. DOOSAN Boiler Instrument Insert Location- (Connection Insert list)
  • 25. DOOSAN Boiler Instrument Insert Location- (Connection Detail)
  • 26. DOOSAN Boiler Instrument Insert Location- (Side Elevation View)
  • 27. DOOSAN Boiler Instrument Insert Location- (Plan Section View)
  • 28. DOOSAN Support Steel For Ret. Sootblowers (1/2)
  • 29. DOOSAN Support Steel For Ret. Sootblowers (2/2)
  • 30. DOOSAN 24 -G/A Drawing - (Reference Picture) Furnace Wall Lance Tube Axial Type Fan (F.D fan & I.D fan) Centrifugal Type Fan (G.R fan) Long Retractable Soot Blower