SlideShare a Scribd company logo
1 of 45
Power Factor Correction
of
Toitskraal 11kV feeder
Kruger Greyvenstein
Project initiator: Sydney Mamosadi
1 July 2014
2
CONTENT
• Introduction
• Background
• Problem Statement
• Solution
• Specifications
• Scope of work
• Simulations & Results
• Costing
• Return on investment
• Conclusion
• Recommendations
Kruger Greyvenstein
3
Introduction
• Some lines on our Distribution Networks have bad power factors,
meaning they have a lot of inductive loads and therefore consumes a lot
of reactive energy.
• The reactive energy must be supplied from the source (which in Dx case
is Tx) and be transmitted through our network. The effect of the reactive
energy on our networks are:
• Higher line loading (Higher reactive currents)
• Increased voltage drop across lines.
• More technical losses
• Shorten lifetime of apparatus such as TRF’s
• The idea is to minimize the reactive power as much as possible
Kruger Greyvenstein
4
Background
Project: Power factor correction of the 11kV Toitskraal feeder:
Substation Background:
•Toitskraal 22/11kV substation.
•It is equipped with 3 × 5MVA 22/11kV TRF’s
•3 × 22kV incoming feeders: Marble Hall 1, Marble Hall 2 and Valschfontein
•2 × 11kV outgoing feeders: Toitskraal & Elandsdrift
Kruger Greyvenstein
5
Background:
Kruger Greyvenstein
Toitskraal subToitskraal sub
6
Background:
Kruger Greyvenstein
7
Problem Statement:
11kV Toitskraal feeder:
•The Feeder have an peak load power factor of 0.78 (lagging)
•The backbone close to the substation is overloaded at certain points during
peak loading
•The line is feeding an agricultural area
•Loads mostly consists of pumps and center pivot irrigation systems
• Motors used in those implements are one of the main reasons for high
reactive energy consumption.
Kruger Greyvenstein
8
Problem Statement:
Kruger Greyvenstein
ToitskraalToitskraal
9
Problem Statement:
Phasor Diagram:
Kruger Greyvenstein
38°38°
PF = 0.78PF = 0.78
10
Problem Statement:
PF correction requirements:
•MV 90 data. Period: (01/03/2013 – 01/03/2014):
According to the standard: Network Planning Guideline for Shunt Capacitors, power
factor correction is necessary if:
•PF < 0.85
•Qmax ≥ 300 kVAr
•Qmin ≥ 150 kVAr
Kruger Greyvenstein
P (KW) Q (KVAr) S (KVA)
max 3670 2600 4500
min 750 300 900
average 1368.949 1038.212 1757.675
Requirements for PF
correction
Requirements for PF
correction
11
Solution
• Static VAr Compensators
• Capacitor bank inside the substation
• Pole mounted Shunt Capacitor banks
Kruger Greyvenstein
12
Solution
Best option:
Is to install Pole mounted Shunt Capacitor banks on the feeder for power factor
correction.
Advantages:
•Reduce voltage drop on the feeder
•Pole mounted Capacitors supply reactive energy close to the load.
•Reduce the KVAr as well as the KVA from the source
•Reduce loading on lines, and transformers
•Reduce losses on MV network as well as HV network
•In a substation with multiple MV feeders, if one pole mounted cap bank fail, the effect is
minimal. If there is one cap bank on the busbar of a substation and it fails, then everything
is lost.
Kruger Greyvenstein
13
Cap bank
Kruger Greyvenstein
Source
(Sub)
Source
(Sub)
14
Solution
MV Pole mounted switched shunt capacitor bank
Kruger Greyvenstein
15
Specifications
1) Capacitor bank Type:
Two types:
1. Fixed Capacitor banks
2. Switched Capacitor banks
A Combination of the two types will be used:
• A Fixed shunt Capacitor bank for compensation of the low loading period.
• A Switched shunt Capacitor bank can switch in at a certain level to help
compensate for the High Loading period.
Kruger Greyvenstein
16
Specifications
2) Capacitor bank sizes:
Low Loading compensation:
•Use 1 × 500 kVAr, fixed capacitor bank for low load compensation.
Peak load compensation:
•Use 1 × 750 kVAr, switched capacitor bank for Peak load compensation.
Kruger Greyvenstein
17
Specifications
3) Capacitor bank location:
•A shunt capacitor bank must be installed as close as possible to the load for max
effectiveness.
•On an MV feeder with a lot of loads (evenly distributed) the placement can be as
follow:
• Qfixed – Approximately half way down the feeder
• Qswitched – Approximately 2/3 down the feeder
•The capacitor banks are placed such to have the best possible effect on the voltage
profile.
Kruger Greyvenstein
18
Specifications
Kruger Greyvenstein
Capacitor Bank -Capacitor Bank -
1 (Fixed)1 (Fixed)
3 (switched)3 (switched)
19
Scope of Work
• Install 1 × 500 KVAr, 11kV Pole mounted fixed shunt capacitor bank on pole
number TOT44
• Install 1 × 750 KVAr, 11kV Pole mounted switched shunt capacitor bank on pole
number TOT54/21
• Install pole mounted capacitor banks on existing pole structures
• Connect capacitor banks in parallel with overhead lines
Kruger Greyvenstein
20
Simulations & Results
Toitskraal 11kV feeder Load Profile:
High Loading Scenario: S = 4500 KVA
Low Loading Scenario: S = 600 KVA
Kruger Greyvenstein
21
Simulations & Results
Toitskraal 11kV feeder Load Profile:
High Loading Scenario: S = 2600 KVA
Low Loading Scenario: S = 300 KVA
Kruger Greyvenstein
22
Simulations & Results
Voltage Profiles:
Peak Loading:
Existing Voltage Profile: New Voltage Profile:
Kruger Greyvenstein
Distance (km)Distance (km) Distance (km)Distance (km)
1.051.05
0.950.95
1.051.05
0.950.95
23
Simulations & Results
Effect of switched Cap bank:
Just before switching: Just after switching:
Max voltage rise = 1.66 %
Kruger Greyvenstein
Voltage rise ≤ 5 % ???Voltage rise ≤ 5 % ???
24
Simulations & Results
Worst case voltage rise:
Load = 0.2 MVA with the fixed capacitor bank in service
Kruger Greyvenstein
1.051.05
0.950.95
25
Simulations & Results
Line Loadings: (Peak load)
Existing: After cap bank installation:
Kruger Greyvenstein
Line Loadings Total Apparent Power
% MVA
110.2685 4.500961
99.67498 4.066381
61.28087 1.773238
58.49818 1.691852
56.07303 2.280289
55.5811 2.240934
55.57835 2.255222
54.83763 2.172903
54.8356 2.179777
41.62442 1.688606
31.73271 1.286541
31.24099 1.26635
27.50092 1.108903
Line Loading Total Apparent Power
% MVA
93.10929 3.800553
82.91329 3.38289
61.23579 1.773208
58.4551 1.691823
43.14478 1.755841
42.73481 1.729538
42.73446 1.736708
42.12045 1.685888
42.12024 1.689293
41.59377 1.688581
31.70923 1.286519
31.21788 1.266329
27.48053 1.108891
26
Simulations & Results
Effect of capacitor banks on Load Profile:
Saving of 700kVA at peak load.
Kruger Greyvenstein
Min LoadMin Load
Max LoadMax Load
Switched Cap
bank switches in
Switched Cap
bank switches in
27
Simulations & Results
Technical losses:
High Loading:
Kruger Greyvenstein
Total technical
losses saved =
26.42kW
Total technical
losses saved =
26.42kW
Before After: Saved:
Total Losses (kW) Losses (total) (kW) Losses (kW)
0.78677 0.47264 0.31413 26.4 kW
0.29626 0.17797 0.11829
10.2697 6.10054 4.16916
39.27777 23.62674 15.65103 103
0.831 0.51671 0.31429 76.6
1.79652 1.10541 0.69111
3.89029 2.32922 1.56107
3.92558 2.35474 1.57084
7.60112 4.55907 3.04205
1.09612 0.67443 0.42169
0.62016 0.61774 0.00242
0.37412 0.44714 -0.07302
7.45818 8.90733 -1.44915
1.1766 1.50331 -0.32671
5.44805 5.42675 0.0213
0.47577 0.47391 0.00186
2.18447 2.1759 0.00857
0.33384 0.33253 0.00131
1.61049 1.60416 0.00633
0.25054 0.24956 0.00098
0 0.02758 -0.02758
0 0.02666 -0.02666
0 0.02654 -0.02654
2.83566 1.84561 0.99005
0.09286 0.07835 0.01451
0.12125 0.10229 0.01896
0.09257 0.08147 0.0111
0.28011 0.27112 0.00899
0.24497 0.26479 -0.01982
0.17485 0.32183 -0.14698
0.15182 0.18643 -0.03461
1.09164 1.43769 -0.34605
0.11045 0.17007 -0.05962
Total Losses saved =
Losses Before =
Losses After =
28
Costing:
Kruger Greyvenstein
Microsoft Excel
97-2003 Worksheet
29
Return on investment:
• Because there is a return on the investment, the Total costing of the
project can be worked backed in time because of the saving:
• 700 kVA will be saved during peak loading
• The reduced load will free up capacity for additional customers on the feeder
• Extend the lifetime of apparatus for ex. TRF’s
• The technical losses will be reduced with 26.4 kW during peak loading
• The customer will still pay exactly the same; the saving will be only on
ESKOM’s side.
Kruger Greyvenstein
30
Return on investment:
Annual Technical losses saving:
Kruger Greyvenstein
31
Return on investment:
Annual Reactive Energy saving:
Kruger Greyvenstein
C:UsersGreyveJK
Documents1) Work1) EI
32
Return on investment:
Total annual project saving:
•The total project cost can be worked back in 4.65 months.
Kruger Greyvenstein
33
Conclusion
• Power factor correction of this feeder results in a better optimized network
• The installation of Shunt Capacitor Banks on this MV feeder have multiple
advantages on the network
• It can serve as a perfect temporary solution for the overloading and under
voltages, but must be used as a permanent solution for bad power factors
• A whole lot of money can be saved by implementing this project (± 3
Million per year) after the project cost is worked back
• If power factor correction can be done for all our MV feeders ESKOM can
save a lot of money
Kruger Greyvenstein
34
Recommendations
• As Harmonics on the network presents significant risk to capacitors, an
independent Harmonic recording is essential before the capacitor banks
be installed.
• Before implementing this project do power factor correction of the
Toitskraal – Elandsdrift 11kV feeder as well. Otherwise the capacitor
banks on the Toitskraal feeder will supply the Elandsdrift feeder as well
which means that the desired effect on the Toitskraal fdr won’t take place.
Kruger Greyvenstein
Thank you
36
Cap bank
Kruger Greyvenstein
Source
(Sub)
Source
(Sub)
37
Simulations & Results
Fault levels:
Kruger Greyvenstein
Single Phase:   3 - Phase:
11kV 22kV   11kV 22kV
Min  3.25 2.447     5.04 7.67 
Max  3.258 2.46     5.06  7.87
38
Simulations & Results
Toitskraal 11kV fdr Load Profile:
Kruger Greyvenstein
39
Simulations & Results
Load Profile:
Kruger Greyvenstein
40
Introduction
Kruger Greyvenstein
41
Specifications
High Loading compensation:
•Use 1 × 750 KVAr, switched capacitor banks for high load compensation, at two
different locations on the feeder.
Kruger Greyvenstein
42
Scope of work
1) Capacitor bank Type:
• Fixed shunt Capacitor bank (Pole Mounted):
• Switched shunt Capacitor bank:
1) Fixed Capacitor bank (Pole Mounted):
Kruger Greyvenstein
Advantages Disadvantages
• Space efficient (pole mounted)
• Not expensive
• Easy installation (single pole structure)
• Low installation cost (single pole
structure)
• Low maintenance
• Can’t switch in and out automatically
• May result in overcompensation during
low loading periods resulting in over
voltages and increased system losses
43
Scope of work
2) Switching Capacitor bank (Pole mounted):
Kruger Greyvenstein
Advantages Disadvantages
• Sufficient compensation during high
loading periods
• Reduce compensation during low
loading periods to prevent
overcompensation.
• Automatically switch capacitors in
and out to maintain PF limits
• Space efficient (pole mounted)
• Low installation cost (single pole
structure)
• Low maintenance
• More expensive
• More complicated installation
44
Scope of work
Conclusion:
A Combination of the two can be used:
•A Fixed Capacitor bank for compensation of the low loading period.
•A Switched Capacitor bank can switch in at a certain level to help compensate for
the High Loading period.
All formulas is according to the standard: Network Planning Guidelines for shunt capacitors
Kruger Greyvenstein
45
Simulations & Results
Voltage Profiles:
High Loading:
Existing Voltage Profile: New Voltage Profile:
Kruger Greyvenstein
1.051.05
0.950.95 0.950.95
1.051.05

More Related Content

What's hot

Reactive Power : Problems and Solutions
Reactive Power : Problems and SolutionsReactive Power : Problems and Solutions
Reactive Power : Problems and SolutionsAbhinav Dubey
 
Line commutated converters
Line commutated convertersLine commutated converters
Line commutated convertersSrashti Vyas
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Rohini Haridas
 
Automatic Power Factor Detection And Correction using Arduino
Automatic Power Factor Detection And Correction using ArduinoAutomatic Power Factor Detection And Correction using Arduino
Automatic Power Factor Detection And Correction using ArduinoSouvik Dutta
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSKarthik Bharadwaj
 
Micro computer control of dc drive
Micro computer control of dc driveMicro computer control of dc drive
Micro computer control of dc driveraviarmugam
 
Lv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizingLv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizingAsif Eqbal
 
Synchronous condensers
Synchronous condensersSynchronous condensers
Synchronous condensersujvnl
 
Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power controlCaner Göksel Sonuzun
 
Power system protection
Power system protectionPower system protection
Power system protectionAnu Priya
 
Unit commitment in power system
Unit commitment in power systemUnit commitment in power system
Unit commitment in power systemAbrar Ahmed
 
Flexible Ac Transmission System
Flexible Ac Transmission SystemFlexible Ac Transmission System
Flexible Ac Transmission SystemBrunda R
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLsurendra rawat
 

What's hot (20)

Reactive Power : Problems and Solutions
Reactive Power : Problems and SolutionsReactive Power : Problems and Solutions
Reactive Power : Problems and Solutions
 
Line commutated converters
Line commutated convertersLine commutated converters
Line commutated converters
 
Facts lectures-2014
Facts lectures-2014Facts lectures-2014
Facts lectures-2014
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)
 
Automatic Power Factor Detection And Correction using Arduino
Automatic Power Factor Detection And Correction using ArduinoAutomatic Power Factor Detection And Correction using Arduino
Automatic Power Factor Detection And Correction using Arduino
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTS
 
Micro computer control of dc drive
Micro computer control of dc driveMicro computer control of dc drive
Micro computer control of dc drive
 
Inverters
InvertersInverters
Inverters
 
FACT devices
FACT devicesFACT devices
FACT devices
 
Sepic
SepicSepic
Sepic
 
Lv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizingLv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizing
 
Synchronous condensers
Synchronous condensersSynchronous condensers
Synchronous condensers
 
Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power control
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 
Unit commitment
Unit commitmentUnit commitment
Unit commitment
 
Power system protection
Power system protectionPower system protection
Power system protection
 
Unit commitment in power system
Unit commitment in power systemUnit commitment in power system
Unit commitment in power system
 
Flexible Ac Transmission System
Flexible Ac Transmission SystemFlexible Ac Transmission System
Flexible Ac Transmission System
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCL
 
Gauss seidel method
Gauss seidel methodGauss seidel method
Gauss seidel method
 

Similar to Power Factor correction of Toitskraal 11kV feeder

Capacitor installation and re conductoring
Capacitor installation and re conductoringCapacitor installation and re conductoring
Capacitor installation and re conductoringYusuf A. KHALIL
 
Morelia workshop presentation william ross
Morelia workshop presentation william rossMorelia workshop presentation william ross
Morelia workshop presentation william rossBenito Ortiz Bejar
 
Design of Synchronverter based Microgrid
Design of Synchronverter based MicrogridDesign of Synchronverter based Microgrid
Design of Synchronverter based MicrogridSomsubhra Ghosh
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptxPoojaAnupGarg
 
Operational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaOperational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaSmarter Grid Solutions
 
SungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_PresentationSungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_PresentationSung Pil Oe
 
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUESpower factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUESEMERSON EDUARDO RODRIGUES
 
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeedAnalyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeedAushiq Ali Memon
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Parker Hannifin Corporation
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMASWATHYSANAND1
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...f95346
 
Flexible ac transmission using svc 16000
Flexible ac transmission using svc 16000Flexible ac transmission using svc 16000
Flexible ac transmission using svc 16000Vivek Bhakta
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptxTalhaAbdulRehman2
 

Similar to Power Factor correction of Toitskraal 11kV feeder (20)

Capacitor installation and re conductoring
Capacitor installation and re conductoringCapacitor installation and re conductoring
Capacitor installation and re conductoring
 
Ssfcl
SsfclSsfcl
Ssfcl
 
Morelia workshop presentation william ross
Morelia workshop presentation william rossMorelia workshop presentation william ross
Morelia workshop presentation william ross
 
Design of Synchronverter based Microgrid
Design of Synchronverter based MicrogridDesign of Synchronverter based Microgrid
Design of Synchronverter based Microgrid
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
Operational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaOperational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and America
 
SungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_PresentationSungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_Presentation
 
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUESpower factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
 
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeedAnalyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeed
 
CESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORTCESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORT
 
Viva
VivaViva
Viva
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
 
Power factor improvement
Power factor improvementPower factor improvement
Power factor improvement
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
 
Flexible ac transmission using svc 16000
Flexible ac transmission using svc 16000Flexible ac transmission using svc 16000
Flexible ac transmission using svc 16000
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
 
Solar ppt
Solar pptSolar ppt
Solar ppt
 
4771_doc_1
4771_doc_14771_doc_1
4771_doc_1
 
Energy Storage solutions
Energy Storage solutionsEnergy Storage solutions
Energy Storage solutions
 

Power Factor correction of Toitskraal 11kV feeder

  • 1. Power Factor Correction of Toitskraal 11kV feeder Kruger Greyvenstein Project initiator: Sydney Mamosadi 1 July 2014
  • 2. 2 CONTENT • Introduction • Background • Problem Statement • Solution • Specifications • Scope of work • Simulations & Results • Costing • Return on investment • Conclusion • Recommendations Kruger Greyvenstein
  • 3. 3 Introduction • Some lines on our Distribution Networks have bad power factors, meaning they have a lot of inductive loads and therefore consumes a lot of reactive energy. • The reactive energy must be supplied from the source (which in Dx case is Tx) and be transmitted through our network. The effect of the reactive energy on our networks are: • Higher line loading (Higher reactive currents) • Increased voltage drop across lines. • More technical losses • Shorten lifetime of apparatus such as TRF’s • The idea is to minimize the reactive power as much as possible Kruger Greyvenstein
  • 4. 4 Background Project: Power factor correction of the 11kV Toitskraal feeder: Substation Background: •Toitskraal 22/11kV substation. •It is equipped with 3 × 5MVA 22/11kV TRF’s •3 × 22kV incoming feeders: Marble Hall 1, Marble Hall 2 and Valschfontein •2 × 11kV outgoing feeders: Toitskraal & Elandsdrift Kruger Greyvenstein
  • 7. 7 Problem Statement: 11kV Toitskraal feeder: •The Feeder have an peak load power factor of 0.78 (lagging) •The backbone close to the substation is overloaded at certain points during peak loading •The line is feeding an agricultural area •Loads mostly consists of pumps and center pivot irrigation systems • Motors used in those implements are one of the main reasons for high reactive energy consumption. Kruger Greyvenstein
  • 9. 9 Problem Statement: Phasor Diagram: Kruger Greyvenstein 38°38° PF = 0.78PF = 0.78
  • 10. 10 Problem Statement: PF correction requirements: •MV 90 data. Period: (01/03/2013 – 01/03/2014): According to the standard: Network Planning Guideline for Shunt Capacitors, power factor correction is necessary if: •PF < 0.85 •Qmax ≥ 300 kVAr •Qmin ≥ 150 kVAr Kruger Greyvenstein P (KW) Q (KVAr) S (KVA) max 3670 2600 4500 min 750 300 900 average 1368.949 1038.212 1757.675 Requirements for PF correction Requirements for PF correction
  • 11. 11 Solution • Static VAr Compensators • Capacitor bank inside the substation • Pole mounted Shunt Capacitor banks Kruger Greyvenstein
  • 12. 12 Solution Best option: Is to install Pole mounted Shunt Capacitor banks on the feeder for power factor correction. Advantages: •Reduce voltage drop on the feeder •Pole mounted Capacitors supply reactive energy close to the load. •Reduce the KVAr as well as the KVA from the source •Reduce loading on lines, and transformers •Reduce losses on MV network as well as HV network •In a substation with multiple MV feeders, if one pole mounted cap bank fail, the effect is minimal. If there is one cap bank on the busbar of a substation and it fails, then everything is lost. Kruger Greyvenstein
  • 14. 14 Solution MV Pole mounted switched shunt capacitor bank Kruger Greyvenstein
  • 15. 15 Specifications 1) Capacitor bank Type: Two types: 1. Fixed Capacitor banks 2. Switched Capacitor banks A Combination of the two types will be used: • A Fixed shunt Capacitor bank for compensation of the low loading period. • A Switched shunt Capacitor bank can switch in at a certain level to help compensate for the High Loading period. Kruger Greyvenstein
  • 16. 16 Specifications 2) Capacitor bank sizes: Low Loading compensation: •Use 1 × 500 kVAr, fixed capacitor bank for low load compensation. Peak load compensation: •Use 1 × 750 kVAr, switched capacitor bank for Peak load compensation. Kruger Greyvenstein
  • 17. 17 Specifications 3) Capacitor bank location: •A shunt capacitor bank must be installed as close as possible to the load for max effectiveness. •On an MV feeder with a lot of loads (evenly distributed) the placement can be as follow: • Qfixed – Approximately half way down the feeder • Qswitched – Approximately 2/3 down the feeder •The capacitor banks are placed such to have the best possible effect on the voltage profile. Kruger Greyvenstein
  • 18. 18 Specifications Kruger Greyvenstein Capacitor Bank -Capacitor Bank - 1 (Fixed)1 (Fixed) 3 (switched)3 (switched)
  • 19. 19 Scope of Work • Install 1 × 500 KVAr, 11kV Pole mounted fixed shunt capacitor bank on pole number TOT44 • Install 1 × 750 KVAr, 11kV Pole mounted switched shunt capacitor bank on pole number TOT54/21 • Install pole mounted capacitor banks on existing pole structures • Connect capacitor banks in parallel with overhead lines Kruger Greyvenstein
  • 20. 20 Simulations & Results Toitskraal 11kV feeder Load Profile: High Loading Scenario: S = 4500 KVA Low Loading Scenario: S = 600 KVA Kruger Greyvenstein
  • 21. 21 Simulations & Results Toitskraal 11kV feeder Load Profile: High Loading Scenario: S = 2600 KVA Low Loading Scenario: S = 300 KVA Kruger Greyvenstein
  • 22. 22 Simulations & Results Voltage Profiles: Peak Loading: Existing Voltage Profile: New Voltage Profile: Kruger Greyvenstein Distance (km)Distance (km) Distance (km)Distance (km) 1.051.05 0.950.95 1.051.05 0.950.95
  • 23. 23 Simulations & Results Effect of switched Cap bank: Just before switching: Just after switching: Max voltage rise = 1.66 % Kruger Greyvenstein Voltage rise ≤ 5 % ???Voltage rise ≤ 5 % ???
  • 24. 24 Simulations & Results Worst case voltage rise: Load = 0.2 MVA with the fixed capacitor bank in service Kruger Greyvenstein 1.051.05 0.950.95
  • 25. 25 Simulations & Results Line Loadings: (Peak load) Existing: After cap bank installation: Kruger Greyvenstein Line Loadings Total Apparent Power % MVA 110.2685 4.500961 99.67498 4.066381 61.28087 1.773238 58.49818 1.691852 56.07303 2.280289 55.5811 2.240934 55.57835 2.255222 54.83763 2.172903 54.8356 2.179777 41.62442 1.688606 31.73271 1.286541 31.24099 1.26635 27.50092 1.108903 Line Loading Total Apparent Power % MVA 93.10929 3.800553 82.91329 3.38289 61.23579 1.773208 58.4551 1.691823 43.14478 1.755841 42.73481 1.729538 42.73446 1.736708 42.12045 1.685888 42.12024 1.689293 41.59377 1.688581 31.70923 1.286519 31.21788 1.266329 27.48053 1.108891
  • 26. 26 Simulations & Results Effect of capacitor banks on Load Profile: Saving of 700kVA at peak load. Kruger Greyvenstein Min LoadMin Load Max LoadMax Load Switched Cap bank switches in Switched Cap bank switches in
  • 27. 27 Simulations & Results Technical losses: High Loading: Kruger Greyvenstein Total technical losses saved = 26.42kW Total technical losses saved = 26.42kW Before After: Saved: Total Losses (kW) Losses (total) (kW) Losses (kW) 0.78677 0.47264 0.31413 26.4 kW 0.29626 0.17797 0.11829 10.2697 6.10054 4.16916 39.27777 23.62674 15.65103 103 0.831 0.51671 0.31429 76.6 1.79652 1.10541 0.69111 3.89029 2.32922 1.56107 3.92558 2.35474 1.57084 7.60112 4.55907 3.04205 1.09612 0.67443 0.42169 0.62016 0.61774 0.00242 0.37412 0.44714 -0.07302 7.45818 8.90733 -1.44915 1.1766 1.50331 -0.32671 5.44805 5.42675 0.0213 0.47577 0.47391 0.00186 2.18447 2.1759 0.00857 0.33384 0.33253 0.00131 1.61049 1.60416 0.00633 0.25054 0.24956 0.00098 0 0.02758 -0.02758 0 0.02666 -0.02666 0 0.02654 -0.02654 2.83566 1.84561 0.99005 0.09286 0.07835 0.01451 0.12125 0.10229 0.01896 0.09257 0.08147 0.0111 0.28011 0.27112 0.00899 0.24497 0.26479 -0.01982 0.17485 0.32183 -0.14698 0.15182 0.18643 -0.03461 1.09164 1.43769 -0.34605 0.11045 0.17007 -0.05962 Total Losses saved = Losses Before = Losses After =
  • 29. 29 Return on investment: • Because there is a return on the investment, the Total costing of the project can be worked backed in time because of the saving: • 700 kVA will be saved during peak loading • The reduced load will free up capacity for additional customers on the feeder • Extend the lifetime of apparatus for ex. TRF’s • The technical losses will be reduced with 26.4 kW during peak loading • The customer will still pay exactly the same; the saving will be only on ESKOM’s side. Kruger Greyvenstein
  • 30. 30 Return on investment: Annual Technical losses saving: Kruger Greyvenstein
  • 31. 31 Return on investment: Annual Reactive Energy saving: Kruger Greyvenstein C:UsersGreyveJK Documents1) Work1) EI
  • 32. 32 Return on investment: Total annual project saving: •The total project cost can be worked back in 4.65 months. Kruger Greyvenstein
  • 33. 33 Conclusion • Power factor correction of this feeder results in a better optimized network • The installation of Shunt Capacitor Banks on this MV feeder have multiple advantages on the network • It can serve as a perfect temporary solution for the overloading and under voltages, but must be used as a permanent solution for bad power factors • A whole lot of money can be saved by implementing this project (± 3 Million per year) after the project cost is worked back • If power factor correction can be done for all our MV feeders ESKOM can save a lot of money Kruger Greyvenstein
  • 34. 34 Recommendations • As Harmonics on the network presents significant risk to capacitors, an independent Harmonic recording is essential before the capacitor banks be installed. • Before implementing this project do power factor correction of the Toitskraal – Elandsdrift 11kV feeder as well. Otherwise the capacitor banks on the Toitskraal feeder will supply the Elandsdrift feeder as well which means that the desired effect on the Toitskraal fdr won’t take place. Kruger Greyvenstein
  • 37. 37 Simulations & Results Fault levels: Kruger Greyvenstein Single Phase:   3 - Phase: 11kV 22kV   11kV 22kV Min  3.25 2.447     5.04 7.67  Max  3.258 2.46     5.06  7.87
  • 38. 38 Simulations & Results Toitskraal 11kV fdr Load Profile: Kruger Greyvenstein
  • 39. 39 Simulations & Results Load Profile: Kruger Greyvenstein
  • 41. 41 Specifications High Loading compensation: •Use 1 × 750 KVAr, switched capacitor banks for high load compensation, at two different locations on the feeder. Kruger Greyvenstein
  • 42. 42 Scope of work 1) Capacitor bank Type: • Fixed shunt Capacitor bank (Pole Mounted): • Switched shunt Capacitor bank: 1) Fixed Capacitor bank (Pole Mounted): Kruger Greyvenstein Advantages Disadvantages • Space efficient (pole mounted) • Not expensive • Easy installation (single pole structure) • Low installation cost (single pole structure) • Low maintenance • Can’t switch in and out automatically • May result in overcompensation during low loading periods resulting in over voltages and increased system losses
  • 43. 43 Scope of work 2) Switching Capacitor bank (Pole mounted): Kruger Greyvenstein Advantages Disadvantages • Sufficient compensation during high loading periods • Reduce compensation during low loading periods to prevent overcompensation. • Automatically switch capacitors in and out to maintain PF limits • Space efficient (pole mounted) • Low installation cost (single pole structure) • Low maintenance • More expensive • More complicated installation
  • 44. 44 Scope of work Conclusion: A Combination of the two can be used: •A Fixed Capacitor bank for compensation of the low loading period. •A Switched Capacitor bank can switch in at a certain level to help compensate for the High Loading period. All formulas is according to the standard: Network Planning Guidelines for shunt capacitors Kruger Greyvenstein
  • 45. 45 Simulations & Results Voltage Profiles: High Loading: Existing Voltage Profile: New Voltage Profile: Kruger Greyvenstein 1.051.05 0.950.95 0.950.95 1.051.05

Editor's Notes

  1. All the many circles are an indication of the many center pivot irrigation systems each containing many motors/pumps.
  2. Al die tegniese besluite: wat/waar/hoe instaleer
  3. Al die tegniese besluite: wat/waar/hoe instaleer
  4. Al die tegniese besluite: wat/waar/hoe instaleer
  5. Al die tegniese besluite: wat/waar/hoe instaleer
  6. If the load would drop to 0.2 MVA, which is highly unlikely but possible, the voltage profile will look like this. Still within the limits. There won’t be a rapid voltage change because at this stage only the fixed cap bank will be in service and it is permanently in service. There won’t be any switching.
  7. The graph illustrates what influence the cap bank will have on the load when the load grows from it’s lowest value all the way to it’s peak value. The fixed cap bank will permanently be in service; that is why the new load is lower since the start. When the switched cap bank switches in later the load drops even further.
  8. Al die tegniese besluite: wat/waar/hoe instaleer
  9. Al die tegniese besluite: wat/waar/hoe instaleer
  10. Al die tegniese besluite: wat/waar/hoe instaleer
  11. Al die tegniese besluite: wat/waar/hoe instaleer