SlideShare a Scribd company logo
1 of 8
Download to read offline
1. What were the three key elements that were part of Buck Knives' five-year plan to reduce
costs? Which one did they implement immediately? 2. There were some key executive-level
managers who became huge advocates of the lean process. The article said that these managers
acted as "a catalyst to speed the permeation of lean throughout the culture." These managers
worked in which function/department? 3. Our book introduces the concept of the value chain,
which is similar to what Buck Knives calls "value streams." What was the biggest hurdle that
Buck faced when converting to value streams? How many years had they been doing things the
old way? 4. Buck tried to implement 2 major changes at the same time and learned a valuable
lesson of what NOT to do that they repeatedly cite. What was it? 5. Look at the "Box Score"
chart at the bottom of p. 2 which summarizes the benefits that Buck Knives achieved through
implementing lean principles. Which do you feel is the most important? Why? ( 12 paragraph
answer please)
By Tonya Vinas Although lean principles and practices have broad application in manufacturing.
the ease of that application can vary based on what is being produced, to whom it is being sold,
competitive pressures, location, corporate structure, workforce charcieristics, availability of raw
materials, contractual obligations, and other attributes that make each lean joumey different.
Buck Knives, a Post Falls, Idaho-based manufacturer of knives for outdoor recreation and
personal use, had more reasons than most to eschew lean: - Its three biggest customers are large
chain retailers and catalogs, who can be highly demanding of suppliers and are notoriously
inconsistent with replenishment and sales-forecast accuracy. - Making high-quality knives
involves craftsmanship skills, which don't translate easily into standard work. - Raw materials
include both metals - which have long procurement cycles and volatile prices - and specialty
materials such as giraffe bone and mother of pearl - which are rare, strictly regulated, and have
complicated procurement requirements. - Forty to forty-five percent of sales come in the last
three months of the year, making for highly unleveled demand. - As it started implementing lean,
the company also had to relocate its company headquarters and manufacturing facility from San
Diego to Post Falls and implement a new enterprise resource planning (ERP) system. Despite
these challenges, Buck Knives has so fervently cmbraced lean that it now does nearly everything
differently - from allocations of costs for shop-floor supplies to working with its key retail
customer to level load fulfillment. Buck's efforts began with the creation of a single assembly
cell while it was still a largebatch producer and occupied a plant that was 45% larger than its
current plant. Since then, lean ideology has changed leadership's thinking so much that they have
thrown out their old performance metrics and are in the process of creating new ones that reflect
the goals of lean.
Becoming Lean to Survive Several factors led Buck leadership to determine in 2001 that the
company had to drastically change if it wanted to keep manufacturing in the United States. The
cost of doing business had risen dramatically in California, Buck's home since the 1940 s.
Additionally, a sudden and unexpected sales drop of a key product and the recession that
followed the 911 terrorist attacks led to three unprofitable years. Simultaneously, competitors in
China were becoming better at manufacturing quality knives, and Buck managers calculated a
30% cost differential between their company and its overseas competitors. "The business reason
for launching lean was survival," said CEO C.J. Beck, a descendent of company founders.
"Tweaking was not going to keep up with the bleeding." The company created a five-year plan to
reduce costs by at least 30% that included three key elements: moving to a state with lower
energy, labor, and regulatory costs; buying a new ERP system; and creating a lean-oriented
culture. The first two goals had long-term timeframes, but the company started on lean right
away. They employed consultants, sent a group of 25 employees for off-site lean training, and
began targeting production for improvememt. At the time Buck operated with a mass-production
model with disconnected functional areas. Finished-goods and WIP were everywhere. "At any
time, one of the production areas easily had two-to-three months of inventory," said William
Keys, director of lean manufacturine. "Five batches here, 10 batches there. And a batch ranged
anywhere from 25 to 50 knives. We literally had thousands of knives in WIP inventory." Their
finst step was to convert from mass production to assembly cells. Keys said the first cell was
created during the initial lean training and was suceessful. Leaders started with one group, and
then that group trained another group and helped them to convert into a cell. This continued over
several months until most of the production floor had been converted. By this time, the company
began focusing more on its out-of-state move and devoted less time to expanding lean principles
to other areas of the company. The cells continued to function successfully, and the company
would occasionally hold teaching events. Although managers had much to do related to the
relocation, lean thinking continued to influence their decisions. Lean Enterprise institule
"One of the things we realized when we were creating the assembly cells was that we had
consolidated into an area that was about half the size, and we had reduced WIP by 60%."
Consequently, they decided that their next facility could be onethird smaller and should be
designed to support flow. Also, once the company did relocate in 2005, it needed to hire about
200 new employees, all of whom it trained in lean concepts right away. It was in September of
2005 that Buck CFO Phyllis Best took a group of Buck managers to a conference on lean
accounting. Speakers included Brian Maskell, Orry Fiume, Jean Cunningham, and other people
who were using new accounting concepts that better reflect and better suppont lean management
than traditional accounting concepts. (Lean-accounting principles reward inventory reduction,
favor value-creation over piece-part pricing, and give an accurate portrayal of cash flow and
costs. Traditional accounting methods do not support these goals.) "It was kind of a hard thing to
aceept," Keys said. "It made sense, but some of the things were counter to what we had been
doing since the company was founded. But they came back very much convinced that we had to
move in this direction." The injection of these new accounting principles into Buck's continuous
improvement efforts - just when the company was reactivating its lean focus, launching
production at a new site, and hiring new employees - acted as a catalyst to speed the permeation
of lean throughout the culture. This happened because managers in the function that most drives
strategic decision-making at the executive level - accounting and finance - became lean
evangelists, just like. the operations folks. Converting to Value Streams One of the first things
companies often do when adopting lean accounting is to reorganize into value streams, which
Buck did. Keys and others identified four value streams based on knife designs and added a fifth
value stream to represent sourced knives, which the company manufacturers via contractors in
China. They chose value-stream managers internally, picking the leaders based on experience.
As with many companies that reorganize into value streams, Buck's biggest hurdle came from
operators who wanted to cling to functional roles, particularly in the area of blade fabrication,
which includes a variety of skills with long histories of craftsmanship. "Reorganizing into value
streams is fairly easy," Keys said. "The challenge is how to move forward after that. For
instance, in Value Streams 1, 2, and 3, we began to include fabrication people. Their actual work
didn't change, but in Fabrication, people identified with Fabrication. They didn't identify with a
particular product. For instance, they would say, "We are hollow-grind operators." You have to
realize that with the value streams, in a course of a day we changed how things had been done
for 45 years."
Keys said management's strategy was to keep reinforcing what the goal was, how the company
was going to achieve the goal, and why it was important to achieve the goal. "We still haven't
gotten to where we want to be, but it's better than when we started, "Keys said. Some batching
still takes place in Fabrication, which has duties such as grinding and stamping knife blades,
some of which are specialty knives made for collectors. Those batch sizes, however, are about
half of their pre-value-stream sizes, and lead time in Fabrication has dropped from six to eight
weeks to two to three weeks. Fabrication remains a target improvement area for the value
streams, one of which has a goal of reducing fabrication time by 50% this year. Leading this
kaizen are Bruce Sundahl, lean/continuous improvement manager, Jim Hypes, value-stream
manager and Cindy Eby, a buyer for the value stream. Additionally. Hypes and Jeff Hubbard,
another value stream manager, are crosstraining their employees in Assembly and Fabrication,
seeding the effort with a group of production employees who became certified in lean through a
local manufacturing-assistance program last summer and went through cross-training as part of
the process. Addressing Cyclical Sales In addition to Fabrication, a small amount of batching
still takes place in the heattreating function and limited clam-shell packaging, but otherwise the
entire production floor is organized into cells that are part of value streams. Each stream operates
as a separate profit center and plans work according to a 30 -day forecast that is produced at
monthly mectings involving Sales, Accounting, and Operations. Prior to these cooperative
meetings, Sales and Operations never communicated, and this fed exeessive inventories of
mismatched parts, overstocked finished goods, and piles of WIP waiting for the next process.
"When we started having joint meetings, we began to communicate in a new way, " CFO Best
said. "And now, Sales is responsible for the sales forecast, and Operations is waiting to do their
planning based on that forecast." Materials flow based on multiple kanban systems. Cells track
perfommance on a white board, listing the production plan for each shift and metrics on how
each cell is performing compared with the plan. The individual value streams manage their own
costs. To deal with the cyclical nature of the retail market, Buck decided to reduce finished-
goods inventory to one month but increase flexibility with continuous improvement. It is also
beginning to ereate vendor-managed inventory programs with some of its larger clicnts.
Additionally, Buck began level-loading production for its largest client, Wal-Mart, which
historically has been good at forecasting 12-month sales totals, but not so good at month-to-
month forecasts. Buck takes Wal-Mart's 12 -month forecast and divides the totals into 10 equal
amounts to be Lean Enderprise Institute
produced each month between January and Oetober. Now, instead of scrambling when Wal-
Mart's monthly forecasts change, Buck relies on this inventory or its increased flexibility to
respond quickly if inventory can't cover the monthly order. "Sales has taken responsibility for the
forecasting, and we are holding the plants [the Post Falls plant and contract plants in China]
accountable for anything that they build over the planned, level load, so there's a little bit of
tension there," Best said. "Sales might foresee a spike later in the year, and maybe Operations is
just building to a kanban. So Sales might start to panic and say, "Maybe we should increase our
forecast a little bit because we don't see Operations responding." And manufacturing is standing
back saying, 'We've got plenty of time, we' ve got plenty of capacity. We don 't need to build that
yet. ' We still build things we don't need, but not nearly as much as we used to." As an example,
the company historically has held two "clearance sales" each year to sell excess finished goods.
In 2007, it didn't have to hold any. One way Buck increased flexibility was through a 5S effort
that ultimately led to dispersing the packaging function (except for a small amount of clam-shell
packaging) to individual cells within the value streams. The improvement began in 2007 when
Sundahl launched a 5S initiative for packaging, which took place in one area outside of the cells.
It was determined that more space was needed to address a bottleneck in packaging, and such an
investment would cost "well above six figures," according to Sundahl. Phil Duckett, executive
vice president of Operations, challenged Bruce Sundahl to come up with an altemative. His
response was to work collaboratively with the value-stream managers and shipping manger to
move packaging to the cells. By early fall, they had proved the concept in one cell and in one
value stream. Despite the looming busy season, Duckett gave Sundahl permission to continue
with the change. "Rather than putting their foot on the break, they put their foot on the gas pedal,
and I think that helped with how fast the change happened," Sundahl said. "Everyone knew that
the busy season was coming, and we got it all converted in four months." The packaging move
did more than allow Buck to avoid an expensive capital outlay, it also: - Allowed for the
reassignment of several employees to other areas because the cell-based tasks require fewer
people. - Removed a bottleneck in the supplier kanban system because the signals to suppliers
would get hung up - sometimes for days - while finished goods waited for packaging.
- Helped the company to accept and complete all of its orders in the final quarter of 2007.
Previously, the company would concentrate on filling high-volume orders and turn down smaller
onders during this busy time. Because of the level-loading plan with Wal-Mart and because
finished goods were packaged before orders came in, the company had enough capacity to
complete all orders. It did not have to decline any sales opportunitics. Uncovering True Costs
Buck has increased flexibility in other ways and has reaped multiple benefits. Some of these
opportunities, however, would have remained hidden had the company not converted to the lean-
accounting practices taught by Maskell, whom it hired for training and consulting. C.J. Buck
gives this example: The company uses a fine blank machine to cut blades from metal and was
faced with having to invest in new customized tooling for the machine to produce a new product.
Tooling would have cost as much as $80,000 and would have had a fourmonth turnaround.
Maskell asked if the company had idle capacity elsewhere that could handle the increased
demand. They did: a laser cutting machinc, but it cuts blades at the rate of 60 to 80 an hour while
the fine blank machine can produce 600 to 800 an hour. According to traditional-accounting
principles, the large-batch option would have been most profitable. But using lean-accounting
principles, which favor flexibility over large-batch production, the laser machine was the better
option, and that's what the team chose. "Looking at our capacity, we just don't have that many
products that need a rate of 800 an hour," Buck said. "We actually had excess capacity in the fine
blank machine. We needed help in the smaller runs. Standard costing says the obvious solution is
to buy the machine that can make the most product, but that's not what we needed." Best
attributes the increased use of the lasser-cutting machine and other changes with increasing
flexibility enough to give the company a unique advantage. For instance, the company offers
quick tumaround on customizcd consumer Webbased orders, something competitors can't do.
Additionally, the company expects to continue to save in tooling costs by using laser cutting.
"The laser is slower, but it allows you to have smaller batches and not invest in the tooling
costs," she said. "In the past the sales people would be optimistic about sales, which meant we
would invest a lot in tooling sometimes, and then sales wouldn't come through. Now we've
smartened up. Now we say, "If demand gets there, we can ahwys order the tooling. +. Lean
Enterphise institule
Using the more holistic lean-accounting approach also led to the company pulling some work
back from being outsourced to six Chinese contract manufacturers. Using theories and methods
learned from Maskell, Hubbard documented that handles that were being manufactured in China
at $6 a handle would cost $2 a handle to make at the Post Falls plant. The production was moved
in house, and now the company uses the variable-cost model to plan production for all new
products. (Such a model accounts for actual costs and value created, not just a per-unit price.)
Chris Potts, cost accounting manager at Buck, said the model evaluates three factors: 1) Capacity
and headcount, 2) Material costs, and 3) Additional incremental costs. "The whole premise here
is to look at cash flow and see what the real cost is, not the estimated cost based on a model that
you built back at the beginning of the year when you had certain assumptions," Potts said. "In the
past, we would have looked at a fully burdened cost regardless of whether we had excess
capacity." Recently, using this technique led to the decision to produce a SI million order in Post
Falls instead of China. The result was a much higher profit margin, Best said, because Buck used
assets it already had instead of writing a check to a contract manufacturer and paying related
import and transportation foes. New Model, New Metrics As Buck was adopting lean accounting
and ramping up lean projects at its new plant, it also invested in a new ERP system. This
provided an important lesson learned that Buck mangers repeatedly cite: Don't attempt to install
a new ERP system while starting massive lean conversions. Wait until you are farther along.
Buck Knives has had to invest countless hours converting the ERP system from its traditional-
accounting focus to value-stream/lean-accounting focus. The work continues. Potts is constantly
refining the reports he produces for value-stream managers that doctment costs and profits. He
does this in conjunction with lean process changes. For instance, the company is in the process of
creating supermarkets at each value stream that will hold production supplies, some of which are
used by everyone and currently are warehoused in a central location. The supermarkets will
allow for more accurate capturing of supply costs by value stream and reduce the need for
warchousing. Lean Enterprise Institute
"Each year as we go forward, we'll get closer and closer to having a true, actual cost for all of
these things," Ponts said. "This will be the first year we'll be able to take a look at this year's
actual versus last year's actual. So we'll be able to finetune our expectations." In addition to the
finance-oriented measures, Buck is recreating is performance metrics. This need has arisen from
both the cultural changes that have taken place and the obliteration of the old ERP system.
C.J.Buck said this is where most of his focus as a leader is these days - asking not just what are
the answers, but what should be the questions. When the new performance metries are rolled out,
they likely will be some of the most well-tuned lean performance measures created by a
manufacturer, In so many ways like this, Buck Knives is an idyllic lean operation - a company
that is building not just products based on lean principles. but a culture based on lean principles.
"This is a family business. It has a very specific culture," Buck said. "I like the way lean invites
you to share information because sharing information can help you. That strikes me as common
sense. It also reinforees that I don't want robots. Trained people are by far your best asset. And as
people learn more and become more flexible, it adds flexibility and robustness to your
operations." For More Information Buck Knives -- Leam more about the company and its history
here . Lean Enterprise Institute Senior Exccutive Series - Read an interview with Buck Knives
CEO C.J. Buck about lean management as a strategy and how his role as an executive changed.
See all the Senior Executive interviews in the Lean Thinkers' Comer. The Lean Enterprise
Institute (LEI) runs monthly regional workshops on basic and more advanced lean tools and lean
management. You can read complete descriptions of workshop content with the latest dates and
locations at IEI's raining page. LEI workbooks and training materials - all designed to de-mystify
What a sensei does - show you what steps to take on Monday morning to implement lean
concepts. Visit the LEI product catalog to see the resources available for supporting lean
transformations. Lean Accounting - Leam more about the movement to transition away from
traditional standard cost accounting, which often sends the wrong signals during a lean
conversion to a costing system based on product value streams. Glossary (Adapted from the
Leon lexicin)
Five S Five related terms, beginning with an S sound, describing workplace practices conducive
to visual control and lean production. The five terms in Japanese are: 1. Seiri: Separate needed
from unneeded items-tools, parts, materials, paperwork - and discard the unneeded. 2. Seiton:
Neatly arrange what is left-a place for everything and everything in its place. 3. Seiso: Clean and
wash. 4. Seiketsu: Cleanliness resulting from regular performance of the first three Ss. 5.
Shitsuke: Discipline, to perform the first four Ss. Level Loading (Heijunka) Leveling the type
and quantity of production over a fixed period of time. This enables production to efficiently
meet customer demands while avoiding batching and results in minimum inventories, capital
costs, manpower, and production lead time through the whole value stream. Supermarket The
location where a predetermined standard inventory is kept to supply downstream processes.
Supermarkets ordinarily are located near the supplying process to help that process see customer
usage and requirements. Each item in a supermarket has a specific location from which a
material handler withdraws products in the precise amounts needed by a downstream process. As
an item is removed, a signal to make more (such as a kanban card or an empty bin) is taken by
the material handler to the supplying process.

More Related Content

Similar to 1. What were the three key elements that were part of Buck Knives.pdf

Case on coca cola n dabur
Case on coca cola n daburCase on coca cola n dabur
Case on coca cola n daburSayyed Latif
 
The Value Stream Analysis ( Vsa ) Essay
The Value Stream Analysis ( Vsa ) EssayThe Value Stream Analysis ( Vsa ) Essay
The Value Stream Analysis ( Vsa ) EssayKelly Ratkovic
 
(ISM207) How the Principles of Lean Transform Innovation
(ISM207) How the Principles of Lean Transform Innovation(ISM207) How the Principles of Lean Transform Innovation
(ISM207) How the Principles of Lean Transform InnovationAmazon Web Services
 
The Last Word: The 50-Year Journey to Digital Business
The Last Word: The 50-Year Journey to Digital BusinessThe Last Word: The 50-Year Journey to Digital Business
The Last Word: The 50-Year Journey to Digital BusinessCognizant
 
Driving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six SigmaDriving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six SigmaLakesia Wright
 
Driving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six SigmaDriving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six SigmaLakesia Wright
 
Process change - change managment
Process change - change managmentProcess change - change managment
Process change - change managmentAdarsh Pawaiya
 
ODP-Vol44,No4-Alexander_Huggins
ODP-Vol44,No4-Alexander_HugginsODP-Vol44,No4-Alexander_Huggins
ODP-Vol44,No4-Alexander_HugginsJacqui Alexander
 
Four Organic Sales Growth Strategies
Four Organic Sales Growth StrategiesFour Organic Sales Growth Strategies
Four Organic Sales Growth StrategiesMike Nager
 
Strategic Change - Revolution
Strategic Change - RevolutionStrategic Change - Revolution
Strategic Change - Revolutionemmabutler14
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsARC Advisory Group
 
HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...
HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...
HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...HCL Technologies
 
SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...
SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...
SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...Global Business Intel
 
Business Model Innovations (BMI)
Business Model Innovations (BMI)Business Model Innovations (BMI)
Business Model Innovations (BMI)Michael McDonald
 
Transforming Project Delivery in MoD Defence Equipment and Support webinar
Transforming Project Delivery in MoD Defence Equipment and Support webinarTransforming Project Delivery in MoD Defence Equipment and Support webinar
Transforming Project Delivery in MoD Defence Equipment and Support webinarAssociation for Project Management
 

Similar to 1. What were the three key elements that were part of Buck Knives.pdf (20)

Case on coca cola n dabur
Case on coca cola n daburCase on coca cola n dabur
Case on coca cola n dabur
 
The Value Stream Analysis ( Vsa ) Essay
The Value Stream Analysis ( Vsa ) EssayThe Value Stream Analysis ( Vsa ) Essay
The Value Stream Analysis ( Vsa ) Essay
 
(ISM207) How the Principles of Lean Transform Innovation
(ISM207) How the Principles of Lean Transform Innovation(ISM207) How the Principles of Lean Transform Innovation
(ISM207) How the Principles of Lean Transform Innovation
 
Unit1 introduction bpr
Unit1 introduction bprUnit1 introduction bpr
Unit1 introduction bpr
 
The Last Word: The 50-Year Journey to Digital Business
The Last Word: The 50-Year Journey to Digital BusinessThe Last Word: The 50-Year Journey to Digital Business
The Last Word: The 50-Year Journey to Digital Business
 
Driving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six SigmaDriving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six Sigma
 
Driving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six SigmaDriving Operation Innovation Using Lean Six Sigma
Driving Operation Innovation Using Lean Six Sigma
 
Process change - change managment
Process change - change managmentProcess change - change managment
Process change - change managment
 
ODP-Vol44,No4-Alexander_Huggins
ODP-Vol44,No4-Alexander_HugginsODP-Vol44,No4-Alexander_Huggins
ODP-Vol44,No4-Alexander_Huggins
 
Four Organic Sales Growth Strategies
Four Organic Sales Growth StrategiesFour Organic Sales Growth Strategies
Four Organic Sales Growth Strategies
 
Six Sigma Cases
Six Sigma CasesSix Sigma Cases
Six Sigma Cases
 
Strategic Change - Revolution
Strategic Change - RevolutionStrategic Change - Revolution
Strategic Change - Revolution
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM Projects
 
HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...
HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...
HCLT Case Study : HCL enables Strategic Transformation & Business focused Inn...
 
SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...
SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...
SCL Event - Mike Dicken, Dairies Operations Director - Dairy Crest - S&OP / I...
 
Business process re engineering
Business process re engineeringBusiness process re engineering
Business process re engineering
 
Business Model Innovations (BMI)
Business Model Innovations (BMI)Business Model Innovations (BMI)
Business Model Innovations (BMI)
 
eBook: Repurposing your Content
eBook: Repurposing your ContenteBook: Repurposing your Content
eBook: Repurposing your Content
 
SOP-case-study-Henkel-Mexicana
SOP-case-study-Henkel-MexicanaSOP-case-study-Henkel-Mexicana
SOP-case-study-Henkel-Mexicana
 
Transforming Project Delivery in MoD Defence Equipment and Support webinar
Transforming Project Delivery in MoD Defence Equipment and Support webinarTransforming Project Delivery in MoD Defence Equipment and Support webinar
Transforming Project Delivery in MoD Defence Equipment and Support webinar
 

More from aniljain719651

1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdf
1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdf1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdf
1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdfaniljain719651
 
1. The market reacted poorly to Credit Suisses announcement regardi.pdf
1. The market reacted poorly to Credit Suisses announcement regardi.pdf1. The market reacted poorly to Credit Suisses announcement regardi.pdf
1. The market reacted poorly to Credit Suisses announcement regardi.pdfaniljain719651
 
1. The information and material that forms the heart of your project.pdf
1. The information and material that forms the heart of your project.pdf1. The information and material that forms the heart of your project.pdf
1. The information and material that forms the heart of your project.pdfaniljain719651
 
1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdf
1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdf1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdf
1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdfaniljain719651
 
1. Suppose two people, Jake and Jill, have different prior beliefs a.pdf
1. Suppose two people, Jake and Jill, have different prior beliefs a.pdf1. Suppose two people, Jake and Jill, have different prior beliefs a.pdf
1. Suppose two people, Jake and Jill, have different prior beliefs a.pdfaniljain719651
 
1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdf
1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdf1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdf
1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdfaniljain719651
 
1. Si el candidato de un presidente a la Corte Suprema es un constru.pdf
1. Si el candidato de un presidente a la Corte Suprema es un constru.pdf1. Si el candidato de un presidente a la Corte Suprema es un constru.pdf
1. Si el candidato de un presidente a la Corte Suprema es un constru.pdfaniljain719651
 
1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdf
1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdf1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdf
1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdfaniljain719651
 
1. Sketch a kinetics curve for the movement of lactose into E. coli .pdf
1. Sketch a kinetics curve for the movement of lactose into E. coli .pdf1. Sketch a kinetics curve for the movement of lactose into E. coli .pdf
1. Sketch a kinetics curve for the movement of lactose into E. coli .pdfaniljain719651
 
1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdf
1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdf1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdf
1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdfaniljain719651
 
1. Section1.- Populating the list of persons on the person listing f.pdf
1. Section1.- Populating the list of persons on the person listing f.pdf1. Section1.- Populating the list of persons on the person listing f.pdf
1. Section1.- Populating the list of persons on the person listing f.pdfaniljain719651
 
1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdf
1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdf1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdf
1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdfaniljain719651
 
1. Section1.- Populating the list of persons on the person listing.pdf
1. Section1.- Populating the list of persons on the person listing.pdf1. Section1.- Populating the list of persons on the person listing.pdf
1. Section1.- Populating the list of persons on the person listing.pdfaniljain719651
 
1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdf
1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdf1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdf
1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdfaniljain719651
 
1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdf
1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdf1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdf
1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdfaniljain719651
 
1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdf
1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdf1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdf
1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdfaniljain719651
 
1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdf
1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdf1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdf
1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdfaniljain719651
 
1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdf
1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdf1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdf
1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdfaniljain719651
 
1. You are an analyst reviewing the impact of currency translation.pdf
1. You are an analyst reviewing the impact of currency translation.pdf1. You are an analyst reviewing the impact of currency translation.pdf
1. You are an analyst reviewing the impact of currency translation.pdfaniljain719651
 
1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdf
1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdf1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdf
1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdfaniljain719651
 

More from aniljain719651 (20)

1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdf
1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdf1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdf
1. THE UNITED STATES has all biomes except ____.Group of answer ch.pdf
 
1. The market reacted poorly to Credit Suisses announcement regardi.pdf
1. The market reacted poorly to Credit Suisses announcement regardi.pdf1. The market reacted poorly to Credit Suisses announcement regardi.pdf
1. The market reacted poorly to Credit Suisses announcement regardi.pdf
 
1. The information and material that forms the heart of your project.pdf
1. The information and material that forms the heart of your project.pdf1. The information and material that forms the heart of your project.pdf
1. The information and material that forms the heart of your project.pdf
 
1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdf
1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdf1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdf
1. Scope Objectives of IBM�s Stretch Project (IBM 7030) detail- .pdf
 
1. Suppose two people, Jake and Jill, have different prior beliefs a.pdf
1. Suppose two people, Jake and Jill, have different prior beliefs a.pdf1. Suppose two people, Jake and Jill, have different prior beliefs a.pdf
1. Suppose two people, Jake and Jill, have different prior beliefs a.pdf
 
1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdf
1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdf1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdf
1. Rara vez se utilizan equipos multifuncionales para desarrollar un.pdf
 
1. Si el candidato de un presidente a la Corte Suprema es un constru.pdf
1. Si el candidato de un presidente a la Corte Suprema es un constru.pdf1. Si el candidato de un presidente a la Corte Suprema es un constru.pdf
1. Si el candidato de un presidente a la Corte Suprema es un constru.pdf
 
1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdf
1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdf1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdf
1. Sulfate- or sulfur-reducing bacteria would most likely be found i.pdf
 
1. Sketch a kinetics curve for the movement of lactose into E. coli .pdf
1. Sketch a kinetics curve for the movement of lactose into E. coli .pdf1. Sketch a kinetics curve for the movement of lactose into E. coli .pdf
1. Sketch a kinetics curve for the movement of lactose into E. coli .pdf
 
1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdf
1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdf1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdf
1. Seg�n la hip�tesis m�s aceptada, el origen del genoma nuclear inv.pdf
 
1. Section1.- Populating the list of persons on the person listing f.pdf
1. Section1.- Populating the list of persons on the person listing f.pdf1. Section1.- Populating the list of persons on the person listing f.pdf
1. Section1.- Populating the list of persons on the person listing f.pdf
 
1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdf
1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdf1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdf
1. Seg�n Darwin, si un grupo muestra un comportamiento m�s moral que.pdf
 
1. Section1.- Populating the list of persons on the person listing.pdf
1. Section1.- Populating the list of persons on the person listing.pdf1. Section1.- Populating the list of persons on the person listing.pdf
1. Section1.- Populating the list of persons on the person listing.pdf
 
1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdf
1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdf1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdf
1. �Cu�l de las siguientes estructuras hace que las cianobacterias s.pdf
 
1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdf
1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdf1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdf
1. �Cu�l de los siguientes debe evitarse al motivar a los miembros d.pdf
 
1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdf
1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdf1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdf
1. �Cu�l de las siguientes es una raz�n para la descentralizaci�n.pdf
 
1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdf
1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdf1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdf
1. �Cu�l de las siguientes afirmaciones no es verdadera a. Los an.pdf
 
1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdf
1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdf1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdf
1. �Cu�l de las siguientes afirmaciones es verdadera sobre los siste.pdf
 
1. You are an analyst reviewing the impact of currency translation.pdf
1. You are an analyst reviewing the impact of currency translation.pdf1. You are an analyst reviewing the impact of currency translation.pdf
1. You are an analyst reviewing the impact of currency translation.pdf
 
1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdf
1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdf1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdf
1. X tiene una ventaja comparativa sobre Y en la producci�n de un bi.pdf
 

Recently uploaded

Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptNishitharanjan Rout
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnershipsexpandedwebsite
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesAmanpreetKaur157993
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxCeline George
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code ExamplesPeter Brusilovsky
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesPooky Knightsmith
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsSandeep D Chaudhary
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...EADTU
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024Borja Sotomayor
 
The Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDFThe Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDFVivekanand Anglo Vedic Academy
 
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...Nguyen Thanh Tu Collection
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSAnaAcapella
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfPondicherry University
 
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhleson0603
 
MOOD STABLIZERS DRUGS.pptx
MOOD     STABLIZERS           DRUGS.pptxMOOD     STABLIZERS           DRUGS.pptx
MOOD STABLIZERS DRUGS.pptxPoojaSen20
 
male presentation...pdf.................
male presentation...pdf.................male presentation...pdf.................
male presentation...pdf.................MirzaAbrarBaig5
 

Recently uploaded (20)

ESSENTIAL of (CS/IT/IS) class 07 (Networks)
ESSENTIAL of (CS/IT/IS) class 07 (Networks)ESSENTIAL of (CS/IT/IS) class 07 (Networks)
ESSENTIAL of (CS/IT/IS) class 07 (Networks)
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
 
Supporting Newcomer Multilingual Learners
Supporting Newcomer  Multilingual LearnersSupporting Newcomer  Multilingual Learners
Supporting Newcomer Multilingual Learners
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategies
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code Examples
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical Principles
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & Systems
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024
 
The Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDFThe Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDF
 
Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
 
MOOD STABLIZERS DRUGS.pptx
MOOD     STABLIZERS           DRUGS.pptxMOOD     STABLIZERS           DRUGS.pptx
MOOD STABLIZERS DRUGS.pptx
 
male presentation...pdf.................
male presentation...pdf.................male presentation...pdf.................
male presentation...pdf.................
 

1. What were the three key elements that were part of Buck Knives.pdf

  • 1. 1. What were the three key elements that were part of Buck Knives' five-year plan to reduce costs? Which one did they implement immediately? 2. There were some key executive-level managers who became huge advocates of the lean process. The article said that these managers acted as "a catalyst to speed the permeation of lean throughout the culture." These managers worked in which function/department? 3. Our book introduces the concept of the value chain, which is similar to what Buck Knives calls "value streams." What was the biggest hurdle that Buck faced when converting to value streams? How many years had they been doing things the old way? 4. Buck tried to implement 2 major changes at the same time and learned a valuable lesson of what NOT to do that they repeatedly cite. What was it? 5. Look at the "Box Score" chart at the bottom of p. 2 which summarizes the benefits that Buck Knives achieved through implementing lean principles. Which do you feel is the most important? Why? ( 12 paragraph answer please) By Tonya Vinas Although lean principles and practices have broad application in manufacturing. the ease of that application can vary based on what is being produced, to whom it is being sold, competitive pressures, location, corporate structure, workforce charcieristics, availability of raw materials, contractual obligations, and other attributes that make each lean joumey different. Buck Knives, a Post Falls, Idaho-based manufacturer of knives for outdoor recreation and personal use, had more reasons than most to eschew lean: - Its three biggest customers are large chain retailers and catalogs, who can be highly demanding of suppliers and are notoriously inconsistent with replenishment and sales-forecast accuracy. - Making high-quality knives involves craftsmanship skills, which don't translate easily into standard work. - Raw materials include both metals - which have long procurement cycles and volatile prices - and specialty materials such as giraffe bone and mother of pearl - which are rare, strictly regulated, and have complicated procurement requirements. - Forty to forty-five percent of sales come in the last three months of the year, making for highly unleveled demand. - As it started implementing lean, the company also had to relocate its company headquarters and manufacturing facility from San Diego to Post Falls and implement a new enterprise resource planning (ERP) system. Despite these challenges, Buck Knives has so fervently cmbraced lean that it now does nearly everything differently - from allocations of costs for shop-floor supplies to working with its key retail customer to level load fulfillment. Buck's efforts began with the creation of a single assembly cell while it was still a largebatch producer and occupied a plant that was 45% larger than its current plant. Since then, lean ideology has changed leadership's thinking so much that they have thrown out their old performance metrics and are in the process of creating new ones that reflect
  • 2. the goals of lean. Becoming Lean to Survive Several factors led Buck leadership to determine in 2001 that the company had to drastically change if it wanted to keep manufacturing in the United States. The cost of doing business had risen dramatically in California, Buck's home since the 1940 s. Additionally, a sudden and unexpected sales drop of a key product and the recession that followed the 911 terrorist attacks led to three unprofitable years. Simultaneously, competitors in China were becoming better at manufacturing quality knives, and Buck managers calculated a 30% cost differential between their company and its overseas competitors. "The business reason for launching lean was survival," said CEO C.J. Beck, a descendent of company founders. "Tweaking was not going to keep up with the bleeding." The company created a five-year plan to reduce costs by at least 30% that included three key elements: moving to a state with lower energy, labor, and regulatory costs; buying a new ERP system; and creating a lean-oriented culture. The first two goals had long-term timeframes, but the company started on lean right away. They employed consultants, sent a group of 25 employees for off-site lean training, and began targeting production for improvememt. At the time Buck operated with a mass-production model with disconnected functional areas. Finished-goods and WIP were everywhere. "At any time, one of the production areas easily had two-to-three months of inventory," said William Keys, director of lean manufacturine. "Five batches here, 10 batches there. And a batch ranged anywhere from 25 to 50 knives. We literally had thousands of knives in WIP inventory." Their finst step was to convert from mass production to assembly cells. Keys said the first cell was created during the initial lean training and was suceessful. Leaders started with one group, and then that group trained another group and helped them to convert into a cell. This continued over several months until most of the production floor had been converted. By this time, the company began focusing more on its out-of-state move and devoted less time to expanding lean principles to other areas of the company. The cells continued to function successfully, and the company would occasionally hold teaching events. Although managers had much to do related to the relocation, lean thinking continued to influence their decisions. Lean Enterprise institule "One of the things we realized when we were creating the assembly cells was that we had consolidated into an area that was about half the size, and we had reduced WIP by 60%." Consequently, they decided that their next facility could be onethird smaller and should be designed to support flow. Also, once the company did relocate in 2005, it needed to hire about 200 new employees, all of whom it trained in lean concepts right away. It was in September of 2005 that Buck CFO Phyllis Best took a group of Buck managers to a conference on lean accounting. Speakers included Brian Maskell, Orry Fiume, Jean Cunningham, and other people
  • 3. who were using new accounting concepts that better reflect and better suppont lean management than traditional accounting concepts. (Lean-accounting principles reward inventory reduction, favor value-creation over piece-part pricing, and give an accurate portrayal of cash flow and costs. Traditional accounting methods do not support these goals.) "It was kind of a hard thing to aceept," Keys said. "It made sense, but some of the things were counter to what we had been doing since the company was founded. But they came back very much convinced that we had to move in this direction." The injection of these new accounting principles into Buck's continuous improvement efforts - just when the company was reactivating its lean focus, launching production at a new site, and hiring new employees - acted as a catalyst to speed the permeation of lean throughout the culture. This happened because managers in the function that most drives strategic decision-making at the executive level - accounting and finance - became lean evangelists, just like. the operations folks. Converting to Value Streams One of the first things companies often do when adopting lean accounting is to reorganize into value streams, which Buck did. Keys and others identified four value streams based on knife designs and added a fifth value stream to represent sourced knives, which the company manufacturers via contractors in China. They chose value-stream managers internally, picking the leaders based on experience. As with many companies that reorganize into value streams, Buck's biggest hurdle came from operators who wanted to cling to functional roles, particularly in the area of blade fabrication, which includes a variety of skills with long histories of craftsmanship. "Reorganizing into value streams is fairly easy," Keys said. "The challenge is how to move forward after that. For instance, in Value Streams 1, 2, and 3, we began to include fabrication people. Their actual work didn't change, but in Fabrication, people identified with Fabrication. They didn't identify with a particular product. For instance, they would say, "We are hollow-grind operators." You have to realize that with the value streams, in a course of a day we changed how things had been done for 45 years." Keys said management's strategy was to keep reinforcing what the goal was, how the company was going to achieve the goal, and why it was important to achieve the goal. "We still haven't gotten to where we want to be, but it's better than when we started, "Keys said. Some batching still takes place in Fabrication, which has duties such as grinding and stamping knife blades, some of which are specialty knives made for collectors. Those batch sizes, however, are about half of their pre-value-stream sizes, and lead time in Fabrication has dropped from six to eight weeks to two to three weeks. Fabrication remains a target improvement area for the value streams, one of which has a goal of reducing fabrication time by 50% this year. Leading this kaizen are Bruce Sundahl, lean/continuous improvement manager, Jim Hypes, value-stream manager and Cindy Eby, a buyer for the value stream. Additionally. Hypes and Jeff Hubbard,
  • 4. another value stream manager, are crosstraining their employees in Assembly and Fabrication, seeding the effort with a group of production employees who became certified in lean through a local manufacturing-assistance program last summer and went through cross-training as part of the process. Addressing Cyclical Sales In addition to Fabrication, a small amount of batching still takes place in the heattreating function and limited clam-shell packaging, but otherwise the entire production floor is organized into cells that are part of value streams. Each stream operates as a separate profit center and plans work according to a 30 -day forecast that is produced at monthly mectings involving Sales, Accounting, and Operations. Prior to these cooperative meetings, Sales and Operations never communicated, and this fed exeessive inventories of mismatched parts, overstocked finished goods, and piles of WIP waiting for the next process. "When we started having joint meetings, we began to communicate in a new way, " CFO Best said. "And now, Sales is responsible for the sales forecast, and Operations is waiting to do their planning based on that forecast." Materials flow based on multiple kanban systems. Cells track perfommance on a white board, listing the production plan for each shift and metrics on how each cell is performing compared with the plan. The individual value streams manage their own costs. To deal with the cyclical nature of the retail market, Buck decided to reduce finished- goods inventory to one month but increase flexibility with continuous improvement. It is also beginning to ereate vendor-managed inventory programs with some of its larger clicnts. Additionally, Buck began level-loading production for its largest client, Wal-Mart, which historically has been good at forecasting 12-month sales totals, but not so good at month-to- month forecasts. Buck takes Wal-Mart's 12 -month forecast and divides the totals into 10 equal amounts to be Lean Enderprise Institute produced each month between January and Oetober. Now, instead of scrambling when Wal- Mart's monthly forecasts change, Buck relies on this inventory or its increased flexibility to respond quickly if inventory can't cover the monthly order. "Sales has taken responsibility for the forecasting, and we are holding the plants [the Post Falls plant and contract plants in China] accountable for anything that they build over the planned, level load, so there's a little bit of tension there," Best said. "Sales might foresee a spike later in the year, and maybe Operations is just building to a kanban. So Sales might start to panic and say, "Maybe we should increase our forecast a little bit because we don't see Operations responding." And manufacturing is standing back saying, 'We've got plenty of time, we' ve got plenty of capacity. We don 't need to build that yet. ' We still build things we don't need, but not nearly as much as we used to." As an example, the company historically has held two "clearance sales" each year to sell excess finished goods. In 2007, it didn't have to hold any. One way Buck increased flexibility was through a 5S effort that ultimately led to dispersing the packaging function (except for a small amount of clam-shell
  • 5. packaging) to individual cells within the value streams. The improvement began in 2007 when Sundahl launched a 5S initiative for packaging, which took place in one area outside of the cells. It was determined that more space was needed to address a bottleneck in packaging, and such an investment would cost "well above six figures," according to Sundahl. Phil Duckett, executive vice president of Operations, challenged Bruce Sundahl to come up with an altemative. His response was to work collaboratively with the value-stream managers and shipping manger to move packaging to the cells. By early fall, they had proved the concept in one cell and in one value stream. Despite the looming busy season, Duckett gave Sundahl permission to continue with the change. "Rather than putting their foot on the break, they put their foot on the gas pedal, and I think that helped with how fast the change happened," Sundahl said. "Everyone knew that the busy season was coming, and we got it all converted in four months." The packaging move did more than allow Buck to avoid an expensive capital outlay, it also: - Allowed for the reassignment of several employees to other areas because the cell-based tasks require fewer people. - Removed a bottleneck in the supplier kanban system because the signals to suppliers would get hung up - sometimes for days - while finished goods waited for packaging. - Helped the company to accept and complete all of its orders in the final quarter of 2007. Previously, the company would concentrate on filling high-volume orders and turn down smaller onders during this busy time. Because of the level-loading plan with Wal-Mart and because finished goods were packaged before orders came in, the company had enough capacity to complete all orders. It did not have to decline any sales opportunitics. Uncovering True Costs Buck has increased flexibility in other ways and has reaped multiple benefits. Some of these opportunities, however, would have remained hidden had the company not converted to the lean- accounting practices taught by Maskell, whom it hired for training and consulting. C.J. Buck gives this example: The company uses a fine blank machine to cut blades from metal and was faced with having to invest in new customized tooling for the machine to produce a new product. Tooling would have cost as much as $80,000 and would have had a fourmonth turnaround. Maskell asked if the company had idle capacity elsewhere that could handle the increased demand. They did: a laser cutting machinc, but it cuts blades at the rate of 60 to 80 an hour while the fine blank machine can produce 600 to 800 an hour. According to traditional-accounting principles, the large-batch option would have been most profitable. But using lean-accounting principles, which favor flexibility over large-batch production, the laser machine was the better option, and that's what the team chose. "Looking at our capacity, we just don't have that many products that need a rate of 800 an hour," Buck said. "We actually had excess capacity in the fine blank machine. We needed help in the smaller runs. Standard costing says the obvious solution is to buy the machine that can make the most product, but that's not what we needed." Best
  • 6. attributes the increased use of the lasser-cutting machine and other changes with increasing flexibility enough to give the company a unique advantage. For instance, the company offers quick tumaround on customizcd consumer Webbased orders, something competitors can't do. Additionally, the company expects to continue to save in tooling costs by using laser cutting. "The laser is slower, but it allows you to have smaller batches and not invest in the tooling costs," she said. "In the past the sales people would be optimistic about sales, which meant we would invest a lot in tooling sometimes, and then sales wouldn't come through. Now we've smartened up. Now we say, "If demand gets there, we can ahwys order the tooling. +. Lean Enterphise institule Using the more holistic lean-accounting approach also led to the company pulling some work back from being outsourced to six Chinese contract manufacturers. Using theories and methods learned from Maskell, Hubbard documented that handles that were being manufactured in China at $6 a handle would cost $2 a handle to make at the Post Falls plant. The production was moved in house, and now the company uses the variable-cost model to plan production for all new products. (Such a model accounts for actual costs and value created, not just a per-unit price.) Chris Potts, cost accounting manager at Buck, said the model evaluates three factors: 1) Capacity and headcount, 2) Material costs, and 3) Additional incremental costs. "The whole premise here is to look at cash flow and see what the real cost is, not the estimated cost based on a model that you built back at the beginning of the year when you had certain assumptions," Potts said. "In the past, we would have looked at a fully burdened cost regardless of whether we had excess capacity." Recently, using this technique led to the decision to produce a SI million order in Post Falls instead of China. The result was a much higher profit margin, Best said, because Buck used assets it already had instead of writing a check to a contract manufacturer and paying related import and transportation foes. New Model, New Metrics As Buck was adopting lean accounting and ramping up lean projects at its new plant, it also invested in a new ERP system. This provided an important lesson learned that Buck mangers repeatedly cite: Don't attempt to install a new ERP system while starting massive lean conversions. Wait until you are farther along. Buck Knives has had to invest countless hours converting the ERP system from its traditional- accounting focus to value-stream/lean-accounting focus. The work continues. Potts is constantly refining the reports he produces for value-stream managers that doctment costs and profits. He does this in conjunction with lean process changes. For instance, the company is in the process of creating supermarkets at each value stream that will hold production supplies, some of which are used by everyone and currently are warehoused in a central location. The supermarkets will allow for more accurate capturing of supply costs by value stream and reduce the need for warchousing. Lean Enterprise Institute
  • 7. "Each year as we go forward, we'll get closer and closer to having a true, actual cost for all of these things," Ponts said. "This will be the first year we'll be able to take a look at this year's actual versus last year's actual. So we'll be able to finetune our expectations." In addition to the finance-oriented measures, Buck is recreating is performance metrics. This need has arisen from both the cultural changes that have taken place and the obliteration of the old ERP system. C.J.Buck said this is where most of his focus as a leader is these days - asking not just what are the answers, but what should be the questions. When the new performance metries are rolled out, they likely will be some of the most well-tuned lean performance measures created by a manufacturer, In so many ways like this, Buck Knives is an idyllic lean operation - a company that is building not just products based on lean principles. but a culture based on lean principles. "This is a family business. It has a very specific culture," Buck said. "I like the way lean invites you to share information because sharing information can help you. That strikes me as common sense. It also reinforees that I don't want robots. Trained people are by far your best asset. And as people learn more and become more flexible, it adds flexibility and robustness to your operations." For More Information Buck Knives -- Leam more about the company and its history here . Lean Enterprise Institute Senior Exccutive Series - Read an interview with Buck Knives CEO C.J. Buck about lean management as a strategy and how his role as an executive changed. See all the Senior Executive interviews in the Lean Thinkers' Comer. The Lean Enterprise Institute (LEI) runs monthly regional workshops on basic and more advanced lean tools and lean management. You can read complete descriptions of workshop content with the latest dates and locations at IEI's raining page. LEI workbooks and training materials - all designed to de-mystify What a sensei does - show you what steps to take on Monday morning to implement lean concepts. Visit the LEI product catalog to see the resources available for supporting lean transformations. Lean Accounting - Leam more about the movement to transition away from traditional standard cost accounting, which often sends the wrong signals during a lean conversion to a costing system based on product value streams. Glossary (Adapted from the Leon lexicin) Five S Five related terms, beginning with an S sound, describing workplace practices conducive to visual control and lean production. The five terms in Japanese are: 1. Seiri: Separate needed from unneeded items-tools, parts, materials, paperwork - and discard the unneeded. 2. Seiton: Neatly arrange what is left-a place for everything and everything in its place. 3. Seiso: Clean and wash. 4. Seiketsu: Cleanliness resulting from regular performance of the first three Ss. 5. Shitsuke: Discipline, to perform the first four Ss. Level Loading (Heijunka) Leveling the type and quantity of production over a fixed period of time. This enables production to efficiently
  • 8. meet customer demands while avoiding batching and results in minimum inventories, capital costs, manpower, and production lead time through the whole value stream. Supermarket The location where a predetermined standard inventory is kept to supply downstream processes. Supermarkets ordinarily are located near the supplying process to help that process see customer usage and requirements. Each item in a supermarket has a specific location from which a material handler withdraws products in the precise amounts needed by a downstream process. As an item is removed, a signal to make more (such as a kanban card or an empty bin) is taken by the material handler to the supplying process.