Provisional Operations 30 April 2014
1. Provisional Operations
30 April 2014
Presented to:
Citizens’ Advisory Commission
Presented by:
Kim Jackson
Operations Manager
2. Path to Operations
Continue marching forward to start Provisional Operations
(Certification Period for Operations & Maintenance staff)
4 Steps for Agent Readiness follow to verify people, paper and
equipment are ready:
1. Provisional Operations
– Certification period for plant staff and integration of plant
departments/activities
2. Integrated Facility Testing & HVAC Readiness
– Final tuning of equipment & HVAC setup
3. Optimization
– Formal graded exercises by the Plant to verify readiness
4. Integrated Operations Demonstrations
– Formal graded exercises by PCAPP and stakeholders to verify readiness
2
3. ORR Major Milestones – The Road to
Initial Agent Operations
*Major Milestones per
the PCAPP Integrated
Master Schedule (IMS)
1
9
8
4
14
15
Lab Dilute Agent Operations Mini-ORR
Boiler Ignition Readiness
Assessment
Start Operational Readiness Demo (IOD) – JUN
2015
Agent Entry Readiness and Agent Containment and Confinement
Controls – AUG 2014
Start ERB Provisional Operations/Operations Certifications – OCT 2014
Start APB Provisional Operations/Operations Certifications –
NOV 2014
Contingency Training Readiness/Crew Certification –
JAN 2015
Begin Plant “Soft” Lockdown (Familiarization) – FEB
2015
Start BTA Provisional Operations/Operations Certifications –
NOV 2014 (Optional – Not required per ACWA Policy #26)
Yard Provisional Operations – AUG 2014
Systemization
Complete/Declare Readiness –
JUL 2015
Complete PCAPP
Systemization (for Pilot
Testing )– SEP 2015
Training Facility Available for Practical Factors – Readiness Check
Pre-Systemization Complete
Training Facility Available for Toxic Area Training – Readiness Check
10
11
12
13
Environmental Readiness – MAR 2015
16
Key Readiness
Milestones
COMPLETE
IN PROGRESS
NOT STARTED
* Incremental Readiness
Assessments will overlap
– they are not strictly
sequential
6
5
3
2
7
3
4. Provisional Operations ~ 2 Month
Period
Period for Operations & Maintenance
staff to gain proficiency and complete
certifications
• Achieved through normal operations and
contingency exercises to build proficiency
– Split into four areas: Yard Utilities,
Enhanced Reconfiguration Building, Agent
Processing Building and Biotreatment Area
• Four months away from kicking off Yard
Utility exercises
– Normal operations will focus on utility
operations (e.g. compressors, boilers)
– Contingencies will focus on industrial
spill response and confined space rescue
– Equipment recovery drills for loss of utility
equipment will be performed
4
5. Yard Provisional Operations
Internal Drills and Exercises to Confirm Proficiency in
the Yard
Normal Operations Evolutions:
• Utility Operations (Compressors, Electrical, Fire Water, Boilers)
• Equipment Rotations
• Rounds and Readings, and response to abnormal indications
• Preventive Maintenance and Corrective Maintenance (allows maintenance to
practice expected maintenance evolutions)
• Routine shift practices (shift turnover, log keeping)
Contingency Evolutions:
• HAZMAT response, including confined space rescue
• Loss of Plant Air Recovery
• Loss of Instrument Air Recovery
• Loss of Power Recovery
5
6. Activities to Prepare for Operations
Emergency Response Team
(ERT) standup underway
• Received final trucks/trailers and
ambulance from TOCDF and UMCDF
• ERT courses kick off April 2014
• Project all four crews to have ERT
stood up by Aug 2014
Draft drill packages have been
developed for all normal
operations and contingencies
• All packages will be provided to ORR
Team to kick off stakeholder review
(April 2014)
6
7. Activities to Prepare for Provisional
Operations
Toxic Area Training (TAT) kicked off – Operations & Maintenance
(O&M) training in progress
• Operations Support Backups Priority for classes
• Maintenance and Operations to follow April 2014 – April 2015
Training Facility Projectile Mortar Disassembly and Munitions
Washout System installation nearing completion
• Provides Maintenance hands-on ability to practice preventive maintenance
and corrective maintenance (such as a Cavity Access Machine replacement)
• Maintenance training scheduled for summer 2014
Training Facility Simulator Courses for Control Room Operators
kicks off April 2014
• Started in April – all four Control Room crews in progress to complete in
2015
Final hiring wave in progress for O&M staff
• March-July 2014 brings on remaining plant personnel
7