SlideShare a Scribd company logo
1 of 8
Truss End
Link Failure
Forth Road Bridge
22 December 2015
What’s Been Done – SITE / CONSTRUCTION
• Safety Paramount
• >250 Site Safety Inductions
• Exceptional Dedication in Face of Challenging Environment
• 11 sub-contractors
• Temporary Access – Scaffold / MEWP / Barge
• 67 Scaffolders
• Steel Fabrication / Welding / Jacking
• 46 Specialist Welder / Fabricators
What’s Been Done – INSPECTION / INVESTIGATION
• Close Visual Inspection Entire Bridge
• 76 Engineers & Inspectors (55 Rope Access Qualified)
• High resolution Drones used for 1st time
• Non Destructive Testing
• Ultrasonic Tests, Magnetic Particle Inspection
• 21 Engineers & Technicians
• CCTV Camera observing crack 24/7
What’s Been Done - DESIGN
• Design / Check / Certification of Repair completed in
parallel with fabricating ‘splints’
• 53 staff (including 21 Chartered Engineers)
• Design of Temporary Access – Scaffold (Hanging &
Tower) ; MEWP ; Barge
• 16 Engineers & Technicians
• Design of Sophisticated Structural Monitoring System
• 14 Specialist Engineers
• 1st Time used on Forth Road Bridge – similar system to Queensferry
• Design of Traffic Routes / Signage / VMS
• 38 Engineers & Technicians
What’s Been Done - COMMUNICATIONS
• Websites – Forth Bridge & Dedicated Site
• Media Enquiries
• 120no.
• >400 Press articles
• Twitter Followers
• 43,006
• Facebook Likes
• 360,000
• 2 million engaged via facebook
• Physical Model Created
Controlled Load Test To Observe Structural Behaviour
Why HGV Restriction
• Lower Pin NOT
rotating as
hoped
• Strain Gauges
measured live
results during
load test
Next Steps
• Re-open to all traffic (except HGV’s)
• Load Test verification
• Sophisticated Strain Gauge / Structural Monitoring Device verification
• Non destructive testing verification
• Independent expert verification
• Full inspection of bridge verification
• Permits 91% of traffic to re-use the bridge and a
32% reduction in loading
• Committed to HGV re-opening
• Permanent Design - Completion early January 2016
• Strain Gauge / Structural Monitoring Device
• All 8 truss end link areas – mid January 2016
• Start Construction to NE Link
• January 2016

More Related Content

What's hot

Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Sadr elevated-expressway
Sadr elevated-expresswaySadr elevated-expressway
Sadr elevated-expresswayYousef Bertina
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
400kv gis substation erection sequence
400kv gis substation erection sequence400kv gis substation erection sequence
400kv gis substation erection sequenceAnbarasu Balakrishnan
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCrosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...Alex Matveev
 

What's hot (11)

Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Targeted assessment program update Greg Connolly
Targeted assessment program update Greg ConnollyTargeted assessment program update Greg Connolly
Targeted assessment program update Greg Connolly
 
Sadr elevated-expressway
Sadr elevated-expresswaySadr elevated-expressway
Sadr elevated-expressway
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
Narrow Pavement Widening - Beaumont District
Narrow Pavement Widening - Beaumont DistrictNarrow Pavement Widening - Beaumont District
Narrow Pavement Widening - Beaumont District
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
400kv gis substation erection sequence
400kv gis substation erection sequence400kv gis substation erection sequence
400kv gis substation erection sequence
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank Station
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
 

Similar to Forth Road Bridge - Truss End Link failure -22 dec

Euro-Rigging presentation 2013
Euro-Rigging presentation 2013Euro-Rigging presentation 2013
Euro-Rigging presentation 2013wesseln
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cvGeoff Chandler
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
 
MnDOT UAS Project Presentation - 2016 ASCE
MnDOT UAS Project Presentation - 2016 ASCEMnDOT UAS Project Presentation - 2016 ASCE
MnDOT UAS Project Presentation - 2016 ASCEJennifer Zink
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersjose bonifacio de souza leite cuadros
 
QA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptx
QA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptxQA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptx
QA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptxarissa13
 
The Primrose East Bridge
The Primrose East BridgeThe Primrose East Bridge
The Primrose East BridgeJill Reeves
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
Mohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah
 
Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & ToubroJAIPRAKASH PATIL
 
Modular Switches and Crossings
Modular Switches and CrossingsModular Switches and Crossings
Modular Switches and CrossingsSteven Johnson
 
Inspection testing rope access capability sheet rev12
Inspection testing rope access capability sheet rev12Inspection testing rope access capability sheet rev12
Inspection testing rope access capability sheet rev12Philip Collinson
 

Similar to Forth Road Bridge - Truss End Link failure -22 dec (20)

Euro-Rigging presentation 2013
Euro-Rigging presentation 2013Euro-Rigging presentation 2013
Euro-Rigging presentation 2013
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cv
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
MnDOT UAS Project Presentation - 2016 ASCE
MnDOT UAS Project Presentation - 2016 ASCEMnDOT UAS Project Presentation - 2016 ASCE
MnDOT UAS Project Presentation - 2016 ASCE
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
QA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptx
QA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptxQA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptx
QA-QC_Processes_for_QA-QC_for_HL-LHC_Coil_Fabrication.pptx
 
The Primrose East Bridge
The Primrose East BridgeThe Primrose East Bridge
The Primrose East Bridge
 
Ipc bridge inspection presentation 2018
Ipc bridge inspection presentation 2018Ipc bridge inspection presentation 2018
Ipc bridge inspection presentation 2018
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Infrastructure preservation bridge inspection presentation 2018
Infrastructure preservation bridge inspection presentation 2018Infrastructure preservation bridge inspection presentation 2018
Infrastructure preservation bridge inspection presentation 2018
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Mohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah Ibrahim
Mohamed Salah Ibrahim
 
Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn CV 2017
Greg Southorn CV 2017
 
Bridge defects
Bridge defectsBridge defects
Bridge defects
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & Toubro
 
Modular Switches and Crossings
Modular Switches and CrossingsModular Switches and Crossings
Modular Switches and Crossings
 
Inspection testing rope access capability sheet rev12
Inspection testing rope access capability sheet rev12Inspection testing rope access capability sheet rev12
Inspection testing rope access capability sheet rev12
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

Forth Road Bridge - Truss End Link failure -22 dec

  • 1. Truss End Link Failure Forth Road Bridge 22 December 2015
  • 2. What’s Been Done – SITE / CONSTRUCTION • Safety Paramount • >250 Site Safety Inductions • Exceptional Dedication in Face of Challenging Environment • 11 sub-contractors • Temporary Access – Scaffold / MEWP / Barge • 67 Scaffolders • Steel Fabrication / Welding / Jacking • 46 Specialist Welder / Fabricators
  • 3. What’s Been Done – INSPECTION / INVESTIGATION • Close Visual Inspection Entire Bridge • 76 Engineers & Inspectors (55 Rope Access Qualified) • High resolution Drones used for 1st time • Non Destructive Testing • Ultrasonic Tests, Magnetic Particle Inspection • 21 Engineers & Technicians • CCTV Camera observing crack 24/7
  • 4. What’s Been Done - DESIGN • Design / Check / Certification of Repair completed in parallel with fabricating ‘splints’ • 53 staff (including 21 Chartered Engineers) • Design of Temporary Access – Scaffold (Hanging & Tower) ; MEWP ; Barge • 16 Engineers & Technicians • Design of Sophisticated Structural Monitoring System • 14 Specialist Engineers • 1st Time used on Forth Road Bridge – similar system to Queensferry • Design of Traffic Routes / Signage / VMS • 38 Engineers & Technicians
  • 5. What’s Been Done - COMMUNICATIONS • Websites – Forth Bridge & Dedicated Site • Media Enquiries • 120no. • >400 Press articles • Twitter Followers • 43,006 • Facebook Likes • 360,000 • 2 million engaged via facebook • Physical Model Created
  • 6. Controlled Load Test To Observe Structural Behaviour
  • 7. Why HGV Restriction • Lower Pin NOT rotating as hoped • Strain Gauges measured live results during load test
  • 8. Next Steps • Re-open to all traffic (except HGV’s) • Load Test verification • Sophisticated Strain Gauge / Structural Monitoring Device verification • Non destructive testing verification • Independent expert verification • Full inspection of bridge verification • Permits 91% of traffic to re-use the bridge and a 32% reduction in loading • Committed to HGV re-opening • Permanent Design - Completion early January 2016 • Strain Gauge / Structural Monitoring Device • All 8 truss end link areas – mid January 2016 • Start Construction to NE Link • January 2016