SlideShare a Scribd company logo
1 of 16
Semi high speed train Appropriate Track Heavy axle load train
Challenges & possible solutions for appropriate Track
technology for mixed traffic regime of Semi high speeds
& heavy axle loads BASED ON GLOBAL EXPERIENCE
By
M.M. Agarwal & K.K Miglani 1
1. Synopsis/Introduction
* IR are going ahead in a big way to introduce semi high speed trains which
should be cost effective & can be done expediously. On the same track,
the Railway are also planning to run heavy axle load trains to improve its
economy & make Railway self reliant.
* Track, being the basic infrastructure has to be updated/developed to
provide appropriate track technology as to ensure that it meets the
challenges of mixed traffic of semi high speed as well as of heavy axle
loads.
* The authors have made a detailed study of track standards required for
high speed trains/semi high speed trains as well as trains with heavy axle
loads on Indian Railways as well as of other developed railway system of
world such as Japan, Germany, France, USA etc.
* Based on experience gained by Global Railways including Indian
Railway the authors have made an effort to suggest appropriate Track
technology, to give best output to IR with safety, comfort & efficiency
for mixed traffic regime of Semi high speed & heavy axle load trains.
2
2. Methodology adopted to tackle the problem
* As there is hardly any literature available of running semi high
speed trains on IR as well as on world Railways. It is proposed to
make a study of high speed railway systems as well as of Semi-
high speed trains at global level including Indian railways & try
to get an idea of track standards for the same.
* Similarly, it is proposed to have a study of running heavy axle loads
trains on Global railways including Indian Railways & get an Idea
of track standards for the same.
* As track standards/specifications are bit different in moving semi-
high speed trains on one side & heavy axle load trains on other
side, it is a challenging job for Railway engineers to optimize the
track standards so as to move both types of traffic with
maximum efficiency.
* Finally taking an overall view, efforts have been made to suggest
appropriate track technology which can give optimum output in
mixed traffic regime of semi high speed & heavy axle loads
traffic.
3
3. High Speed trains on World Railways
* What is a high speed train: UIC defines a high speed train as
one that runs over 250 kmph. on dedicated tracks or at over 200
kmph. on upgraded conventional tracks.
* History of High Speed Railways
(i) The Construction of first high speed railways started in 1959 in
Japan of Tokaido-Osaka Section. Operations began on 1 Oct,
1964. This line is the world’s busiest high-speed rail line.
(ii) This revolutionary concept of high speed trains was caught on in
Europe in the 1980s ,followed by other countries like USA,
Russia & lately in China. In the last four decades, there has been
spectacular technological progress allowing speeds to be raised to
350 kmph.
(iii) High speed lines in the world exceeding 250 kmph. is about 30000
kms.
4
3.1 Track Structure used on High Speed Routes (HSR)
A study has been made of few high speed routes viz SNCF, Japanese
Railways, German Railways (DB), Spanish Railways Belgium Railways.
From study of these railways it is observed that most of the leading railways
operating at High speed use conventional track consisting rails fastened on
sleepers with elastic fastenings. The average Track structure being adopted
on High speed Railways is given in subsequently table.
3.2 High Speed Train on Indian Railways
(Mumbai-Ahmedabad High Speed rail corridor)
The Mumbai-Ahmedabad high-speed rail corridor for running of Bullet
trains is an approved high-speed rail corridor project connecting the cities of
Mumbai and Ahmedabad in India.
* MOU has been signed by the Govt. of India and Japan on 12 Dec, 2015.
* The project is estimated to cost 97,636 crore (US$ 15 billion).
Technical Features:
* Length of line : 508 kms; * Track gauge: 1,435 mm (4’ 8½”) Standard
Gauge
* Speed : 320 to 350 kmph; * Completion Time: 7 Years from 2019-2016
5
3.3 Other Features of Special Structures for High Speed Railway
1. Turnouts : When the speed on straight track is above 250 Kmph, High speed turnouts
with speed on curved track from 80 to 100 Kmph are warranted.
* Turnout : Flatter switch entry; for reduction of lateral forces & increased passenger comfort .
Design Movable Nose Crossing for reduction of gap at crossing
2 Bridges : Bridges as well as bridge approaches are the vulnerable points, Strengthen the
existing bridge network with minimum disruption to traffic and cost effectiveness.
3. Tunnels : Tunnel cross sections on high speed lines will be guided by the aerodynamic
Phenomena in the tunnel; * To reduce this effect, tunnel hoods are specially
designed with pressure release shafts.
4. Grade Separation/ : Grade separation/Level Crossings:
Level Crossing Normally level crossing is not suitable for
high speed train operation
5. Tilting trains on : To overcome the limitation of speed on
Curves account of sharp curves particularly on
mixed traffic routes, where it is not possible
to cant the track, vehicles with tilting
suspension system having tilting mechanisms Figure 1: Tilting Train
can be used. 6
4. Semi high speed Railways
* What is Semi High Speed Trains
Semi high speed trains are generally those trains which run at operational speed of 160 to 200
kmph with an average speed of about 110 kmph.
* IR are one of few Railways in world, which are planning to run semi high speed trains in big way.
* India has recently (5th April 2016) inaugurated the semi high speed train Gatimaan Express which
is India’s first semi high speed train running at top speed of 160 km/h from Delhi to Agra.
* Efforts to increase speed to 160-200 kmph.
Indian Railways aims to increase the speed of passenger
trains to 160-200 km/h on dedicated conventional tracks.
They intend to improve their existing conventional lines
to handle speeds up to 160 km/h, and plan to go for
speed above 160 kmph after removing the constraints.
Figure 2 Gatimaan Express
* Track Structure:
RDSO has specified track structure for Semi high speed for speed upto 160
kmph & also for speed from 160 to 200 kmph as give in para 3.2 of main paper.
* Constraints to be renewed for introducing semi high speed trains faster than
160 kmph. for (i) Sharp Curves (ii) Turnouts (iii)Improvement of track
geometry: 7
5. Heavy Axle load trains
The phrase ‘Heavy Haul operation’ came into prominence with the first Heavy Haul
Conference held in Perth in Western Australia in 1978. A large number of heavy
haul trains are being operated in America, Australia, Africa, Europe, Brazil,
Scandinavia and UK for last 3 to 4 decades.
* Experience of world Railways for design & maintenance of Track structure
The problems faced by some of the important heavy haul systems in the world
railways, in Construction and operation with special reference to Indian
Railways were studied. The case studies are :
* Burlington Railways of North America: oldest Heavy Haul operated railway
constructed in the decade 1970-1980.
* Fortescue Railway of Western Australia world’s newest Heavy- Haul, railway
* Hamersley Railways of North West Australia for maintenance of Heavy Haul
Railway Lines.
* Based on experience of the world Railway ‘Track structure’ & problem
areas have been identified. 8
* Track Structure was studied & these are given in table subsequently
* Problem areas particularly about Formation, Rails, Sleepers, Ballast, Track
fittings, Points & crossing as well as track maintenance & their remedial
measures were assessed as given in para 4.2 of the paper.
5.1 Dedicated Freight Corridor (D.F.C) of IR
In order to cater for heavy axle load traffic, Indian Railways have taken an
ambitious project of dedicated freight corridor, where only heavy axle load
freight trains will run at a speed of 100 kmph
* Details of approved DFC Projects
Two projects approved as DFC projects are Western Corridor from Delhi to
Mumbai (Dadri-Rewari-Vadodara-Mumbai) and Eastern Corridor from Delhi
to Howrah (Khurja- Kanpur-Sonnagar-Howrah).
* Type of traffic &axle load: 25 tonne double stack container movement with
15000 tonne trailing loads: 30 tonne for bridges. (Completion Date: October
2019)
9
6. Appropriate Track technology for mixed traffic regime of
Semi high speed & heavy axle load
The studies of Track requirements to run High speed railways, semi high speed
railways as well as heavy axle load trains on IR and also for developed global
Railways viz Japan, Germany, France, & USA etc as well as UIC standards have
given certain ideas to adopt track standards/ specifications & other requirement
of track technology for mixed traffic
Studies Undertaken
The studies are basically for 3 types of traffic requirement
* High speed traffic: (This is done as there is very little global experience
of semi- high speed traffic)
* Semi high speed traffic mostly on IR.
* Heavy axle load traffic on world railways.
* Heavy axle load traffic on IR (Dedicated Freight Corridor)
Decision
Based on close analysis of studies undertaken for 4 types of traffic and taking an
overall practical, view Appropriate Track standards are suggested as given in
next Table
10
Track structure for
high speed Railways
of World
Track structure for
Semi high speed
Railways.
Track structure for
heavy axle load trains of
world
Track structure for
DFC
Recommended track structure for
IR
1. Rail About 60 kg/m
CWR
71 kg & 90 UTS 60to 68 km routes 60 kg 110 UTS 60 kg UIC rails
2. Sleepers Concrete sleepers
or Glass fibre
glasses
Mono block PRC
sleepers
Mostly PSC Sleepers
Some places wooden
sleepers
PSC Sleepers PSC sleepers
3. Sleeper Density 1660 to 1724
sleepers per km
1660 nos per km. 1660 to 1800 nos.
per km
PSC 1660 Nos.
per km.
1660 sleeper per km
4. Fastenings- Double
Elastic fastenings
type
Leaf spring/TGV
noble/Vossloh
with rubber pads
ERC clips mark III
with rubber pad 6mm
thick
Special type of
fastening
--- Double Elastic fastening
5. Ballast * Ballasted track
with 30 to 40 mm
ballast cusion or
ballastless track
250/300 mm depth
with 150 mm sub
ballast
Hard stone ballast
with 300 mm
cysguib iver 150 mm
syv-ballast
Machine
crushed ballast
with 300 mm
ballast cushion
Hard stone ballast having
cushion of 250-300 mm
with 150 mm sub-ballast.
6. Minimum radius
of curve
varying from
4000 m to 6500
m
7250 m 6000 to 10000 m 1750 m 1750 mm
7. Max. superelevation
(Cant)
varying from 150
mm to 180 mm
140 mm 180 mm -- 165 mm
8. Cant deficiency varying from 50
mm to 112 mm
65 mm 100 -- 75 mm (In special cases
100 mm)
9. Minimum vertical
radius
varying 20000 m
to 25000 m
24000 m -- 4000 m
10. Maximum
gradient
0.15 to 0.20 % 0.1 % or 1 in 1000 1 in 400 1 in 400
11
6.1 Fittings & Fastenings for Appropriate Track
Due to heavy axle load, there is possibility of heavy wear & tear on fitting & fastening as per global
experience.
* Fastening get loose very fast and thereby effecting track geometry.
* Rubber pads get damaged early. Heavy crushing of rubber pads as can be seen in figure on main
paper.
* Glued Insulated Joint start failing because either insulation
insulation gets broken or failure of glue which bonds the
joints.
In order to overcome these problems, the following remedies
are suggested
(i) Double elastic fastenings are recommended.
(ii) Develop better design of rail pads like ‘Three Point Pad’ as
seen in figure
(iii) Bonded Insulated Joints are worst effected & their design
to be further improved by looking after the problems in Figure 3 : Three Point Pad
current design, maintenance & operation
Points & Crossing:
* To be modernised to cater for higher speed of atleast 50 kmph & preferably 75 to 100 kmph.
* Thick web, fixed heel type, head hardened switches with flatter entry & cast mangense crossing.
* Indian Railways have already designed a new high speed turnout of 1:12 type which have
potential of 50 kmph as given in figure 6.1 of the paper.
12
Track Items Recommended track structure
1. Formation Formation should be stable so as to take heavy load and also for semi-high speed of 160 to 200 kmph
2. Rail
60 kg UIC rails having 90 UTS are recommended which can be suitable for semi high speed (160 to 200
kmph) as well as high axle load traffic up to 25 tonne axle load.
3. Sleeper Prestressed concrete (PSC) sleepers are recommended. The sleeper density should be 1660 sleeper per km.
4. Ballast
Ballasted track is recommended with hard stone ballast having full ballast cushion of 250 mm to 300 mm
with 150 mm sub ballast. IF necessary, work hardening to be done to improve quality of ballast.
5. Fitting & Fastenings
(i) Double elastic fastenings are recommended.
(ii) To carry heavy axle load & to avoid failure of rubber pad, develop better design of rail pads like
‘Three Point Pad’
(iii) Bonded Insulated Joints due to heavy axle loads these joints are worst effected & their design to
be further improved by looking after the problems in current design, maintenance & operation
6. Points & Crossing
To be modernised to cater for higher speed of atleast 50 kmph & preferably 75 kmph to 100 kmph.
Indian Railways have already designed a new high speed turnout of 1:12 type which have potential of 50
kmph
7. Maximum Curvature For comfort & safety it should not be sharper than 1° (1750 m)
8.Maximum
superelevation
In order to provide proper comfort to traveling public as well as to provide safety to passengers/goods,
maximum superelevation of 150 mm is recommended.
9. Vertical Curve
A very smooth vertical curve is necessary for semi high speed railway to provide maximum comfort to
passengers. The minimum vertical radius recommended is 4000 m for safe & smooth ride.
10. Ruling Gradient
Considering comfort of passengers & safety of passenger/goods, max. gradient recommended is 1 in 400.
6.2 Recommended Track structure to suit the requirement of mixed traffic
13
6.3 Recommended Maintenance & Other Features
Track Maintenance:
* Track has to be maintained mechanically by a fleet of modern track machines.
* Regular monitoring of track is required by sophisticated/modern track recording car
* Isolated track defects should be attended by off-track tampers.
Rail Grinding: Due to heavy loads rail develops defect like Rapid rail wear & excessive
wear of rail on curves. Reprofiling should be done by Rail Grinding machine for
prolonging rail life as well to prevent defects in rail head.
Track Transition areas (Bridge approaches, Level crossings & special track works)
* Due to differential settlement, extra track stiffness and differential damping track
Components gets damaged quite early.
* Extra track maintenance is required of these difficult locations
Bridges: Bridges should be designed for heavier loading. Quality of bridge construction
and maintenance requires to be improved.
Level Crossings:
- No Unmanned level crossing
- Manned level crossing should be avoided. However, in unavoidable circumstances, it
must be interlocked with signals. 14
Improvement in Rolling Stock
LHB coaches are cleared for regular operation upto a maximum speed of 160
kmph. However for higher speed all the coaches will have to be air conditioned
to avoid dust ingress and air blast.
TALGO Coaches : Trains on conventional rail-
roads have been the fore-runners for Higher-Speed
Trains” in Spain, France, Switzerland and Russia.,
* Talgo coaches with their lower weight generate
lower centrifugal forces and can run faster.
* Talgo coaches trains are one of the possible
alternatives for running semi-high trains on IR.
Tilting trains: To overcome the limitation of speed
on account of tight curves vehicles with tilting Figure 4: Talgo Coaches Train
suspension system can be used.
- For mixed traffic requirement, tilting trains are not recommended for IR due to
practical problems based on Global experience.
Fencing: For speed higher than 160 kmph fencing of the entire section may
become necessary. For speed upto 160 kmph, fencing can be need based in the
vicinity of the habilitation and in approach of major bridges, level crossings etc.
15
7. Summarising
Based on experience of Global Railways including
Indian Railways for, (i) high speed routes (ii) semi-high
speed routes (iii) Heavy axle load routes including DFC.
Appropriate Track-technology has been suggested,
consisting of track standards, track maintenance etc
which is likely to meet the challenge of mixed traffic
regime of running of semi high speed trains as well as
heavy axle load trains.
THANKS
16

More Related Content

What's hot

BANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATIONBANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATIONMasudul Robin
 
Planning principles of Railways Engineering
Planning principles of Railways EngineeringPlanning principles of Railways Engineering
Planning principles of Railways EngineeringLatif Hyder Wadho
 
Urban infrastructure on mono, metro and underground
Urban infrastructure on mono, metro and undergroundUrban infrastructure on mono, metro and underground
Urban infrastructure on mono, metro and undergroundLydia Lyven
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...Hossam Shafiq I
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gaugeMani Vel
 
Mr. mohamad dichari us standards for railroad types, infrastructure and are...
Mr. mohamad dichari   us standards for railroad types, infrastructure and are...Mr. mohamad dichari   us standards for railroad types, infrastructure and are...
Mr. mohamad dichari us standards for railroad types, infrastructure and are...imadhammoud
 
Unit ii railways
Unit ii railwaysUnit ii railways
Unit ii railwaysVipul Naidu
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...Hossam Shafiq I
 
Railway engineering
Railway engineeringRailway engineering
Railway engineeringjmaghade99
 
CV213 (S5) Transportation Engineering
CV213 (S5) Transportation Engineering CV213 (S5) Transportation Engineering
CV213 (S5) Transportation Engineering TANZEEL HABEEBULLA
 
Railway engineering.
Railway engineering.Railway engineering.
Railway engineering.Md Khan
 
Training Report on indian railways on AC COACH MAINTANCES
Training Report on indian railways on AC COACH MAINTANCESTraining Report on indian railways on AC COACH MAINTANCES
Training Report on indian railways on AC COACH MAINTANCESPawan Sharma
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineeringDnyaneshwar More
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway TrackArbaz Kazi
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveysMani Vel
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportALOK RAJ
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...Hossam Shafiq I
 
NWR summer training report
NWR summer training reportNWR summer training report
NWR summer training reportKaushu Deshwal
 

What's hot (20)

BANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATIONBANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATION
 
Planning principles of Railways Engineering
Planning principles of Railways EngineeringPlanning principles of Railways Engineering
Planning principles of Railways Engineering
 
Urban infrastructure on mono, metro and underground
Urban infrastructure on mono, metro and undergroundUrban infrastructure on mono, metro and underground
Urban infrastructure on mono, metro and underground
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gauge
 
Mr. mohamad dichari us standards for railroad types, infrastructure and are...
Mr. mohamad dichari   us standards for railroad types, infrastructure and are...Mr. mohamad dichari   us standards for railroad types, infrastructure and are...
Mr. mohamad dichari us standards for railroad types, infrastructure and are...
 
Unit ii railways
Unit ii railwaysUnit ii railways
Unit ii railways
 
Rail Deflection
Rail DeflectionRail Deflection
Rail Deflection
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
CV213 (S5) Transportation Engineering
CV213 (S5) Transportation Engineering CV213 (S5) Transportation Engineering
CV213 (S5) Transportation Engineering
 
Railway engineering.
Railway engineering.Railway engineering.
Railway engineering.
 
Training Report on indian railways on AC COACH MAINTANCES
Training Report on indian railways on AC COACH MAINTANCESTraining Report on indian railways on AC COACH MAINTANCES
Training Report on indian railways on AC COACH MAINTANCES
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineering
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveys
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
 
NWR summer training report
NWR summer training reportNWR summer training report
NWR summer training report
 
Railway engineering part1
Railway engineering part1Railway engineering part1
Railway engineering part1
 

Similar to 2.02 mm agarwal(1)

High Speed Train - seminar ppt
High Speed Train - seminar pptHigh Speed Train - seminar ppt
High Speed Train - seminar pptNarayanKumar40
 
High speed rail (h2 s)
High speed rail (h2 s)High speed rail (h2 s)
High speed rail (h2 s)Kumar M.
 
seminar presentation on high speed train
 seminar presentation on high speed train seminar presentation on high speed train
seminar presentation on high speed trainmechanical Singh
 
Anuvrat_REPORT AT SPRING FAILURE
Anuvrat_REPORT AT SPRING FAILUREAnuvrat_REPORT AT SPRING FAILURE
Anuvrat_REPORT AT SPRING FAILUREAnuvrat Shukla
 
Types of tracks in pakistan
Types of tracks in pakistanTypes of tracks in pakistan
Types of tracks in pakistanAYAZ AHMAD
 
Globalization and indian railways
Globalization and indian railwaysGlobalization and indian railways
Globalization and indian railwaysChitresh Shrivastva
 
IRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier SelectionIRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier SelectionIRJET Journal
 
Indian railways - past and present
Indian railways -  past and presentIndian railways -  past and present
Indian railways - past and presentChitresh Shrivastva
 
Carriage and wagon
Carriage and wagon Carriage and wagon
Carriage and wagon Deewan singh
 
electric loco shed lalllguda
electric loco shed lalllgudaelectric loco shed lalllguda
electric loco shed lalllgudazakriya furkhan
 
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailIRJET Journal
 
Indian Freight Trains
Indian Freight TrainsIndian Freight Trains
Indian Freight TrainsVipin Subhash
 

Similar to 2.02 mm agarwal(1) (20)

High Speed Train - seminar ppt
High Speed Train - seminar pptHigh Speed Train - seminar ppt
High Speed Train - seminar ppt
 
High speed rail (h2 s)
High speed rail (h2 s)High speed rail (h2 s)
High speed rail (h2 s)
 
seminar presentation on high speed train
 seminar presentation on high speed train seminar presentation on high speed train
seminar presentation on high speed train
 
D012531923
D012531923D012531923
D012531923
 
Anuvrat_REPORT AT SPRING FAILURE
Anuvrat_REPORT AT SPRING FAILUREAnuvrat_REPORT AT SPRING FAILURE
Anuvrat_REPORT AT SPRING FAILURE
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Types of tracks in pakistan
Types of tracks in pakistanTypes of tracks in pakistan
Types of tracks in pakistan
 
Globalization and indian railways
Globalization and indian railwaysGlobalization and indian railways
Globalization and indian railways
 
IRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier SelectionIRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier Selection
 
Indian railways - past and present
Indian railways -  past and presentIndian railways -  past and present
Indian railways - past and present
 
Carriage and wagon
Carriage and wagon Carriage and wagon
Carriage and wagon
 
electric loco shed lalllguda
electric loco shed lalllgudaelectric loco shed lalllguda
electric loco shed lalllguda
 
Skybus ppt
Skybus pptSkybus ppt
Skybus ppt
 
Indian railways
Indian railwaysIndian railways
Indian railways
 
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
 
Railway Gauge
Railway GaugeRailway Gauge
Railway Gauge
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
 
Indian railway
Indian railwayIndian railway
Indian railway
 
Railway System in Indiapptx
Railway System in IndiapptxRailway System in Indiapptx
Railway System in Indiapptx
 
Indian Freight Trains
Indian Freight TrainsIndian Freight Trains
Indian Freight Trains
 

Recently uploaded

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

2.02 mm agarwal(1)

  • 1. Semi high speed train Appropriate Track Heavy axle load train Challenges & possible solutions for appropriate Track technology for mixed traffic regime of Semi high speeds & heavy axle loads BASED ON GLOBAL EXPERIENCE By M.M. Agarwal & K.K Miglani 1
  • 2. 1. Synopsis/Introduction * IR are going ahead in a big way to introduce semi high speed trains which should be cost effective & can be done expediously. On the same track, the Railway are also planning to run heavy axle load trains to improve its economy & make Railway self reliant. * Track, being the basic infrastructure has to be updated/developed to provide appropriate track technology as to ensure that it meets the challenges of mixed traffic of semi high speed as well as of heavy axle loads. * The authors have made a detailed study of track standards required for high speed trains/semi high speed trains as well as trains with heavy axle loads on Indian Railways as well as of other developed railway system of world such as Japan, Germany, France, USA etc. * Based on experience gained by Global Railways including Indian Railway the authors have made an effort to suggest appropriate Track technology, to give best output to IR with safety, comfort & efficiency for mixed traffic regime of Semi high speed & heavy axle load trains. 2
  • 3. 2. Methodology adopted to tackle the problem * As there is hardly any literature available of running semi high speed trains on IR as well as on world Railways. It is proposed to make a study of high speed railway systems as well as of Semi- high speed trains at global level including Indian railways & try to get an idea of track standards for the same. * Similarly, it is proposed to have a study of running heavy axle loads trains on Global railways including Indian Railways & get an Idea of track standards for the same. * As track standards/specifications are bit different in moving semi- high speed trains on one side & heavy axle load trains on other side, it is a challenging job for Railway engineers to optimize the track standards so as to move both types of traffic with maximum efficiency. * Finally taking an overall view, efforts have been made to suggest appropriate track technology which can give optimum output in mixed traffic regime of semi high speed & heavy axle loads traffic. 3
  • 4. 3. High Speed trains on World Railways * What is a high speed train: UIC defines a high speed train as one that runs over 250 kmph. on dedicated tracks or at over 200 kmph. on upgraded conventional tracks. * History of High Speed Railways (i) The Construction of first high speed railways started in 1959 in Japan of Tokaido-Osaka Section. Operations began on 1 Oct, 1964. This line is the world’s busiest high-speed rail line. (ii) This revolutionary concept of high speed trains was caught on in Europe in the 1980s ,followed by other countries like USA, Russia & lately in China. In the last four decades, there has been spectacular technological progress allowing speeds to be raised to 350 kmph. (iii) High speed lines in the world exceeding 250 kmph. is about 30000 kms. 4
  • 5. 3.1 Track Structure used on High Speed Routes (HSR) A study has been made of few high speed routes viz SNCF, Japanese Railways, German Railways (DB), Spanish Railways Belgium Railways. From study of these railways it is observed that most of the leading railways operating at High speed use conventional track consisting rails fastened on sleepers with elastic fastenings. The average Track structure being adopted on High speed Railways is given in subsequently table. 3.2 High Speed Train on Indian Railways (Mumbai-Ahmedabad High Speed rail corridor) The Mumbai-Ahmedabad high-speed rail corridor for running of Bullet trains is an approved high-speed rail corridor project connecting the cities of Mumbai and Ahmedabad in India. * MOU has been signed by the Govt. of India and Japan on 12 Dec, 2015. * The project is estimated to cost 97,636 crore (US$ 15 billion). Technical Features: * Length of line : 508 kms; * Track gauge: 1,435 mm (4’ 8½”) Standard Gauge * Speed : 320 to 350 kmph; * Completion Time: 7 Years from 2019-2016 5
  • 6. 3.3 Other Features of Special Structures for High Speed Railway 1. Turnouts : When the speed on straight track is above 250 Kmph, High speed turnouts with speed on curved track from 80 to 100 Kmph are warranted. * Turnout : Flatter switch entry; for reduction of lateral forces & increased passenger comfort . Design Movable Nose Crossing for reduction of gap at crossing 2 Bridges : Bridges as well as bridge approaches are the vulnerable points, Strengthen the existing bridge network with minimum disruption to traffic and cost effectiveness. 3. Tunnels : Tunnel cross sections on high speed lines will be guided by the aerodynamic Phenomena in the tunnel; * To reduce this effect, tunnel hoods are specially designed with pressure release shafts. 4. Grade Separation/ : Grade separation/Level Crossings: Level Crossing Normally level crossing is not suitable for high speed train operation 5. Tilting trains on : To overcome the limitation of speed on Curves account of sharp curves particularly on mixed traffic routes, where it is not possible to cant the track, vehicles with tilting suspension system having tilting mechanisms Figure 1: Tilting Train can be used. 6
  • 7. 4. Semi high speed Railways * What is Semi High Speed Trains Semi high speed trains are generally those trains which run at operational speed of 160 to 200 kmph with an average speed of about 110 kmph. * IR are one of few Railways in world, which are planning to run semi high speed trains in big way. * India has recently (5th April 2016) inaugurated the semi high speed train Gatimaan Express which is India’s first semi high speed train running at top speed of 160 km/h from Delhi to Agra. * Efforts to increase speed to 160-200 kmph. Indian Railways aims to increase the speed of passenger trains to 160-200 km/h on dedicated conventional tracks. They intend to improve their existing conventional lines to handle speeds up to 160 km/h, and plan to go for speed above 160 kmph after removing the constraints. Figure 2 Gatimaan Express * Track Structure: RDSO has specified track structure for Semi high speed for speed upto 160 kmph & also for speed from 160 to 200 kmph as give in para 3.2 of main paper. * Constraints to be renewed for introducing semi high speed trains faster than 160 kmph. for (i) Sharp Curves (ii) Turnouts (iii)Improvement of track geometry: 7
  • 8. 5. Heavy Axle load trains The phrase ‘Heavy Haul operation’ came into prominence with the first Heavy Haul Conference held in Perth in Western Australia in 1978. A large number of heavy haul trains are being operated in America, Australia, Africa, Europe, Brazil, Scandinavia and UK for last 3 to 4 decades. * Experience of world Railways for design & maintenance of Track structure The problems faced by some of the important heavy haul systems in the world railways, in Construction and operation with special reference to Indian Railways were studied. The case studies are : * Burlington Railways of North America: oldest Heavy Haul operated railway constructed in the decade 1970-1980. * Fortescue Railway of Western Australia world’s newest Heavy- Haul, railway * Hamersley Railways of North West Australia for maintenance of Heavy Haul Railway Lines. * Based on experience of the world Railway ‘Track structure’ & problem areas have been identified. 8
  • 9. * Track Structure was studied & these are given in table subsequently * Problem areas particularly about Formation, Rails, Sleepers, Ballast, Track fittings, Points & crossing as well as track maintenance & their remedial measures were assessed as given in para 4.2 of the paper. 5.1 Dedicated Freight Corridor (D.F.C) of IR In order to cater for heavy axle load traffic, Indian Railways have taken an ambitious project of dedicated freight corridor, where only heavy axle load freight trains will run at a speed of 100 kmph * Details of approved DFC Projects Two projects approved as DFC projects are Western Corridor from Delhi to Mumbai (Dadri-Rewari-Vadodara-Mumbai) and Eastern Corridor from Delhi to Howrah (Khurja- Kanpur-Sonnagar-Howrah). * Type of traffic &axle load: 25 tonne double stack container movement with 15000 tonne trailing loads: 30 tonne for bridges. (Completion Date: October 2019) 9
  • 10. 6. Appropriate Track technology for mixed traffic regime of Semi high speed & heavy axle load The studies of Track requirements to run High speed railways, semi high speed railways as well as heavy axle load trains on IR and also for developed global Railways viz Japan, Germany, France, & USA etc as well as UIC standards have given certain ideas to adopt track standards/ specifications & other requirement of track technology for mixed traffic Studies Undertaken The studies are basically for 3 types of traffic requirement * High speed traffic: (This is done as there is very little global experience of semi- high speed traffic) * Semi high speed traffic mostly on IR. * Heavy axle load traffic on world railways. * Heavy axle load traffic on IR (Dedicated Freight Corridor) Decision Based on close analysis of studies undertaken for 4 types of traffic and taking an overall practical, view Appropriate Track standards are suggested as given in next Table 10
  • 11. Track structure for high speed Railways of World Track structure for Semi high speed Railways. Track structure for heavy axle load trains of world Track structure for DFC Recommended track structure for IR 1. Rail About 60 kg/m CWR 71 kg & 90 UTS 60to 68 km routes 60 kg 110 UTS 60 kg UIC rails 2. Sleepers Concrete sleepers or Glass fibre glasses Mono block PRC sleepers Mostly PSC Sleepers Some places wooden sleepers PSC Sleepers PSC sleepers 3. Sleeper Density 1660 to 1724 sleepers per km 1660 nos per km. 1660 to 1800 nos. per km PSC 1660 Nos. per km. 1660 sleeper per km 4. Fastenings- Double Elastic fastenings type Leaf spring/TGV noble/Vossloh with rubber pads ERC clips mark III with rubber pad 6mm thick Special type of fastening --- Double Elastic fastening 5. Ballast * Ballasted track with 30 to 40 mm ballast cusion or ballastless track 250/300 mm depth with 150 mm sub ballast Hard stone ballast with 300 mm cysguib iver 150 mm syv-ballast Machine crushed ballast with 300 mm ballast cushion Hard stone ballast having cushion of 250-300 mm with 150 mm sub-ballast. 6. Minimum radius of curve varying from 4000 m to 6500 m 7250 m 6000 to 10000 m 1750 m 1750 mm 7. Max. superelevation (Cant) varying from 150 mm to 180 mm 140 mm 180 mm -- 165 mm 8. Cant deficiency varying from 50 mm to 112 mm 65 mm 100 -- 75 mm (In special cases 100 mm) 9. Minimum vertical radius varying 20000 m to 25000 m 24000 m -- 4000 m 10. Maximum gradient 0.15 to 0.20 % 0.1 % or 1 in 1000 1 in 400 1 in 400 11
  • 12. 6.1 Fittings & Fastenings for Appropriate Track Due to heavy axle load, there is possibility of heavy wear & tear on fitting & fastening as per global experience. * Fastening get loose very fast and thereby effecting track geometry. * Rubber pads get damaged early. Heavy crushing of rubber pads as can be seen in figure on main paper. * Glued Insulated Joint start failing because either insulation insulation gets broken or failure of glue which bonds the joints. In order to overcome these problems, the following remedies are suggested (i) Double elastic fastenings are recommended. (ii) Develop better design of rail pads like ‘Three Point Pad’ as seen in figure (iii) Bonded Insulated Joints are worst effected & their design to be further improved by looking after the problems in Figure 3 : Three Point Pad current design, maintenance & operation Points & Crossing: * To be modernised to cater for higher speed of atleast 50 kmph & preferably 75 to 100 kmph. * Thick web, fixed heel type, head hardened switches with flatter entry & cast mangense crossing. * Indian Railways have already designed a new high speed turnout of 1:12 type which have potential of 50 kmph as given in figure 6.1 of the paper. 12
  • 13. Track Items Recommended track structure 1. Formation Formation should be stable so as to take heavy load and also for semi-high speed of 160 to 200 kmph 2. Rail 60 kg UIC rails having 90 UTS are recommended which can be suitable for semi high speed (160 to 200 kmph) as well as high axle load traffic up to 25 tonne axle load. 3. Sleeper Prestressed concrete (PSC) sleepers are recommended. The sleeper density should be 1660 sleeper per km. 4. Ballast Ballasted track is recommended with hard stone ballast having full ballast cushion of 250 mm to 300 mm with 150 mm sub ballast. IF necessary, work hardening to be done to improve quality of ballast. 5. Fitting & Fastenings (i) Double elastic fastenings are recommended. (ii) To carry heavy axle load & to avoid failure of rubber pad, develop better design of rail pads like ‘Three Point Pad’ (iii) Bonded Insulated Joints due to heavy axle loads these joints are worst effected & their design to be further improved by looking after the problems in current design, maintenance & operation 6. Points & Crossing To be modernised to cater for higher speed of atleast 50 kmph & preferably 75 kmph to 100 kmph. Indian Railways have already designed a new high speed turnout of 1:12 type which have potential of 50 kmph 7. Maximum Curvature For comfort & safety it should not be sharper than 1° (1750 m) 8.Maximum superelevation In order to provide proper comfort to traveling public as well as to provide safety to passengers/goods, maximum superelevation of 150 mm is recommended. 9. Vertical Curve A very smooth vertical curve is necessary for semi high speed railway to provide maximum comfort to passengers. The minimum vertical radius recommended is 4000 m for safe & smooth ride. 10. Ruling Gradient Considering comfort of passengers & safety of passenger/goods, max. gradient recommended is 1 in 400. 6.2 Recommended Track structure to suit the requirement of mixed traffic 13
  • 14. 6.3 Recommended Maintenance & Other Features Track Maintenance: * Track has to be maintained mechanically by a fleet of modern track machines. * Regular monitoring of track is required by sophisticated/modern track recording car * Isolated track defects should be attended by off-track tampers. Rail Grinding: Due to heavy loads rail develops defect like Rapid rail wear & excessive wear of rail on curves. Reprofiling should be done by Rail Grinding machine for prolonging rail life as well to prevent defects in rail head. Track Transition areas (Bridge approaches, Level crossings & special track works) * Due to differential settlement, extra track stiffness and differential damping track Components gets damaged quite early. * Extra track maintenance is required of these difficult locations Bridges: Bridges should be designed for heavier loading. Quality of bridge construction and maintenance requires to be improved. Level Crossings: - No Unmanned level crossing - Manned level crossing should be avoided. However, in unavoidable circumstances, it must be interlocked with signals. 14
  • 15. Improvement in Rolling Stock LHB coaches are cleared for regular operation upto a maximum speed of 160 kmph. However for higher speed all the coaches will have to be air conditioned to avoid dust ingress and air blast. TALGO Coaches : Trains on conventional rail- roads have been the fore-runners for Higher-Speed Trains” in Spain, France, Switzerland and Russia., * Talgo coaches with their lower weight generate lower centrifugal forces and can run faster. * Talgo coaches trains are one of the possible alternatives for running semi-high trains on IR. Tilting trains: To overcome the limitation of speed on account of tight curves vehicles with tilting Figure 4: Talgo Coaches Train suspension system can be used. - For mixed traffic requirement, tilting trains are not recommended for IR due to practical problems based on Global experience. Fencing: For speed higher than 160 kmph fencing of the entire section may become necessary. For speed upto 160 kmph, fencing can be need based in the vicinity of the habilitation and in approach of major bridges, level crossings etc. 15
  • 16. 7. Summarising Based on experience of Global Railways including Indian Railways for, (i) high speed routes (ii) semi-high speed routes (iii) Heavy axle load routes including DFC. Appropriate Track-technology has been suggested, consisting of track standards, track maintenance etc which is likely to meet the challenge of mixed traffic regime of running of semi high speed trains as well as heavy axle load trains. THANKS 16