SlideShare a Scribd company logo
1 of 2
Download to read offline
ELECTRICAL MATERIAL SCIENCE
FARIS K.K [ AP. EEE ] Al-Ameen Engg College , Shoranur
1
Ee 306 power system analysis Chapter – 5 part 2
SYLLABUS
Unit commitment – introduction- constraints on unit commitment-spinning reserve- thermal unit
constraints – hydro constraints
5.1 UNIT COMMITMENT
Unit commitment is the process of deciding when and which generating units at each
power station to start-up and shut-down to meet the load demand.
Defenition: - Determination of Generation mix to achieve estimated output level to meet the
demand of electricity for a specified time interval while satisfying all constraints.
5.2 CONSTRAINTS IN UNIT COMMITMENT:
Unit commitment problem can have many constraints depending on different rules
imposed on scheduling by individual power system, power pool, reliability council etc. They are
 Spinning reserve
 Thermal units Constraints
 Hydro Constraints
 Must Run Constraints
 Fuel Constraints
5.3 SPINNING RESERVE
 Spinning reserve is the total amount of generation available from all units
synchronized (i.e., spinning) on the system, minus the present load and losses.
 When a generator is lost, there must be ample reserve on other units to compensate
up for the loss in a specified time period.
 It is must be allocated among fast responding units and slow responding units based
on far drop in system frequency.
 This allows the automatic generation control system to restore the specified
frequency.
5.4THERMAL UNITS CONSTRAINTS
Thermal units require a team of personnel to operate them, especially when turned on and
turned off. Since temperature changes can only be gradual some hours are required to bring the
unit on-line. Due to these restrictions in the operation of a thermal plant, various constraints arise,
such as
ELECTRICAL MATERIAL SCIENCE
FARIS K.K [ AP. EEE ] Al-Ameen Engg College , Shoranur
2
 Minimum up time: once the unit is running, it should not be turned off immediately
 Minimum down time: once the unit is turned off , there is a minimum time before it can be
turned on.
 Crew constraints: In a plant with more than one unit there may not be enough personnel to
attend both the units if both are turned on or off at the same time and hence at the same time
both cannot be turned on or off.
5.5 HYDRO CONSTRAINTS
Most of the power systems are hydro electric units. It depends on the availability of water.
5.6 MUST RUN CONSTRAINTS
Some units must run during certain times of the year for voltage support on the
transmission network or for supply of steam for uses outside the steam plant itself.
5.7 FUEL CONSTRAINTS
Some units may have limited fuel, or else have constraints that require them to burn a
specified amount of fuel in a given time.
5.8 COMPARISON BETWEEN UNIT COMMITMENT & ECONOMIC DISPATCH
UNIT COMMITMENT ECONOMIC DISPATCH
It is the process of when and which
generating units at each power station to
start up& shutdown
It is the process of distributing load among
various generating units based on cost
UC focus on power system reliability ED focus on computational approach
In UC, units are committed based on their
efficiency
In ED, all units are committed for optimal
result

More Related Content

What's hot

Lecture 9 load equalization
Lecture 9 load equalizationLecture 9 load equalization
Lecture 9 load equalizationSwapnil Gadgune
 
vacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission systemvacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission systemKMEA ENGINEERING COLLEGE
 
Powerpoint Presentation on Series Reactors
Powerpoint Presentation on Series ReactorsPowerpoint Presentation on Series Reactors
Powerpoint Presentation on Series ReactorsSuresh Mohta
 
Lecture 1 to 4 introduction to electrical drive
Lecture 1 to 4 introduction to electrical driveLecture 1 to 4 introduction to electrical drive
Lecture 1 to 4 introduction to electrical driveSwapnil Gadgune
 
transformer substation
transformer substation transformer substation
transformer substation saleh1412
 
DG synchronizing Panel Manufacturer and Suppliers in India
DG synchronizing Panel Manufacturer and Suppliers in IndiaDG synchronizing Panel Manufacturer and Suppliers in India
DG synchronizing Panel Manufacturer and Suppliers in IndiaMohit Bathineni
 
Automatic star delta starter using relays and adjustable 14000
Automatic star delta starter using relays and adjustable  14000Automatic star delta starter using relays and adjustable  14000
Automatic star delta starter using relays and adjustable 14000Vivek Bhakta
 
E044039044
E044039044E044039044
E044039044inventy
 
Power system stability
Power system  stabilityPower system  stability
Power system stabilityDeepak John
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design) SayanSarkar55
 
تصنيف الاستقرارية
تصنيف الاستقراريةتصنيف الاستقرارية
تصنيف الاستقراريةmohammedhammed
 
Power System Stability & Control
Power System Stability & ControlPower System Stability & Control
Power System Stability & ControlAzimah Aziz
 
Introduction to Electrical Drive
Introduction to Electrical DriveIntroduction to Electrical Drive
Introduction to Electrical DriveSwapnil Gadgune
 
Facilities Planning at KE
Facilities Planning at KEFacilities Planning at KE
Facilities Planning at KEHabib Ali Khan
 
203definitionclassificationofpowersystemstability
203definitionclassificationofpowersystemstability 203definitionclassificationofpowersystemstability
203definitionclassificationofpowersystemstability Venkata Tadi
 
Unit i-ac drives
Unit i-ac drivesUnit i-ac drives
Unit i-ac driveskasirajan18
 

What's hot (20)

2015 ZHV MSS Sales Sheet
2015 ZHV MSS Sales Sheet2015 ZHV MSS Sales Sheet
2015 ZHV MSS Sales Sheet
 
CURRENT LIMITING REACTORS
CURRENT  LIMITING  REACTORSCURRENT  LIMITING  REACTORS
CURRENT LIMITING REACTORS
 
Lecture 9 load equalization
Lecture 9 load equalizationLecture 9 load equalization
Lecture 9 load equalization
 
vacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission systemvacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission system
 
Powerpoint Presentation on Series Reactors
Powerpoint Presentation on Series ReactorsPowerpoint Presentation on Series Reactors
Powerpoint Presentation on Series Reactors
 
Lecture 1 to 4 introduction to electrical drive
Lecture 1 to 4 introduction to electrical driveLecture 1 to 4 introduction to electrical drive
Lecture 1 to 4 introduction to electrical drive
 
transformer substation
transformer substation transformer substation
transformer substation
 
DG synchronizing Panel Manufacturer and Suppliers in India
DG synchronizing Panel Manufacturer and Suppliers in IndiaDG synchronizing Panel Manufacturer and Suppliers in India
DG synchronizing Panel Manufacturer and Suppliers in India
 
Automatic star delta starter using relays and adjustable 14000
Automatic star delta starter using relays and adjustable  14000Automatic star delta starter using relays and adjustable  14000
Automatic star delta starter using relays and adjustable 14000
 
E044039044
E044039044E044039044
E044039044
 
Power system stability
Power system  stabilityPower system  stability
Power system stability
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
تصنيف الاستقرارية
تصنيف الاستقراريةتصنيف الاستقرارية
تصنيف الاستقرارية
 
Power System Stability & Control
Power System Stability & ControlPower System Stability & Control
Power System Stability & Control
 
Rps plant
Rps plantRps plant
Rps plant
 
Introduction to Electrical Drive
Introduction to Electrical DriveIntroduction to Electrical Drive
Introduction to Electrical Drive
 
Facilities Planning at KE
Facilities Planning at KEFacilities Planning at KE
Facilities Planning at KE
 
203definitionclassificationofpowersystemstability
203definitionclassificationofpowersystemstability 203definitionclassificationofpowersystemstability
203definitionclassificationofpowersystemstability
 
Unit i-ac drives
Unit i-ac drivesUnit i-ac drives
Unit i-ac drives
 
Relays
  Relays  Relays
Relays
 

Similar to EE 306 POWER SYSTEM ANALYSIS KTU NOTES

Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Asha Anu Kurian
 
Experience feedback steam turbine
Experience feedback steam turbineExperience feedback steam turbine
Experience feedback steam turbineSouvik Dutta
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Living Online
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...theijes
 
Lecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-SubhiLecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-SubhiAniruddhaRay11
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protectionSaifUrrehman183
 
load_frequency_control_in_microgrid.pdf
load_frequency_control_in_microgrid.pdfload_frequency_control_in_microgrid.pdf
load_frequency_control_in_microgrid.pdfRaveendra Reddy
 
Electric Power Management for a Grid Connected Renewable Energy Sources
Electric Power Management for a Grid Connected Renewable Energy SourcesElectric Power Management for a Grid Connected Renewable Energy Sources
Electric Power Management for a Grid Connected Renewable Energy Sourcestheijes
 
stationary applications of fuel cells
stationary applications of fuel cellsstationary applications of fuel cells
stationary applications of fuel cellsRosh Mani
 
Redundant power supply architecture for self healing substation using ultraca...
Redundant power supply architecture for self healing substation using ultraca...Redundant power supply architecture for self healing substation using ultraca...
Redundant power supply architecture for self healing substation using ultraca...eSAT Publishing House
 
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid IJMER
 

Similar to EE 306 POWER SYSTEM ANALYSIS KTU NOTES (20)

Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
Physical structure and characteristics of energy storage systems
Physical structure and characteristics of energy storage systemsPhysical structure and characteristics of energy storage systems
Physical structure and characteristics of energy storage systems
 
Voltage stability enhancement for large scale squirrel cage induction generat...
Voltage stability enhancement for large scale squirrel cage induction generat...Voltage stability enhancement for large scale squirrel cage induction generat...
Voltage stability enhancement for large scale squirrel cage induction generat...
 
Experience feedback steam turbine
Experience feedback steam turbineExperience feedback steam turbine
Experience feedback steam turbine
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
 
N0447376
N0447376N0447376
N0447376
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
Class 16 load shedding
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
 
Lecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-SubhiLecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protection
 
load_frequency_control_in_microgrid.pdf
load_frequency_control_in_microgrid.pdfload_frequency_control_in_microgrid.pdf
load_frequency_control_in_microgrid.pdf
 
Electric Power Management for a Grid Connected Renewable Energy Sources
Electric Power Management for a Grid Connected Renewable Energy SourcesElectric Power Management for a Grid Connected Renewable Energy Sources
Electric Power Management for a Grid Connected Renewable Energy Sources
 
stationary applications of fuel cells
stationary applications of fuel cellsstationary applications of fuel cells
stationary applications of fuel cells
 
Economic load dispatch
Economic load dispatch Economic load dispatch
Economic load dispatch
 
Redundant power supply architecture for self healing substation using ultraca...
Redundant power supply architecture for self healing substation using ultraca...Redundant power supply architecture for self healing substation using ultraca...
Redundant power supply architecture for self healing substation using ultraca...
 
H011117484
H011117484H011117484
H011117484
 
9. PPT.pptx
9. PPT.pptx9. PPT.pptx
9. PPT.pptx
 
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid
 

Recently uploaded

22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 

Recently uploaded (20)

22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 

EE 306 POWER SYSTEM ANALYSIS KTU NOTES

  • 1. ELECTRICAL MATERIAL SCIENCE FARIS K.K [ AP. EEE ] Al-Ameen Engg College , Shoranur 1 Ee 306 power system analysis Chapter – 5 part 2 SYLLABUS Unit commitment – introduction- constraints on unit commitment-spinning reserve- thermal unit constraints – hydro constraints 5.1 UNIT COMMITMENT Unit commitment is the process of deciding when and which generating units at each power station to start-up and shut-down to meet the load demand. Defenition: - Determination of Generation mix to achieve estimated output level to meet the demand of electricity for a specified time interval while satisfying all constraints. 5.2 CONSTRAINTS IN UNIT COMMITMENT: Unit commitment problem can have many constraints depending on different rules imposed on scheduling by individual power system, power pool, reliability council etc. They are  Spinning reserve  Thermal units Constraints  Hydro Constraints  Must Run Constraints  Fuel Constraints 5.3 SPINNING RESERVE  Spinning reserve is the total amount of generation available from all units synchronized (i.e., spinning) on the system, minus the present load and losses.  When a generator is lost, there must be ample reserve on other units to compensate up for the loss in a specified time period.  It is must be allocated among fast responding units and slow responding units based on far drop in system frequency.  This allows the automatic generation control system to restore the specified frequency. 5.4THERMAL UNITS CONSTRAINTS Thermal units require a team of personnel to operate them, especially when turned on and turned off. Since temperature changes can only be gradual some hours are required to bring the unit on-line. Due to these restrictions in the operation of a thermal plant, various constraints arise, such as
  • 2. ELECTRICAL MATERIAL SCIENCE FARIS K.K [ AP. EEE ] Al-Ameen Engg College , Shoranur 2  Minimum up time: once the unit is running, it should not be turned off immediately  Minimum down time: once the unit is turned off , there is a minimum time before it can be turned on.  Crew constraints: In a plant with more than one unit there may not be enough personnel to attend both the units if both are turned on or off at the same time and hence at the same time both cannot be turned on or off. 5.5 HYDRO CONSTRAINTS Most of the power systems are hydro electric units. It depends on the availability of water. 5.6 MUST RUN CONSTRAINTS Some units must run during certain times of the year for voltage support on the transmission network or for supply of steam for uses outside the steam plant itself. 5.7 FUEL CONSTRAINTS Some units may have limited fuel, or else have constraints that require them to burn a specified amount of fuel in a given time. 5.8 COMPARISON BETWEEN UNIT COMMITMENT & ECONOMIC DISPATCH UNIT COMMITMENT ECONOMIC DISPATCH It is the process of when and which generating units at each power station to start up& shutdown It is the process of distributing load among various generating units based on cost UC focus on power system reliability ED focus on computational approach In UC, units are committed based on their efficiency In ED, all units are committed for optimal result