The document provides an overview of project management concepts and the critical path method for scheduling projects. It discusses that project management involves applying knowledge, skills, and tools to project activities to meet stakeholder needs on time and within budget. The critical path method is a scheduling technique that identifies the longest continuous chain of dependent tasks in a project as the critical path, where any delays will impact the overall project completion date. The document outlines the key steps and elements of critical path method scheduling, including defining activities, estimating durations, sequencing tasks, and determining start dates, finish dates, and float.
3. a set of interrelated activities to achieve a specific
goal …
in a specific timeframe ...
to create a unique product or service
A project is a temporary endeavor which has
a definite beginning and a definite end
3
4. 4
PM is the application of:
KNOWLEDGE
SKILLS
TOOLS & TECHNIQUES
to project activities in order to meet or exceed
stakeholders need & expectations from a project
i.e. 75% art and 25% science.
5. Phases are generally sequential
Phases are connected from the beginning of a
project to its end
Phases are concluded with acceptance of
deliverables
Not uncommon to have overlapping phases
Generic
JKR Plan Design Procurement Construction Hand Over
Concept Develop Execute Finalise
5
6. 1. Assembling an incompetent and incompatible team
2. Lack of common project goals
3. Poor leadership at all levels
4. Poor planning
5. Failure to identify, document & track requirements –
poor monitoring and control
6. Poor communication
7. Bad reporting of progress
8. Inadequate or misused methods – wrong tools
9. Insufficient funds
6
7. JKR Project Lifecycle – 5 Phases
PLAN CONSRUCT FINALISE
PROCURE
DESIGN
Project Manager / HOPT
Design Manager / HODTs SO & SO Representative
Pre Construction Post Construction
7
11. PWD Form 203 (Rev.2007)
11
PWD Form DB (Rev.2007)
12. Although they are allied disciplines, but are not the
same
Project planning involves creating project
development strategy, which include;
Overall strategy how works will be broken down for
control
How the control is to be managed
What construction method to be employed
The zones of operation and their interface
Interface between the various participants
Strategy to maximise efficiency with respect to cost and
time
Risk management
12
13. Scheduling is a mixture of art and science, involving
interpretation of the results of project planning by
using appropriate software tools and techniques to
ascertain;
Start and finish dates of activities
Method of sequencing one or more activities in relation to
other activities
Duration of the activities
Who will perform the activities
Resources to be applied to the activities
Communication and reporting formats, timing, etc
13
16. 16
Keep project
teams
organized
Is project on
schedule
(time &
cost)?
What happen
if change is
introduced?
Minimise
wastage/rework
Optimise usage
of resources
More effective
project progress
reporting
17. Contractor
Basis to estimate resources (men, machines,
materials)
Cash flow throughout project duration
Basis for execution, coordination and monitoring &
controlling of works
Basis/evidence to support progress claim and
Extension of Time application
17
18. Superintending Officer
Basis to set project contract baseline (time, scope &
cost)
Basis for monitoring & controlling progress of works
18
21. 21
Guideline contains work program components and
items that needs to be included in a work program
Guideline consists of checklist for assessing work
program submitted by contractor /consultant for
approval
Provide guidance for the contractor’s in
preparation of work program
24. CPM is
It
Critical path is
Any delay
24
25. CPM is mathematical method to determine project
finish date base on sequencing and activity duration
It use network analysis to identify activities in the
critical path
Critical path is the longest path in the network or
path with zero total slack
Any delay in completing the tasks on critical path will
result in project delay unless appropriate measure is
taken to bring back the progress on track
25
26. CPM consists of three core steps:
1. Planning
2. Analyzing and scheduling
3. Controlling tasks
Two basic method of CPM diagrams:
1. Arrow Diagram Method (ADM)
2. Precedence Diagram Method (PDM)
26
27. Arrow Diagram Method:
Activities are represented by arrows
Also known as the activity-on-arrow (AOA)
Uses dummy activity (dotted line) to show logic
Only has finish to start relationship
27
28. Precedence Diagram Method:
Activities are represented as nodes (boxes)
Also known as the activity-on-node (AON)
Arrow shows the relationship
Have 4 types of relationships; FS, FF, SS, SF
28
29. Key elements include attributes such as:
Early start date (ES)
Late start date (LS)
Early finish date (EF)
Late finish date (LF)
Slack or Float
Total Float –
Free Float –
29
30. Key elements include attributes such as:
Early start date (ES)
Late start date (LS)
Early finish date (EF)
Late finish date (LF)
Slack or Float
Total Float – Amount of time a task can slip without affecting
project’s finish date
Free Float – Amount of time a task can slip without causing
delay to the subsequent tasks
30
31. 2 steps:
Forward pass
Backward pass
Total slack
31
ES Dur EF
Description
LS
Total
Slack
LF
32. 2 steps:
Forward pass
ES = EFpre + 1
Backward pass
LF = LSsuc - 1
Total slack
32
ES Dur EF
Description
LS
Total
Slack
LF EF = ES + Dur -1
LS = LF – Dur + 1
= LF – EF or
= LS – ES