Inspection and Testing of Wiring Installation:
❖ After completing the new wiring or extending the old wiring, it should be inspected
and tested as per IE rules before connecting it to the supply. This test is being done
by using meggar of 500V.
❖ The following tests should be carried out on domestic wiring installation:
► Continuity Test/ Open Circuit Test
► Insulation Resistance Test between conductors
► Resistance Test between conductor and Earth
► Earth Continuity test
► Polarity Test
1.) Continuity Test/ Open Circuit Test:
► By performing this test, it is being checked whether any conductor of wire
is broken or not or is separated from any terminal or not. short circuit
between any wires is also being checked.
► Steps to perform this test:
1.Main MCB/switch is kept OFF. All fuses are being removed.
2. All lamps are kept in all holders, all switches are kept OFF, three pin
socket is shorted with small piece of wire. Regulators are kept in ON
position. All MCBs of distribution board/ sub circuits are kept ON.
3. E & L terminals of Megger are connected to outgoing terminals of
Main MCB.
4. Megger is being operated at rated speed and after that On the all
switches one by one and take the readings. If Megger shows Zero
Reading at ON position and Infinite Reading at OFF position then
continuity of wires is said to be OK. if in both positions if shows
Infinite reading then wire is said to be open and if it shows zero
reading in both positions the wire is said to be short circuited.
5. after performing this test, shorten links should be taken off.
2.) Insulation Resistance Test between conductors:
► By performing this test, Insulation quality of conducting wires is being
checked. Further it is also being checked whether any conductors are
shorten due to any reason or not.
► Steps to perform this test:
1.Main MCB/switch is kept OFF. all fuses are being removed.
2. All lamps and loads are removed from holders and sockets
respectively. all switches are kept ON. Regulators are kept in ON
position. All MCBs of distribution board/ sub circuits are kept ON.
3. E & L terminals of Megger are connected to outgoing terminals of
Main MCB.
4. Megger reading should not be less than 1 MΩ. According to I.E. rules
Insulation Resistance =
3.)Resistance Test between conductor and Earth:
► By performing this test, it is being checked whether Insulation of
conducting wire is broken or not or conducting wire is separated from any
terminal and whether it came in contact with metal parts or not.
► Steps to perform this test:
1. Main MCB/switch is kept OFF. all fuses are being removed.
2. All lamps are kept in all holders, all switches are kept ON, three pin
socket is shorted with small piece of wire. Regulators are kept in ON
position. All MCBs of distribution board/ sub circuits are kept ON.
3. Outgoing terminals of Main MCB are being shorted with wire and it is
connected with L terminal of Megger and E terminal of Megger is
connected to Earth.
4. Megger reading should not be less than 1 MΩ. According to I.E. rules
Insulation Resistance =
 after performing this test, shorten links should be taken off.
4.) Earth Continuity test:
► By doing this test, the continuity of Earthing Electrode is being checked
and also it is being checked that all metal parts are earthed or not.
► Steps to perform this test:
1. Megger’s E terminal is connected to earth and L terminal is connected
with Earth terminal of all sockets simultaneously. If Megger shows
Zero Reading then earth continuity is said to be OK.
2. Megger’s E terminal is connected to earth and L terminal is connected
all metal parts simultaneously. If Megger shows Zero Reading then
earth continuity is said to be OK. otherwise Earthing is not Ok.
5.) Polarity Test:
► According to I.E. rule, switch should be always kept in Phase wire. Which
is being checked by this test.
► Steps to perform this test:
1. Main MCB/switch is kept OFF. all fuses are being removed.
2. All switches are kept OFF.
3. Phase wire of the outgoing Terminal of Main switch/MCB is connected
with one terminal of Megger. Other Terminal of Megger is being
lengthen by wire and it is being checked at all switches’ incoming
terminal. and then by operating Megger at rated speed, reading is
taken.
4. if Megger shows Zero Reading then Polarity of the switch is said to be
OK. Otherwise connection should have to be interchanged.
THANK YOU

More Related Content

What's hot

Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And FunctionsNitendra Kumar Singh
 
Unit 03 Construction & Operation of Watt meter & Energy meter
Unit   03 Construction & Operation of Watt meter & Energy meterUnit   03 Construction & Operation of Watt meter & Energy meter
Unit 03 Construction & Operation of Watt meter & Energy meterPremanandDesai
 
Electrical instruments ppt
Electrical instruments pptElectrical instruments ppt
Electrical instruments pptAmey Waghmare
 
Inspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesInspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesLeonardo ENERGY
 
Circuit Breakers for Low Voltage Applications
Circuit Breakers for Low Voltage ApplicationsCircuit Breakers for Low Voltage Applications
Circuit Breakers for Low Voltage ApplicationsIsham Rashik
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system componentsPrasanna Rao
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
Experiment no. 5
Experiment no. 5Experiment no. 5
Experiment no. 5Suhas Chate
 
Introduction to active and passive components
Introduction to active and passive components Introduction to active and passive components
Introduction to active and passive components DeependraGoswami
 
Basic Electrical
Basic Electrical Basic Electrical
Basic Electrical ddsshukla
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformerROOPAL PANCHOLI
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionAman Ansari
 
Electrodynamometer type instrument.pptx
Electrodynamometer type instrument.pptxElectrodynamometer type instrument.pptx
Electrodynamometer type instrument.pptxChandraPrakash715640
 
Automatic transfer switch (ats)
Automatic transfer switch (ats)Automatic transfer switch (ats)
Automatic transfer switch (ats)Mark Anthony Enoy
 
Circuit Analysis – DC Circuits
Circuit Analysis – DC CircuitsCircuit Analysis – DC Circuits
Circuit Analysis – DC CircuitsVesa Linja-aho
 

What's hot (20)

Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And Functions
 
Unit 03 Construction & Operation of Watt meter & Energy meter
Unit   03 Construction & Operation of Watt meter & Energy meterUnit   03 Construction & Operation of Watt meter & Energy meter
Unit 03 Construction & Operation of Watt meter & Energy meter
 
Insulation Resistance Test
Insulation Resistance TestInsulation Resistance Test
Insulation Resistance Test
 
Electrical instruments ppt
Electrical instruments pptElectrical instruments ppt
Electrical instruments ppt
 
Inspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesInspection of Electrical Installations in Homes
Inspection of Electrical Installations in Homes
 
Circuit Breakers for Low Voltage Applications
Circuit Breakers for Low Voltage ApplicationsCircuit Breakers for Low Voltage Applications
Circuit Breakers for Low Voltage Applications
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Experiment no. 5
Experiment no. 5Experiment no. 5
Experiment no. 5
 
Panel designing
Panel designingPanel designing
Panel designing
 
Introduction to active and passive components
Introduction to active and passive components Introduction to active and passive components
Introduction to active and passive components
 
Basic Electrical
Basic Electrical Basic Electrical
Basic Electrical
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
 
Contactor
ContactorContactor
Contactor
 
Electrodynamometer type instrument.pptx
Electrodynamometer type instrument.pptxElectrodynamometer type instrument.pptx
Electrodynamometer type instrument.pptx
 
Energy meter
Energy meterEnergy meter
Energy meter
 
Automatic transfer switch (ats)
Automatic transfer switch (ats)Automatic transfer switch (ats)
Automatic transfer switch (ats)
 
Circuit Analysis – DC Circuits
Circuit Analysis – DC CircuitsCircuit Analysis – DC Circuits
Circuit Analysis – DC Circuits
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 

Similar to Inspection and testing of wiring installation

Undertake basic electrical tasks
Undertake basic electrical tasksUndertake basic electrical tasks
Undertake basic electrical taskscatherinelindsay
 
Armature & field coil inspection
Armature & field coil inspectionArmature & field coil inspection
Armature & field coil inspectioncoolabhi1236
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenancePremanandDesai
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
MEASUREMENT OF RESISTANCE
MEASUREMENT OF RESISTANCEMEASUREMENT OF RESISTANCE
MEASUREMENT OF RESISTANCESARUNKUMARKP
 
Motor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarMotor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarjavid iqbal sodagar
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - labPremanandDesai
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Measurement of insulation resistance javid iqbal sodagar converted
Measurement of insulation resistance javid iqbal sodagar convertedMeasurement of insulation resistance javid iqbal sodagar converted
Measurement of insulation resistance javid iqbal sodagar convertedjavid iqbal sodagar
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxDrNiveditaSingh3
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.Geetesh Verma
 
testing-grounding-systems.ppt
testing-grounding-systems.ppttesting-grounding-systems.ppt
testing-grounding-systems.pptBayuAnggoro46
 
Cable preparation in CCTV
Cable preparation in CCTVCable preparation in CCTV
Cable preparation in CCTVhepzijustin
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxRAJKIRANR3
 

Similar to Inspection and testing of wiring installation (20)

Electrical testing
Electrical testingElectrical testing
Electrical testing
 
Undertake basic electrical tasks
Undertake basic electrical tasksUndertake basic electrical tasks
Undertake basic electrical tasks
 
Armature & field coil inspection
Armature & field coil inspectionArmature & field coil inspection
Armature & field coil inspection
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenance
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
MEASUREMENT OF RESISTANCE
MEASUREMENT OF RESISTANCEMEASUREMENT OF RESISTANCE
MEASUREMENT OF RESISTANCE
 
Motor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarMotor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagar
 
Testing of cb
Testing of cbTesting of cb
Testing of cb
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
HVDCT LAB MANUAL.docx
HVDCT LAB MANUAL.docxHVDCT LAB MANUAL.docx
HVDCT LAB MANUAL.docx
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Measurement of insulation resistance javid iqbal sodagar converted
Measurement of insulation resistance javid iqbal sodagar convertedMeasurement of insulation resistance javid iqbal sodagar converted
Measurement of insulation resistance javid iqbal sodagar converted
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
testing-grounding-systems.ppt
testing-grounding-systems.ppttesting-grounding-systems.ppt
testing-grounding-systems.ppt
 
Cable preparation in CCTV
Cable preparation in CCTVCable preparation in CCTV
Cable preparation in CCTV
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Inspection and testing of wiring installation

  • 1. Inspection And Testing of Wiring Installation By Abhisek Bhandari
  • 2. Inspection and Testing of Wiring Installation: ❖ After completing the new wiring or extending the old wiring, it should be inspected and tested as per IE rules before connecting it to the supply. This test is being done by using meggar of 500V. ❖ The following tests should be carried out on domestic wiring installation: ► Continuity Test/ Open Circuit Test ► Insulation Resistance Test between conductors ► Resistance Test between conductor and Earth ► Earth Continuity test ► Polarity Test
  • 3. 1.) Continuity Test/ Open Circuit Test:
  • 4. ► By performing this test, it is being checked whether any conductor of wire is broken or not or is separated from any terminal or not. short circuit between any wires is also being checked. ► Steps to perform this test: 1.Main MCB/switch is kept OFF. All fuses are being removed. 2. All lamps are kept in all holders, all switches are kept OFF, three pin socket is shorted with small piece of wire. Regulators are kept in ON position. All MCBs of distribution board/ sub circuits are kept ON. 3. E & L terminals of Megger are connected to outgoing terminals of Main MCB. 4. Megger is being operated at rated speed and after that On the all switches one by one and take the readings. If Megger shows Zero Reading at ON position and Infinite Reading at OFF position then continuity of wires is said to be OK. if in both positions if shows Infinite reading then wire is said to be open and if it shows zero reading in both positions the wire is said to be short circuited. 5. after performing this test, shorten links should be taken off.
  • 5. 2.) Insulation Resistance Test between conductors:
  • 6. ► By performing this test, Insulation quality of conducting wires is being checked. Further it is also being checked whether any conductors are shorten due to any reason or not. ► Steps to perform this test: 1.Main MCB/switch is kept OFF. all fuses are being removed. 2. All lamps and loads are removed from holders and sockets respectively. all switches are kept ON. Regulators are kept in ON position. All MCBs of distribution board/ sub circuits are kept ON. 3. E & L terminals of Megger are connected to outgoing terminals of Main MCB. 4. Megger reading should not be less than 1 MΩ. According to I.E. rules Insulation Resistance =
  • 7. 3.)Resistance Test between conductor and Earth:
  • 8. ► By performing this test, it is being checked whether Insulation of conducting wire is broken or not or conducting wire is separated from any terminal and whether it came in contact with metal parts or not. ► Steps to perform this test: 1. Main MCB/switch is kept OFF. all fuses are being removed. 2. All lamps are kept in all holders, all switches are kept ON, three pin socket is shorted with small piece of wire. Regulators are kept in ON position. All MCBs of distribution board/ sub circuits are kept ON. 3. Outgoing terminals of Main MCB are being shorted with wire and it is connected with L terminal of Megger and E terminal of Megger is connected to Earth. 4. Megger reading should not be less than 1 MΩ. According to I.E. rules Insulation Resistance =  after performing this test, shorten links should be taken off.
  • 10. ► By doing this test, the continuity of Earthing Electrode is being checked and also it is being checked that all metal parts are earthed or not. ► Steps to perform this test: 1. Megger’s E terminal is connected to earth and L terminal is connected with Earth terminal of all sockets simultaneously. If Megger shows Zero Reading then earth continuity is said to be OK. 2. Megger’s E terminal is connected to earth and L terminal is connected all metal parts simultaneously. If Megger shows Zero Reading then earth continuity is said to be OK. otherwise Earthing is not Ok.
  • 12. ► According to I.E. rule, switch should be always kept in Phase wire. Which is being checked by this test. ► Steps to perform this test: 1. Main MCB/switch is kept OFF. all fuses are being removed. 2. All switches are kept OFF. 3. Phase wire of the outgoing Terminal of Main switch/MCB is connected with one terminal of Megger. Other Terminal of Megger is being lengthen by wire and it is being checked at all switches’ incoming terminal. and then by operating Megger at rated speed, reading is taken. 4. if Megger shows Zero Reading then Polarity of the switch is said to be OK. Otherwise connection should have to be interchanged.