SlideShare a Scribd company logo
1 of 10
Download to read offline
PROBLEMS:
An anchored sheet pile wall of total height 15m is penetrated 4.5 m into a
sandy stratum. It retains a similar sandy soil on its back upto its top with a
horizontal ground surface. The tie bars are horizontal and are provided at a
depth of 2 m below the top. The free water level stands at a height of 8 m above
the dredge line on both sides of the wall. The bulk density of sand above the
free water level is 1.60 3
t/m and the submerged density below the water level is
1 3
t/m . The angle of internal friction of sand is 35˚. Determine the factor of
safety with respect to passive resistance of soil for the given depth of
penetration. What is the anchor pull per metre length of the wall?
1. A gravity wall with a 6 m high vertical back has to retain a cohesionless
backfill with horizontal ground surface. The bulk density of the backfill is
1.60 3
t/m and the angle of shearing resistance is 30˚. The wall is to be 1.4 m
wide at the top. Determine the minimum base width of the wall for no
tension to develop at the base. Also find the factor of safety against sliding
assuming the angle of friction between the base of the wall and the
foundation soil as 30˚. The active pressure may be calculated by the Rankine
theory. The density of the wall is 2 3
t/m .
2. For the cantilever sheet pile wall shown below, compute the depth of
embedment of sheet pile.
3m
3m
D
φ = 30˚
γ = 2t/m3
γ ′ = 1t/m3
φ = 30˚
Ra
y′
a
Z
3. In the problem given above, if the soil below the dredge line is cohesive, with
uc = 7.5 3
t/m , uφ = 0˚ and γ ′ = 1.0 3
t/m , compute the depth of embedment
of sheet pile.
4. A 10 m depth and 8 m wide vertical cut is to be made in the subsoil given in
the figure. Compute and comment on the following with respect to the design
of a stable bracing system. a) Factory of safety against bottom heave,
(assume cN =7);
b) Factor of safety against clay bursting;
c) Maximum ground movement and the extent of movement;
d) Axial loads for which the struts are to be designed by considering
apparent earth pressure distribution;
e) Maximum bending moment on the inbuilt wale;
f) Maximum bending moment on the diaphragm wall;
g) Number of pumps required for dewatering purpose during
construction.
Assume 6
soilk 10−
= = 10-6
cm/sec and capacity of each pump = 36
m10−
/se and
an unconfined aquifer condition.
3m
3m
D
φ = 30˚
γ = 2t/m3
γ ′ = 1t/m3 c = 7.5 t/m2
γ ′ = 1t/m3
φ = 30˚
a
e
b
d
2m
3m
3m
4m
Firm clay
c = 40kN/m2
Soft clay
c = 25kN/m2
γ = 18kN/m3
Stiff clay
c = 60kN/m2
Sand
N > 40
- 3m
- 13m
- 16m
h
2m
SOLUTIONS:
7.3/1,27.0
'sin1
'sin1
,35' ===
+
−
=°= apa
KKK
φ
φ
φ
The pressure distribution on the wall is shown in the following figure. The pressures
are calculated for 1m length of the wall:
p1 = 0.27x1.6x2.5 = 1.08 2
t/m .
p2 = 0.27x1.0x12.5 =3.375 2
t/m .
1P = 0.5x1.08x2.5 = 1.35 t acting at 12.5+2.5/3 = 13.33m from B.
2P = 1.08x12.5 = 13.5 t acting at 12.5/2 = 6.25m from B.
3P = 0.5x3.375x12.5 = 21.09 t acting at 12.5/3 = 4.17m from B.
The mobilised passive pressure pmP acts at a height of 1.5m from B. Taking
moments about E, the level of tie bars, we get pmP = 24.08 t.
Ultimate passive resistance Pp of soil is given by:
pP = ½ pK γ ′x 2
4.5 = 37.46 t.
Therefore Factor of safety F = pP / pmP = 1.56
Total active pressure aP = 35.94 t
Anchor pull TR = pP - pmP = 11.86 t per metre length of the wall.
2. When φ ′ = 30˚, aK = 1/3
Consider 1m length of the wall. Total active pressure
2
a a
1
P K H 9.6t
2
γ= =
E
P2
RT
P1
p1
P3
p2
Pp
2.5m
8m
4.5m
1.5m
2m
B
A
aP acts horizontally at a height of 2m from the heel.
For no tension to develop at the base, the resultant of aP and the weight of wall
intersects the base at a distance of 2b/3 from the heel. For taking moments the
section of the wall may be divided into a rectangle of height 6m and width 1.4m
(top width) and a triangle of height 6m and base width (b – 1.4) metres. The
moments of the forces are taken about the heel.
From the moment equation we get, b = 2.77m
Total weight W of the wall per metre length = 1.4 x 2.77 x 6 x 2 / 2 = 23.27 t
The factor of safety F against sliding is given as follows:
39.1
6.9
30tan27.23'tan
=
°
==
a
P
W
F
δ
3. Here, φ = 30˚
3/1
sin1
sin1
=
+
−
=
φ
φ
A
K and
3
sin1
sin1
=
−
+
=
φ
φ
P
K
Earth pressure at the dredge line,
AeP = (2 x 3 + 1x 3)1/3 = 3 2
t/m
The distance of point of zero pressure below dredge line is given by
( )
m
KK
P
a
AP
Ae
125.1
'
=
−
=
γ
Resultant of all the forces above point O,
aR = 12.19 t/m
Taking the moment of all the forces about point O
y ′ = 2.92m
Passive earth pressure at point O
poP = 30 2
t/m
If the depth of penetration of sheet pile below O is Y, pressure at the base of
the wall is given by :
pb2P = 1(3-1/3)Y = 2.67Y
pb1P = 30 + 2.67Y
Substituting the values aR = 12.19 2
t/m , y ′ = 2.92m, pb2P = 2.67Y and pb1P = 30 +
2.67Y in the following equations,
pb2 a
pb1 pb2
p Y-2R
Z=
p +p
6 aR (Y+y′) + Z2
( pb2P + pb1P ) – pb2P 2
Y = 0
we get,
4
Y + 13.48 3
Y + 89.71 2
Y – 467.69Y – 981.97 = 0
The solution of the equation by trial and error yields, Y = 4.24m
With Y = 4.24m,
pb2P = 11.32 2
t/m
pb1P = 41.32 2
t/m
Hence we get, Z = 0.45m
Check: Σ ΣFH = 0; aR + ( pb2P + ppb1)Z/2 - pb2P Y/2 = 0
or 12.19 + (11.32 + 41.32) x 0.45/2 – 11.32 x 4.24/2 ≈ 0.
Hence in order.
Depth of pile penetration, D = a + Y = 1.125 + 4.24 = 5.37m
Increase D by 30 percent and adopt depth of pile penetration as 5.37 x 1.30 =
6.98m.
4. Effective stress at the dredge line,
q′ = 2 x 3 + 1 x 3 = 9 2
t/m
The earth pressure diagram is shown in the figure.
The resultant of all the forces above the dredge line, Ra = 12.19 v acts at a height
y′ above the dredge line y′ = 1.86m
Substituting in the eqn. ( )
( )
0
'2
'12
2'42
=
+
+
−−−
qc
RycR
DRqcD
u
aua
au
2
D – 1.16D – 4.34 = 0
Hence we get, D = 2.74m
Check: ∑ = 0
Depth of embedment provided = 2.74 x 1.30 = 3.56m.
. From stability considerations :
a) Bottom heave:
H = 10m , γ = 18kN/ 3
m , c = 25kN/ 4
m , 1D = minimum of B/ 2 or D = 8 2
or 2 i.e. 1D = 2.
2t/m2
12.19t/m
2
y′=1.86m
3t/m2
Z
Therefore, Stability No. = γ H/c = 7.2 >6 . hence the diaphragm wall is required.





 +
++
=
∑
f
DH
D
cH
f
D
c
cN
FOS
γ
γ
1
= 2.81 > 2, hence it is safe against bottom heave.
b) Clay bursting :
h
B
cH
H
FOS
w
γ
γ 1
1
2+
= = 1.32 > 1.3, therefore, it is safe against clay bursting.
c)
From Peck’s chart we find that the present situation lies in the zone II.
Maximum ground movement:
Hence maximum ground movement δ = 2x10/100 = 0.2 m = 200 mm.
And the maximum extent of ground movement L = 3x10 = 30 m.
d)
From structural considerations:
Strut loads;
Soft clay






−=
H
c
mHpa
γ
γ
4
1 , N = γH/c = 7.2 > 4, ∴m = 1.
∴ ap = 80kN/ 2
m .
Hence for struts @ 3m c/c, the following are the strut loads:
1P = 540kN , 2P = 720kN, 3P = 600kN.
e)
mkNm
Pl
M /72
10
2
max
==
Maximum bending moment of the diaphragm wall:
f)
Span of the inbuilt wales l = 3m c/c.
Moment in inbuilt wale:
Ud1 w = 80kN/ 2
m .
mkNm
wl
M /90
8
2
max
==∴ .
g)
Discharge per well, Q;
Dewatering criteria:
2m
3m
3m
2m
P1
P2
P3
2.5m
7.5m
p
a
( )
( )rR
hHk
Q
/log3.2
22
−
=
π
where, k = 6
10−
cm/sec.
H = 16 – 3 = 13m.
h = 16 – 10 = 6m.
r = 4m.
R = 10r = 40m.
∴Q = 1.82 x 6
10− 3
m /sec.
Hence the number of pumps required = 1.82 x 6
10−
/ 6
10−
= 1.82 ≈2.

More Related Content

What's hot

Moment Distribution Method SA-2
Moment Distribution Method SA-2Moment Distribution Method SA-2
Moment Distribution Method SA-2Kaizer Dave
 
Resistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidosResistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidosAndre Luiz Vicente
 
Wind load calculation
Wind load calculationWind load calculation
Wind load calculationGodfrey James
 
Aços e ligas especiais (costa & mei)
Aços e ligas especiais (costa & mei)Aços e ligas especiais (costa & mei)
Aços e ligas especiais (costa & mei)Daniel Murasawa
 
Circuitos elétricos joseph a. edminister - coleção schaum
Circuitos elétricos   joseph a. edminister - coleção schaumCircuitos elétricos   joseph a. edminister - coleção schaum
Circuitos elétricos joseph a. edminister - coleção schaumReginaldo Dantas
 
Resistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidosResistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidosAndre Luiz Vicente
 
Calculation of dead load
Calculation of dead loadCalculation of dead load
Calculation of dead loadRidhdhi Gandhi
 
Problems on piles and deep footing
Problems on piles and deep footingProblems on piles and deep footing
Problems on piles and deep footingLatif Hyder Wadho
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram constructionPritesh Parmar
 
Resistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidosResistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidosAndre Luiz Vicente
 

What's hot (20)

Deep beams
Deep beams Deep beams
Deep beams
 
Box culvert
Box culvertBox culvert
Box culvert
 
Moment Distribution Method SA-2
Moment Distribution Method SA-2Moment Distribution Method SA-2
Moment Distribution Method SA-2
 
TDC scritto 22 ottobre 2016
TDC scritto 22 ottobre 2016TDC scritto 22 ottobre 2016
TDC scritto 22 ottobre 2016
 
Resistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidosResistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap13 - Exercícios resolvidos
 
Bending stress
Bending stressBending stress
Bending stress
 
Autocad Structural Detailing
Autocad Structural Detailing Autocad Structural Detailing
Autocad Structural Detailing
 
Wind load calculation
Wind load calculationWind load calculation
Wind load calculation
 
Aços e ligas especiais (costa & mei)
Aços e ligas especiais (costa & mei)Aços e ligas especiais (costa & mei)
Aços e ligas especiais (costa & mei)
 
Torsion
TorsionTorsion
Torsion
 
Structural engineering ii
Structural engineering iiStructural engineering ii
Structural engineering ii
 
Circuitos elétricos joseph a. edminister - coleção schaum
Circuitos elétricos   joseph a. edminister - coleção schaumCircuitos elétricos   joseph a. edminister - coleção schaum
Circuitos elétricos joseph a. edminister - coleção schaum
 
Resistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidosResistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap08 - Exercícios resolvidos
 
Deep beam
Deep beamDeep beam
Deep beam
 
Flanged beams design for t beam
Flanged beams   design for t beamFlanged beams   design for t beam
Flanged beams design for t beam
 
Calculation of dead load
Calculation of dead loadCalculation of dead load
Calculation of dead load
 
And 605 ultima varianta
And  605    ultima variantaAnd  605    ultima varianta
And 605 ultima varianta
 
Problems on piles and deep footing
Problems on piles and deep footingProblems on piles and deep footing
Problems on piles and deep footing
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram construction
 
Resistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidosResistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidos
Resistência dos Materiais - Hibbeler 5ª Ed.Cap04 - Exercícios resolvidos
 

Viewers also liked

Sheet pile ccsp
Sheet pile ccspSheet pile ccsp
Sheet pile ccspidesplan
 
Sheet Pile Retaining Wall
Sheet Pile Retaining WallSheet Pile Retaining Wall
Sheet Pile Retaining WallJim McMullan
 
Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)
Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)
Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)pmcgough
 
Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil Ahmed Ebid
 
Sheet pile (usefulsearch.org) (useful search)
Sheet pile (usefulsearch.org) (useful search)Sheet pile (usefulsearch.org) (useful search)
Sheet pile (usefulsearch.org) (useful search)Make Mannan
 
SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS
SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS
SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS IAEME Publication
 
Sheet pile and bulkhead (usefulsearch.org) (useful search)
Sheet pile and bulkhead (usefulsearch.org)  (useful search)Sheet pile and bulkhead (usefulsearch.org)  (useful search)
Sheet pile and bulkhead (usefulsearch.org) (useful search)Make Mannan
 
Top 8 structural engineer resume samples
Top 8 structural engineer resume samplesTop 8 structural engineer resume samples
Top 8 structural engineer resume samplesRyanGiggs012
 
Applications of rock classifications
Applications of rock classifications Applications of rock classifications
Applications of rock classifications Sourabh Jain
 
Re retaining walls1
Re retaining walls1Re retaining walls1
Re retaining walls1astraeaeos
 
Rock slope stability analysis lec 1
Rock slope stability analysis lec 1Rock slope stability analysis lec 1
Rock slope stability analysis lec 1aquarius123
 
Chapter 3 load and stress analysis final
Chapter 3  load and stress analysis finalChapter 3  load and stress analysis final
Chapter 3 load and stress analysis finalKhalil Alhatab
 
A Designer's Introduction to the Development, Design and Application of Vinyl...
A Designer's Introduction to the Development, Design and Application of Vinyl...A Designer's Introduction to the Development, Design and Application of Vinyl...
A Designer's Introduction to the Development, Design and Application of Vinyl...Docks & Marinas, Inc.
 
Independant study on Reinforced soil retaining wall
Independant study on Reinforced soil retaining wallIndependant study on Reinforced soil retaining wall
Independant study on Reinforced soil retaining wallparas6904
 
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015Hossameldin Ahmed
 
GEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITYGEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITYNgo Hung Long
 
Metoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet PileMetoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet PileIMRA MORALDY
 
Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Ulimella Siva Sankar
 

Viewers also liked (20)

Sheet pile ccsp
Sheet pile ccspSheet pile ccsp
Sheet pile ccsp
 
Sheet Pile Retaining Wall
Sheet Pile Retaining WallSheet Pile Retaining Wall
Sheet Pile Retaining Wall
 
Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)
Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)
Prediction Of Ground Settlement Response To Sheet Pile Extraction (P. Mc Gough)
 
Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil
 
Sheet pile (usefulsearch.org) (useful search)
Sheet pile (usefulsearch.org) (useful search)Sheet pile (usefulsearch.org) (useful search)
Sheet pile (usefulsearch.org) (useful search)
 
SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS
SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS
SOIL-SHEET PILE INTERACTION - PART I: A REVIEW OF THEORIES AND DESIGN METHODS
 
Types of Sheet Piles
Types of Sheet PilesTypes of Sheet Piles
Types of Sheet Piles
 
Sheet pile and bulkhead (usefulsearch.org) (useful search)
Sheet pile and bulkhead (usefulsearch.org)  (useful search)Sheet pile and bulkhead (usefulsearch.org)  (useful search)
Sheet pile and bulkhead (usefulsearch.org) (useful search)
 
Top 8 structural engineer resume samples
Top 8 structural engineer resume samplesTop 8 structural engineer resume samples
Top 8 structural engineer resume samples
 
Applications of rock classifications
Applications of rock classifications Applications of rock classifications
Applications of rock classifications
 
Re retaining walls1
Re retaining walls1Re retaining walls1
Re retaining walls1
 
Rock slope stability analysis lec 1
Rock slope stability analysis lec 1Rock slope stability analysis lec 1
Rock slope stability analysis lec 1
 
Chapter 3 load and stress analysis final
Chapter 3  load and stress analysis finalChapter 3  load and stress analysis final
Chapter 3 load and stress analysis final
 
A Designer's Introduction to the Development, Design and Application of Vinyl...
A Designer's Introduction to the Development, Design and Application of Vinyl...A Designer's Introduction to the Development, Design and Application of Vinyl...
A Designer's Introduction to the Development, Design and Application of Vinyl...
 
Independant study on Reinforced soil retaining wall
Independant study on Reinforced soil retaining wallIndependant study on Reinforced soil retaining wall
Independant study on Reinforced soil retaining wall
 
RQD
RQDRQD
RQD
 
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
 
GEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITYGEOTECHNICAL SLOPE STABILITY
GEOTECHNICAL SLOPE STABILITY
 
Metoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet PileMetoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet Pile
 
Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...
 

Similar to P&b m6

Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Latif Hyder Wadho
 
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...Dr.youssef hamida
 
Examples-Answers-all-Sections-2up
Examples-Answers-all-Sections-2upExamples-Answers-all-Sections-2up
Examples-Answers-all-Sections-2upsyed ahmed taran
 
Problems on bearing capacity of soil
Problems on bearing capacity of soilProblems on bearing capacity of soil
Problems on bearing capacity of soilLatif Hyder Wadho
 
Gte ii-readytoprint
Gte ii-readytoprintGte ii-readytoprint
Gte ii-readytoprintjagadish108
 
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...Make Mannan
 
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Make Mannan
 
Examen 2 fundaciones
Examen 2 fundacionesExamen 2 fundaciones
Examen 2 fundacionesAndres9586
 
Ejerciciosresueltosdinamicadefluidos2
Ejerciciosresueltosdinamicadefluidos2Ejerciciosresueltosdinamicadefluidos2
Ejerciciosresueltosdinamicadefluidos2Bruno Reyes A.
 
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...Make Mannan
 
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...Make Mannan
 
Analysis of composite beam and design of grannular piles foundation for kalya...
Analysis of composite beam and design of grannular piles foundation for kalya...Analysis of composite beam and design of grannular piles foundation for kalya...
Analysis of composite beam and design of grannular piles foundation for kalya...PrathyushaMalladi2
 
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...Make Mannan
 
Retaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wall
Retaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wallRetaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wall
Retaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wallDr.Youssef Hammida
 
Retaining wall(الجدران الاستنادية).- Scant Piles
Retaining wall(الجدران الاستنادية).- Scant PilesRetaining wall(الجدران الاستنادية).- Scant Piles
Retaining wall(الجدران الاستنادية).- Scant PilesDr.youssef hamida
 

Similar to P&b m6 (20)

Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)
 
Gte ii-ready
Gte ii-readyGte ii-ready
Gte ii-ready
 
Gte ii-ready
Gte ii-readyGte ii-ready
Gte ii-ready
 
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
 
Examples-Answers-all-Sections-2up
Examples-Answers-all-Sections-2upExamples-Answers-all-Sections-2up
Examples-Answers-all-Sections-2up
 
Problems on bearing capacity of soil
Problems on bearing capacity of soilProblems on bearing capacity of soil
Problems on bearing capacity of soil
 
Gte ii-readytoprint
Gte ii-readytoprintGte ii-readytoprint
Gte ii-readytoprint
 
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
 
3. Foundation. Examples.pdf
3. Foundation. Examples.pdf3. Foundation. Examples.pdf
3. Foundation. Examples.pdf
 
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
 
Examen 2 fundaciones
Examen 2 fundacionesExamen 2 fundaciones
Examen 2 fundaciones
 
Ejerciciosresueltosdinamicadefluidos2
Ejerciciosresueltosdinamicadefluidos2Ejerciciosresueltosdinamicadefluidos2
Ejerciciosresueltosdinamicadefluidos2
 
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
 
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...
 
Ho1
Ho1Ho1
Ho1
 
Analysis of composite beam and design of grannular piles foundation for kalya...
Analysis of composite beam and design of grannular piles foundation for kalya...Analysis of composite beam and design of grannular piles foundation for kalya...
Analysis of composite beam and design of grannular piles foundation for kalya...
 
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
Question and Answers on Terzaghi’s Bearing Capacity Theory (usefulsearch.org)...
 
Retaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wall
Retaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wallRetaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wall
Retaining walls (الجدران الاستنادية)-steel sheet piles - sheet piles wall
 
Retaining wall(الجدران الاستنادية).- Scant Piles
Retaining wall(الجدران الاستنادية).- Scant PilesRetaining wall(الجدران الاستنادية).- Scant Piles
Retaining wall(الجدران الاستنادية).- Scant Piles
 
setlement.pptx
setlement.pptxsetlement.pptx
setlement.pptx
 

Recently uploaded

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 

Recently uploaded (20)

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 

P&b m6

  • 1. PROBLEMS: An anchored sheet pile wall of total height 15m is penetrated 4.5 m into a sandy stratum. It retains a similar sandy soil on its back upto its top with a horizontal ground surface. The tie bars are horizontal and are provided at a depth of 2 m below the top. The free water level stands at a height of 8 m above the dredge line on both sides of the wall. The bulk density of sand above the free water level is 1.60 3 t/m and the submerged density below the water level is 1 3 t/m . The angle of internal friction of sand is 35˚. Determine the factor of safety with respect to passive resistance of soil for the given depth of penetration. What is the anchor pull per metre length of the wall? 1. A gravity wall with a 6 m high vertical back has to retain a cohesionless backfill with horizontal ground surface. The bulk density of the backfill is 1.60 3 t/m and the angle of shearing resistance is 30˚. The wall is to be 1.4 m wide at the top. Determine the minimum base width of the wall for no tension to develop at the base. Also find the factor of safety against sliding assuming the angle of friction between the base of the wall and the foundation soil as 30˚. The active pressure may be calculated by the Rankine theory. The density of the wall is 2 3 t/m . 2. For the cantilever sheet pile wall shown below, compute the depth of embedment of sheet pile. 3m 3m D φ = 30˚ γ = 2t/m3 γ ′ = 1t/m3 φ = 30˚ Ra y′ a Z
  • 2. 3. In the problem given above, if the soil below the dredge line is cohesive, with uc = 7.5 3 t/m , uφ = 0˚ and γ ′ = 1.0 3 t/m , compute the depth of embedment of sheet pile. 4. A 10 m depth and 8 m wide vertical cut is to be made in the subsoil given in the figure. Compute and comment on the following with respect to the design of a stable bracing system. a) Factory of safety against bottom heave, (assume cN =7); b) Factor of safety against clay bursting; c) Maximum ground movement and the extent of movement; d) Axial loads for which the struts are to be designed by considering apparent earth pressure distribution; e) Maximum bending moment on the inbuilt wale; f) Maximum bending moment on the diaphragm wall; g) Number of pumps required for dewatering purpose during construction. Assume 6 soilk 10− = = 10-6 cm/sec and capacity of each pump = 36 m10− /se and an unconfined aquifer condition. 3m 3m D φ = 30˚ γ = 2t/m3 γ ′ = 1t/m3 c = 7.5 t/m2 γ ′ = 1t/m3 φ = 30˚ a e b d
  • 3. 2m 3m 3m 4m Firm clay c = 40kN/m2 Soft clay c = 25kN/m2 γ = 18kN/m3 Stiff clay c = 60kN/m2 Sand N > 40 - 3m - 13m - 16m h 2m SOLUTIONS: 7.3/1,27.0 'sin1 'sin1 ,35' === + − =°= apa KKK φ φ φ The pressure distribution on the wall is shown in the following figure. The pressures are calculated for 1m length of the wall: p1 = 0.27x1.6x2.5 = 1.08 2 t/m . p2 = 0.27x1.0x12.5 =3.375 2 t/m .
  • 4. 1P = 0.5x1.08x2.5 = 1.35 t acting at 12.5+2.5/3 = 13.33m from B. 2P = 1.08x12.5 = 13.5 t acting at 12.5/2 = 6.25m from B. 3P = 0.5x3.375x12.5 = 21.09 t acting at 12.5/3 = 4.17m from B. The mobilised passive pressure pmP acts at a height of 1.5m from B. Taking moments about E, the level of tie bars, we get pmP = 24.08 t. Ultimate passive resistance Pp of soil is given by: pP = ½ pK γ ′x 2 4.5 = 37.46 t. Therefore Factor of safety F = pP / pmP = 1.56 Total active pressure aP = 35.94 t Anchor pull TR = pP - pmP = 11.86 t per metre length of the wall. 2. When φ ′ = 30˚, aK = 1/3 Consider 1m length of the wall. Total active pressure 2 a a 1 P K H 9.6t 2 γ= = E P2 RT P1 p1 P3 p2 Pp 2.5m 8m 4.5m 1.5m 2m B A
  • 5. aP acts horizontally at a height of 2m from the heel. For no tension to develop at the base, the resultant of aP and the weight of wall intersects the base at a distance of 2b/3 from the heel. For taking moments the section of the wall may be divided into a rectangle of height 6m and width 1.4m (top width) and a triangle of height 6m and base width (b – 1.4) metres. The moments of the forces are taken about the heel. From the moment equation we get, b = 2.77m Total weight W of the wall per metre length = 1.4 x 2.77 x 6 x 2 / 2 = 23.27 t The factor of safety F against sliding is given as follows: 39.1 6.9 30tan27.23'tan = ° == a P W F δ 3. Here, φ = 30˚ 3/1 sin1 sin1 = + − = φ φ A K and 3 sin1 sin1 = − + = φ φ P K Earth pressure at the dredge line, AeP = (2 x 3 + 1x 3)1/3 = 3 2 t/m The distance of point of zero pressure below dredge line is given by ( ) m KK P a AP Ae 125.1 ' = − = γ Resultant of all the forces above point O, aR = 12.19 t/m Taking the moment of all the forces about point O y ′ = 2.92m
  • 6. Passive earth pressure at point O poP = 30 2 t/m If the depth of penetration of sheet pile below O is Y, pressure at the base of the wall is given by : pb2P = 1(3-1/3)Y = 2.67Y pb1P = 30 + 2.67Y Substituting the values aR = 12.19 2 t/m , y ′ = 2.92m, pb2P = 2.67Y and pb1P = 30 + 2.67Y in the following equations, pb2 a pb1 pb2 p Y-2R Z= p +p 6 aR (Y+y′) + Z2 ( pb2P + pb1P ) – pb2P 2 Y = 0 we get, 4 Y + 13.48 3 Y + 89.71 2 Y – 467.69Y – 981.97 = 0 The solution of the equation by trial and error yields, Y = 4.24m With Y = 4.24m, pb2P = 11.32 2 t/m pb1P = 41.32 2 t/m Hence we get, Z = 0.45m Check: Σ ΣFH = 0; aR + ( pb2P + ppb1)Z/2 - pb2P Y/2 = 0 or 12.19 + (11.32 + 41.32) x 0.45/2 – 11.32 x 4.24/2 ≈ 0. Hence in order. Depth of pile penetration, D = a + Y = 1.125 + 4.24 = 5.37m Increase D by 30 percent and adopt depth of pile penetration as 5.37 x 1.30 = 6.98m.
  • 7. 4. Effective stress at the dredge line, q′ = 2 x 3 + 1 x 3 = 9 2 t/m The earth pressure diagram is shown in the figure. The resultant of all the forces above the dredge line, Ra = 12.19 v acts at a height y′ above the dredge line y′ = 1.86m Substituting in the eqn. ( ) ( ) 0 '2 '12 2'42 = + + −−− qc RycR DRqcD u aua au 2 D – 1.16D – 4.34 = 0 Hence we get, D = 2.74m Check: ∑ = 0 Depth of embedment provided = 2.74 x 1.30 = 3.56m. . From stability considerations : a) Bottom heave: H = 10m , γ = 18kN/ 3 m , c = 25kN/ 4 m , 1D = minimum of B/ 2 or D = 8 2 or 2 i.e. 1D = 2. 2t/m2 12.19t/m 2 y′=1.86m 3t/m2 Z
  • 8. Therefore, Stability No. = γ H/c = 7.2 >6 . hence the diaphragm wall is required.       + ++ = ∑ f DH D cH f D c cN FOS γ γ 1 = 2.81 > 2, hence it is safe against bottom heave. b) Clay bursting : h B cH H FOS w γ γ 1 1 2+ = = 1.32 > 1.3, therefore, it is safe against clay bursting. c) From Peck’s chart we find that the present situation lies in the zone II. Maximum ground movement: Hence maximum ground movement δ = 2x10/100 = 0.2 m = 200 mm. And the maximum extent of ground movement L = 3x10 = 30 m. d) From structural considerations: Strut loads;
  • 9. Soft clay       −= H c mHpa γ γ 4 1 , N = γH/c = 7.2 > 4, ∴m = 1. ∴ ap = 80kN/ 2 m . Hence for struts @ 3m c/c, the following are the strut loads: 1P = 540kN , 2P = 720kN, 3P = 600kN. e) mkNm Pl M /72 10 2 max == Maximum bending moment of the diaphragm wall: f) Span of the inbuilt wales l = 3m c/c. Moment in inbuilt wale: Ud1 w = 80kN/ 2 m . mkNm wl M /90 8 2 max ==∴ . g) Discharge per well, Q; Dewatering criteria: 2m 3m 3m 2m P1 P2 P3 2.5m 7.5m p a
  • 10. ( ) ( )rR hHk Q /log3.2 22 − = π where, k = 6 10− cm/sec. H = 16 – 3 = 13m. h = 16 – 10 = 6m. r = 4m. R = 10r = 40m. ∴Q = 1.82 x 6 10− 3 m /sec. Hence the number of pumps required = 1.82 x 6 10− / 6 10− = 1.82 ≈2.