SlideShare a Scribd company logo
1 of 13
Download to read offline
ID Task
Mode
Task Name Duration Manpower start date end date
1 ADMINSTARATIONS BLDG. FINISHED PRODUCTS WAREHOUSE BLDG. (B01) 25 days
2 FIRE ALARM 20 days
3 1st Fix (CODUIT) 0 days 02/05/2021 20/05/2021
4 2nd Fix (CABLE) 0 days 15/05/2021 05/06/2021
5 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 10 days 6
6 Testing & Comissioning 10 days 6
7 FIRE FIGHTING 10 days
8 1st Fix (PIPE INSTALTION) 10 days 6
9 2nd Fix (PIPE PAINTING) 5 days 6
10 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6
11 Testing & Comissioning 5 days 6
12 SMOKE & VENTILATION 25 days
13 DUCT INSTALATION 25 days 8 1/12/2021 25/12/2021
14 OUTLET INSTALATION 7 days 6 26/12/2021 06/1/2022
15 FANS INSTALATION 4 days 4 10/01/2022 14/1/2022
16 RESEARCH,Q.C,SYRUP,OINTMENT,SUPPOSITORIES & NEW AEROSOLE BLDG. (B02) 9 days
17 FIRE ALARM 9 days
18 1st Fix (CODUIT) 0 days 01/11/2021 10/11/2021
19 2nd Fix (CABLE) 0 days 08/11/2021 20/11/2021
20 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 6 days 6
21 Testing & Comissioning 3 days 6
22 FIRE FIGHTING 5 days
23 1st Fix (PIPE INSTALTION) 5 days 6
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
24 2nd Fix (PIPE PAINTING) 2 days 6
25 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 2 days 6
26 Testing & Comissioning 2 days 6
27 POWDER,CENTRAL PILL PACKING & WORKSHOPS BLDG. (B03) 10 days
28 FIRE ALARM 10 days
29 1st Fix (CODUIT) 0 days 02/06/2021 10/06/2021
30 2nd Fix (CABLE) 0 days 09/06/2021 20/06/2021
31 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
32 Testing & Comissioning 5 days 6
33 FIRE FIGHTING 5 days
34 1st Fix (PIPE INSTALTION) 5 days 15/10/2021 25/10/2021
35 2nd Fix (PIPE PAINTING) 3 days 25/10/2021 30/10/2021
36 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 6
37 Testing & Comissioning 1 day 6
38 AEROSOLE BLDG. (B04) 30 days
39 FIRE ALARM 30 days
40 1st Fix (CODUIT) 15 days 6
41 2nd Fix (CABLE) 5 days 6
42 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
43 Testing & Comissioning 5 days 6
44 FIRE FIGHTING 10 days
45 1st Fix (PIPE INSTALTION) 10 days 6
46 2nd Fix (PIPE PAINTING) 5 days 6
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
47 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6
48 Testing & Comissioning 3 days 6
49 PILLS & RIVO BLDG. (B05) 40 days
50 FIRE ALARM 40 days
51 1st Fix (CODUIT) 20 days 6
52 2nd Fix (CABLE) 10 days 6
53 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
54 Testing & Comissioning 5 days 6
55 FIRE FIGHTING 20 days
56 1st Fix (PIPE INSTALTION) 20 days 6
57 2nd Fix (PIPE PAINTING) 7 days 6
58 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6
59 Testing & Comissioning 2 days 6
60 SUPPLIES BLDG. (B06) 20 days
61 FIRE ALARM 12 days
62 1st Fix (CODUIT) 0 days 12/04/2021 10/05/2021
63 2nd Fix (CABLE) 0 days 05/05/2021 01/06/2021
64 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 6 days 6
65 Testing & Comissioning 6 days 6
66 FIRE FIGHTING 20 days
67 1st Fix (PIPE INSTALTION) 20 days 6
68 2nd Fix (PIPE PAINTING) 7 days 6
69 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
70 Testing & Comissioning 2 days 6
71 SMOKE & VENTILATION 20 days
72 DUCT INSTALATION 20 days 8
73 OUTLET INSTALATION 5 days 6
74 FANS INSTALATION 3 days 4
75 MATERIALS BLDGS. (B07) 45 days
76 FIRE ALARM 45 days
77 1st Fix (CODUIT) 25 days 6
78 2nd Fix (CABLE) 10 days 6
79 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6
80 Testing & Comissioning 5 days 6
81 FIRE FIGHTING 25 days
82 1st Fix (PIPE INSTALTION) 25 days 6
83 2nd Fix (PIPE PAINTING) 10 days 6
84 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6
85 Testing & Comissioning 5 days 6
86 SMOKE & VENTILATION 20 days
87 DUCT INSTALATION 20 days 8
88 OUTLET INSTALATION 5 days 6
89 FANS INSTALATION 3 days 4
90 QUALITY ASSURANCE & OINTMENT PACKING BLDG. (B08) 13 days
91 FIRE Alarm 13 days
92 1st Fix (CODUIT) 7 days 6
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
93 2nd Fix (CABLE) 3 days 6
94 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 6
95 Testing & Comissioning 1 day 6
96 FIRE Fighting 4 days
97 1st Fix (PIPE INSTALTION) 4 days 4
98 2nd Fix (PIPE PAINTING) 2 days 4
99 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 2 days 4
100 Testing & Comissioning 1 day 4
101 Trea Ted Water Plant (B09) 5 days
102 FIRE Alarm 5 days
103 1st Fix (CODUIT) 0 days 01/07/2021 04/07/2021
104 2nd Fix (CABLE) 0 days 03/07/2021 08/07/2021
105 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 4
106 Testing & Comissioning 2 days 4
107 FIRE Fighting 1 day
108 F.E INSTALATION 1 day 1
109 BOILER BLDG. & MAIN ELEC. STATION (B10) 10 days
110 FIRE Alarm 2 days
111 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
112 2nd Fix (CABLE) 0 days 27/04/2021 03/05/2021
113 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 0 days 22/06/2021 05/07/2021
114 Testing & Comissioning 2 days 4
115 FIRE Fighting 10 days
10/
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
116 1st Fix (PIPE INSTALTION) 8 days 4 10/07/2021 18/07/2021
117 2nd Fix (PIPE PAINTING) 3 days 4 19/07/2021 21/07/2021
118 Finishing (SPRINKLER & FHC & VALVES & CYLINDER INSTALTION) 10 days 4 22/07/2021 01/08/2021
119 Testing & Comissioning 2 days 4
120 CENTRAL A.C. BLDG. (B11) 4 days
121 FIRE Alarm 4 days
122 1st Fix (CODUIT) 0 days 01/05/2021 03/05/2021
123 2nd Fix (CABLE) 0 days 02/05/2021 05/05/2021
124 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4
125 Testing & Comissioning 2 days 4
126 FIRE Fighting 1 day
127 F.E INSTALATION 1 day 1
128 GLASS WORKS HANGER (B12) 4 days
129 FIRE Alarm 4 days
130 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
131 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
132 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4
133 Testing & Comissioning 2 days 4
134 FIRE Fighting 4 days
135 1st Fix (PIPE INSTALTION) 4 days 4
136 2nd Fix (PIPE PAINTING) 2 days 4
137 Finishing (FHC & VALVES INSTALTION) 1 day 2
138 Testing & Comissioning 1 day 2
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
139 WARE HOUSE BLDG.(B13) 26 days
140 FIRE Alarm 26 days
141 1st Fix (CODUIT) 10 days 6
142 2nd Fix (CABLE) 10 days 6
143 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 6
144 Testing & Comissioning 3 days 6
145 FIRE Fighting 20 days
146 1st Fix (PIPE INSTALTION) 20 days 6
147 2nd Fix (PIPE PAINTING) 7 days 6
148 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6
149 Testing & Comissioning 2 days 6
150 SMOKE & VENTILATION 20 days
151 DUCT INSTALATION 15 days 6
152 OUTLET INSTALATION 4 days 4
153 FANS INSTALATION 2 days 2
154 NURSERY & CLINIC BLDG. (B14) 2 days
155 FIRE ALARM 2 days
156 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
157 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
158 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 4
159 Testing & Comissioning 1 day 4
160 FIRE Fighting 1 day
161 F.E INSTALATION 1 day 1
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
162 ENGINEERING MANAGEMENT BLDG. (B15) 2 days
163 FIRE Alarm 2 days
164 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
165 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
166 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 4
167 Testing & Comissioning 1 day 4
168 FIRE Fighting 1 day
169 F.E INSTALATION 1 day 1
170 MASJID BLDG. (B16) 2 days
171 FIRE Alarm 2 days
172 1st Fix (CODUIT) 0 days 23/04/2021 28/04/2021
173 2nd Fix (CABLE) 0 days 27/04/2021 29/04/2021
174 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2
175 Testing & Comissioning 1 day 2
176 FIRE Fighting 1 day
177 F.E INSTALATION 1 day 1
178 ENTRANCE GATE (B17) 4 days
179 FIRE Alarm 4 days
180 1st Fix (CODUIT) 1 day 2
181 2nd Fix (CABLE) 1 day 2
182 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2
183 Testing & Comissioning 1 day 2
184 FIRE Fighting 1 day
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
185 F.E INSTALATION 1 day 1
186 INDUSTRIAL SAFETY BLDG. (B18) 3 days
187 FIRE Alarm 3 days
188 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
189 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
190 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4
191 Testing & Comissioning 1 day 4
192 FIRE FIGHTING 1 day
193 F.E INSTALATION 1 day 1
194 TRANSPORTATION BLDG. (B19) 5 days
195 FIRE Alarm 5 days
196 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
197 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
198 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 2
199 Testing & Comissioning 2 days 2
200 FIRE Fighting 2 days
201 1st Fix (PIPE INSTALTION) 2 days 2
202 2nd Fix (PIPE PAINTING) 1 day 2
203 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 2
204 Testing & Comissioning 1 day 2
205 WARE HOUSE BLDG. (B20) 2 days
206 FIRE Alarm 2 days
207 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021
10/
10/
10/
10/
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
208 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021
209 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2
210 Testing & Comissioning 1 day 2
211 FIRE Fighting 2 days
212 1st Fix (PIPE INSTALTION) 2 days 2
213 2nd Fix (PIPE PAINTING) 1 day 2
214 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 2
215 Testing & Comissioning 1 day 2
216 HAZARD MATERIALS WAREHOUSE (B21) 42 days
217 CIVIL 92 days
218 Soil Test 5 days 2 25/02/2021 01/03/2021
219 Removal 1 day 2 29/05/2021 29/05/2021
220 Secent Piles 60 days 8 01/06/2021 30/07/2021
221 Excavation 2 days 4 31/07/2021 01/08/2021
222 Replacement Layer 7 days 4 02/08/2021 08/08/2021
223 Termite Soil treatment 1 day 2 09/058/2021 09/08/2021
224 polyethlene sheet works under Foundation 1 day 2 09/08/2021 09/08/2021
225 Base Plain Concrete 5 days 6 10/08/2021 15/08/2021
226 Base Insulations 5 days 4 16/08/2021 20/08/2021
227 Base Reinforced Concrete 8 days 8 21/08/2021 28/08/2021
228 Wall & Columns Reinforced Concret 92 days 8 01/09/2021 01/12/2021
229 Backfill 1 day 2 02/12/2021 02/12/2021
230 Steel Structure 30 days 10 01/01/2021 30/01/2022
10/
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
231 Bricks Building 5 days 8 01/ 02/2022 05/02/2022
232 Interior Finishing 20 days 8 06/02/2022 26/02/2022
233 Exterior Finishing 20 days 8 06/02/2022 26/02/2022
234 Doors& Stairs Installation 3 days 2 25/02/2022 27/02/2022
235 Interlock 7 days 6 22/02/2022 28/02/2022
236 FIRE FIGHting 7 days
237 1st Fix (PIPE INSTALTION) 10 days 6 01/03/2022 10/03/2022
238 2nd Fix (PIPE PAINTING) 5 days 6 11/03/2022 15/03/2022
239 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6 16/03/2022 18/03/2022
240 Testing & Comissioning 2 days 6 19/03/2022 20/03/2022
241 FIRE Alarm 53 days
242 1st Fix (CODUIT) 3 days 6 01/03/2022 03/03/2022
243 2nd Fix (CABLE) 2 days 6 04/03/2022 05/03/2022
244 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 6 06/03/2022 06/03/2022
245 Testing & Comissioning 1 day 6 07/03/2022
246 SMOKE & VENTILATION 20 days
247 DUCT INSTALATION 8 days 6 01/03/2022 08/03/2022
248 OUTLET INSTALATION 3 days 4 09/08/2022 11/03/2022
249 FANS INSTALATION 2 days 2 12/03/2022 13/03/2022
250 ELECTRIC WORKS 20 days
251 1st Fix (CODUIT) 5 days 4 01/10/2021 05/10/2021
252 2nd Fix (CABLE) 3 days 4 01/01/2021 03/03/2022
253 LIGHTING FIXTURE INSTALATION 3 days 4 04/03/2022 06/03/2022
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
254 EARTING WORKS 7 days 4 01/03/2022 07/03/2022
255 LIGHT CURRENT & CAMERA AND DATA WORKS 4 days 4 07/03/2022 10/03/2022
256 PORTABLE &FIREFIGHTING WATER TANK (B22) 84 days
257 CIVIL 84 days
258 Soil Test 5 days 2 25/02/2021 01/03/2021
259 Removal 5 days 2 01/04/2021 05/04/2021
260 Secent Piles 42 days 8 18/04/2021 29/05/2021
261 Excavation 2 days 4 30/05/2021 31/05/2021
262 Replacement Layer 10 days 4 13/06/2021 22/06/2021
263 Termite Soil treatment 1 day 2 26/06/2021 26/06/2021
264 polyethlene sheet works under Foundation 1 day 2 27/06/2021 27/06/2021
265 Plain Concrete 1 day 6 28/06/2021 28/06/2021
266 Base Insulations 7 days 4 29/06/2021 05/07/2021
267 Base Reinforced Concrete& Columns 20 days 6 06/07/2021 25/07/2021
268 Wall Insulation 5 days 6 26/07/2021 30/07/2021
269 Wall Reinforced Concret 10 days 8 01/08/2021 10/08/2021
270 Ceiling Reinforced Concret 5 days 8 11/08/2021 15/08/2021
271 Ceiling Insulation 3 days 6 01/12/2021 03/12/2021
272 Interior Finishing 60 days 6 01/11/2021 30/12/2021
273 Backfill 1 day 2 31/12/2021 31/12/2021
274 Asphalt 14 days 8 01/01/2022 14/01/2022
275 Interlock 10 days 6 15/01/2022 25/01/2022
276 Pump Room Instalation 15 days 6 01/01/2022 15/01/2022
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: ADCO
Date: Mon 12/13/21
ID Task
Mode
Task Name Duration Manpower start date end date
277 FIRE Fighting 5 days
278 1st Fix (PIPE INSTALTION) 2 days 2 01/01/2022 02/01/2022
279 2nd Fix (PIPE PAINTING) 2 days 2 03/01/2022 04/01/2022
280 Finishing (SPRINKLER & VALVES INSTALTION) 1 day 2 05/01/2022 05/01/2022
281 Testing & Comissioning 5 days 4 06/01/2022 10/01/2022
282 FIRE Alarm 2 days
283 1st Fix (CODUIT) 2 days 4 01/01/2022 02/01/2022
284 2nd Fix (CABLE) 2 days 4 03/01/2022 04/01/2022
285 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2 05/01/2022 05/01/2022
286 Testing & Comissioning 1 day 2 06/01/2022 06/01/2022
287 Outer Network 30 days
288 Fire Fighting 30 days 10
289 Fire Alarm 30 days 8
290 Water Supply 30 days 8
291 Pump Room Main Cable 1 day 8
292 UPS 2 days 4
293 BMS 2 days 4
E M B E
Septe Jan
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 13
Project: ADCO
Date: Mon 12/13/21

More Related Content

Similar to ADCO Time plan.pdf

Similar to ADCO Time plan.pdf (13)

Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
PPT_14.03.2022.pptx
PPT_14.03.2022.pptxPPT_14.03.2022.pptx
PPT_14.03.2022.pptx
 
program
programprogram
program
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
Slide4 mp psht1of6
Slide4 mp psht1of6Slide4 mp psht1of6
Slide4 mp psht1of6
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
BERNARDO ANA DOS SANTOS MONDLANE
BERNARDO ANA DOS SANTOS MONDLANEBERNARDO ANA DOS SANTOS MONDLANE
BERNARDO ANA DOS SANTOS MONDLANE
 
20220214 20220704 - d26821027 - draft
20220214   20220704 - d26821027 - draft20220214   20220704 - d26821027 - draft
20220214 20220704 - d26821027 - draft
 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
Typical Project Format.pptx
Typical Project Format.pptxTypical Project Format.pptx
Typical Project Format.pptx
 
CPM
CPMCPM
CPM
 
Popop
PopopPopop
Popop
 

More from abdo badr

8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdf
8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdf8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdf
8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdfabdo badr
 
الاقتراح الاولfat.docx
الاقتراح الاولfat.docxالاقتراح الاولfat.docx
الاقتراح الاولfat.docxabdo badr
 
Sun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdf
Sun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdfSun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdf
Sun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdfabdo badr
 
برنامج زمنى لقسم الاقراص ’March 22.pdf
برنامج زمنى لقسم الاقراص ’March 22.pdfبرنامج زمنى لقسم الاقراص ’March 22.pdf
برنامج زمنى لقسم الاقراص ’March 22.pdfabdo badr
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfabdo badr
 
CLEANING_VALIDATION_PRESENTATION.ppt
CLEANING_VALIDATION_PRESENTATION.pptCLEANING_VALIDATION_PRESENTATION.ppt
CLEANING_VALIDATION_PRESENTATION.pptabdo badr
 
04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...
04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...
04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...abdo badr
 
TUFTAD_Seyfang_DPI_filling_20150305_draft1.pdf
TUFTAD_Seyfang_DPI_filling_20150305_draft1.pdfTUFTAD_Seyfang_DPI_filling_20150305_draft1.pdf
TUFTAD_Seyfang_DPI_filling_20150305_draft1.pdfabdo badr
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptxabdo badr
 
chemistry_3sec.pdf
chemistry_3sec.pdfchemistry_3sec.pdf
chemistry_3sec.pdfabdo badr
 
dokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptx
dokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptxdokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptx
dokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptxabdo badr
 
PHAR_article_37004_en_1.pdf
PHAR_article_37004_en_1.pdfPHAR_article_37004_en_1.pdf
PHAR_article_37004_en_1.pdfabdo badr
 

More from abdo badr (13)

8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdf
8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdf8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdf
8.4 PERFORMANCE QUALIFICATION PROTOCOL FOR DISPENSING BOOTH (1).pdf
 
الاقتراح الاولfat.docx
الاقتراح الاولfat.docxالاقتراح الاولfat.docx
الاقتراح الاولfat.docx
 
Sun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdf
Sun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdfSun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdf
Sun-Pharma-Risk-Management-Policy-Synopsis-May-2022.pdf
 
برنامج زمنى لقسم الاقراص ’March 22.pdf
برنامج زمنى لقسم الاقراص ’March 22.pdfبرنامج زمنى لقسم الاقراص ’March 22.pdf
برنامج زمنى لقسم الاقراص ’March 22.pdf
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdf
 
CLEANING_VALIDATION_PRESENTATION.ppt
CLEANING_VALIDATION_PRESENTATION.pptCLEANING_VALIDATION_PRESENTATION.ppt
CLEANING_VALIDATION_PRESENTATION.ppt
 
04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...
04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...
04_ISPEs_Guides_and_How_They_Apply_to_Cleaning_and_Cleaning_Validation_by_Ste...
 
TUFTAD_Seyfang_DPI_filling_20150305_draft1.pdf
TUFTAD_Seyfang_DPI_filling_20150305_draft1.pdfTUFTAD_Seyfang_DPI_filling_20150305_draft1.pdf
TUFTAD_Seyfang_DPI_filling_20150305_draft1.pdf
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
chemistry_3sec.pdf
chemistry_3sec.pdfchemistry_3sec.pdf
chemistry_3sec.pdf
 
dokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptx
dokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptxdokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptx
dokumen.tips_validation-of-water-system-for-pharmaceutical-use.pptx
 
PHAR_article_37004_en_1.pdf
PHAR_article_37004_en_1.pdfPHAR_article_37004_en_1.pdf
PHAR_article_37004_en_1.pdf
 
17025.pptx
17025.pptx17025.pptx
17025.pptx
 

Recently uploaded

Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)
Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)
Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)Lokesh Kothari
 
Story of the Origin of Some Foods in Bengal.docx
Story of the Origin of Some Foods in Bengal.docxStory of the Origin of Some Foods in Bengal.docx
Story of the Origin of Some Foods in Bengal.docxTapas Kumar Basu
 
Elo Cakes | Premium Cake Shop | Order Now
Elo Cakes | Premium Cake Shop | Order NowElo Cakes | Premium Cake Shop | Order Now
Elo Cakes | Premium Cake Shop | Order NowElo Cakes
 
FSSAI.ppt Food safety standards act in RAFN
FSSAI.ppt Food safety standards act in RAFNFSSAI.ppt Food safety standards act in RAFN
FSSAI.ppt Food safety standards act in RAFNLokesh Kothari
 
100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...
100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...
100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...drjose256
 
Grocery_ POS_ Billing _Software (1).pptx
Grocery_ POS_ Billing _Software (1).pptxGrocery_ POS_ Billing _Software (1).pptx
Grocery_ POS_ Billing _Software (1).pptxQueueBuster
 
NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...
NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...
NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...Amil baba
 
Postharvest technology and manageent.ppt
Postharvest technology  and manageent.pptPostharvest technology  and manageent.ppt
Postharvest technology and manageent.pptnazmulhrt
 
NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...
NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...
NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...Amil Baba Dawood bangali
 

Recently uploaded (10)

Chaine des Rotisseurs Gala Dinner Menu May 25 2024 Cambodia
Chaine des Rotisseurs Gala Dinner Menu May 25 2024 CambodiaChaine des Rotisseurs Gala Dinner Menu May 25 2024 Cambodia
Chaine des Rotisseurs Gala Dinner Menu May 25 2024 Cambodia
 
Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)
Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)
Medical Foods final.ppt (Regulatory Aspects of Food & Nutraceiticals)
 
Story of the Origin of Some Foods in Bengal.docx
Story of the Origin of Some Foods in Bengal.docxStory of the Origin of Some Foods in Bengal.docx
Story of the Origin of Some Foods in Bengal.docx
 
Elo Cakes | Premium Cake Shop | Order Now
Elo Cakes | Premium Cake Shop | Order NowElo Cakes | Premium Cake Shop | Order Now
Elo Cakes | Premium Cake Shop | Order Now
 
FSSAI.ppt Food safety standards act in RAFN
FSSAI.ppt Food safety standards act in RAFNFSSAI.ppt Food safety standards act in RAFN
FSSAI.ppt Food safety standards act in RAFN
 
100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...
100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...
100^%)( FORDSBURG))(*((+27838792658))*))௹ )Abortion Pills for Sale in Benoni,...
 
Grocery_ POS_ Billing _Software (1).pptx
Grocery_ POS_ Billing _Software (1).pptxGrocery_ POS_ Billing _Software (1).pptx
Grocery_ POS_ Billing _Software (1).pptx
 
NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...
NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...
NO1 Top Black Magic Expert Specialist In UK Black Magic Expert Specialist In ...
 
Postharvest technology and manageent.ppt
Postharvest technology  and manageent.pptPostharvest technology  and manageent.ppt
Postharvest technology and manageent.ppt
 
NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...
NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...
NO1 Pakistan Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Y...
 

ADCO Time plan.pdf

  • 1. ID Task Mode Task Name Duration Manpower start date end date 1 ADMINSTARATIONS BLDG. FINISHED PRODUCTS WAREHOUSE BLDG. (B01) 25 days 2 FIRE ALARM 20 days 3 1st Fix (CODUIT) 0 days 02/05/2021 20/05/2021 4 2nd Fix (CABLE) 0 days 15/05/2021 05/06/2021 5 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 10 days 6 6 Testing & Comissioning 10 days 6 7 FIRE FIGHTING 10 days 8 1st Fix (PIPE INSTALTION) 10 days 6 9 2nd Fix (PIPE PAINTING) 5 days 6 10 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6 11 Testing & Comissioning 5 days 6 12 SMOKE & VENTILATION 25 days 13 DUCT INSTALATION 25 days 8 1/12/2021 25/12/2021 14 OUTLET INSTALATION 7 days 6 26/12/2021 06/1/2022 15 FANS INSTALATION 4 days 4 10/01/2022 14/1/2022 16 RESEARCH,Q.C,SYRUP,OINTMENT,SUPPOSITORIES & NEW AEROSOLE BLDG. (B02) 9 days 17 FIRE ALARM 9 days 18 1st Fix (CODUIT) 0 days 01/11/2021 10/11/2021 19 2nd Fix (CABLE) 0 days 08/11/2021 20/11/2021 20 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 6 days 6 21 Testing & Comissioning 3 days 6 22 FIRE FIGHTING 5 days 23 1st Fix (PIPE INSTALTION) 5 days 6 10/ 10/ 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: ADCO Date: Mon 12/13/21
  • 2. ID Task Mode Task Name Duration Manpower start date end date 24 2nd Fix (PIPE PAINTING) 2 days 6 25 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 2 days 6 26 Testing & Comissioning 2 days 6 27 POWDER,CENTRAL PILL PACKING & WORKSHOPS BLDG. (B03) 10 days 28 FIRE ALARM 10 days 29 1st Fix (CODUIT) 0 days 02/06/2021 10/06/2021 30 2nd Fix (CABLE) 0 days 09/06/2021 20/06/2021 31 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6 32 Testing & Comissioning 5 days 6 33 FIRE FIGHTING 5 days 34 1st Fix (PIPE INSTALTION) 5 days 15/10/2021 25/10/2021 35 2nd Fix (PIPE PAINTING) 3 days 25/10/2021 30/10/2021 36 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 6 37 Testing & Comissioning 1 day 6 38 AEROSOLE BLDG. (B04) 30 days 39 FIRE ALARM 30 days 40 1st Fix (CODUIT) 15 days 6 41 2nd Fix (CABLE) 5 days 6 42 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6 43 Testing & Comissioning 5 days 6 44 FIRE FIGHTING 10 days 45 1st Fix (PIPE INSTALTION) 10 days 6 46 2nd Fix (PIPE PAINTING) 5 days 6 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: ADCO Date: Mon 12/13/21
  • 3. ID Task Mode Task Name Duration Manpower start date end date 47 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6 48 Testing & Comissioning 3 days 6 49 PILLS & RIVO BLDG. (B05) 40 days 50 FIRE ALARM 40 days 51 1st Fix (CODUIT) 20 days 6 52 2nd Fix (CABLE) 10 days 6 53 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6 54 Testing & Comissioning 5 days 6 55 FIRE FIGHTING 20 days 56 1st Fix (PIPE INSTALTION) 20 days 6 57 2nd Fix (PIPE PAINTING) 7 days 6 58 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6 59 Testing & Comissioning 2 days 6 60 SUPPLIES BLDG. (B06) 20 days 61 FIRE ALARM 12 days 62 1st Fix (CODUIT) 0 days 12/04/2021 10/05/2021 63 2nd Fix (CABLE) 0 days 05/05/2021 01/06/2021 64 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 6 days 6 65 Testing & Comissioning 6 days 6 66 FIRE FIGHTING 20 days 67 1st Fix (PIPE INSTALTION) 20 days 6 68 2nd Fix (PIPE PAINTING) 7 days 6 69 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: ADCO Date: Mon 12/13/21
  • 4. ID Task Mode Task Name Duration Manpower start date end date 70 Testing & Comissioning 2 days 6 71 SMOKE & VENTILATION 20 days 72 DUCT INSTALATION 20 days 8 73 OUTLET INSTALATION 5 days 6 74 FANS INSTALATION 3 days 4 75 MATERIALS BLDGS. (B07) 45 days 76 FIRE ALARM 45 days 77 1st Fix (CODUIT) 25 days 6 78 2nd Fix (CABLE) 10 days 6 79 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 5 days 6 80 Testing & Comissioning 5 days 6 81 FIRE FIGHTING 25 days 82 1st Fix (PIPE INSTALTION) 25 days 6 83 2nd Fix (PIPE PAINTING) 10 days 6 84 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 5 days 6 85 Testing & Comissioning 5 days 6 86 SMOKE & VENTILATION 20 days 87 DUCT INSTALATION 20 days 8 88 OUTLET INSTALATION 5 days 6 89 FANS INSTALATION 3 days 4 90 QUALITY ASSURANCE & OINTMENT PACKING BLDG. (B08) 13 days 91 FIRE Alarm 13 days 92 1st Fix (CODUIT) 7 days 6 E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: ADCO Date: Mon 12/13/21
  • 5. ID Task Mode Task Name Duration Manpower start date end date 93 2nd Fix (CABLE) 3 days 6 94 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 6 95 Testing & Comissioning 1 day 6 96 FIRE Fighting 4 days 97 1st Fix (PIPE INSTALTION) 4 days 4 98 2nd Fix (PIPE PAINTING) 2 days 4 99 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 2 days 4 100 Testing & Comissioning 1 day 4 101 Trea Ted Water Plant (B09) 5 days 102 FIRE Alarm 5 days 103 1st Fix (CODUIT) 0 days 01/07/2021 04/07/2021 104 2nd Fix (CABLE) 0 days 03/07/2021 08/07/2021 105 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 4 106 Testing & Comissioning 2 days 4 107 FIRE Fighting 1 day 108 F.E INSTALATION 1 day 1 109 BOILER BLDG. & MAIN ELEC. STATION (B10) 10 days 110 FIRE Alarm 2 days 111 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021 112 2nd Fix (CABLE) 0 days 27/04/2021 03/05/2021 113 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 0 days 22/06/2021 05/07/2021 114 Testing & Comissioning 2 days 4 115 FIRE Fighting 10 days 10/ 10/ 10/ 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 5 Project: ADCO Date: Mon 12/13/21
  • 6. ID Task Mode Task Name Duration Manpower start date end date 116 1st Fix (PIPE INSTALTION) 8 days 4 10/07/2021 18/07/2021 117 2nd Fix (PIPE PAINTING) 3 days 4 19/07/2021 21/07/2021 118 Finishing (SPRINKLER & FHC & VALVES & CYLINDER INSTALTION) 10 days 4 22/07/2021 01/08/2021 119 Testing & Comissioning 2 days 4 120 CENTRAL A.C. BLDG. (B11) 4 days 121 FIRE Alarm 4 days 122 1st Fix (CODUIT) 0 days 01/05/2021 03/05/2021 123 2nd Fix (CABLE) 0 days 02/05/2021 05/05/2021 124 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4 125 Testing & Comissioning 2 days 4 126 FIRE Fighting 1 day 127 F.E INSTALATION 1 day 1 128 GLASS WORKS HANGER (B12) 4 days 129 FIRE Alarm 4 days 130 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021 131 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021 132 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4 133 Testing & Comissioning 2 days 4 134 FIRE Fighting 4 days 135 1st Fix (PIPE INSTALTION) 4 days 4 136 2nd Fix (PIPE PAINTING) 2 days 4 137 Finishing (FHC & VALVES INSTALTION) 1 day 2 138 Testing & Comissioning 1 day 2 10/ 10/ 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 6 Project: ADCO Date: Mon 12/13/21
  • 7. ID Task Mode Task Name Duration Manpower start date end date 139 WARE HOUSE BLDG.(B13) 26 days 140 FIRE Alarm 26 days 141 1st Fix (CODUIT) 10 days 6 142 2nd Fix (CABLE) 10 days 6 143 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 6 144 Testing & Comissioning 3 days 6 145 FIRE Fighting 20 days 146 1st Fix (PIPE INSTALTION) 20 days 6 147 2nd Fix (PIPE PAINTING) 7 days 6 148 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6 149 Testing & Comissioning 2 days 6 150 SMOKE & VENTILATION 20 days 151 DUCT INSTALATION 15 days 6 152 OUTLET INSTALATION 4 days 4 153 FANS INSTALATION 2 days 2 154 NURSERY & CLINIC BLDG. (B14) 2 days 155 FIRE ALARM 2 days 156 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021 157 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021 158 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 4 159 Testing & Comissioning 1 day 4 160 FIRE Fighting 1 day 161 F.E INSTALATION 1 day 1 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 7 Project: ADCO Date: Mon 12/13/21
  • 8. ID Task Mode Task Name Duration Manpower start date end date 162 ENGINEERING MANAGEMENT BLDG. (B15) 2 days 163 FIRE Alarm 2 days 164 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021 165 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021 166 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 4 167 Testing & Comissioning 1 day 4 168 FIRE Fighting 1 day 169 F.E INSTALATION 1 day 1 170 MASJID BLDG. (B16) 2 days 171 FIRE Alarm 2 days 172 1st Fix (CODUIT) 0 days 23/04/2021 28/04/2021 173 2nd Fix (CABLE) 0 days 27/04/2021 29/04/2021 174 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2 175 Testing & Comissioning 1 day 2 176 FIRE Fighting 1 day 177 F.E INSTALATION 1 day 1 178 ENTRANCE GATE (B17) 4 days 179 FIRE Alarm 4 days 180 1st Fix (CODUIT) 1 day 2 181 2nd Fix (CABLE) 1 day 2 182 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2 183 Testing & Comissioning 1 day 2 184 FIRE Fighting 1 day 10/ 10/ 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 8 Project: ADCO Date: Mon 12/13/21
  • 9. ID Task Mode Task Name Duration Manpower start date end date 185 F.E INSTALATION 1 day 1 186 INDUSTRIAL SAFETY BLDG. (B18) 3 days 187 FIRE Alarm 3 days 188 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021 189 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021 190 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 2 days 4 191 Testing & Comissioning 1 day 4 192 FIRE FIGHTING 1 day 193 F.E INSTALATION 1 day 1 194 TRANSPORTATION BLDG. (B19) 5 days 195 FIRE Alarm 5 days 196 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021 197 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021 198 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 3 days 2 199 Testing & Comissioning 2 days 2 200 FIRE Fighting 2 days 201 1st Fix (PIPE INSTALTION) 2 days 2 202 2nd Fix (PIPE PAINTING) 1 day 2 203 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 2 204 Testing & Comissioning 1 day 2 205 WARE HOUSE BLDG. (B20) 2 days 206 FIRE Alarm 2 days 207 1st Fix (CODUIT) 0 days 22/04/2021 29/04/2021 10/ 10/ 10/ 10/ 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 9 Project: ADCO Date: Mon 12/13/21
  • 10. ID Task Mode Task Name Duration Manpower start date end date 208 2nd Fix (CABLE) 0 days 27/04/2021 05/05/2021 209 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2 210 Testing & Comissioning 1 day 2 211 FIRE Fighting 2 days 212 1st Fix (PIPE INSTALTION) 2 days 2 213 2nd Fix (PIPE PAINTING) 1 day 2 214 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 1 day 2 215 Testing & Comissioning 1 day 2 216 HAZARD MATERIALS WAREHOUSE (B21) 42 days 217 CIVIL 92 days 218 Soil Test 5 days 2 25/02/2021 01/03/2021 219 Removal 1 day 2 29/05/2021 29/05/2021 220 Secent Piles 60 days 8 01/06/2021 30/07/2021 221 Excavation 2 days 4 31/07/2021 01/08/2021 222 Replacement Layer 7 days 4 02/08/2021 08/08/2021 223 Termite Soil treatment 1 day 2 09/058/2021 09/08/2021 224 polyethlene sheet works under Foundation 1 day 2 09/08/2021 09/08/2021 225 Base Plain Concrete 5 days 6 10/08/2021 15/08/2021 226 Base Insulations 5 days 4 16/08/2021 20/08/2021 227 Base Reinforced Concrete 8 days 8 21/08/2021 28/08/2021 228 Wall & Columns Reinforced Concret 92 days 8 01/09/2021 01/12/2021 229 Backfill 1 day 2 02/12/2021 02/12/2021 230 Steel Structure 30 days 10 01/01/2021 30/01/2022 10/ E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 10 Project: ADCO Date: Mon 12/13/21
  • 11. ID Task Mode Task Name Duration Manpower start date end date 231 Bricks Building 5 days 8 01/ 02/2022 05/02/2022 232 Interior Finishing 20 days 8 06/02/2022 26/02/2022 233 Exterior Finishing 20 days 8 06/02/2022 26/02/2022 234 Doors& Stairs Installation 3 days 2 25/02/2022 27/02/2022 235 Interlock 7 days 6 22/02/2022 28/02/2022 236 FIRE FIGHting 7 days 237 1st Fix (PIPE INSTALTION) 10 days 6 01/03/2022 10/03/2022 238 2nd Fix (PIPE PAINTING) 5 days 6 11/03/2022 15/03/2022 239 Finishing (SPRINKLER & FHC & VALVES INSTALTION) 3 days 6 16/03/2022 18/03/2022 240 Testing & Comissioning 2 days 6 19/03/2022 20/03/2022 241 FIRE Alarm 53 days 242 1st Fix (CODUIT) 3 days 6 01/03/2022 03/03/2022 243 2nd Fix (CABLE) 2 days 6 04/03/2022 05/03/2022 244 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 6 06/03/2022 06/03/2022 245 Testing & Comissioning 1 day 6 07/03/2022 246 SMOKE & VENTILATION 20 days 247 DUCT INSTALATION 8 days 6 01/03/2022 08/03/2022 248 OUTLET INSTALATION 3 days 4 09/08/2022 11/03/2022 249 FANS INSTALATION 2 days 2 12/03/2022 13/03/2022 250 ELECTRIC WORKS 20 days 251 1st Fix (CODUIT) 5 days 4 01/10/2021 05/10/2021 252 2nd Fix (CABLE) 3 days 4 01/01/2021 03/03/2022 253 LIGHTING FIXTURE INSTALATION 3 days 4 04/03/2022 06/03/2022 E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 11 Project: ADCO Date: Mon 12/13/21
  • 12. ID Task Mode Task Name Duration Manpower start date end date 254 EARTING WORKS 7 days 4 01/03/2022 07/03/2022 255 LIGHT CURRENT & CAMERA AND DATA WORKS 4 days 4 07/03/2022 10/03/2022 256 PORTABLE &FIREFIGHTING WATER TANK (B22) 84 days 257 CIVIL 84 days 258 Soil Test 5 days 2 25/02/2021 01/03/2021 259 Removal 5 days 2 01/04/2021 05/04/2021 260 Secent Piles 42 days 8 18/04/2021 29/05/2021 261 Excavation 2 days 4 30/05/2021 31/05/2021 262 Replacement Layer 10 days 4 13/06/2021 22/06/2021 263 Termite Soil treatment 1 day 2 26/06/2021 26/06/2021 264 polyethlene sheet works under Foundation 1 day 2 27/06/2021 27/06/2021 265 Plain Concrete 1 day 6 28/06/2021 28/06/2021 266 Base Insulations 7 days 4 29/06/2021 05/07/2021 267 Base Reinforced Concrete& Columns 20 days 6 06/07/2021 25/07/2021 268 Wall Insulation 5 days 6 26/07/2021 30/07/2021 269 Wall Reinforced Concret 10 days 8 01/08/2021 10/08/2021 270 Ceiling Reinforced Concret 5 days 8 11/08/2021 15/08/2021 271 Ceiling Insulation 3 days 6 01/12/2021 03/12/2021 272 Interior Finishing 60 days 6 01/11/2021 30/12/2021 273 Backfill 1 day 2 31/12/2021 31/12/2021 274 Asphalt 14 days 8 01/01/2022 14/01/2022 275 Interlock 10 days 6 15/01/2022 25/01/2022 276 Pump Room Instalation 15 days 6 01/01/2022 15/01/2022 E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 12 Project: ADCO Date: Mon 12/13/21
  • 13. ID Task Mode Task Name Duration Manpower start date end date 277 FIRE Fighting 5 days 278 1st Fix (PIPE INSTALTION) 2 days 2 01/01/2022 02/01/2022 279 2nd Fix (PIPE PAINTING) 2 days 2 03/01/2022 04/01/2022 280 Finishing (SPRINKLER & VALVES INSTALTION) 1 day 2 05/01/2022 05/01/2022 281 Testing & Comissioning 5 days 4 06/01/2022 10/01/2022 282 FIRE Alarm 2 days 283 1st Fix (CODUIT) 2 days 4 01/01/2022 02/01/2022 284 2nd Fix (CABLE) 2 days 4 03/01/2022 04/01/2022 285 Finishing (PANEL & DETECTOR INSTALATION AND TERMINATION ) 1 day 2 05/01/2022 05/01/2022 286 Testing & Comissioning 1 day 2 06/01/2022 06/01/2022 287 Outer Network 30 days 288 Fire Fighting 30 days 10 289 Fire Alarm 30 days 8 290 Water Supply 30 days 8 291 Pump Room Main Cable 1 day 8 292 UPS 2 days 4 293 BMS 2 days 4 E M B E Septe Jan Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 13 Project: ADCO Date: Mon 12/13/21