ADCO Time plan.pdf
- 1. ID Task
Mode
Task Name Duration Manpower start date end date
1 ADMINSTARATIONS BLDG. FINISHED PRODUCTS WAREHOUSE BLDG. (B01) 25 days
2 FIRE ALARM 20 days
3 1st Fix (CODUIT) 0 days 02/05/2021 20/05/2021
4 2nd Fix (CABLE) 0 days 15/05/2021 05/06/2021
5 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 10 days 6
6 Testing & Comissioning 10 days 6
7 FIRE FIGHTING 10 days
8 1st Fix (PIPE INSTALTION) 10 days 6
9 2nd Fix (PIPE PAINTING) 5 days 6
10 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6
11 Testing & Comissioning 5 days 6
12 SMOKE & VENTILATION 25 days
13 DUCT INSTALATION 25 days 8 1/12/2021 25/12/2021
14 OUTLET INSTALATION 7 days 6 26/12/2021 06/1/2022
15 FANS INSTALATION 4 days 4 10/01/2022 14/1/2022
16 RESEARCH,Q.C,SYRUP,OINTMENT,SUPPOSITORIES & NEW AEROSOLE BLDG. (B02) 9 days
17 FIRE ALARM 9 days
18 1st Fix (CODUIT) 0 days 01/11/2021 10/11/2021
19 2nd Fix (CABLE) 0 days 08/11/2021 20/11/2021
20 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 6 days 6
21 Testing & Comissioning 3 days 6
22 FIRE FIGHTING 5 days
23 1st Fix (PIPE INSTALTION) 5 days 6
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: ADCO
Date: Mon 12/13/21
- 2. ID Task
Mode
Task Name Duration Manpower start date end date
24 2nd Fix (PIPE PAINTING) 2 days 6
25 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 2 days 6
26 Testing & Comissioning 2 days 6
27 POWDER,CENTRAL PILL PACKING & WORKSHOPS BLDG. (B03) 10 days
28 FIRE ALARM 10 days
29 1st Fix (CODUIT) 0 days 02/06/2021 10/06/2021
30 2nd Fix (CABLE) 0 days 09/06/2021 20/06/2021
31 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
32 Testing & Comissioning 5 days 6
33 FIRE FIGHTING 5 days
34 1st Fix (PIPE INSTALTION) 5 days 15/10/2021 25/10/2021
35 2nd Fix (PIPE PAINTING) 3 days 25/10/2021 30/10/2021
36 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 6
37 Testing & Comissioning 1 day 6
38 AEROSOLE BLDG. (B04) 30 days
39 FIRE ALARM 30 days
40 1st Fix (CODUIT) 15 days 6
41 2nd Fix (CABLE) 5 days 6
42 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
43 Testing & Comissioning 5 days 6
44 FIRE FIGHTING 10 days
45 1st Fix (PIPE INSTALTION) 10 days 6
46 2nd Fix (PIPE PAINTING) 5 days 6
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: ADCO
Date: Mon 12/13/21
- 3. ID Task
Mode
Task Name Duration Manpower start date end date
47 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6
48 Testing & Comissioning 3 days 6
49 PILLS & RIVO BLDG. (B05) 40 days
50 FIRE ALARM 40 days
51 1st Fix (CODUIT) 20 days 6
52 2nd Fix (CABLE) 10 days 6
53 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
54 Testing & Comissioning 5 days 6
55 FIRE FIGHTING 20 days
56 1st Fix (PIPE INSTALTION) 20 days 6
57 2nd Fix (PIPE PAINTING) 7 days 6
58 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6
59 Testing & Comissioning 2 days 6
60 SUPPLIES BLDG. (B06) 20 days
61 FIRE ALARM 12 days
62 1st Fix (CODUIT) 0 days 12/04/2021 10/05/2021
63 2nd Fix (CABLE) 0 days 05/05/2021 01/06/2021
64 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 6 days 6
65 Testing & Comissioning 6 days 6
66 FIRE FIGHTING 20 days
67 1st Fix (PIPE INSTALTION) 20 days 6
68 2nd Fix (PIPE PAINTING) 7 days 6
69 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: ADCO
Date: Mon 12/13/21
- 4. ID Task
Mode
Task Name Duration Manpower start date end date
70 Testing & Comissioning 2 days 6
71 SMOKE & VENTILATION 20 days
72 DUCT INSTALATION 20 days 8
73 OUTLET INSTALATION 5 days 6
74 FANS INSTALATION 3 days 4
75 MATERIALS BLDGS. (B07) 45 days
76 FIRE ALARM 45 days
77 1st Fix (CODUIT) 25 days 6
78 2nd Fix (CABLE) 10 days 6
79 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
80 Testing & Comissioning 5 days 6
81 FIRE FIGHTING 25 days
82 1st Fix (PIPE INSTALTION) 25 days 6
83 2nd Fix (PIPE PAINTING) 10 days 6
84 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6
85 Testing & Comissioning 5 days 6
86 SMOKE & VENTILATION 20 days
87 DUCT INSTALATION 20 days 8
88 OUTLET INSTALATION 5 days 6
89 FANS INSTALATION 3 days 4
90 QUALITY ASSURANCE & OINTMENT PACKING BLDG. (B08) 13 days
91 FIRE Alarm 13 days
92 1st Fix (CODUIT) 7 days 6
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: ADCO
Date: Mon 12/13/21
- 5. ID Task
Mode
Task Name Duration Manpower start date end date
93 2nd Fix (CABLE) 3 days 6
94 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 6
95 Testing & Comissioning 1 day 6
96 FIRE Fighting 4 days
97 1st Fix (PIPE INSTALTION) 4 days 4
98 2nd Fix (PIPE PAINTING) 2 days 4
99 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 2 days 4
100 Testing & Comissioning 1 day 4
101 Trea Ted Water Plant (B09) 5 days
102 FIRE Alarm 5 days
103 1st Fix (CODUIT) 0 days 01/07/2021 04/07/2021
104 2nd Fix (CABLE) 0 days 03/07/2021 08/07/2021
105 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 4
106 Testing & Comissioning 2 days 4
107 FIRE Fighting 1 day
108 F.E INSTALATION 1 day 1
109 BOILER BLDG. & MAIN ELEC. STATION (B10) 10 days
110 FIRE Alarm 2 days
111 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
112 2nd Fix (CABLE) 0 days 27/04/2021 03/05/2021
113 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 0 days 22/06/2021 05/07/2021
114 Testing & Comissioning 2 days 4
115 FIRE Fighting 10 days
10/
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: ADCO
Date: Mon 12/13/21
- 6. ID Task
Mode
Task Name Duration Manpower start date end date
116 1st Fix (PIPE INSTALTION) 8 days 4 10/07/2021 18/07/2021
117 2nd Fix (PIPE PAINTING) 3 days 4 19/07/2021 21/07/2021
118 Finishing (SPRINKLER & FHC & VALVES & CYLINDER INSTALTION) 10 days 4 22/07/2021 01/08/2021
119 Testing & Comissioning 2 days 4
120 CENTRAL A.C. BLDG. (B11) 4 days
121 FIRE Alarm 4 days
122 1st Fix (CODUIT) 0 days 01/05/2021 03/05/2021
123 2nd Fix (CABLE) 0 days 02/05/2021 05/05/2021
124 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4
125 Testing & Comissioning 2 days 4
126 FIRE Fighting 1 day
127 F.E INSTALATION 1 day 1
128 GLASS WORKS HANGER (B12) 4 days
129 FIRE Alarm 4 days
130 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
131 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
132 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4
133 Testing & Comissioning 2 days 4
134 FIRE Fighting 4 days
135 1st Fix (PIPE INSTALTION) 4 days 4
136 2nd Fix (PIPE PAINTING) 2 days 4
137 Finishing (FHC & VALVES INSTALTION) 1 day 2
138 Testing & Comissioning 1 day 2
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: ADCO
Date: Mon 12/13/21
- 7. ID Task
Mode
Task Name Duration Manpower start date end date
139 WARE HOUSE BLDG.(B13) 26 days
140 FIRE Alarm 26 days
141 1st Fix (CODUIT) 10 days 6
142 2nd Fix (CABLE) 10 days 6
143 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 6
144 Testing & Comissioning 3 days 6
145 FIRE Fighting 20 days
146 1st Fix (PIPE INSTALTION) 20 days 6
147 2nd Fix (PIPE PAINTING) 7 days 6
148 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6
149 Testing & Comissioning 2 days 6
150 SMOKE & VENTILATION 20 days
151 DUCT INSTALATION 15 days 6
152 OUTLET INSTALATION 4 days 4
153 FANS INSTALATION 2 days 2
154 NURSERY & CLINIC BLDG. (B14) 2 days
155 FIRE ALARM 2 days
156 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
157 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
158 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 4
159 Testing & Comissioning 1 day 4
160 FIRE Fighting 1 day
161 F.E INSTALATION 1 day 1
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: ADCO
Date: Mon 12/13/21
- 8. ID Task
Mode
Task Name Duration Manpower start date end date
162 ENGINEERING MANAGEMENT BLDG. (B15) 2 days
163 FIRE Alarm 2 days
164 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
165 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
166 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 4
167 Testing & Comissioning 1 day 4
168 FIRE Fighting 1 day
169 F.E INSTALATION 1 day 1
170 MASJID BLDG. (B16) 2 days
171 FIRE Alarm 2 days
172 1st Fix (CODUIT) 0 days 23/04/2021 28/04/2021
173 2nd Fix (CABLE) 0 days 27/04/2021 29/04/2021
174 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2
175 Testing & Comissioning 1 day 2
176 FIRE Fighting 1 day
177 F.E INSTALATION 1 day 1
178 ENTRANCE GATE (B17) 4 days
179 FIRE Alarm 4 days
180 1st Fix (CODUIT) 1 day 2
181 2nd Fix (CABLE) 1 day 2
182 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2
183 Testing & Comissioning 1 day 2
184 FIRE Fighting 1 day
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: ADCO
Date: Mon 12/13/21
- 9. ID Task
Mode
Task Name Duration Manpower start date end date
185 F.E INSTALATION 1 day 1
186 INDUSTRIAL SAFETY BLDG. (B18) 3 days
187 FIRE Alarm 3 days
188 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
189 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
190 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4
191 Testing & Comissioning 1 day 4
192 FIRE FIGHTING 1 day
193 F.E INSTALATION 1 day 1
194 TRANSPORTATION BLDG. (B19) 5 days
195 FIRE Alarm 5 days
196 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
197 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
198 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 2
199 Testing & Comissioning 2 days 2
200 FIRE Fighting 2 days
201 1st Fix (PIPE INSTALTION) 2 days 2
202 2nd Fix (PIPE PAINTING) 1 day 2
203 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 2
204 Testing & Comissioning 1 day 2
205 WARE HOUSE BLDG. (B20) 2 days
206 FIRE Alarm 2 days
207 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
10/
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: ADCO
Date: Mon 12/13/21
- 10. ID Task
Mode
Task Name Duration Manpower start date end date
208 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
209 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2
210 Testing & Comissioning 1 day 2
211 FIRE Fighting 2 days
212 1st Fix (PIPE INSTALTION) 2 days 2
213 2nd Fix (PIPE PAINTING) 1 day 2
214 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 2
215 Testing & Comissioning 1 day 2
216 HAZARD MATERIALS WAREHOUSE (B21) 42 days
217 CIVIL 92 days
218 Soil Test 5 days 2 25/02/2021 01/03/2021
219 Removal 1 day 2 29/05/2021 29/05/2021
220 Secent Piles 60 days 8 01/06/2021 30/07/2021
221 Excavation 2 days 4 31/07/2021 01/08/2021
222 Replacement Layer 7 days 4 02/08/2021 08/08/2021
223 Termite Soil treatment 1 day 2 09/058/2021 09/08/2021
224 polyethlene sheet works under Foundation 1 day 2 09/08/2021 09/08/2021
225 Base Plain Concrete 5 days 6 10/08/2021 15/08/2021
226 Base Insulations 5 days 4 16/08/2021 20/08/2021
227 Base Reinforced Concrete 8 days 8 21/08/2021 28/08/2021
228 Wall & Columns Reinforced Concret 92 days 8 01/09/2021 01/12/2021
229 Backfill 1 day 2 02/12/2021 02/12/2021
230 Steel Structure 30 days 10 01/01/2021 30/01/2022
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: ADCO
Date: Mon 12/13/21
- 11. ID Task
Mode
Task Name Duration Manpower start date end date
231 Bricks Building 5 days 8 01/ 02/2022 05/02/2022
232 Interior Finishing 20 days 8 06/02/2022 26/02/2022
233 Exterior Finishing 20 days 8 06/02/2022 26/02/2022
234 Doors& Stairs Installation 3 days 2 25/02/2022 27/02/2022
235 Interlock 7 days 6 22/02/2022 28/02/2022
236 FIRE FIGHting 7 days
237 1st Fix (PIPE INSTALTION) 10 days 6 01/03/2022 10/03/2022
238 2nd Fix (PIPE PAINTING) 5 days 6 11/03/2022 15/03/2022
239 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6 16/03/2022 18/03/2022
240 Testing & Comissioning 2 days 6 19/03/2022 20/03/2022
241 FIRE Alarm 53 days
242 1st Fix (CODUIT) 3 days 6 01/03/2022 03/03/2022
243 2nd Fix (CABLE) 2 days 6 04/03/2022 05/03/2022
244 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 6 06/03/2022 06/03/2022
245 Testing & Comissioning 1 day 6 07/03/2022
246 SMOKE & VENTILATION 20 days
247 DUCT INSTALATION 8 days 6 01/03/2022 08/03/2022
248 OUTLET INSTALATION 3 days 4 09/08/2022 11/03/2022
249 FANS INSTALATION 2 days 2 12/03/2022 13/03/2022
250 ELECTRIC WORKS 20 days
251 1st Fix (CODUIT) 5 days 4 01/10/2021 05/10/2021
252 2nd Fix (CABLE) 3 days 4 01/01/2021 03/03/2022
253 LIGHTING FIXTURE INSTALATION 3 days 4 04/03/2022 06/03/2022
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: ADCO
Date: Mon 12/13/21
- 12. ID Task
Mode
Task Name Duration Manpower start date end date
254 EARTING WORKS 7 days 4 01/03/2022 07/03/2022
255 LIGHT CURRENT & CAMERA AND DATA WORKS 4 days 4 07/03/2022 10/03/2022
256 PORTABLE &FIREFIGHTING WATER TANK (B22) 84 days
257 CIVIL 84 days
258 Soil Test 5 days 2 25/02/2021 01/03/2021
259 Removal 5 days 2 01/04/2021 05/04/2021
260 Secent Piles 42 days 8 18/04/2021 29/05/2021
261 Excavation 2 days 4 30/05/2021 31/05/2021
262 Replacement Layer 10 days 4 13/06/2021 22/06/2021
263 Termite Soil treatment 1 day 2 26/06/2021 26/06/2021
264 polyethlene sheet works under Foundation 1 day 2 27/06/2021 27/06/2021
265 Plain Concrete 1 day 6 28/06/2021 28/06/2021
266 Base Insulations 7 days 4 29/06/2021 05/07/2021
267 Base Reinforced Concrete& Columns 20 days 6 06/07/2021 25/07/2021
268 Wall Insulation 5 days 6 26/07/2021 30/07/2021
269 Wall Reinforced Concret 10 days 8 01/08/2021 10/08/2021
270 Ceiling Reinforced Concret 5 days 8 11/08/2021 15/08/2021
271 Ceiling Insulation 3 days 6 01/12/2021 03/12/2021
272 Interior Finishing 60 days 6 01/11/2021 30/12/2021
273 Backfill 1 day 2 31/12/2021 31/12/2021
274 Asphalt 14 days 8 01/01/2022 14/01/2022
275 Interlock 10 days 6 15/01/2022 25/01/2022
276 Pump Room Instalation 15 days 6 01/01/2022 15/01/2022
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: ADCO
Date: Mon 12/13/21
- 13. ID Task
Mode
Task Name Duration Manpower start date end date
277 FIRE Fighting 5 days
278 1st Fix (PIPE INSTALTION) 2 days 2 01/01/2022 02/01/2022
279 2nd Fix (PIPE PAINTING) 2 days 2 03/01/2022 04/01/2022
280 Finishing (SPRINKLER & VALVES INSTALTION) 1 day 2 05/01/2022 05/01/2022
281 Testing & Comissioning 5 days 4 06/01/2022 10/01/2022
282 FIRE Alarm 2 days
283 1st Fix (CODUIT) 2 days 4 01/01/2022 02/01/2022
284 2nd Fix (CABLE) 2 days 4 03/01/2022 04/01/2022
285 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2 05/01/2022 05/01/2022
286 Testing & Comissioning 1 day 2 06/01/2022 06/01/2022
287 Outer Network 30 days
288 Fire Fighting 30 days 10
289 Fire Alarm 30 days 8
290 Water Supply 30 days 8
291 Pump Room Main Cable 1 day 8
292 UPS 2 days 4
293 BMS 2 days 4
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 13
Project: ADCO
Date: Mon 12/13/21