SlideShare a Scribd company logo
1 of 41
With and without losses
Unit Commitment
By Asha Anu Kurian
Department of EEE
Saintgits College of Engineering
 Introduction
 Different constraints
 ELD neglecting losses
 With losses
 Methods of calculating penalty factor and loss coefficient
Part II
Cost
function
Co-ordination equation
 The system load changes in cyclic manner.
 It is not advisable to keep all the units available all the time.
 When system load decreases, it is better to shut down one or
more units.
 When the system load increases at a latter time, units are to
be brought in.
◦ Unit commitment problem is finding the shut down and commissioning
rule so that the total cost of generation over a period of time, say one
day, is minimum.
 The following are data pertaining to three units in a plant.
Unit 1: Min. = 150 MW; Max. = 600 MW
C1 = 5610 + 79.2 P1 + 0.01562 P1 2 Rs / h
Unit 2: Min. = 100 MW; Max. = 400 MW
C 2 = 3100 + 78.5 P 2 + 0.0194 P 2 2 Rs / h
Unit 3: Min. = 50 MW; Max. = 200 MW
C 3 = 936 + 95.64 P 3 + 0.05784 P 3 2 Rs / h
What unit or combination of units should be used to supply a load of 550 MW most
economically?
To solve this problem, simply try all combination of three units. Some combinations
will be infeasible if the sum of all maximum MW for the units committed is less than
the load or if the sum of all minimum MW for the units committed is greater than the
load. For each feasible combination, units will be dispatched using equal incremental
cost rule studied earlier. The results are presented in the Table below.
1. Spinning Reserve
Total amount of generation available from all synchronized
units on the system – (present load +losses).
Spinning reserve must be carried out such that loss of one or
more units does not cause too far a drop in system frequency.
Should obey certain rules set by reliability council,that specify
how the reserve is to be allocated.
Typical rule
1.Spinning reserves are kept in power system to meet the
unexpected load demand or failure of any generator etc.
2.Spinning reserve are usually allocated as a percentage of given
forecasted peak demand or
3.Reserve should be capable of making up of losses of heavily loaded
line
4.Reserve should be function of Probability of not having sufficient
generation to meet load
5.Reserve must be allocated wisely between fast responding unit and
slow responding unit which allows c the agc to restore the frequency
and interchange quickly in the event of generating unit outage
Beyond spinning reserves,other classes of reserve involve
Scheduled Reserve or off line reserve
This includes quick start diesel or gas turbine units or most
hydro units or pumped storage hydro units-can be brought online
,synchronised and brought to full capacity
These reserves must be spread around the power system
 to avoid transmission system limitations
To run various parts of the system as island if they need to be
electrically disconnected
1.Minimum up time: When a thermal unit is brought in, it cannot be turned off
immediately. Once it is committed, it has to be in the system for a specified
minimum up time.
2.Minimum down time: When a thermal unit is decommitted, it cannot be
turned on immediately. It has to remain decommitted for a specified
minimum down time.
3.Crew constraint: A plant always has two or more generating units. It may
not be possible to turn on more than one generating unit at the same time
due to non-availability of operating personnel.
4.Transition cost: Whenever the status of one unit is changed some transition
cost is involved and this has to be taken into account.
Hydro constraints:
Most of the systems have hydroelectric units also. The operation of
hydro units, depend on the availability of water. Moreover, hydro-
projects are multipurpose projects. Irrigation requirements also determine
the operation of hydro plants.
Must run unit:
Sometimes it is a must to run one or two units from the consideration of
voltage support and system stability.
Fuel supply constraint:
Availability of fuel is limited in some situations we need to account such
cases also.
Nuclear constraint:
If a nuclear plant is part of the system, another constraint is added. A
nuclear plant has to be operated as a base load plant only.
 A base load power plant is a power station that usually
provides a continuous supply of electricity throughout the
year with some minimum power generation requirement.

More Related Content

What's hot

Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
Deepak John
 
Objectives of shunt compensation
Objectives of shunt compensationObjectives of shunt compensation
Objectives of shunt compensation
Ayyarao T S L V
 

What's hot (20)

Fixed and variable speed turbine
Fixed and variable speed turbineFixed and variable speed turbine
Fixed and variable speed turbine
 
Base Load Plants and Peak Load Plant
Base Load Plants and Peak Load PlantBase Load Plants and Peak Load Plant
Base Load Plants and Peak Load Plant
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
 
Economic dispatch
Economic dispatch  Economic dispatch
Economic dispatch
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
Swing equation
Swing equationSwing equation
Swing equation
 
FACTS DEVICES
FACTS DEVICESFACTS DEVICES
FACTS DEVICES
 
Phasor Measurement Unit (PMU)
 Phasor Measurement Unit (PMU) Phasor Measurement Unit (PMU)
Phasor Measurement Unit (PMU)
 
Reactive power compensation
Reactive power compensationReactive power compensation
Reactive power compensation
 
Load Forecasting
Load ForecastingLoad Forecasting
Load Forecasting
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factor
 
WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)
 
Objectives of shunt compensation
Objectives of shunt compensationObjectives of shunt compensation
Objectives of shunt compensation
 
Gauss seidel method
Gauss seidel methodGauss seidel method
Gauss seidel method
 
Fault analysis using z bus
Fault analysis using z busFault analysis using z bus
Fault analysis using z bus
 
Swing equation
Swing equationSwing equation
Swing equation
 
Power System Stabilizer
Power System StabilizerPower System Stabilizer
Power System Stabilizer
 
PPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITYPPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITY
 
Distributed generation b 3
Distributed generation b 3Distributed generation b 3
Distributed generation b 3
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNING
 

Similar to Economic load dispatch(with and without losses)

Similar to Economic load dispatch(with and without losses) (20)

Unit commitment
Unit commitmentUnit commitment
Unit commitment
 
EE 306 POWER SYSTEM ANALYSIS KTU NOTES
EE 306 POWER SYSTEM ANALYSIS KTU NOTESEE 306 POWER SYSTEM ANALYSIS KTU NOTES
EE 306 POWER SYSTEM ANALYSIS KTU NOTES
 
Contigency analysis and security system taking different cases
Contigency analysis  and security system taking different casesContigency analysis  and security system taking different cases
Contigency analysis and security system taking different cases
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
An Automatic Load Controller for Domestic Applications
An Automatic Load Controller for Domestic ApplicationsAn Automatic Load Controller for Domestic Applications
An Automatic Load Controller for Domestic Applications
 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
Class 16 load shedding
 
Solar power plant at peak load by smart dsiatribution system
Solar power plant at peak load by smart dsiatribution systemSolar power plant at peak load by smart dsiatribution system
Solar power plant at peak load by smart dsiatribution system
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
 
Improving the Reliability of the Distribution Grid Using a Distributed Restor...
Improving the Reliability of the Distribution Grid Using a Distributed Restor...Improving the Reliability of the Distribution Grid Using a Distributed Restor...
Improving the Reliability of the Distribution Grid Using a Distributed Restor...
 
Power system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter fivePower system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter five
 
DG synchronizing Panel Manufacturer and Suppliers in India
DG synchronizing Panel Manufacturer and Suppliers in IndiaDG synchronizing Panel Manufacturer and Suppliers in India
DG synchronizing Panel Manufacturer and Suppliers in India
 
Designing Solar PV Systems (Rooftops)
Designing Solar PV Systems(Rooftops)Designing Solar PV Systems(Rooftops)
Designing Solar PV Systems (Rooftops)
 
Design solar pv system
Design solar pv systemDesign solar pv system
Design solar pv system
 
Physical structure and characteristics of energy storage systems
Physical structure and characteristics of energy storage systemsPhysical structure and characteristics of energy storage systems
Physical structure and characteristics of energy storage systems
 
How.to.design.a.solar.photo.voltaic.power.system.for.home.business
How.to.design.a.solar.photo.voltaic.power.system.for.home.businessHow.to.design.a.solar.photo.voltaic.power.system.for.home.business
How.to.design.a.solar.photo.voltaic.power.system.for.home.business
 
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
 

More from Asha Anu Kurian

More from Asha Anu Kurian (10)

Automatic generation control&voltage control(module 5:ktu syllabus)
Automatic generation control&voltage control(module 5:ktu syllabus)Automatic generation control&voltage control(module 5:ktu syllabus)
Automatic generation control&voltage control(module 5:ktu syllabus)
 
Newtonraphson algorithm derivation
Newtonraphson algorithm derivationNewtonraphson algorithm derivation
Newtonraphson algorithm derivation
 
Load flow studies 19
Load flow studies 19Load flow studies 19
Load flow studies 19
 
Symmetrical fault analysis problem
Symmetrical fault analysis problemSymmetrical fault analysis problem
Symmetrical fault analysis problem
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
 
Corona
CoronaCorona
Corona
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 
Hv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationHv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generation
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
high voltage engineering module1(EE369)-KTU
high voltage engineering module1(EE369)-KTUhigh voltage engineering module1(EE369)-KTU
high voltage engineering module1(EE369)-KTU
 

Recently uploaded

scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
meharikiros2
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 

Recently uploaded (20)

School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 

Economic load dispatch(with and without losses)

  • 1. With and without losses Unit Commitment By Asha Anu Kurian Department of EEE Saintgits College of Engineering
  • 2.  Introduction  Different constraints  ELD neglecting losses  With losses  Methods of calculating penalty factor and loss coefficient
  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 24.
  • 26.
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.  The system load changes in cyclic manner.  It is not advisable to keep all the units available all the time.  When system load decreases, it is better to shut down one or more units.  When the system load increases at a latter time, units are to be brought in. ◦ Unit commitment problem is finding the shut down and commissioning rule so that the total cost of generation over a period of time, say one day, is minimum.
  • 33.  The following are data pertaining to three units in a plant. Unit 1: Min. = 150 MW; Max. = 600 MW C1 = 5610 + 79.2 P1 + 0.01562 P1 2 Rs / h Unit 2: Min. = 100 MW; Max. = 400 MW C 2 = 3100 + 78.5 P 2 + 0.0194 P 2 2 Rs / h Unit 3: Min. = 50 MW; Max. = 200 MW C 3 = 936 + 95.64 P 3 + 0.05784 P 3 2 Rs / h What unit or combination of units should be used to supply a load of 550 MW most economically? To solve this problem, simply try all combination of three units. Some combinations will be infeasible if the sum of all maximum MW for the units committed is less than the load or if the sum of all minimum MW for the units committed is greater than the load. For each feasible combination, units will be dispatched using equal incremental cost rule studied earlier. The results are presented in the Table below.
  • 34.
  • 35.
  • 36.
  • 37. 1. Spinning Reserve Total amount of generation available from all synchronized units on the system – (present load +losses). Spinning reserve must be carried out such that loss of one or more units does not cause too far a drop in system frequency. Should obey certain rules set by reliability council,that specify how the reserve is to be allocated. Typical rule 1.Spinning reserves are kept in power system to meet the unexpected load demand or failure of any generator etc. 2.Spinning reserve are usually allocated as a percentage of given forecasted peak demand or
  • 38. 3.Reserve should be capable of making up of losses of heavily loaded line 4.Reserve should be function of Probability of not having sufficient generation to meet load 5.Reserve must be allocated wisely between fast responding unit and slow responding unit which allows c the agc to restore the frequency and interchange quickly in the event of generating unit outage Beyond spinning reserves,other classes of reserve involve Scheduled Reserve or off line reserve This includes quick start diesel or gas turbine units or most hydro units or pumped storage hydro units-can be brought online ,synchronised and brought to full capacity These reserves must be spread around the power system  to avoid transmission system limitations To run various parts of the system as island if they need to be electrically disconnected
  • 39. 1.Minimum up time: When a thermal unit is brought in, it cannot be turned off immediately. Once it is committed, it has to be in the system for a specified minimum up time. 2.Minimum down time: When a thermal unit is decommitted, it cannot be turned on immediately. It has to remain decommitted for a specified minimum down time. 3.Crew constraint: A plant always has two or more generating units. It may not be possible to turn on more than one generating unit at the same time due to non-availability of operating personnel. 4.Transition cost: Whenever the status of one unit is changed some transition cost is involved and this has to be taken into account.
  • 40. Hydro constraints: Most of the systems have hydroelectric units also. The operation of hydro units, depend on the availability of water. Moreover, hydro- projects are multipurpose projects. Irrigation requirements also determine the operation of hydro plants. Must run unit: Sometimes it is a must to run one or two units from the consideration of voltage support and system stability. Fuel supply constraint: Availability of fuel is limited in some situations we need to account such cases also. Nuclear constraint: If a nuclear plant is part of the system, another constraint is added. A nuclear plant has to be operated as a base load plant only.
  • 41.  A base load power plant is a power station that usually provides a continuous supply of electricity throughout the year with some minimum power generation requirement.