T4S or Technical Standard and Specifications Including Safety Standards -2008
This presentation through the light on the rules and standard to be followed for the designing, installation, testing and commissioning of City Gas Distribution (CGD) network with Gas supply source as LNG Storage and Re-gasification plant and the distribution network made up by the use of MDPE pipelines, as per the technical and safety guidelines given by PNGRB in T4S 2008.
20. Redundancy : In engineering redundancy is the duplication of critical components or functions of a system
with the intention of increasing reliability of the system, usually in the form of a backup or fail-safe, or to
improve actual system performance.
Fail-safe : In engineering, a fail safe is a design feature or practice that in the event of a specific type
of failure, inherently responds in a way that will cause minimal or no harm to other equipment, to the
environment or to people.
34. NOTES:
1. Cover shall be measured from the top of coated pipe to the top of the undisturbed surface of soil.
2. For river / watercourses that are prone to scour and/or erosion, the specified cover shall be measured
from the expected lowest bed profile after scouring/ erosion. Where scour level cannot be established, an
additional cover of minimum 1 meter shall be provided from the existing bed of the river/water course.
3 The cover shall be measured from the top of road or top of rail, as the case may be.
4 Under water pipelines are avoided in case of MDPE network and in such situation Horizontal Directional
Drilling (HDD) is performed.
**
Whenever the above provisions of cover cannot be provided due to site constraints, additional protection
in form of casing/ concreting etc. shall be provided.
37. Standard dimension ratio (SDR) is a method of rating a pipe's durability against pressure.
The standard dimension ratio describes the correlation between the pipe diameter and the thickness of the pipe.
SDR = Outer Dia. of Pipe
Thickness of Pipe
Pipes with a lower SDR can withstand higher pressures.
53. (1) Surface gas detection survey :
This survey is a continuous sampling of the atmosphere at or near ground level for buried gas facilities
with a portable or mobile gas detector system capable of detecting a concentration of 50 ppm of gas in air
at any sampling point.
(2) Subsurface gas detector survey (including bar hole surveys)
This survey is a sampling of the subsurface atmosphere with a combustible gas indicator (CGI) or other device
capable of detecting 0.5% gas in air at the sample point
The survey shall be conducted by performing tests with a CGI in a series of available openings (confined spaces
and small substructures) and/or bar holes over, or adjacent to, the gas facility.
(3) Vegetation survey
This survey uses visual observations to detect abnormal or unusual indications in vegetation. All visual
indications shall be evaluated using a combustible gas indicator (CGI).
*Other acceptable survey methods shall be used for locations within a vegetation survey area where vegetation
is not adequate to indicate the presence of leakage.
54. (4) Pressure drop test
A test to determine if an isolated segment of pipeline loses pressure due to leakage.
(5) Bubble leakage test
The exposed piping systems shall be reasonably cleaned and completely coated with the solution. Leaks are indicated
by the presence of bubbles. The bubble-forming solution shall not be used on piping unless it has been determined
by investigation or test that the piping is adequately resistant to direct contact with the solution
(6) Ultrasonic leakage test
This method is used for testing of exposed piping facilities test based upon the concept that as the line
pressure increases, the magnitude of the ultrasonic energy generated by a leak increases.