Source: own photos
1
 The test for water tightness is to be performed on the pipe before it is completely covered,
yet it has to be covered to such an extent as to prevent a change in position during the
test.
 Final backfilling of the trench may be started only after the entire pipeline has been
checked, the tightness tests have been performed, all measurements for earthworks and
pipe-laying works have been made, the pipeline has been appropriately secured and all
important points of the pipeline have been staked out as fixed points. The staked-out
points are to be recorded in separate as-built drawings.
 Regardless of the general acceptability in testing of separate system elements, having
considered most frequent leakage points (pipe saddle, house connections to revision &
collection chambers), it is highly recommended that system as a whole is being tested.
2
Leak tightness:
 Testing should include connections, manholes and inspection chambers.
Procedures and requirements for testing gravity pipelines:
 Testing with air;
 Testing with water.
Testing with air:
 Method not appropriate for manholes and inspection chambers, just for pipelines;
 Suitable airtight plugs shall be used to avoid errors arising from the test equipment;
 Special care required for testing of large DN for safety reasons;
 Due to incapability for testing of the whole “system” including the collectors, house
connections, collection & inspection chambers, manholes, water testing method is
recommended for application.
3
Testing with water:
 Test pressure is equivalent to or resulting from filling the test section up to the
ground level of the upstream manhole, with a max. pressure of 50 kPa and a min.
pressure of 10 kPa measured at the top of the pipe.
 Conditioning time: after the pipeline and/or manholes are filled and the required
test pressure applied, conditioning may be necessary (usually 1 h is sufficient, for
dry climatic conditions a longer period is required as well as for concrete pipes)
 Testing time: 30 ± 1 min
Source: own photos
4
PLUGGING BALLOON SEALING THE
CHAMBER
TESTED CHAMBER FILLED WITH
WATER
Source: own photos
5
Source: own photos
6
Testing with water:
 Test pressure is equivalent to or resulting
from filling the test section up to the ground
level of the upstream manhole, with a max.
pressure of 50 kPa and a min. pressure of
10 kPa measured at the top of the pipe.

 Settling time: after the pipeline and/or
manholes are filled and the required test
pressure applied, conditioning may be
necessary (generally for testing in dry
climate 1 h settling time is sufficient; a
longer period may be required for dry
climatic conditions in case of concrete
pipes);
 Testing time: 30 ± 1 min
Source: own photos
7
 Test requirements: pressure shall be
maintained within 1 kPa of the test
pressure by topping up with water. Total
amount of water added during the test to
achieve this requirement shall be
measured and recorded with the head of
water at the required test pressure.
The test is satisfactory if the amount of
added water is not greater than:
 0.15 l/m2 during 30 min for pipelines;
 0.20 l/m2 during 30 min for pipelines
including manholes;
 0.40 l/m2 during 30 min for manholes and
inspection chambers
(m2 refers to the wetted internal surface)
Source: own photos
8
Testing individual joints
 Unless otherwise specified, individual
joints can be tested instead of whole
pipeline if the pipe diameter is > DN1000
 The surface area for testing with water is
taken as that represented by 1 m length of
pipe, if not otherwise specified with a test
pressure of 50 kPa at the top of the pipe.
 Visual inspection by Contractor and
Engineer has to be conducted prior to
backfilling of pipelines.
 Prior to scheduling of tightness testing,
Contractor must officially announce
testing with appropriate letter supported
with required survey data of sections to
be tested.
Source: own photo
9
 The Contractor's Surveyor is to measure all the
parameters of installed system, based on
submitted survey data, the Engineer will prepare
test sheet for the use on testing.
 Test Certificates issued by Engineer, signed and
supported with survey drawings might be part of
payment request and/or As-Built documentation.
 Contractor is fully responsible for the quality of
executed works and the strict respect of the
testing procedures
Source: own
10
11
12
Source: own
13

More Related Content

What's hot

Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideChukwuma Anyanwu, PMP, CCP
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Emeka Ngwobia
 
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerPiping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerVarun Patel
 
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.SPII Compact Wellhead - Worldwide Oilfield Machine Inc.
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.womgroup
 
VISUAL INSPECTION pt 2
VISUAL INSPECTION   pt 2VISUAL INSPECTION   pt 2
VISUAL INSPECTION pt 2Mogekwu Chinye
 
T4S - Technical Standard and Specifications including Safety Standards
T4S - Technical Standard and Specifications including Safety StandardsT4S - Technical Standard and Specifications including Safety Standards
T4S - Technical Standard and Specifications including Safety StandardsAbhishek Padiyar
 
API 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory CourseAPI 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory CoursepetroEDGE
 
Operation and Maintenance of Gates
Operation and Maintenance of GatesOperation and Maintenance of Gates
Operation and Maintenance of GatesIEI GSC
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookAli Meshaikhis
 

What's hot (20)

Pipeline construction management
Pipeline construction managementPipeline construction management
Pipeline construction management
 
Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guide
 
TPI - Example Report.
TPI - Example Report.TPI - Example Report.
TPI - Example Report.
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.
 
Piping Introduction
Piping IntroductionPiping Introduction
Piping Introduction
 
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerPiping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.SPII Compact Wellhead - Worldwide Oilfield Machine Inc.
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
VISUAL INSPECTION pt 2
VISUAL INSPECTION   pt 2VISUAL INSPECTION   pt 2
VISUAL INSPECTION pt 2
 
T4S - Technical Standard and Specifications including Safety Standards
T4S - Technical Standard and Specifications including Safety StandardsT4S - Technical Standard and Specifications including Safety Standards
T4S - Technical Standard and Specifications including Safety Standards
 
Piping Fundamentals .pdf
Piping Fundamentals .pdfPiping Fundamentals .pdf
Piping Fundamentals .pdf
 
API 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory CourseAPI 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory Course
 
Operation and Maintenance of Gates
Operation and Maintenance of GatesOperation and Maintenance of Gates
Operation and Maintenance of Gates
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbook
 
Wellhead basics
Wellhead basicsWellhead basics
Wellhead basics
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
 
Basic piping
Basic pipingBasic piping
Basic piping
 

Similar to Tightness testing of gravity pipelines

Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingAbhijeet Nagle
 
S3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENTS3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENTno suhaila
 
Dc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and TipsDc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and TipsSimon MECO FanCoil Unit
 
Pressure_Switch_Leak_Detection_F14
Pressure_Switch_Leak_Detection_F14Pressure_Switch_Leak_Detection_F14
Pressure_Switch_Leak_Detection_F14Hugo Nguyen, MBA
 
Chapter 3 - Groundwater Flow to Wells.pdf
Chapter 3 - Groundwater Flow to Wells.pdfChapter 3 - Groundwater Flow to Wells.pdf
Chapter 3 - Groundwater Flow to Wells.pdfWONDIMUELIAS
 
MANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfMANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfamgothusandeep
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide LaboratoryBahzad5
 
DEKON VRF Air conditioner installation tips
DEKON VRF Air conditioner installation tipsDEKON VRF Air conditioner installation tips
DEKON VRF Air conditioner installation tipsSimon MECO FanCoil Unit
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEKaran Patel
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...hydrologywebsite1
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...hydrologyproject001
 
Flushing cleaning procedure
Flushing  cleaning procedureFlushing  cleaning procedure
Flushing cleaning procedureNatee Tsui
 
pipefitting pressure-test
pipefitting pressure-testpipefitting pressure-test
pipefitting pressure-testIzzuwan Yusoff
 
Pipeline,Vessels Hydrotesting and procedures
Pipeline,Vessels  Hydrotesting and proceduresPipeline,Vessels  Hydrotesting and procedures
Pipeline,Vessels Hydrotesting and proceduresPravinVispute3
 
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptxCNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptxRishabh Sirvaiya
 
Slug Test Procedures
Slug Test ProceduresSlug Test Procedures
Slug Test Procedurestpttk
 

Similar to Tightness testing of gravity pipelines (20)

Edited j6.doc
Edited j6.docEdited j6.doc
Edited j6.doc
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / Hydrotesting
 
S3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENTS3 SANITARY PIPE WORK ASSIGNMENT
S3 SANITARY PIPE WORK ASSIGNMENT
 
Dc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and TipsDc inverter vrf installation instructions and Tips
Dc inverter vrf installation instructions and Tips
 
Piping hydrotest
Piping hydrotestPiping hydrotest
Piping hydrotest
 
Pressure_Switch_Leak_Detection_F14
Pressure_Switch_Leak_Detection_F14Pressure_Switch_Leak_Detection_F14
Pressure_Switch_Leak_Detection_F14
 
Detail product SGS test 2015 - VIB factory.PDF
Detail product SGS test  2015 - VIB factory.PDFDetail product SGS test  2015 - VIB factory.PDF
Detail product SGS test 2015 - VIB factory.PDF
 
Chapter 3 - Groundwater Flow to Wells.pdf
Chapter 3 - Groundwater Flow to Wells.pdfChapter 3 - Groundwater Flow to Wells.pdf
Chapter 3 - Groundwater Flow to Wells.pdf
 
MANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfMANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdf
 
Liquid permeability
Liquid permeabilityLiquid permeability
Liquid permeability
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
DEKON VRF Air conditioner installation tips
DEKON VRF Air conditioner installation tipsDEKON VRF Air conditioner installation tips
DEKON VRF Air conditioner installation tips
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 
Flushing cleaning procedure
Flushing  cleaning procedureFlushing  cleaning procedure
Flushing cleaning procedure
 
pipefitting pressure-test
pipefitting pressure-testpipefitting pressure-test
pipefitting pressure-test
 
Pipeline,Vessels Hydrotesting and procedures
Pipeline,Vessels  Hydrotesting and proceduresPipeline,Vessels  Hydrotesting and procedures
Pipeline,Vessels Hydrotesting and procedures
 
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptxCNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
 
Slug Test Procedures
Slug Test ProceduresSlug Test Procedures
Slug Test Procedures
 

More from Vladimir Popovic

Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...Vladimir Popovic
 
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirSeismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirVladimir Popovic
 
3-Days Construction Schedule
3-Days Construction Schedule3-Days Construction Schedule
3-Days Construction ScheduleVladimir Popovic
 
Water Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesWater Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesVladimir Popovic
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsVladimir Popovic
 
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsVladimir Popovic
 
Sealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesSealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesVladimir Popovic
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESVladimir Popovic
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopVladimir Popovic
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Vladimir Popovic
 
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionMan Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionVladimir Popovic
 
Standard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsStandard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsVladimir Popovic
 
Ozurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectOzurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectVladimir Popovic
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Vladimir Popovic
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Vladimir Popovic
 
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresMan Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresVladimir Popovic
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingVladimir Popovic
 
Kostajnica City - WS/WW Project
Kostajnica City - WS/WW ProjectKostajnica City - WS/WW Project
Kostajnica City - WS/WW ProjectVladimir Popovic
 
Derventa City Water Supply Project
Derventa City Water Supply ProjectDerventa City Water Supply Project
Derventa City Water Supply ProjectVladimir Popovic
 
Kakanj City Waste Water Project
Kakanj City Waste Water ProjectKakanj City Waste Water Project
Kakanj City Waste Water ProjectVladimir Popovic
 

More from Vladimir Popovic (20)

Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
Rehabilitation of Municipal Water Supply and Wastewater Infrastructure in Bat...
 
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoirSeismic concrete Bore Piles at Makhinjauri water supply reservoir
Seismic concrete Bore Piles at Makhinjauri water supply reservoir
 
3-Days Construction Schedule
3-Days Construction Schedule3-Days Construction Schedule
3-Days Construction Schedule
 
Water Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing ExamplesWater Supply Pipelines Channel Crossing Examples
Water Supply Pipelines Channel Crossing Examples
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
 
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Lashis-Gele Water RC Reservoir, Existing Conditions
 
Sealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod HolesSealing of Wall Shutter Tie-Rod Holes
Sealing of Wall Shutter Tie-Rod Holes
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-Stop
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
 
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 ConstructionMan Made River Project – Libya - Gharyan Tank 300.000m3 Construction
Man Made River Project – Libya - Gharyan Tank 300.000m3 Construction
 
Standard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elementsStandard Waste Water Manholes of precast concrete elements
Standard Waste Water Manholes of precast concrete elements
 
Ozurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectOzurgeti City / Water Supply Project
Ozurgeti City / Water Supply Project
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
 
Man Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor StructuresMan Made River Project IV Phase / Ghadames Project - Minor Structures
Man Made River Project IV Phase / Ghadames Project - Minor Structures
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
 
Kostajnica City - WS/WW Project
Kostajnica City - WS/WW ProjectKostajnica City - WS/WW Project
Kostajnica City - WS/WW Project
 
Derventa City Water Supply Project
Derventa City Water Supply ProjectDerventa City Water Supply Project
Derventa City Water Supply Project
 
Kakanj City Waste Water Project
Kakanj City Waste Water ProjectKakanj City Waste Water Project
Kakanj City Waste Water Project
 

Recently uploaded

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Tightness testing of gravity pipelines

  • 2.  The test for water tightness is to be performed on the pipe before it is completely covered, yet it has to be covered to such an extent as to prevent a change in position during the test.  Final backfilling of the trench may be started only after the entire pipeline has been checked, the tightness tests have been performed, all measurements for earthworks and pipe-laying works have been made, the pipeline has been appropriately secured and all important points of the pipeline have been staked out as fixed points. The staked-out points are to be recorded in separate as-built drawings.  Regardless of the general acceptability in testing of separate system elements, having considered most frequent leakage points (pipe saddle, house connections to revision & collection chambers), it is highly recommended that system as a whole is being tested. 2
  • 3. Leak tightness:  Testing should include connections, manholes and inspection chambers. Procedures and requirements for testing gravity pipelines:  Testing with air;  Testing with water. Testing with air:  Method not appropriate for manholes and inspection chambers, just for pipelines;  Suitable airtight plugs shall be used to avoid errors arising from the test equipment;  Special care required for testing of large DN for safety reasons;  Due to incapability for testing of the whole “system” including the collectors, house connections, collection & inspection chambers, manholes, water testing method is recommended for application. 3
  • 4. Testing with water:  Test pressure is equivalent to or resulting from filling the test section up to the ground level of the upstream manhole, with a max. pressure of 50 kPa and a min. pressure of 10 kPa measured at the top of the pipe.  Conditioning time: after the pipeline and/or manholes are filled and the required test pressure applied, conditioning may be necessary (usually 1 h is sufficient, for dry climatic conditions a longer period is required as well as for concrete pipes)  Testing time: 30 ± 1 min Source: own photos 4
  • 5. PLUGGING BALLOON SEALING THE CHAMBER TESTED CHAMBER FILLED WITH WATER Source: own photos 5
  • 7. Testing with water:  Test pressure is equivalent to or resulting from filling the test section up to the ground level of the upstream manhole, with a max. pressure of 50 kPa and a min. pressure of 10 kPa measured at the top of the pipe.   Settling time: after the pipeline and/or manholes are filled and the required test pressure applied, conditioning may be necessary (generally for testing in dry climate 1 h settling time is sufficient; a longer period may be required for dry climatic conditions in case of concrete pipes);  Testing time: 30 ± 1 min Source: own photos 7
  • 8.  Test requirements: pressure shall be maintained within 1 kPa of the test pressure by topping up with water. Total amount of water added during the test to achieve this requirement shall be measured and recorded with the head of water at the required test pressure. The test is satisfactory if the amount of added water is not greater than:  0.15 l/m2 during 30 min for pipelines;  0.20 l/m2 during 30 min for pipelines including manholes;  0.40 l/m2 during 30 min for manholes and inspection chambers (m2 refers to the wetted internal surface) Source: own photos 8
  • 9. Testing individual joints  Unless otherwise specified, individual joints can be tested instead of whole pipeline if the pipe diameter is > DN1000  The surface area for testing with water is taken as that represented by 1 m length of pipe, if not otherwise specified with a test pressure of 50 kPa at the top of the pipe.  Visual inspection by Contractor and Engineer has to be conducted prior to backfilling of pipelines.  Prior to scheduling of tightness testing, Contractor must officially announce testing with appropriate letter supported with required survey data of sections to be tested. Source: own photo 9
  • 10.  The Contractor's Surveyor is to measure all the parameters of installed system, based on submitted survey data, the Engineer will prepare test sheet for the use on testing.  Test Certificates issued by Engineer, signed and supported with survey drawings might be part of payment request and/or As-Built documentation.  Contractor is fully responsible for the quality of executed works and the strict respect of the testing procedures Source: own 10
  • 11. 11
  • 12. 12