2. DOOSAN
Contents
2. Work Boundaries
1. Definition & Mission
2 -
4. Layout Considerations
3. Design Objectives
5. Understanding of G/A Drawing
6. Introduction of G/A for MD II
7. Appendix
3. DOOSAN
3 -1. Definition & Mission
• The General Arrangement drawing is a basic document which shows
the arrangement of the Boiler, Steel Structure, Auxiliary equipments,
Air & Gas ducts and Major Piping etc. relative to each other in the
Proper area specified by Customer.
• The G/A drawing visualizes the actual size of the various equipments
and represents them in a scaled down manner in both elevation and
plan views.
G/A drawing is just for indicating the general information, but all the more information of actual
platform area, partial platform elevation and local stair/ladder location etc. refer to the relevant
steelwork drawings.
• The mission of G/A drawing
To ensure optimum arrangement/position of the various equipments
within the available space. (Economical efficiency)
To ensure easy access and maintenance.
To co-ordinate between detailed design and Aux. equipments.
5. DOOSAN
3. Objectives
- Cost estimation
- Presentation in the proposal
- Guiding contract drafting
• For Proposal Stage
- Client approval and erection.
- Facilitate detailed design engineers on the relative arrangement / location of the
various boiler components and guides them during detail engineering.
- Provide information for basic design of Steel Structure, Piping & Duct Layout.
- Provide knowledge on the location, access, space availability, handling facilities
to plan maintenance activities.(To help O&M personnel)
- Provide information on interface details with other’s scope of work.
(To avoid interference between equipments, steel structure, piping etc.)
• For Contract Stage
5 -
6. DOOSAN
6 -4. Boiler G/A Considerations (1/3)
- Plant Elevation (ex, Mean Sea Level)
- Boiler Specification
• General Information
- Equipment Maintenance Space
- Boiler(Furnace) Envelope Dimensions & Instrument Connection Location
- Furnace & Back-pass Opening Location
(Soot blower, CCTV, Observation Door, Access Door etc.)
• Boiler Proper
- Buckstay Elevation
- Interface & Terminal Point
- Thermal Expansion Movement
7. DOOSAN
7 -
- Fans (F.D Fan, I.D Fan, P.A Fan, Seal Air Fan)
• Major Equipments (Location, Dimension & Shape)
- GAPH (Gas Air Preheater)
- SCAH (Steam Coil Air Heater)
- Environmental Equipments (FGD, SCR, ESP)
- Equipment Handling Device (Monorail Hoist, Crane, etc)
- Elevator (Passenger)
4. Boiler G/A Considerations (2/3)
8. DOOSAN
8 -
- Duct Configuration Including Size & Shape
• Air & Flue Gas System
- Column Location and Main Staircase Location
• Structural Steel
- Maintenance & Access Platform Elevations
- Damper, Expansion Joint & Access Door Location
- Major Pipe Runs, Pipe Size & Elevations (MS, HR, CR & FW)
• Piping
- Large Valve Locations (MOV. S/V)
- Instrument Connection Location
4. Boiler G/A Considerations (3/3)
9. DOOSAN
9 -
- Key Plan Drawing
• Kind of G/A Drawings
5. Understanding of Boiler G/A Drawing
- Plan View Drawing (Floor Plan)
- Side & Front/Rear Elevation View Drawing
- 3-Dimensional View (by PDS)
• Basic Knowledge to Reading the G/A
- Unit Quantity (Number)
- North Direction & Plant Elevation
- Kind of Equipments & Future Facilities
- General Notes in Drawing
- Legend & Abbreviation etc. in Drawing
10. DOOSAN
10 -6. Introduction of G/A for MD II
- Key Plan & Each Plan View
- Side Elevation View
- Front & Rear Elevation View
- Reference Picture
• Unit Description
• General Layout Graphic
• Heating Surface & Steam Circuit
• Water Circuit (Economizer)
• Lifting Device for Equipment Maintenance
• Access Door Location in Boiler Pressure Part
• G/A Drawings
11. DOOSAN
11 -
Name of Plant Mong Duong II TPP
Generation (MWe) 560MW x 2 units
Evaporation 1.912 ton/hr
Type of boiler
Subcritical,
Drum Type and Natural
Circulation
Balanced Draft, Semi-Outdoor
Firing Type
Slot Burners
(Downshot Firing System)
Total 36ea Burners
(Slot Burner 24 + Wall Burner 12)
Fuel Anthracite Coal
Boiler Size (m)
Furnace Width : 28.520
Furnace Depth : 22.712
Furnace Height : 55.217
Executing
• Design :
DOOSAN Babcock & DOOSAN
Co-work
• Manufacturing :
DOOSAN Changwon Factory
• Commissioning :
DOOSAN Babcock & DOOSAN
Co-work
Unit Description
15.0°
PLATEN SH
600
F W
F W
ECONOMISER
FINAL SH
PRI RH 1st BANK
PRI RH 3rd BANK
PRI RH 2nd BANK
PRI SH 1st BANK
PRI SH 3rd BANK
PRI SH 2nd BANK
FINAL RH
12. DOOSAN
12-General Layout Graphic
15
3
23
25
9
13
1
22
19
4
20
26
24
5
14
21
16
17
18
2
611
12
87
27
28
29
30
10
31
26A
21A
26B
27A
Air Duct System ;
Cold air supplied from FD fan is
after heated by hot gas in the
GAPH. and hot air is transported
through wind box into the burner.
for combustion.
Gas Duct System ;
After recovering heat from hot
flue gas at the furnace and
through to the SCR, GAPH,
EP, IDF, FGD(or FGD bypass)
and stack and exhausted to
atmosphere.
Electrostatic
Precipitator
DESCRIPTION OF COMPONENTS
Cold Reheater Pipe
Main Steam Pipe
Final
Superheater
Platen Superheater
Primary Superheater
Downcomers
Steam Drum
Economizer
Feed Water Pipe
Furnace Water Wall
Silencer
Blow Down Tank
Hot Reheater Pipe
Final Reheater
Wall Burner
Slot Burner Set
Gas Air Preheater
Steam Coil Air Heater
Forced Draft Fan
Seal Air Fan
Primary Air Fan
Coal Feeder
Coal Silo
Coal Tripper
Tube Mill
S.C.R
C.I.D Fan
Stack
Primary Reheater
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
21A
22
23
Mixed P.A Duct
24
25
26
26A
26B
Classifiers
Coal Pipes
27
27A Bias Damper
28
29
30
31
SCC Bottom Ash
Sys
13. DOOSAN
15.0°
PLATEN SH
600
F W
F W
ECONOMISER
FINAL SH
PRI RH 1st BANK
PRI RH 3rd BANK
PRI RH 2nd BANK
PRI SH 1st BANK
PRI SH 3rd BANK
PRI SH 2nd BANK
FINAL RH
13 -Heating Surface Arrangement & Steam Circuit
RH Inlet Header
SH Outlet Header
High Gas
Temperature
RH Outlet Header
Final Superheater
Pass
Tertiary Burners
Slot Burner Sets
Economizer
Steam Drum
Reheater Pass
Superheater Pass
Wind box
15. DOOSAN
15 -
The boiler pressure parts have been
designed / selected to ensure both
ready access and long term reliability.
: Access Door
Access Door Location in Boiler Pressure Part
- Size 500 x 500 in Tube walls
- Size 500 x 900 in Furnace hopper
: Observation Door
16. DOOSAN
16 -Equipment Maintenance
- Boiler, Equipment Location & Duct Layout
Lifting Device Supply List /Per Boiler
Equipment
Capacity
x Q’ty
Type
Location
in G/A Dwg.
Remarks
1 F.D Fan (Motor) 20 Ton x 2 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 10m
2 F.D Fan (Rotor) 5 Ton x 2 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 10m
3 P.A Fan (Motor) 16 Ton x 1 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 08m
4 P.A Fan (Rotor) 5 Ton x 1 Sets Motor Driven, Monorail Hoist -310003/310004 Lifting Height 08m
5 I.D Fan (Motor) 29 Ton x 2 Sets Motor Driven, Monorail Hoist -310013/310014 Lifting Height 12m
6 I.D Fan (Rotor) 10 Ton x 1 Sets Motor Driven, Monorail Hoist -310013/310014 Lifting Height 12m
7 Scanner Cooling Air Fan Motor 2 Ton x 1 Set Motor Driven, Monorail Hoist -310005 Lifting Height 08m
8 Gas Air Preheater Basket 2 Ton x 2 Sets Motor Driven, Monorail Hoist -310005 Lifting Height 28m
9 Pulverizer (Motor) 30 Ton x 6 Sets Motor Driven, Monorail Hoist -310004 Lifting Height 14m
10 Pulverizer Ball Charge 2 Ton x 1 Sets Motor Driven, Monorail Hoist -310004 Lifting Height 20m
11
Common Chain Block W/ Geared
Trolley
3.5 Ton x
24Sets
Manual Not Specified Lifting Height 7m
12 Common Chain Block 2 Ton x 2 Sets Manual Not Specified Lifting Height 5m
13
14
15
16
30. DOOSAN
24 -G/A Drawing - (Reference Picture)
Furnace Wall
Lance Tube
Axial Type Fan (F.D fan & I.D fan) Centrifugal Type Fan (G.R fan)
Long Retractable Soot Blower