SlideShare a Scribd company logo
1 of 56
Download to read offline
Sadr Elevated Expressway
TEHRAN
• Client: Municipality of Tehran
• Contractor: Shahid Rajaie Special Group
• Structural Designer: Karane Consulting
Engineers
• Alignment design, sound barrier, lighting,
peripheral structures, etc: Various consultants
Organisations Involved
Why Do We Need the Elevated Expressway?
General Layout
West Ramps
Kaveh Junction
Gheytariye Junction
East Ramps
Project Size
Length,
m
Deck Area,
m2
Width,
m
Min Radius,
m
Max Pier Height,
m
Main Bridge 4,900 112,000 22.7 315 18
Ramps &
Junctions
4,200 43,000 7.8-13.2 40 19.2
Total 9,100 155,000
Main Bridge 72% of
total
Project Requirements and Solutions
Requirement Solution
Rapid construction time Use factory produced precast units
Economy Use concrete
Minimum interference with existing
traffic
Minimise insitu work, work from above
Minimum risk to existing traffic Minimise insitu work, use large units
Work in restricted space Minimise insitu work, work from above
Aesthetics Use factory produced precast units
Use match cast PSC box girders
Main Bridge Superstructure
Cross-Section
Longitudinal-Section
Erection Method: Span-by-span
Pros & Cons of this Method
Pros:
• High erection speed: average of 3 spans per week (Main Bridge
forms 72% of total deck area, so speed is critical)
• No need for access from ground
Cons:
• Needs time for design, fabrication, transport & erection of launching
gantries
• Not suitable on tight curves (Our min R=315 m, so in our case it is not
a problem)
Means Used to Speed up Construction
Use of simple spans
No need to wait for concrete in insitu
joints to gain strength.
Use of external cables
Speeds up casting, no blockage of
ducts during cable installation.
Use of dry joints
Eliminates gluing of joints, therefore
speeds up erection.
Cross Section
Ramp and Junction Superstructures
Longitudinal Section
Erection Method: Balanced cantilever using cranes
from ground
Pros:
• All machinery available, so construction can start immediately
• Can cope with tight curves (Our min R=40 m)
Cons:
• Needs access from ground
• Slower than span by span method
• Interferes with traffic
Pros & Cons of this Method
Main Bridge Piers
Requirements and Solutions
Problem Solution
Region of high seismic activity
Impossible to design by
conventional methodsTall piers
Single columns
Restriction on column dimensions
High column loads during erection &
service
Use Seismic Isolation
Same requirements as for
superstructure
Pier Cross-Beams
Use precast prestressed cross-beams
Ramp & Junction Piers
Same concept used as for main bridge piers
Single Piers
Portal Piers
• Roughly 80% of foundations situated on deep alluvium: Designed as piled
foundations / single shaft foundations.
• For the other 20%, alternative spread footing designs were prepared, but
their widths were wider than the central reserve, so special construction
techniques would have been needed to build them.
• The contractor decided to use piles / single shafts on all foundations.
Foundations
Multiple Pile Foundation
Single Shaft Foundation
Thank You

More Related Content

What's hot (20)

JAISALMER PLANNING
JAISALMER PLANNING JAISALMER PLANNING
JAISALMER PLANNING
 
Desktop Case Study Of Boat House
Desktop Case Study Of Boat HouseDesktop Case Study Of Boat House
Desktop Case Study Of Boat House
 
Bidar fort
Bidar fortBidar fort
Bidar fort
 
Auroville Architecture
Auroville ArchitectureAuroville Architecture
Auroville Architecture
 
R.C.C. STAIRS
R.C.C. STAIRSR.C.C. STAIRS
R.C.C. STAIRS
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliation
 
ARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAK
ARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAKARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAK
ARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAK
 
Building bye laws
Building bye lawsBuilding bye laws
Building bye laws
 
MMBC - VGP MARINE KINGDOM REPORT.pptx
MMBC - VGP MARINE KINGDOM REPORT.pptxMMBC - VGP MARINE KINGDOM REPORT.pptx
MMBC - VGP MARINE KINGDOM REPORT.pptx
 
wankhede stadium case study
wankhede stadium case studywankhede stadium case study
wankhede stadium case study
 
Vernacular architecture in multan
Vernacular architecture in multanVernacular architecture in multan
Vernacular architecture in multan
 
BURJ AL ARAB
BURJ AL ARABBURJ AL ARAB
BURJ AL ARAB
 
Jaipur planning
Jaipur planningJaipur planning
Jaipur planning
 
Long span structure
Long span structureLong span structure
Long span structure
 
H igh rise-01-introduction
H igh rise-01-introductionH igh rise-01-introduction
H igh rise-01-introduction
 
8. Shading devices examples
8. Shading devices examples8. Shading devices examples
8. Shading devices examples
 
meeca masid from hyderabad
meeca masid from hyderabadmeeca masid from hyderabad
meeca masid from hyderabad
 
Laurie Baker
Laurie BakerLaurie Baker
Laurie Baker
 
IUCAA
IUCAAIUCAA
IUCAA
 
Diagrid structural system
Diagrid structural systemDiagrid structural system
Diagrid structural system
 

Similar to Sadr elevated-expressway

Assessment of Underpass on Clark Street and Van Horne
Assessment of Underpass on Clark Street and Van HorneAssessment of Underpass on Clark Street and Van Horne
Assessment of Underpass on Clark Street and Van HorneMichael Masi, Jr. Eng.
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfDanielWisman1
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologyLTDH2013
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Modeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub StructureModeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub StructureAIT Solutions
 
Forth Road Bridge - Truss End Link failure -22 dec
Forth Road Bridge - Truss End Link failure -22 decForth Road Bridge - Truss End Link failure -22 dec
Forth Road Bridge - Truss End Link failure -22 decMike J Ludwig
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Bhishma Bhatti
 
Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structuresAnirudh Gupta
 
St James Presentation short
St James Presentation shortSt James Presentation short
St James Presentation shortDamien Brennan
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
CE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and Sizing
CE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and SizingCE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and Sizing
CE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and SizingFawad Najam
 

Similar to Sadr elevated-expressway (20)

Assessment of Underpass on Clark Street and Van Horne
Assessment of Underpass on Clark Street and Van HorneAssessment of Underpass on Clark Street and Van Horne
Assessment of Underpass on Clark Street and Van Horne
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technology
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
Modeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub StructureModeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub Structure
 
Forth Road Bridge - Truss End Link failure -22 dec
Forth Road Bridge - Truss End Link failure -22 decForth Road Bridge - Truss End Link failure -22 dec
Forth Road Bridge - Truss End Link failure -22 dec
 
CCTVHeadquarters.pdf
CCTVHeadquarters.pdfCCTVHeadquarters.pdf
CCTVHeadquarters.pdf
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
14.30 tarek shuaib, pace
14.30 tarek shuaib, pace14.30 tarek shuaib, pace
14.30 tarek shuaib, pace
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)
 
Precast Construction
Precast ConstructionPrecast Construction
Precast Construction
 
Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structures
 
St James Presentation short
St James Presentation shortSt James Presentation short
St James Presentation short
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
CE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and Sizing
CE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and SizingCE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and Sizing
CE 72.32 (January 2016 Semester) Lecture 5 - Preliminary Design and Sizing
 

Recently uploaded

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 

Recently uploaded (20)

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 

Sadr elevated-expressway

  • 2. • Client: Municipality of Tehran • Contractor: Shahid Rajaie Special Group • Structural Designer: Karane Consulting Engineers • Alignment design, sound barrier, lighting, peripheral structures, etc: Various consultants Organisations Involved
  • 3. Why Do We Need the Elevated Expressway?
  • 9. Project Size Length, m Deck Area, m2 Width, m Min Radius, m Max Pier Height, m Main Bridge 4,900 112,000 22.7 315 18 Ramps & Junctions 4,200 43,000 7.8-13.2 40 19.2 Total 9,100 155,000 Main Bridge 72% of total
  • 10. Project Requirements and Solutions Requirement Solution Rapid construction time Use factory produced precast units Economy Use concrete Minimum interference with existing traffic Minimise insitu work, work from above Minimum risk to existing traffic Minimise insitu work, use large units Work in restricted space Minimise insitu work, work from above Aesthetics Use factory produced precast units Use match cast PSC box girders
  • 14.
  • 15.
  • 16.
  • 17.
  • 18. Pros & Cons of this Method Pros: • High erection speed: average of 3 spans per week (Main Bridge forms 72% of total deck area, so speed is critical) • No need for access from ground Cons: • Needs time for design, fabrication, transport & erection of launching gantries • Not suitable on tight curves (Our min R=315 m, so in our case it is not a problem)
  • 19. Means Used to Speed up Construction Use of simple spans No need to wait for concrete in insitu joints to gain strength. Use of external cables Speeds up casting, no blockage of ducts during cable installation. Use of dry joints Eliminates gluing of joints, therefore speeds up erection.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26. Cross Section Ramp and Junction Superstructures
  • 28. Erection Method: Balanced cantilever using cranes from ground
  • 29. Pros: • All machinery available, so construction can start immediately • Can cope with tight curves (Our min R=40 m) Cons: • Needs access from ground • Slower than span by span method • Interferes with traffic Pros & Cons of this Method
  • 30.
  • 31.
  • 32.
  • 34.
  • 35. Requirements and Solutions Problem Solution Region of high seismic activity Impossible to design by conventional methodsTall piers Single columns Restriction on column dimensions High column loads during erection & service Use Seismic Isolation
  • 36.
  • 37. Same requirements as for superstructure Pier Cross-Beams Use precast prestressed cross-beams
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.
  • 44. Ramp & Junction Piers Same concept used as for main bridge piers Single Piers
  • 46.
  • 47.
  • 48.
  • 49. • Roughly 80% of foundations situated on deep alluvium: Designed as piled foundations / single shaft foundations. • For the other 20%, alternative spread footing designs were prepared, but their widths were wider than the central reserve, so special construction techniques would have been needed to build them. • The contractor decided to use piles / single shafts on all foundations. Foundations
  • 51.
  • 53.
  • 54.
  • 55.