Topics
How much risk management do I need to do?
What about upside risk?
How much risk is too much?
How to stay up to date?
When does risk management end?
…but first…
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 3
Why manage risk on projects?
The most important thing!
All projects are risky
Risks drive us off plan
Risk management effectiveness  Project success
Risk can (should/must) be managed proactively
RISK MANAGEMENT
PRIORITY
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 4
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 5
1. How much risk management?
All projects are risky, but…
Risk process must be scaleable
Ensure level, type & visibility of process match:
riskiness of project
importance of project to organisation
Affects
methodology, tools & techniques
organisation & staffing
reporting requirements etc.
Document decisions in Risk Management Plan
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 6
Define project riskiness
Yes, but how?
Define meaningful “size” criteria for this project (~10)
Determine threshold levels for each criteria
Score project
Use overall score to define project as Small/Medium/Large
Allow shortcuts for “obviously Small/Large”
Scope risk process to match project risk challenge
define /dI’fam/ v.t. state precise meaning
of; describe scope of; outline; mark out
(limits, boundary).
dI’fa
scribe
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 7
Define project riskiness
[Example Project Sizing Tool]
CRITERION Criterion Value = 2 Criterion Value = 4 Criterion Value = 8 Criterion Value = 16 Criterion
Score
Strategic importance Minor contribution to business
objectives
Significant contribution to
business objectives
Major contribution to business
objectives
Critical to business success
Commercial /
contractual complexity
No unusual commercial
arrangements or conditions
Minor deviation from existing
commercial practices
Novel commercial practices, new
to at least one party
Ground-breaking commercial
practices
External constraints
and dependencies
None Some external influence on
elements of the project
Key project objectives depend on
external factors
Overall project success depends
on external factors
Requirement stability Clear fully-defined agreed
objectives
Some requirement uncertainty,
minor changes during project
Major requirement uncertainty,
major changes during project
Requirements not finalised and
subject to negotiation
Technical complexity Routine repeat business, no new
technology
Enhancement of existing
product/service
Novel product/project with some
innovation
Ground-breaking project with
high innovation
Market sector regulatory
characteristics
No regulatory requirements Standard regulatory framework Challenging regulatory
requirements
Highly regulated or novel sector
Project value Small project value
(<$250K)
Significant project value
($250K-1M)
Major project value
($1-3M)
Large project value
(>$3M)
Project duration Duration <3 months Duration 3-12 months Duration 1-3 years Duration >3 years
Project resources Small in-house project team Medium in-house project team Large project team including
external contractors
International project team or
joint venture
Post-project liabilities None Acceptable exposure Significant exposure Punitive exposure
OVERALL PROJECT SCORE
PROJECT SCORE: <35 = Small; 35-74 = Medium; ≥75 = Large
Shortcuts: Project Value <$50K = Small; >$5M = Large
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 8
Scaleable risk process
 Small projects = lower risk challenge = simplified risk process
Medium projects = average risk challenge = typical risk process
Large projects = higher risk challenge = enhanced risk process
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 9
Scaleable risk process
Yes, but how?
 Small projects/simplified risk process
Still include all process steps, but…
Involve fewer people, use existing project meetings, use
fewer/simpler techniques, less detailed updates, simple reporting…
Medium projects/typical risk process
No changes!
Large projects/enhanced risk process
Involve more people, dedicated workshops, use more in-depth
techniques, deeper updates, tailored reporting…
Consider quantitative risk analysis
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 10

Risk = Uncertainty
True or False ?
Risk = Uncertainty that matters
(i.e. can affect objectives)
2. What about upside risk?
What is risk?
≠
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 11
Risk connects uncertainty with objectives
ISO 31000:2018
“The effect of uncertainty on objectives”
What is risk?
Risk includes both opportunities & threats
“An effect is a deviation from the expected.
It can be positive, negative or both…”
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 12
Which impacts matter?
Uncertainties that help as well as
uncertainties that harm
Both need managing proactively
Managing risk means…
…not only preventing potential problems
“Stop things going wrong”
…but also finding potential benefits
“Help things go right”
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 13
Goals of risk management
Minimise threats
Maximise opportunities
Optimise achievement of objectives
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 14
Managing opportunities matters
Yes, but how?
Same risk process
Extended techniques for opportunities
risk identification (find positive uncertainties)
two-dimensional techniques
risk assessment & prioritisation (pick best ones)
Double P-I Matrix
risk responses (make happen, or maximise)
equivalent strategies
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 15
Two-dimensional risk
identification techniques
SWOT Analysis
“We’re good/bad at… So what?”
Assumptions/Constraints Analysis
“What if…? What if not…?”
Fault/Benefit Tree Analysis
“Yes, but how…?”
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 16
VHI
HI
MED
LO
VLO
POSITIVE IMPACT
(Opportunities)
VHI HI MED LO VLO
PROBABILITY
NEGATIVE IMPACT
(Threats)
VHI
HI
MED
LO
VLO
VLO LO MED HI VHI
PROBABILITY
Prioritising opportunities
1
QUICK WINS:
EASY TO GET &
BIG BENEFIT
3
CONSIDER IMPROVING:
EASY BUT
LOWER BENEFIT
2
WORTH EXPLORING:
HARDER TO GET
BUT BIG BENEFIT
4
DON’T
BOTHER!
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 17
Avoid
Reduce
Transfer
Accept
THREAT GENERIC STRATEGY OPPORTUNITY
ELIMINATE UNCERTAINTY
CHANGE SIZE
INVOLVE OTHERS
TAKE THE RISK
Exploit
Enhance
Share
Accept
Responding to opportunities
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 18
3. How much risk is too much risk?
“It depends”… on…
… project objectives
… stakeholder risk appetite
… organisational risk thresholds
One person’s “Critical” is another’s “Who cares?”
Define impact scales (VHI)/HI/MED/LO/(VLO)
Who defines?
Project sponsor with other key stakeholders
Record in Project Charter, business case or Risk Management Plan
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 19
Each risk has one probability of occurrence and at least one impact
Example of project-specific scales
RANK PROB
IMPACT ON PROJECT OBJECTIVES (+ or -)
TIME COST PERFORMANCE
VHI 71-99% >12 weeks >$1000K Effect on overall functionality
HI 51-70% 7-12 weeks $500-1000K Major effect on key parameters
MED 31-50% 3 - 6 weeks $250-500K Minor effect on key parameters
LO 11-30% 1 - 2 weeks $100-250K Effect on >1 minor parameters
VLO 1-10% < 1 week < $100K Effect on 1 minor parameter
NIL - No change No change No change in performance
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 20
Defining HI/MED/LO impacts
Impact = different for each objective
Assume 5-point scale (could be 3 or 4):
For threats:
VHI = intolerable, unacceptable, “Oh no!”
VLO = negligible, insignificant, “Who cares?”
Other points spread between
For opportunities:
VHI = essential, “Can’t miss”, “Must have”
VLO = insignificant, “Who cares?”
Often same as threat scales, could differ
define /dI’fam/ v.t. state precise meaning
of; describe scope of; outline; mark out
(limits, boundary).
dI’fa
scribe
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 21
Threat Impacts Opportunity Impacts
Step 1 – Define VHI Step 2 – Define VLO Step 3 – Set
intermediate values
Step 4 – Define VHI Step 5 – Define VLO Step 6 – Set
intermediate values
Time Cost Time Cost Time Cost Time Cost Time Cost Time Cost
VHI >8 wks >$1m >4 wks >$500k
HI 4-8 wks $500k-1m 3-4 wks
$250k-
500k
MED 2-4 wks
$100k-
500k
2-3 wks $80-$250k
LO 1-2 wks $10k-100k 1-2 wks $10k-80k
VLO <1 wk <$10k <1 wk <$10k
Worked example
Project objective: Release new product to market
Planned timeline = 10 months; project budget = $4M
Delivery >2 months late would miss market window; cost growth to >$5M means cancellation
Earliest feasible delivery date to meet market requirements = 4 weeks early
Cost savings of >$500K would double profit margin
Schedule/budget variation of ±10% is acceptable
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 22
4. How to stay up to date?
Essential because risk changes:
risks happen (opportunities & threats)
risks are resolved
risks time-out
risks get better or worse
new risks emerge
Repeat the entire process?
or
Review/update risk exposure regularly?
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 23
The ATOM solution
INITIATE ATOM PROCESS
FIRST RISK ASSESSMENT
Identify risks
Assess risks
Plan responses
RISK CONTROL
Implement responses
Risk reporting
RISK UPDATE
Risk reviews
REPEAT
REGULARLY
REPEAT FOR
NEW PHASE OR
ON MAJOR
SCOPE CHANGE
MAJOR
REVIEW
MINOR
REVIEW
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 24
The ATOM solution
Major Review and Minor Review
Major
At key lifecycle points (milestones/phases/gates) & on major scope change
Full reassessment of risk exposure – repeat steps in First Risk Assessment
Minor
At regular intervals (to fit project rhythm)
Update existing risk assessment and responses
Scaleable feature
Large projects: more Major Reviews, deeper reassessment
Small projects: mostly Minor Reviews, higher-level
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 25
Risk reviews
Risk review should:
address status of existing risks [all or top-priority only]
identify whether new risks have arisen
confirm risk ownership
consider effectiveness of planned responses
identify new responses where needed
[assess secondary risks]
[check effectiveness of risk process]
[assess implications of any change in project context]
Hold dedicated review workshop or use existing meeting
Remember the risk process is iterative and scaleable
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 26
5. When does risk management end?
Most risk processes appear to be endless!
ISO 31000:2018 Risk
Management – Guidelines
Standard for Risk
Management (2017)
PRAM Guide, Second
edition (2004/2010)
Management of Risk,
Fourth Edition (2022)
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 27
5. When does risk management end?
Most risk processes appear to be endless!
No project risks exist at project completion
Note: There are still risks to handover, execution, maintenance, disposal…
Risk management should end when project ends
Yes, but how?
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 28
The ATOM solution
INITIATE ATOM PROCESS
FIRST RISK ASSESSMENT
Identify risks
Assess risks
Plan responses
RISK CONTROL
Implement responses
Risk reporting
RISK UPDATE
Risk reviews
POST-PROJECT RISK REVIEW
REPEAT
REGULARLY
REPEAT FOR
NEW PHASE OR
ON MAJOR
SCOPE CHANGE
MAJOR
REVIEW
MINOR
REVIEW
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 29
Purpose of post-project risk review
Learn from experience
“Capture risk-related knowledge and experience in a form
that can be used by future similar projects”
“Lessons-learned”
Part of post-project review, or dedicated meeting
Ask open questions:
What risks were identified? Any generic?
What threats happened, what opportunities were missed?
Which responses worked & which didn’t?
What did we do well, and what could have been better?
How much effort was spent on RM? Possible efficiencies?
 “Lessons-to-be-learned”
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 30
Lessons-to-be-learned (L2BL)
Not learned until implemented
Consider L2BL Register
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 31
Final thoughts
© 2010-23 David Hillson/The Risk Doctor Partnership, Slide 32
For further information
Dr David Hillson
The Risk Doctor
+44(0)7717.665222
david@risk-doctor.com
www.risk-doctor.com
www.atom-risk.com
YouTube.com/RiskDoctorVideo

More Related Content

What's hot

Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk ManagementKelvin Fredson
 
Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides SlideTeam
 
Risk management
Risk managementRisk management
Risk managementMECandPMV
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...HIMADRI BANERJI
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk managementIQPC
 
Strategic PMO Implementation تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجي
Strategic PMO Implementation  تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجيStrategic PMO Implementation  تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجي
Strategic PMO Implementation تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجيAbdelrahman Elsheikh PMOC,PMP,CBAP,RMP,ACP,SP,MCITP,ITIL
 
Project management
Project managementProject management
Project managementPooja Rani
 

What's hot (20)

Developing a mature risk mindset, 1 July 2021
Developing a mature risk mindset, 1 July 2021Developing a mature risk mindset, 1 July 2021
Developing a mature risk mindset, 1 July 2021
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
project management essentials
project management essentialsproject management essentials
project management essentials
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Integrating risk and benefits management
Integrating risk and benefits managementIntegrating risk and benefits management
Integrating risk and benefits management
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
Project risk management
Project risk managementProject risk management
Project risk management
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
Project charter-template
Project charter-templateProject charter-template
Project charter-template
 
Risk management
Risk managementRisk management
Risk management
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Strategic PMO Implementation تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجي
Strategic PMO Implementation  تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجيStrategic PMO Implementation  تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجي
Strategic PMO Implementation تأسيس وتشغيل مكتب إدارة المشاريع الإستراتيجي
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project management
Project managementProject management
Project management
 

Similar to Demystifying Project Risk Management

Managing Risk for Sustainable Business by Dr David Hillson
Managing Risk for Sustainable Business by Dr David HillsonManaging Risk for Sustainable Business by Dr David Hillson
Managing Risk for Sustainable Business by Dr David HillsonPMIUKChapter
 
Managing Risk for Sustainability by Dr David Hillson
Managing Risk for Sustainability by Dr David HillsonManaging Risk for Sustainability by Dr David Hillson
Managing Risk for Sustainability by Dr David HillsonPMIUKChapter
 
PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks PECB
 
KIIID Key Impact Investor Information Document (explained)
KIIID Key Impact Investor Information Document (explained)KIIID Key Impact Investor Information Document (explained)
KIIID Key Impact Investor Information Document (explained)Drs Alcanne Houtzaager MA
 
Fundamentals Of Risk Management
Fundamentals Of Risk ManagementFundamentals Of Risk Management
Fundamentals Of Risk ManagementDr David Hancock
 
Cs investing for-impact
Cs investing for-impactCs investing for-impact
Cs investing for-impactch7m
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsRicardo Viana Vargas
 
Top 12 NET IMPACT for investors and innovators
Top 12 NET IMPACT for investors and innovatorsTop 12 NET IMPACT for investors and innovators
Top 12 NET IMPACT for investors and innovatorsDrs Alcanne Houtzaager MA
 
Thomas Walenta - Implementing_change_in_organizations
Thomas Walenta - Implementing_change_in_organizationsThomas Walenta - Implementing_change_in_organizations
Thomas Walenta - Implementing_change_in_organizationsThomas Walenta, PMI Fellow
 
Public Sector Enterprise Risk Management
Public Sector Enterprise Risk ManagementPublic Sector Enterprise Risk Management
Public Sector Enterprise Risk ManagementDr David Hancock
 
Certs-UEM-2015
Certs-UEM-2015Certs-UEM-2015
Certs-UEM-2015Yusof Mohd
 
Impact investing study in the private equity field
Impact investing study in the private equity fieldImpact investing study in the private equity field
Impact investing study in the private equity fieldSitraTalousTeema
 
ASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESS
ASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESSASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESS
ASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESSRobin Beregovska
 

Similar to Demystifying Project Risk Management (20)

Risk descriptions from 'Coconut island' risk workshop
Risk descriptions from 'Coconut island' risk workshopRisk descriptions from 'Coconut island' risk workshop
Risk descriptions from 'Coconut island' risk workshop
 
Managing Risk for Sustainable Business by Dr David Hillson
Managing Risk for Sustainable Business by Dr David HillsonManaging Risk for Sustainable Business by Dr David Hillson
Managing Risk for Sustainable Business by Dr David Hillson
 
Managing Risk for Sustainability by Dr David Hillson
Managing Risk for Sustainability by Dr David HillsonManaging Risk for Sustainability by Dr David Hillson
Managing Risk for Sustainability by Dr David Hillson
 
PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks
 
Cipfa Workshops Scotland
Cipfa Workshops ScotlandCipfa Workshops Scotland
Cipfa Workshops Scotland
 
Risk Management Essay
Risk Management EssayRisk Management Essay
Risk Management Essay
 
KIIID Key Impact Investor Information Document (explained)
KIIID Key Impact Investor Information Document (explained)KIIID Key Impact Investor Information Document (explained)
KIIID Key Impact Investor Information Document (explained)
 
Managing risk in programmes webinar, 2 July 2018
Managing risk in programmes webinar, 2 July 2018Managing risk in programmes webinar, 2 July 2018
Managing risk in programmes webinar, 2 July 2018
 
Fundamentals Of Risk Management
Fundamentals Of Risk ManagementFundamentals Of Risk Management
Fundamentals Of Risk Management
 
Cs investing for-impact
Cs investing for-impactCs investing for-impact
Cs investing for-impact
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled Projects
 
Top 12 NET IMPACT for investors and innovators
Top 12 NET IMPACT for investors and innovatorsTop 12 NET IMPACT for investors and innovators
Top 12 NET IMPACT for investors and innovators
 
Thomas Walenta - Implementing_change_in_organizations
Thomas Walenta - Implementing_change_in_organizationsThomas Walenta - Implementing_change_in_organizations
Thomas Walenta - Implementing_change_in_organizations
 
QRA for overall project risk - Dr David Hillson
QRA for overall project risk - Dr David HillsonQRA for overall project risk - Dr David Hillson
QRA for overall project risk - Dr David Hillson
 
Public Sector Enterprise Risk Management
Public Sector Enterprise Risk ManagementPublic Sector Enterprise Risk Management
Public Sector Enterprise Risk Management
 
Certs-UEM-2015
Certs-UEM-2015Certs-UEM-2015
Certs-UEM-2015
 
Impact investing study in the private equity field
Impact investing study in the private equity fieldImpact investing study in the private equity field
Impact investing study in the private equity field
 
Procept Risk Workshop 2007
Procept Risk Workshop 2007Procept Risk Workshop 2007
Procept Risk Workshop 2007
 
ASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESS
ASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESSASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESS
ASSESSING THE RELATIONSHIP EFFECTIVE RISK ANALYSIS HAVE ON BUSINESS SUCCESS
 
Security Risk Management Essay
Security Risk Management EssaySecurity Risk Management Essay
Security Risk Management Essay
 

More from Association for Project Management

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 

More from Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Recently uploaded

Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 

Recently uploaded (20)

Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 

Demystifying Project Risk Management

  • 1. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 1 DEMYSTIFYING PROJECT RISK MANAGEMENT Practical tips for practitioners Presented by Dr David Hillson HonFAPM, PMI Fellow, CFIRM at APM SWWE Branch meeting, BAWA Bristol, 18 April 2023 The Risk Doctor The Risk Doctor Partnership david@risk-doctor.com www.risk-doctor.com
  • 2. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 2 Topics How much risk management do I need to do? What about upside risk? How much risk is too much? How to stay up to date? When does risk management end? …but first…
  • 3. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 3 Why manage risk on projects? The most important thing! All projects are risky Risks drive us off plan Risk management effectiveness  Project success Risk can (should/must) be managed proactively RISK MANAGEMENT PRIORITY
  • 4. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 4
  • 5. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 5 1. How much risk management? All projects are risky, but… Risk process must be scaleable Ensure level, type & visibility of process match: riskiness of project importance of project to organisation Affects methodology, tools & techniques organisation & staffing reporting requirements etc. Document decisions in Risk Management Plan
  • 6. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 6 Define project riskiness Yes, but how? Define meaningful “size” criteria for this project (~10) Determine threshold levels for each criteria Score project Use overall score to define project as Small/Medium/Large Allow shortcuts for “obviously Small/Large” Scope risk process to match project risk challenge define /dI’fam/ v.t. state precise meaning of; describe scope of; outline; mark out (limits, boundary). dI’fa scribe
  • 7. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 7 Define project riskiness [Example Project Sizing Tool] CRITERION Criterion Value = 2 Criterion Value = 4 Criterion Value = 8 Criterion Value = 16 Criterion Score Strategic importance Minor contribution to business objectives Significant contribution to business objectives Major contribution to business objectives Critical to business success Commercial / contractual complexity No unusual commercial arrangements or conditions Minor deviation from existing commercial practices Novel commercial practices, new to at least one party Ground-breaking commercial practices External constraints and dependencies None Some external influence on elements of the project Key project objectives depend on external factors Overall project success depends on external factors Requirement stability Clear fully-defined agreed objectives Some requirement uncertainty, minor changes during project Major requirement uncertainty, major changes during project Requirements not finalised and subject to negotiation Technical complexity Routine repeat business, no new technology Enhancement of existing product/service Novel product/project with some innovation Ground-breaking project with high innovation Market sector regulatory characteristics No regulatory requirements Standard regulatory framework Challenging regulatory requirements Highly regulated or novel sector Project value Small project value (<$250K) Significant project value ($250K-1M) Major project value ($1-3M) Large project value (>$3M) Project duration Duration <3 months Duration 3-12 months Duration 1-3 years Duration >3 years Project resources Small in-house project team Medium in-house project team Large project team including external contractors International project team or joint venture Post-project liabilities None Acceptable exposure Significant exposure Punitive exposure OVERALL PROJECT SCORE PROJECT SCORE: <35 = Small; 35-74 = Medium; ≥75 = Large Shortcuts: Project Value <$50K = Small; >$5M = Large
  • 8. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 8 Scaleable risk process  Small projects = lower risk challenge = simplified risk process Medium projects = average risk challenge = typical risk process Large projects = higher risk challenge = enhanced risk process
  • 9. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 9 Scaleable risk process Yes, but how?  Small projects/simplified risk process Still include all process steps, but… Involve fewer people, use existing project meetings, use fewer/simpler techniques, less detailed updates, simple reporting… Medium projects/typical risk process No changes! Large projects/enhanced risk process Involve more people, dedicated workshops, use more in-depth techniques, deeper updates, tailored reporting… Consider quantitative risk analysis
  • 10. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 10  Risk = Uncertainty True or False ? Risk = Uncertainty that matters (i.e. can affect objectives) 2. What about upside risk? What is risk? ≠
  • 11. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 11 Risk connects uncertainty with objectives ISO 31000:2018 “The effect of uncertainty on objectives” What is risk? Risk includes both opportunities & threats “An effect is a deviation from the expected. It can be positive, negative or both…”
  • 12. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 12 Which impacts matter? Uncertainties that help as well as uncertainties that harm Both need managing proactively Managing risk means… …not only preventing potential problems “Stop things going wrong” …but also finding potential benefits “Help things go right”
  • 13. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 13 Goals of risk management Minimise threats Maximise opportunities Optimise achievement of objectives
  • 14. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 14 Managing opportunities matters Yes, but how? Same risk process Extended techniques for opportunities risk identification (find positive uncertainties) two-dimensional techniques risk assessment & prioritisation (pick best ones) Double P-I Matrix risk responses (make happen, or maximise) equivalent strategies
  • 15. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 15 Two-dimensional risk identification techniques SWOT Analysis “We’re good/bad at… So what?” Assumptions/Constraints Analysis “What if…? What if not…?” Fault/Benefit Tree Analysis “Yes, but how…?”
  • 16. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 16 VHI HI MED LO VLO POSITIVE IMPACT (Opportunities) VHI HI MED LO VLO PROBABILITY NEGATIVE IMPACT (Threats) VHI HI MED LO VLO VLO LO MED HI VHI PROBABILITY Prioritising opportunities 1 QUICK WINS: EASY TO GET & BIG BENEFIT 3 CONSIDER IMPROVING: EASY BUT LOWER BENEFIT 2 WORTH EXPLORING: HARDER TO GET BUT BIG BENEFIT 4 DON’T BOTHER!
  • 17. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 17 Avoid Reduce Transfer Accept THREAT GENERIC STRATEGY OPPORTUNITY ELIMINATE UNCERTAINTY CHANGE SIZE INVOLVE OTHERS TAKE THE RISK Exploit Enhance Share Accept Responding to opportunities
  • 18. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 18 3. How much risk is too much risk? “It depends”… on… … project objectives … stakeholder risk appetite … organisational risk thresholds One person’s “Critical” is another’s “Who cares?” Define impact scales (VHI)/HI/MED/LO/(VLO) Who defines? Project sponsor with other key stakeholders Record in Project Charter, business case or Risk Management Plan
  • 19. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 19 Each risk has one probability of occurrence and at least one impact Example of project-specific scales RANK PROB IMPACT ON PROJECT OBJECTIVES (+ or -) TIME COST PERFORMANCE VHI 71-99% >12 weeks >$1000K Effect on overall functionality HI 51-70% 7-12 weeks $500-1000K Major effect on key parameters MED 31-50% 3 - 6 weeks $250-500K Minor effect on key parameters LO 11-30% 1 - 2 weeks $100-250K Effect on >1 minor parameters VLO 1-10% < 1 week < $100K Effect on 1 minor parameter NIL - No change No change No change in performance
  • 20. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 20 Defining HI/MED/LO impacts Impact = different for each objective Assume 5-point scale (could be 3 or 4): For threats: VHI = intolerable, unacceptable, “Oh no!” VLO = negligible, insignificant, “Who cares?” Other points spread between For opportunities: VHI = essential, “Can’t miss”, “Must have” VLO = insignificant, “Who cares?” Often same as threat scales, could differ define /dI’fam/ v.t. state precise meaning of; describe scope of; outline; mark out (limits, boundary). dI’fa scribe
  • 21. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 21 Threat Impacts Opportunity Impacts Step 1 – Define VHI Step 2 – Define VLO Step 3 – Set intermediate values Step 4 – Define VHI Step 5 – Define VLO Step 6 – Set intermediate values Time Cost Time Cost Time Cost Time Cost Time Cost Time Cost VHI >8 wks >$1m >4 wks >$500k HI 4-8 wks $500k-1m 3-4 wks $250k- 500k MED 2-4 wks $100k- 500k 2-3 wks $80-$250k LO 1-2 wks $10k-100k 1-2 wks $10k-80k VLO <1 wk <$10k <1 wk <$10k Worked example Project objective: Release new product to market Planned timeline = 10 months; project budget = $4M Delivery >2 months late would miss market window; cost growth to >$5M means cancellation Earliest feasible delivery date to meet market requirements = 4 weeks early Cost savings of >$500K would double profit margin Schedule/budget variation of ±10% is acceptable
  • 22. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 22 4. How to stay up to date? Essential because risk changes: risks happen (opportunities & threats) risks are resolved risks time-out risks get better or worse new risks emerge Repeat the entire process? or Review/update risk exposure regularly?
  • 23. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 23 The ATOM solution INITIATE ATOM PROCESS FIRST RISK ASSESSMENT Identify risks Assess risks Plan responses RISK CONTROL Implement responses Risk reporting RISK UPDATE Risk reviews REPEAT REGULARLY REPEAT FOR NEW PHASE OR ON MAJOR SCOPE CHANGE MAJOR REVIEW MINOR REVIEW
  • 24. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 24 The ATOM solution Major Review and Minor Review Major At key lifecycle points (milestones/phases/gates) & on major scope change Full reassessment of risk exposure – repeat steps in First Risk Assessment Minor At regular intervals (to fit project rhythm) Update existing risk assessment and responses Scaleable feature Large projects: more Major Reviews, deeper reassessment Small projects: mostly Minor Reviews, higher-level
  • 25. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 25 Risk reviews Risk review should: address status of existing risks [all or top-priority only] identify whether new risks have arisen confirm risk ownership consider effectiveness of planned responses identify new responses where needed [assess secondary risks] [check effectiveness of risk process] [assess implications of any change in project context] Hold dedicated review workshop or use existing meeting Remember the risk process is iterative and scaleable
  • 26. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 26 5. When does risk management end? Most risk processes appear to be endless! ISO 31000:2018 Risk Management – Guidelines Standard for Risk Management (2017) PRAM Guide, Second edition (2004/2010) Management of Risk, Fourth Edition (2022)
  • 27. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 27 5. When does risk management end? Most risk processes appear to be endless! No project risks exist at project completion Note: There are still risks to handover, execution, maintenance, disposal… Risk management should end when project ends Yes, but how?
  • 28. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 28 The ATOM solution INITIATE ATOM PROCESS FIRST RISK ASSESSMENT Identify risks Assess risks Plan responses RISK CONTROL Implement responses Risk reporting RISK UPDATE Risk reviews POST-PROJECT RISK REVIEW REPEAT REGULARLY REPEAT FOR NEW PHASE OR ON MAJOR SCOPE CHANGE MAJOR REVIEW MINOR REVIEW
  • 29. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 29 Purpose of post-project risk review Learn from experience “Capture risk-related knowledge and experience in a form that can be used by future similar projects” “Lessons-learned” Part of post-project review, or dedicated meeting Ask open questions: What risks were identified? Any generic? What threats happened, what opportunities were missed? Which responses worked & which didn’t? What did we do well, and what could have been better? How much effort was spent on RM? Possible efficiencies?  “Lessons-to-be-learned”
  • 30. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 30 Lessons-to-be-learned (L2BL) Not learned until implemented Consider L2BL Register
  • 31. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 31 Final thoughts
  • 32. © 2010-23 David Hillson/The Risk Doctor Partnership, Slide 32 For further information Dr David Hillson The Risk Doctor +44(0)7717.665222 david@risk-doctor.com www.risk-doctor.com www.atom-risk.com YouTube.com/RiskDoctorVideo