WEEKLY REPORT NO. 67
2B+G+6Typ+HC. Residential building, on plot no. 373-390, Al
Barsha 1st, Dubai
From 3rd Jan,2016 to 11th Jan,2016
Consultant.
Contractor.
Table of Contents
1.0 Executive Summary............................................................................................................3
1.1 Introduction..................................................................................................................3
1.2Basic Data ......................................................................................................................3
1.3Progress Status..............................................................................................................4
1.4Summary of Work done ................................................................................................5
1.5Risks, Points of Concerns, and Outstanding Issues.......................................................6
2.0 Statutory Authorities .........................................................................................................6
2.1 Statutory Authorities Approvals Tracking Matrix.........................................................6
3.0 Technical Submittals Tracking Schedules and Logs...........................................................7
3.1 Shop Drawings..............................................................................................................7
3.2 Materials / Samples......................................................................................................7
3.3Pre-Qualifications (Subcontractors / Suppliers)............................................................7
3.4Method Statements ......................................................................................................7
3.5Documents ....................................................................................................................7
3.6RFI’s ...............................................................................................................................7
3.7PS/PC tracking matrix .......................................................................................................7
3.8 NCR..............................................................................................................................7
3.9 Safety............................................................................................................................7
4.0 Procurement.......................................................................................................................8
4.1Procurement Tracking Schedule ...................................................................................8
5.0 Programme Of Works.........................................................................................................8
5.1 Progress S-Curve (Overall Monthly and Cumulative based on total Man-days / Man-
hours) .................................................................................................................................8
5.2 Update .........................................................................................................................8
5.3Eight Weeks Look-Ahead...............................................................................................8
5.3 Variation/Claim............................................................................................................8
6.0 Payment Summary.............................................................................................................8
6.1 ......................................................................................................................................8
6.2........................................................................................................................................8
7.0 Equipment and Machinery.................................................................................................8
7.1 Equipment and Machinery..................................................................................................9
8.0KPI ...................................................................................................................................9
8.1 Manpower( Carpenters, Steel Fixers, Masons etc ).................................................9
8.2 Quantities ( Civil and MEP )......................................................................................9
9.0Progress Photos....................................................................................................................9
9.1 Progress Photos ...........................................................................................................9
1.0 Executive Summary
1.1. Introduction
The Project is construction of residential building having 2 Basements Floors, Ground
Floor, 06typical floor, and Health Club Floor at Roof. The Scope of works includes
Structure, finishes, MEP, Provisional Sums works, Testing & Commissioning, Snagging,
and Hand Over.
1.2. Basic Data
Project Name / Title
2B+G+6Typ+Hc. Residential
building,
Client
Mr. Abdul WahidHassan Al
Rostamani
Consultant M/S. Arif&Bintoak
Main Contractor
M/S. Al-ArifContracting CO.
L.L.C
RevisedContract Value
(As per variation orders)
AED 138,512,715
Project Duration 548 Days
RevisedProjectDuration 794 Days
Project CommencementDate (as per LOA) 7th
May 2014
MobilizationCompletionDate 6th
June 2014
Project CompletionDate 9-July-16
Time Elapsed 614Days (77%)
Time Remaining 180 Days(23%)
1.3. Progress Status-Baseline Program
Criteria Planned % Actual % Variance Actual % last
week
% Increased
this week
Overall Project* 100.00%
60.00%
40.00% 59.41% 0.59%
Construction 100.00%
55.33%
44.67%
MEP 100.00%
29.32%
70.68%
Shop Drawings 100.00%
93.04%
6.96%
Materials Sub. &App. 100.00%
97.61%
2.39%
Procurement 100.00% 68.83% 31.17%
(Overall Project Delay) -274 Days
Current Completion Date 08-August-16
1.1. Progress Status-Revised Program
Criteria Planned
%
Actual % Varianc
e
Actual %
last week
% Increased this week
Overall Project*
61.13% 60.00%
1.13% 59.41% 0.59%
Construction
56.13% 55.33%
0.8%
MEP
32.13% 29.32%
2.81%
Shop Drawings
100.00% 93.04%
6.96%
Materials Sub. &App.
100.00% 97.61%
2.39%
Procurement 87.72 68.83% 18.89%
(Overall Project Delay)
-27 Days
Current Completion Date 08-August-16
1.1. Progress Status-Engineer determination
Criteria Planned % Actual % Variance Actual % from 2
weeks
% Increased
this week
Overall Project* 88.85%
60.00%
28.85% 59.41% 0.59%
Construction 85.98%
55.33%
30.65%
MEP 48.72% 29.32% 19.40%
Shop Drawings 100.00%
93.04%
6.96%
Materials Sub. &App. 100.00%
97.61%
2.39%
Procurement 100.00% 68.83% 31.17%
(Overall Project Delay) -49 Days
Current Completion Date 16-June-16
*Longest Path / Reason of Delay - Refer Annexure -1.3
1.2. Summary of Work Done
The following activities in the next Page were progressed
during the reporting period.
S
.
N
o
Activity
Progress this week Cumulative up
to this week
Part01
RCC Roof Slab Completed 100%
Swimming Pool walls & slab Completed 100%
RCC Vertical (terrace floor) Completed 100%
RCC Columns- 6thtoterracefloor Completed 100%
RCC Slab-terrace floor slab Completed 100%
BlockWork-1stFloor Completed 100%
BlockWork-2ndFloor Completed 100%
BlockWork-3rdFloor Completed 100%
BlockWork-4thFloor Completed 100%
BlockWork5th
Floor Completed 100%
Block Work 6th
Floor Completed 100%
BlockWork-B2&B1 Completed 100%
PlasterWork-1stfloor Completed 100%
Plaster Work 2nd
Floor Completed 100%
Plaster Works 3rd Floor Completed 100%
SprayPlaster-B2 Completed 100%
MEP-B2&B1 In progress 75%
MEP Work -1st floor In progress 85%
Parapet Concrete Complete 100%
Plaster in staircase from B2-G.F Completed 100%
Part02
RCC Slab-terrace floor slab Comp leted 100%
RCC Columns 6h Floor Comp leted 100%
Block Work-G.Floor Comp leted 100%
Block Work-2nd Floor&1st
floor Comp leted 100%
MEP work 3rd
floor In progress 65%
RCC slab Roof Completed 100%
Vertical(terrace roof) Completed 100%
Block work 6th
floor Completed 100%
Blockwork5th
floor Completed 100%
BlockWork-3rd Floor Completed 100%
BlockWork-4th Floor Completed 100%
MEP-B2&B1 Completed 100%
Plaster-B2&B1 Completed 100%
Electrical wiring in 1st and 2nd floor Completed 100%
Plaster-1stfloor Completed 100%
Plaster-2nd
Floor Completed 100%
Plaster Works 3rd floor Completed 100%
Plaster in staircase fromB2-G.F Comp leted 100%
Parapet Concrete Completed 100%
Part03
RCC Slab-terrace floor slab Completed 100%
BlockWork-B2&B1 Completed 100%
Block Work-G.F Completed 100%
Block work-F.F Comp leted 100%
Block work S.F Completed 100%
Blockwork-3rdFloor Completed 100%
BlockWork4th
Floor Completed 100 %
Block Work 5th
Floor Completed 100%
Plaster in stair case fromB2-G.F Comp leted 100%
Plaster -1st
Floor Completed 100%
Plaster works 2nd floor Completed 100%
1.1. Risks, Points of Concerns, and Outstanding Issues
The following are risks, points of concerns, and outstanding issues.
General Issues
1. Revised Authority for Gym floor.
2. HVAC Design/redesign.
Issues Regarding HVAC
1. Corridor coordination still in progress PF & EL.
2. Material submittal for Air Curtains sill not received from consultants.
2.0 Statutory Authorities
2.1. Statutory Authorities Approvals Tracking Matrix : Refer Annexure – 2.1
3.0 Technical Submittals Status, Tracking Schedules and Logs
3.1. Shop Drawings :
3.1.1 Civil Shop Drawings : Refer Annexure - 3.1.1
3.1.2 MEP Shop Drawings : Refer Annexure - 3.1.2
3.1.3 PS Item Shop Drawings : Refer Annexure - 3.1.3
3.2. Materials / Samples
3.2.1 Civil Materials : Refer Annexure - 3.2.1
3.2.2 MEP Materials : Refer Annexure - 3.2.2
3.2.3 PS Item Materials : Refer Annexure - 3.2.3
3.2.4 PC Item Materials : Refer Annexure - 3.2.4
Plaster works 3rd floor Completed 100 %
Column for Terrace Floor-roof Completed 100%
Swimming pool deck slab Completed 100%
Parapet Reinforcement Completed 100%
3.3. Pre-Qualifications (Subcontractors / Suppliers) Refer Annexure -3.3
3.4. Method Statement:Refer Annexure – 3.4
3.5 Documents:
3.5.1 Civil Documents : Refer Annexure – 3.5.1
3.5.2 MEP Documents : Refer Annexure – 3.5.2
3.6 RFI’s : Refer Annexure – 3.6
3.7 PS/PC tracking matrix: Refer Annexure – 3.7
3.8 NCR:Refer Annexure - 3.8
3.9 SAFETY :Refer Annexure - 3.9
4.0 Procurement
4.1 General Procurement Log : Refer Annexure - 4.1
4.2 MEP Procurement Log : Refer Annexure - 4.2
4.3 PS Procurement Log : Refer Annexure - 4.3
4.4Long Lead Items : Refer Annexure - 4.4
5.0 Programmed of Works.
5.1. Progress S-Curve (Overall Monthly and Cumulative based on total Man-days /
Man-hours):Refer Annexure -5.1
5.2. Update : Refer Annexure -5.2
5.3. 8 Weeks Look-Ahead : Refer Annexure -5.3
5.4. Variation /Claim: Refer Annexure -5.4
6.0 Payment Summary.
6.1.Payment summary tracking as per attached schedule :Refer Annexure - 7.0
7.0 Resources Histograms and Curves (Planned Vs. Actual)
7.1Equipment and Machinery
Description No of Units
Towercrane 3
Cuttingmachine 1
MixerMachine 1
Bendingmachine 1
Concrete vibrator 10
Carpentrymachine 4
WeldingEquipment 2
Generator 1
RollerCompactor 0
Mobile cranes 0
Water cooler 3
8.0 KPI
8.1 Manpower ( Carpenters, Steel Fixers, Masons etc ).Refer Annexure - 8.0
8.2 Quantities ( Civil and Mep ). Refer Annexure - 8.0
9.0 Progress Photos
9.1Progress Photos :Refer Annexure -7.p1

More Related Content

Viewers also liked

Viewers also liked (10)

Trabajo de formación en centros de trabajo
Trabajo de formación en centros de trabajoTrabajo de formación en centros de trabajo
Trabajo de formación en centros de trabajo
 
Memoria 4
Memoria 4Memoria 4
Memoria 4
 
presentasi TA
presentasi TApresentasi TA
presentasi TA
 
Ple
PlePle
Ple
 
Test gif
Test gifTest gif
Test gif
 
Climate zones group 2
Climate zones group 2Climate zones group 2
Climate zones group 2
 
Wyniki Ogólnopolskiego Badania Inwestorów 2015
Wyniki Ogólnopolskiego Badania Inwestorów 2015Wyniki Ogólnopolskiego Badania Inwestorów 2015
Wyniki Ogólnopolskiego Badania Inwestorów 2015
 
Haier presentation
Haier presentationHaier presentation
Haier presentation
 
Alteraciones Hemodinamicas
Alteraciones HemodinamicasAlteraciones Hemodinamicas
Alteraciones Hemodinamicas
 
Moodle ventajas y desventajas
Moodle ventajas y desventajasMoodle ventajas y desventajas
Moodle ventajas y desventajas
 

Similar to Weekly Progress.521-67

Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
ANACOSTIA GATEWAY report
ANACOSTIA GATEWAY reportANACOSTIA GATEWAY report
ANACOSTIA GATEWAY reportNgo Quan
 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Mourad Iskandar
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report SampleElias Ibrahim
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdfDivyaTadepalli1
 
EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...
EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...
EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...Eduardo H. Pare
 
Project Management Services
Project Management ServicesProject Management Services
Project Management ServicesBruce Tharp
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and faAl-Amin Ahmed Nabin
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioSyed Arafath, PMI-SP certified
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete noteMani Das
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 

Similar to Weekly Progress.521-67 (20)

Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
ANACOSTIA GATEWAY report
ANACOSTIA GATEWAY reportANACOSTIA GATEWAY report
ANACOSTIA GATEWAY report
 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report Sample
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdf
 
Project control
Project controlProject control
Project control
 
EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...
EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...
EDUARDO H. PARE CIVIL, STRUCTURAL & ARCHITECTURAL DESIGN & CONSTRUCTION SPECI...
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and fa
 
Presentation 95
Presentation 95Presentation 95
Presentation 95
 
Project assign 2
Project assign 2Project assign 2
Project assign 2
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-Portfolio
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete note
 
Ici final project
Ici final projectIci final project
Ici final project
 
VACATION WORK REPORT 2
VACATION WORK REPORT 2VACATION WORK REPORT 2
VACATION WORK REPORT 2
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 

Weekly Progress.521-67

  • 1. WEEKLY REPORT NO. 67 2B+G+6Typ+HC. Residential building, on plot no. 373-390, Al Barsha 1st, Dubai From 3rd Jan,2016 to 11th Jan,2016 Consultant. Contractor.
  • 2. Table of Contents 1.0 Executive Summary............................................................................................................3 1.1 Introduction..................................................................................................................3 1.2Basic Data ......................................................................................................................3 1.3Progress Status..............................................................................................................4 1.4Summary of Work done ................................................................................................5 1.5Risks, Points of Concerns, and Outstanding Issues.......................................................6 2.0 Statutory Authorities .........................................................................................................6 2.1 Statutory Authorities Approvals Tracking Matrix.........................................................6 3.0 Technical Submittals Tracking Schedules and Logs...........................................................7 3.1 Shop Drawings..............................................................................................................7 3.2 Materials / Samples......................................................................................................7 3.3Pre-Qualifications (Subcontractors / Suppliers)............................................................7 3.4Method Statements ......................................................................................................7 3.5Documents ....................................................................................................................7 3.6RFI’s ...............................................................................................................................7 3.7PS/PC tracking matrix .......................................................................................................7 3.8 NCR..............................................................................................................................7 3.9 Safety............................................................................................................................7 4.0 Procurement.......................................................................................................................8 4.1Procurement Tracking Schedule ...................................................................................8 5.0 Programme Of Works.........................................................................................................8 5.1 Progress S-Curve (Overall Monthly and Cumulative based on total Man-days / Man- hours) .................................................................................................................................8 5.2 Update .........................................................................................................................8 5.3Eight Weeks Look-Ahead...............................................................................................8 5.3 Variation/Claim............................................................................................................8 6.0 Payment Summary.............................................................................................................8 6.1 ......................................................................................................................................8 6.2........................................................................................................................................8 7.0 Equipment and Machinery.................................................................................................8 7.1 Equipment and Machinery..................................................................................................9
  • 3. 8.0KPI ...................................................................................................................................9 8.1 Manpower( Carpenters, Steel Fixers, Masons etc ).................................................9 8.2 Quantities ( Civil and MEP )......................................................................................9 9.0Progress Photos....................................................................................................................9 9.1 Progress Photos ...........................................................................................................9
  • 4. 1.0 Executive Summary 1.1. Introduction The Project is construction of residential building having 2 Basements Floors, Ground Floor, 06typical floor, and Health Club Floor at Roof. The Scope of works includes Structure, finishes, MEP, Provisional Sums works, Testing & Commissioning, Snagging, and Hand Over. 1.2. Basic Data Project Name / Title 2B+G+6Typ+Hc. Residential building, Client Mr. Abdul WahidHassan Al Rostamani Consultant M/S. Arif&Bintoak Main Contractor M/S. Al-ArifContracting CO. L.L.C RevisedContract Value (As per variation orders) AED 138,512,715 Project Duration 548 Days RevisedProjectDuration 794 Days Project CommencementDate (as per LOA) 7th May 2014 MobilizationCompletionDate 6th June 2014 Project CompletionDate 9-July-16 Time Elapsed 614Days (77%) Time Remaining 180 Days(23%)
  • 5. 1.3. Progress Status-Baseline Program Criteria Planned % Actual % Variance Actual % last week % Increased this week Overall Project* 100.00% 60.00% 40.00% 59.41% 0.59% Construction 100.00% 55.33% 44.67% MEP 100.00% 29.32% 70.68% Shop Drawings 100.00% 93.04% 6.96% Materials Sub. &App. 100.00% 97.61% 2.39% Procurement 100.00% 68.83% 31.17% (Overall Project Delay) -274 Days Current Completion Date 08-August-16 1.1. Progress Status-Revised Program Criteria Planned % Actual % Varianc e Actual % last week % Increased this week Overall Project* 61.13% 60.00% 1.13% 59.41% 0.59% Construction 56.13% 55.33% 0.8% MEP 32.13% 29.32% 2.81% Shop Drawings 100.00% 93.04% 6.96% Materials Sub. &App. 100.00% 97.61% 2.39% Procurement 87.72 68.83% 18.89%
  • 6. (Overall Project Delay) -27 Days Current Completion Date 08-August-16 1.1. Progress Status-Engineer determination Criteria Planned % Actual % Variance Actual % from 2 weeks % Increased this week Overall Project* 88.85% 60.00% 28.85% 59.41% 0.59% Construction 85.98% 55.33% 30.65% MEP 48.72% 29.32% 19.40% Shop Drawings 100.00% 93.04% 6.96% Materials Sub. &App. 100.00% 97.61% 2.39% Procurement 100.00% 68.83% 31.17% (Overall Project Delay) -49 Days Current Completion Date 16-June-16 *Longest Path / Reason of Delay - Refer Annexure -1.3
  • 7. 1.2. Summary of Work Done The following activities in the next Page were progressed during the reporting period.
  • 8. S . N o Activity Progress this week Cumulative up to this week Part01 RCC Roof Slab Completed 100% Swimming Pool walls & slab Completed 100% RCC Vertical (terrace floor) Completed 100% RCC Columns- 6thtoterracefloor Completed 100% RCC Slab-terrace floor slab Completed 100% BlockWork-1stFloor Completed 100% BlockWork-2ndFloor Completed 100% BlockWork-3rdFloor Completed 100% BlockWork-4thFloor Completed 100% BlockWork5th Floor Completed 100% Block Work 6th Floor Completed 100% BlockWork-B2&B1 Completed 100% PlasterWork-1stfloor Completed 100% Plaster Work 2nd Floor Completed 100% Plaster Works 3rd Floor Completed 100% SprayPlaster-B2 Completed 100% MEP-B2&B1 In progress 75% MEP Work -1st floor In progress 85% Parapet Concrete Complete 100% Plaster in staircase from B2-G.F Completed 100% Part02 RCC Slab-terrace floor slab Comp leted 100% RCC Columns 6h Floor Comp leted 100% Block Work-G.Floor Comp leted 100% Block Work-2nd Floor&1st floor Comp leted 100% MEP work 3rd floor In progress 65% RCC slab Roof Completed 100% Vertical(terrace roof) Completed 100% Block work 6th floor Completed 100% Blockwork5th floor Completed 100% BlockWork-3rd Floor Completed 100% BlockWork-4th Floor Completed 100% MEP-B2&B1 Completed 100% Plaster-B2&B1 Completed 100% Electrical wiring in 1st and 2nd floor Completed 100% Plaster-1stfloor Completed 100% Plaster-2nd Floor Completed 100% Plaster Works 3rd floor Completed 100% Plaster in staircase fromB2-G.F Comp leted 100% Parapet Concrete Completed 100% Part03 RCC Slab-terrace floor slab Completed 100% BlockWork-B2&B1 Completed 100% Block Work-G.F Completed 100% Block work-F.F Comp leted 100% Block work S.F Completed 100% Blockwork-3rdFloor Completed 100% BlockWork4th Floor Completed 100 % Block Work 5th Floor Completed 100% Plaster in stair case fromB2-G.F Comp leted 100% Plaster -1st Floor Completed 100% Plaster works 2nd floor Completed 100%
  • 9. 1.1. Risks, Points of Concerns, and Outstanding Issues The following are risks, points of concerns, and outstanding issues. General Issues 1. Revised Authority for Gym floor. 2. HVAC Design/redesign. Issues Regarding HVAC 1. Corridor coordination still in progress PF & EL. 2. Material submittal for Air Curtains sill not received from consultants. 2.0 Statutory Authorities 2.1. Statutory Authorities Approvals Tracking Matrix : Refer Annexure – 2.1 3.0 Technical Submittals Status, Tracking Schedules and Logs 3.1. Shop Drawings : 3.1.1 Civil Shop Drawings : Refer Annexure - 3.1.1 3.1.2 MEP Shop Drawings : Refer Annexure - 3.1.2 3.1.3 PS Item Shop Drawings : Refer Annexure - 3.1.3 3.2. Materials / Samples 3.2.1 Civil Materials : Refer Annexure - 3.2.1 3.2.2 MEP Materials : Refer Annexure - 3.2.2 3.2.3 PS Item Materials : Refer Annexure - 3.2.3 3.2.4 PC Item Materials : Refer Annexure - 3.2.4 Plaster works 3rd floor Completed 100 % Column for Terrace Floor-roof Completed 100% Swimming pool deck slab Completed 100% Parapet Reinforcement Completed 100%
  • 10. 3.3. Pre-Qualifications (Subcontractors / Suppliers) Refer Annexure -3.3 3.4. Method Statement:Refer Annexure – 3.4 3.5 Documents: 3.5.1 Civil Documents : Refer Annexure – 3.5.1 3.5.2 MEP Documents : Refer Annexure – 3.5.2 3.6 RFI’s : Refer Annexure – 3.6 3.7 PS/PC tracking matrix: Refer Annexure – 3.7 3.8 NCR:Refer Annexure - 3.8 3.9 SAFETY :Refer Annexure - 3.9 4.0 Procurement 4.1 General Procurement Log : Refer Annexure - 4.1 4.2 MEP Procurement Log : Refer Annexure - 4.2 4.3 PS Procurement Log : Refer Annexure - 4.3 4.4Long Lead Items : Refer Annexure - 4.4 5.0 Programmed of Works. 5.1. Progress S-Curve (Overall Monthly and Cumulative based on total Man-days / Man-hours):Refer Annexure -5.1 5.2. Update : Refer Annexure -5.2 5.3. 8 Weeks Look-Ahead : Refer Annexure -5.3 5.4. Variation /Claim: Refer Annexure -5.4 6.0 Payment Summary.
  • 11. 6.1.Payment summary tracking as per attached schedule :Refer Annexure - 7.0 7.0 Resources Histograms and Curves (Planned Vs. Actual) 7.1Equipment and Machinery Description No of Units Towercrane 3 Cuttingmachine 1 MixerMachine 1 Bendingmachine 1 Concrete vibrator 10 Carpentrymachine 4 WeldingEquipment 2 Generator 1 RollerCompactor 0 Mobile cranes 0 Water cooler 3 8.0 KPI 8.1 Manpower ( Carpenters, Steel Fixers, Masons etc ).Refer Annexure - 8.0 8.2 Quantities ( Civil and Mep ). Refer Annexure - 8.0 9.0 Progress Photos 9.1Progress Photos :Refer Annexure -7.p1