SlideShare a Scribd company logo
1 of 40
Download to read offline
Oh910i1-8594.pptx/1
Oak Harbor Facilities Plan
City Council Workshop
March 6, 2013
Oh910i1-8594.pptx/2Oh910i1-8594.pptx/2
Tonight’s Agenda
• Facilities Plan Status Update
• Rate Analysis Update
• Schedule and Next Steps
– Technical Aspects
– Public Interface
– Milestone Council Decisions
• How to Stay Involved
• Questions?
Oh910i1-8594.pptx/3Oh910i1-8594.pptx/3
Facilities Plan Status
Oh910i1-8594.pptx/4Oh910i1-8594.pptx/4
Proposed Site
Windjammer Vicinity
Oh910i1-8594.pptx/5Oh910i1-8594.pptx/5
Windjammer Charrette Concept for MBR
Conceptual Plan View
Oh910i1-8594.pptx/6Oh910i1-8594.pptx/6
Total Project Cost Summary
Year 2030
$83.0
$7.6
$2.9
$50
$55
$60
$65
$70
$75
$80
$85
$90
$95
$100
All Facilities Through Year 2030
ProjectCost,Millions
TreatmentFacility Wastewater Conveyance EffluentDischarge
Oh910i1-8594.pptx/7Oh910i1-8594.pptx/7
Phasing Scenarios Depend on City Growth
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
2000 2005 2010 2015 2020 2025 2030 2035
MaximumMonthFlow,mgd
Measured Data
Scenario 1, No Growth
Scenario 2, Intermediate Growth
Scenario 3, ComprehensivePlan
1
2
3
Notes:
1: Currentmeasured capacity is 3.0 mgd.
2: Capacity required at projected year of startup (2017) rangesfrom3.0 to 3.2 mgd.
3: Assuming 3.4 mgd of capacity is constructed in Phase 1, yearsof service
(prior to Phase 2) rangefrom 4 to 13 years.
1
2
3
Oh910i1-8594.pptx/8Oh910i1-8594.pptx/8
Phasing Also Depends on Navy Participation
• Navy currently contributes about 20% of flow to
City facilities
• Scenario 1: Navy continues as a customer
– WWTP sized for City and Navy flows/loads
• Scenario 2: Navy does not continue as a customer
– WWTP sized for City only flows/loads
Oh910i1-8594.pptx/9Oh910i1-8594.pptx/9
$83.0
$72.1
$7.6
$7.6
$2.9
$2.9
$50
$55
$60
$65
$70
$75
$80
$85
$90
$95
$100
All Facilities Through Year 2030 Scenario 1: City + Navy
ProjectCost,Millions
TreatmentFacility Wastewater Conveyance EffluentDischarge
The City'scost share
forthis scenariois
$60.0 M
Total Project Cost Summary
Phase 1, Scenario 1
Oh910i1-8594.pptx/10Oh910i1-8594.pptx/10
$83.0
$72.1
$64.8
$7.6
$7.6
$2.9
$2.9
$2.9
$50
$55
$60
$65
$70
$75
$80
$85
$90
$95
$100
All Facilities Through Year 2030 Scenario 1: City + Navy Scenario 2: City Only
ProjectCost,Millions
TreatmentFacility Wastewater Conveyance EffluentDischarge
The City'scost share
forthis scenariois
$60.0 M
The City'scost share
forthis scenariois
$67.7 M
Total Project Cost Summary
Phase 1, Scenarios 1 and 2
Oh910i1-8594.pptx/11Oh910i1-8594.pptx/11
Phase 1 Scenario Summary
Scenario 1
City + Navy
Scenario 2
City Only
Phase 1 Project Cost $82.6 M $67.7 M
Navy Share (%) 27% n/a
Navy Share of Cost $22.6 M n/a
City Share of Cost $60.0 M $67.7
Oh910i1-8594.pptx/12Oh910i1-8594.pptx/12
Milestone Dates for Plan Approval
Date Action
March 6, 2013 Present Draft Plan to Public
March 19, 2013 Seek Council Approval to Submit Draft Plan
Summer 2013 Ecology Conditional Approval (pending environmental)
Q4 2013 - Q1 2014 Final Environmental Approvals
Oh910i1-8594.pptx/13Oh910i1-8594.pptx/13
Rate Analysis Update
Oh910i1-8594.pptx/14Oh910i1-8594.pptx/14
Two Scenarios for Navy Participation
• Scenario 1: City + Navy
– City provides service to Navy at startup of Phase
1 and through Year 2030
– All project/O&M costs are shared
• Scenario 2: City Only
– City, Navy operate independent facilities through
Year 2030 (Navy no longer a customer)
– All project/O&M costs are born by City
Oh910i1-8594.pptx/15Oh910i1-8594.pptx/15
Navy Cost-Sharing Assumptions
• WWTP Project Costs
– Navy share based on percentage of maximum
month flow (ranges from 21% to 18%)
• WWTP O&M Costs
– Navy share based on percentage of average
annual flow (ranges from 17% to 14%)
• Collection System Project Costs
– Navy provides 100% of costs associated with
conveying Navy flow to Windjammer Vicinity
• Outfall Project Costs
– Navy share based on percentage of peak flow
(approximately 19% at 2030)
Oh910i1-8594.pptx/16Oh910i1-8594.pptx/16
WWTP Funding Assumption Review
• 2010 rate study included assumptions for the
WWTP funding
• Assumptions were conservative given the project
was 5 plus years in the future
• Revised assumptions are conservative yet still
reflect current conditions
• Question: How do the assumptions impact the
adopted rate transition plan?
Oh910i1-8594.pptx/17Oh910i1-8594.pptx/17
Estimated Rate Impact, August 14, 2012
“Base Case” Assumed $70 million Project
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9
Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
$0.00
$10.00
$20.00
$30.00
$40.00
$50.00
$60.00
$70.00
$80.00
$90.00
$100.00
MonthlySewerBill
Summary of Required Single Family Monthly Sewer Bill
“Base Case”
Monthly Rate: $92.20
Oh910i1-8594.pptx/18Oh910i1-8594.pptx/18
Variables include:
1. Borrowing term
2. Interest rate
3. Navy participation
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9
$0.00
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
MonthlySewerBill
Summary of Required Single Family Monthly Sewer Bill
Estimated Rate Impact, August 14, 2012
Rate Scenarios for $93.5 million Project
Monthly Rates range
from $85 to > $115
(Depending on
variable assumptions)
Oh910i1-8594.pptx/19Oh910i1-8594.pptx/19
Updated WWTP Funding Assumptions
• 2 Borrowing terms evaluated: 20 and 30 years
• 2 Interest Rates evaluated: 4.5% and 6.0%
• Updated City’s sewer reserves balance
• Reconciled other key rate analysis assumptions
– Project cost escalated to mid-point
– City portion of project cost based on Navy
participation
– Cost of bonding
– WWTP O&M components and costs
– Project start/end dates
Oh910i1-8594.pptx/20Oh910i1-8594.pptx/20
Three Potential Phase 1 Funding Scenarios
• Scenario 1: City + Navy
– 30 years, 4.5% interest
– Results in lowest City rate
• Scenario 2A: City Only
– 30 years, 4.5% interest
– Rate is higher than Scenario 1; still < “Base Case”
• Scenario 2B: City Only
– 20 years, 6.0% interest
– Highest rate; > “Base Case”
Oh910i1-8594.pptx/21Oh910i1-8594.pptx/21
Comparison of Potential Monthly Sewer Bills
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9
Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
Scenario 1: City + Navy; 30-yrs; 4.5% $40.00 $42.00 $47.00 $51.70 $56.87 $62.56 $68.81 $75.69 $83.26
Scenario 2A: City Only; 30-yrs; 4.5% $40.00 $42.00 $47.00 $52.00 $57.50 $64.40 $72.13 $80.78 $90.48
Scenario 2B: City Only; 20-yrs; 6.0% $40.00 $42.00 $47.00 $52.88 $59.48 $68.11 $77.99 $89.68 $107.62
$0
$20
$40
$60
$80
$100
$120
MonthlySewerBill
RequiredSingle Family Monthly Sewer Bill
Oh910i1-8594.pptx/22Oh910i1-8594.pptx/22
Summary of Rate Impacts, WWTP
• Lowest City rates result from City + Navy
partnership in new facilities
• For “City Only” scenario, City rates held below
“Base Case” with current, reasonable assumptions
• Opportunities to reduce City rate impact due to
new WWTP continue to be explored
– Grants/low-interest loan programs
– Borrowing strategy
– “Value Engineering”
– Project Delivery Method
• Overall rate analysis for sewer utility is ongoing
Oh910i1-8594.pptx/23Oh910i1-8594.pptx/23
Schedule/Next Steps
Oh910i1-8594.pptx/24Oh910i1-8594.pptx/24
Objectives for Next Phase of Project
Through Year-end
• Facilities Plan approved
• Confirm planning assumptions through “Value
Engineering”
• Select final location for WWTP within
Windjammer Vicinity
• Complete preliminary design of WWTP
• Select most appropriate method of construction
• Complete final design of outfall to Oak Harbor
Oh910i1-8594.pptx/25Oh910i1-8594.pptx/25
Key Features of Approach Moving Forward
• Continue to make every effort to deliver an
appropriate facility while controlling cost and
impact on ratepayers
• Maintain flexibility by considering options for final
WWTP site location
• Select final location considering public input, cost
and City policy directives
Oh910i1-8594.pptx/26Oh910i1-8594.pptx/26
Step 1 – Value Engineering
• Completed on large projects to add value,
control cost
• Condition of some funding sources
• Facilitated by an independent 3rd party and panel
of experts
• Summer 2013: Results and recommendations
offered to City Council for consideration
Oh910i1-8594.pptx/27Oh910i1-8594.pptx/27
Step 2 – Select Final WWTP Location Within
Windjammer Vicinity
Oh910i1-8594.pptx/28Oh910i1-8594.pptx/28
Step 2 – Select Final WWTP Location Within
Windjammer Vicinity
A. Spring/Summer 2013: Public meetings, Council
deliberations establish policy, guiding principles
– Property acquisition
– Use of open space
– Additional features/
benefits associated
with facility
– Integration with other
nearby land-use plans
Oh910i1-8594.pptx/29Oh910i1-8594.pptx/29
Step 2 – Select Final WWTP Location Within
Windjammer Vicinity
B. Summer/Fall 2013: Working Group Meetings,
Charrette leverage public input to develop
options within Windjammer Vicinity
Oh910i1-8594.pptx/30Oh910i1-8594.pptx/30
Step 2 – Select Final WWTP Location Within
Windjammer Vicinity
C. Fall 2013: Project team presents analysis of
options to City Council for decision
– Confirm Value Engineering Recommendations
– Confirm treatment facility location
– Confirm approach to integrate facility into
surroundings
• Transportation
• Parks/Open Space
• Commercial/Retail
• Government/Public Facilities
Oh910i1-8594.pptx/31Oh910i1-8594.pptx/31
Step 3 – WWTP Preliminary Design
A. Fall 2013: Procure key process equipment for
design (membranes, UV) based on
qualifications and competitive pricing
Oh910i1-8594.pptx/32Oh910i1-8594.pptx/32
Step 3 – WWTP Preliminary Design
B. Combine technical detail, public input to
develop final “look & feel” of facility
Concept inspired by
June 2012 Charrrett
process.
Alternate concept
showing potentially
different site use.
Oh910i1-8594.pptx/33Oh910i1-8594.pptx/33
Step 3 – WWTP Preliminary Design
B. Combine technical detail, public input to
develop final “look & feel” of facility
Working Group
Meetings throughout
preliminary design.
Oh910i1-8594.pptx/34Oh910i1-8594.pptx/34
Step 3 – WWTP Preliminary Design
C. Develop drawings and specifications to 30
percent level detail
D. Evaluate alternatives to complete the Project
– Design-Bid-Build
– Design-Build
– General Contractor/Construction Manager
E. Spring 2014: Select delivery option and
proceed to final design in early 2014
Oh910i1-8594.pptx/35Oh910i1-8594.pptx/35
Step 4 – Outfall Final Design
• “Fast track” to provide necessary information for
permitting
• Complete in parallel with Steps 1 – 3
• Design complete in fall 2013
• Construction possible in 2014, pending results of
construction delivery analysis
Oh910i1-8594.pptx/36Oh910i1-8594.pptx/36
Significant Council Actions & Decisions
Date Action/Decision
Mar 19, 2013
Council authorizes submission to Ecology;
Approves next phase of project
Summer 2013
Council sets policy and guiding principles to
select final location
Fall 2013
Council selects final location of treatment
facility
Spring 2014
Council approves approach to complete
project
Oh910i1-8594.pptx/37Oh910i1-8594.pptx/37
Overall Project Schedule
OAK HARBOR CLEAN WATER FACILITY
PROPOSED SCHEDULE FOR PROJECT COMPLETION
2013 2014 2015 2016 2017
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
PREDESIGN PHASE
APPROVE
FACILITIES PLAN
CONSTRUCTION PERIOD
START
UP
Agency Draft
Submission
Submit Plans &
Specs
FINALDESIGN PHASE
Oh910i1-8594.pptx/38Oh910i1-8594.pptx/38
How can I stay involved?
Oh910i1-8594.pptx/39
Send an email or give us a call if
you would like to participate:
Joe Stowell, City Engineer
360-279-4520
jstowell@oakharbor.org
Oh910i1-8594.pptx/40Oh910i1-8594.pptx/40
Questions?

More Related Content

What's hot

What's hot (20)

Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
FY18 Budget Workshop Day 1
FY18 Budget Workshop Day 1FY18 Budget Workshop Day 1
FY18 Budget Workshop Day 1
 
Wastewater Master Plan Update
Wastewater Master Plan UpdateWastewater Master Plan Update
Wastewater Master Plan Update
 
C7 aug 14 city council meeting 120814_final
C7 aug 14 city council meeting 120814_finalC7 aug 14 city council meeting 120814_final
C7 aug 14 city council meeting 120814_final
 
Viability Session 4: You have viability evidence – so what?
Viability Session 4: You have viability evidence – so what?Viability Session 4: You have viability evidence – so what?
Viability Session 4: You have viability evidence – so what?
 
Planning & Development Services Fees
Planning & Development Services FeesPlanning & Development Services Fees
Planning & Development Services Fees
 
Wb final presentation
Wb final presentationWb final presentation
Wb final presentation
 
Jim Cliffe - Viability - A local authority perspective
Jim Cliffe - Viability - A local authority perspectiveJim Cliffe - Viability - A local authority perspective
Jim Cliffe - Viability - A local authority perspective
 
CIL implementation
CIL implementationCIL implementation
CIL implementation
 
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
 
Rachel Kester, Trout Unlimited, “TU’s OM&R Jobs Analysis Study”
Rachel Kester, Trout Unlimited, “TU’s OM&R Jobs Analysis Study”Rachel Kester, Trout Unlimited, “TU’s OM&R Jobs Analysis Study”
Rachel Kester, Trout Unlimited, “TU’s OM&R Jobs Analysis Study”
 
140416 oak_harbor_workshp_presentation
140416 oak_harbor_workshp_presentation140416 oak_harbor_workshp_presentation
140416 oak_harbor_workshp_presentation
 
Tampa Stormwater Assessment
Tampa Stormwater AssessmentTampa Stormwater Assessment
Tampa Stormwater Assessment
 
FY17 Budget Amendment No. 1
FY17 Budget Amendment No. 1FY17 Budget Amendment No. 1
FY17 Budget Amendment No. 1
 
FY 21 Budget Amendment No. 2
FY 21 Budget Amendment No. 2FY 21 Budget Amendment No. 2
FY 21 Budget Amendment No. 2
 
Surrey CC: County Council CIL Seminar
Surrey CC: County Council CIL SeminarSurrey CC: County Council CIL Seminar
Surrey CC: County Council CIL Seminar
 
CIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notesCIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notes
 
Fy 2015 16 proposed budget presentation
Fy 2015 16 proposed budget presentationFy 2015 16 proposed budget presentation
Fy 2015 16 proposed budget presentation
 

Viewers also liked

C8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalC8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_final
publicinvolvement
 
C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1
publicinvolvement
 
March 9, 2011 City Council Workshop
March 9, 2011 City Council WorkshopMarch 9, 2011 City Council Workshop
March 9, 2011 City Council Workshop
publicinvolvement
 
April 12 Planning Public Forum
April 12 Planning Public ForumApril 12 Planning Public Forum
April 12 Planning Public Forum
publicinvolvement
 
January 13, 2011 City Council Workshop
January 13, 2011 City Council WorkshopJanuary 13, 2011 City Council Workshop
January 13, 2011 City Council Workshop
publicinvolvement
 
C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11
publicinvolvement
 

Viewers also liked (20)

Oak Harbor Design Open House
Oak Harbor Design Open HouseOak Harbor Design Open House
Oak Harbor Design Open House
 
C8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalC8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_final
 
Oh workshop02 full_final
Oh workshop02 full_finalOh workshop02 full_final
Oh workshop02 full_final
 
Design charrette council presentation
Design charrette council presentationDesign charrette council presentation
Design charrette council presentation
 
C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1
 
Oak Harbor Design Open House summary
Oak Harbor Design Open House summaryOak Harbor Design Open House summary
Oak Harbor Design Open House summary
 
2015 0617 workshop_presentation_outfall_draft_brm
2015 0617 workshop_presentation_outfall_draft_brm2015 0617 workshop_presentation_outfall_draft_brm
2015 0617 workshop_presentation_outfall_draft_brm
 
Oak Harbor Good Neighbor Plan
Oak Harbor Good Neighbor PlanOak Harbor Good Neighbor Plan
Oak Harbor Good Neighbor Plan
 
December 6 Public Forum
December 6 Public ForumDecember 6 Public Forum
December 6 Public Forum
 
March 9, 2011 City Council Workshop
March 9, 2011 City Council WorkshopMarch 9, 2011 City Council Workshop
March 9, 2011 City Council Workshop
 
T5 further refine alts min
T5 further refine alts minT5 further refine alts min
T5 further refine alts min
 
60% Design and Cost Estimate
60% Design and Cost Estimate60% Design and Cost Estimate
60% Design and Cost Estimate
 
Windjammer Park Integration Plan - Council presentation
Windjammer Park Integration Plan - Council presentationWindjammer Park Integration Plan - Council presentation
Windjammer Park Integration Plan - Council presentation
 
April 12 Planning Public Forum
April 12 Planning Public ForumApril 12 Planning Public Forum
April 12 Planning Public Forum
 
Windjammer Park Phase 1 Design Open House
Windjammer Park Phase 1 Design Open HouseWindjammer Park Phase 1 Design Open House
Windjammer Park Phase 1 Design Open House
 
Oak Harbor City Council Workshop: Design Update
Oak Harbor City Council Workshop: Design UpdateOak Harbor City Council Workshop: Design Update
Oak Harbor City Council Workshop: Design Update
 
January 13, 2011 City Council Workshop
January 13, 2011 City Council WorkshopJanuary 13, 2011 City Council Workshop
January 13, 2011 City Council Workshop
 
Clean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate PreviewClean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate Preview
 
Windjammer Park Integration Plan Community Advisory Group meeting 4
Windjammer Park Integration Plan Community Advisory Group meeting 4Windjammer Park Integration Plan Community Advisory Group meeting 4
Windjammer Park Integration Plan Community Advisory Group meeting 4
 
C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11
 

Similar to 130306 City Council Workshop

Local Govt Policy Sheet - August EC
Local Govt Policy Sheet - August ECLocal Govt Policy Sheet - August EC
Local Govt Policy Sheet - August EC
James Touchton, MPA
 
coverpagePVsolarflowers
coverpagePVsolarflowerscoverpagePVsolarflowers
coverpagePVsolarflowers
Dessiray koss
 
January 13 City Council Workshop
January 13 City Council WorkshopJanuary 13 City Council Workshop
January 13 City Council Workshop
publicinvolvement
 
Citistat PPT 01.14.2016
Citistat PPT 01.14.2016Citistat PPT 01.14.2016
Citistat PPT 01.14.2016
Mark Conway
 

Similar to 130306 City Council Workshop (20)

Foundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor ProjectFoundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor Project
 
Town of Carrboro Financial Status and Budget Development
Town of Carrboro Financial Status and Budget DevelopmentTown of Carrboro Financial Status and Budget Development
Town of Carrboro Financial Status and Budget Development
 
Municipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public FundingMunicipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public Funding
 
Project Controls Overview - R2
Project Controls Overview - R2Project Controls Overview - R2
Project Controls Overview - R2
 
RV 2014: TOD Market Dreams + Reality by John Breitinger
RV 2014: TOD Market Dreams + Reality by John BreitingerRV 2014: TOD Market Dreams + Reality by John Breitinger
RV 2014: TOD Market Dreams + Reality by John Breitinger
 
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
 
Item # 5 PPT
Item # 5  PPT Item # 5  PPT
Item # 5 PPT
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentation
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
Local Govt Policy Sheet - August EC
Local Govt Policy Sheet - August ECLocal Govt Policy Sheet - August EC
Local Govt Policy Sheet - August EC
 
Connecticut Green Bank Stakeholder Webinar Quarter 4 FY17
Connecticut Green Bank Stakeholder Webinar Quarter 4 FY17Connecticut Green Bank Stakeholder Webinar Quarter 4 FY17
Connecticut Green Bank Stakeholder Webinar Quarter 4 FY17
 
Work Pricing in construction projects by K C Iyer
Work Pricing in construction projects by K C IyerWork Pricing in construction projects by K C Iyer
Work Pricing in construction projects by K C Iyer
 
coverpagePVsolarflowers
coverpagePVsolarflowerscoverpagePVsolarflowers
coverpagePVsolarflowers
 
Share Sustainability – Sustainable solutions to water and climate challenges...
 Share Sustainability – Sustainable solutions to water and climate challenges... Share Sustainability – Sustainable solutions to water and climate challenges...
Share Sustainability – Sustainable solutions to water and climate challenges...
 
Council Workshop
Council WorkshopCouncil Workshop
Council Workshop
 
January 13 City Council Workshop
January 13 City Council WorkshopJanuary 13 City Council Workshop
January 13 City Council Workshop
 
Kanban for Fixed Price Projects
Kanban for Fixed Price ProjectsKanban for Fixed Price Projects
Kanban for Fixed Price Projects
 
Citistat PPT 01.14.2016
Citistat PPT 01.14.2016Citistat PPT 01.14.2016
Citistat PPT 01.14.2016
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 

More from publicinvolvement

130306 city council workshop revised
130306 city council workshop revised130306 city council workshop revised
130306 city council workshop revised
publicinvolvement
 

More from publicinvolvement (11)

Presentation of Windjammer Park 60% Design to City Council
Presentation of Windjammer Park 60% Design to City CouncilPresentation of Windjammer Park 60% Design to City Council
Presentation of Windjammer Park 60% Design to City Council
 
Preview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City CouncilPreview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City Council
 
Presentation of Windjammer Park Integration Plan to City Council
Presentation of Windjammer Park Integration Plan to City CouncilPresentation of Windjammer Park Integration Plan to City Council
Presentation of Windjammer Park Integration Plan to City Council
 
Windjammer Park Integration Plan Community Advisory Group meeting 5
Windjammer Park Integration Plan Community Advisory Group meeting 5Windjammer Park Integration Plan Community Advisory Group meeting 5
Windjammer Park Integration Plan Community Advisory Group meeting 5
 
Community Advisory Group meeting 5
Community Advisory Group meeting 5Community Advisory Group meeting 5
Community Advisory Group meeting 5
 
Oak Harbor Windjammer Park Integration Plan
Oak Harbor Windjammer Park Integration Plan Oak Harbor Windjammer Park Integration Plan
Oak Harbor Windjammer Park Integration Plan
 
Oak Harbor Community Advisory Group meeing 2 and public open house
Oak Harbor Community Advisory Group meeing 2 and public open houseOak Harbor Community Advisory Group meeing 2 and public open house
Oak Harbor Community Advisory Group meeing 2 and public open house
 
Windjammer Park Integration Plan CAG meeting 1
Windjammer Park Integration Plan CAG meeting 1Windjammer Park Integration Plan CAG meeting 1
Windjammer Park Integration Plan CAG meeting 1
 
150604 Oak Harbor Wastewater Treatment Plant Update
150604 Oak Harbor Wastewater Treatment Plant Update150604 Oak Harbor Wastewater Treatment Plant Update
150604 Oak Harbor Wastewater Treatment Plant Update
 
130306 city council workshop revised
130306 city council workshop revised130306 city council workshop revised
130306 city council workshop revised
 
Volume i executive summary
Volume i executive summaryVolume i executive summary
Volume i executive summary
 

Recently uploaded

THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
Faga1939
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
Diya Sharma
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
PsychicRuben LoveSpells
 

Recently uploaded (20)

China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
 
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 

130306 City Council Workshop