SlideShare a Scribd company logo
1 of 21
Foundry Park
Ranihati-Amta Road, Howrah, West Bengal
developed by
Foundry Cluster Development Association
Department of MSME&T, Govt. of West Bengal
Nodal Organization:WBSIDCL
State Approved Industrial Park (SAIP)
State Approved Industrial Park (SAIP)
LOCATED IN :-
HAULIBAGAN
SAMANTI, JALABISWANATHPUR & SUVARAH
MOUZA), HOWRAH DISTRICT, WEST BENGAL
SITE POTENTIAL :-
 THE SITE IS LOCATED IN THE HEART OF
FOUNDRY INDUSTRY IN EASTERN INDIA
 THE APPROACH TO SITE IS FROM HOWRAH-
AMTA ROAD CONNECTED TO NH-6
Site Location
 Registered under Section 8 of Companies Act on 29th March, 2005 with approval of WBIDC
and WBPCB.
 Project being implemented with partial grant for infrastructural development from Govt.
of India under the Industrial Infrastructure Upgradation Scheme (IIUS), Department of
Promotion of Industry and Internal Trade (DPIIT), Ministry of Commerce & Industry, GoI.
 State Govt has also contributed by way of setting up of STP and upgradation of local
sewarage and drainage system
 Phase-I of around 600 acres with 150 foundries and allied units to be accommodated. Total
area of the project envisaged is 924 acres
About Foundry Park
Project Feature Information
Total Number of Units Planned Foundry Units:
 100 nos. in total in 600 acres
Allied (Core making, pattern making, fettling, painting, fabrication
and machining shops, raw material banks etc.): 50 nos.
Total Envisaged Castings Output  By end of 5th year of Commercial Operations: 5 lakh tonnes per
annum.
Total Envisaged Investment by
Foundry Units
Rs. 2500 crores
Employment Potential Direct Employment: 10,000 people (approx.)
Indirect Employment: 30,000 people
About Foundry Park
Land Parcel for LTS Coverage
Sl No Major Items of Work Scope
1 ROAD WORK 11840 M
2 STORM WATER DRAIN WORK 18225 M
3 EXTERNAL WATER SUPPLY WORK 13000 M
4 WATER WORKS
UGR 3 nos
OHT 3 nos
PH 3 nos
TUBE WELLS 4 nos
5 SEWER NETWORK 12800 M
6 POWER DISTRIBUTION SYSTEM 33/11kv substation 2 nos
Major Scope of Work
7 Common Facility Buildings
I T I building
Testing laboratory & Tool room building
Information, Marketing, HRD & Management upgradation centre
Pump house & its UGR for CFB units
Sub-station building for CFB units
Boundary wall around CFB units
Stakeholders Contribution
Contribution from
Govt. of West Bengal
Grant from
Department of Promotion of Industry and
Internal Trade (DPIIT) Govt. of India
Total Project Cost
Rs 95.02 Cr
1. 129 plots already allotted to stakeholders all from MSME
sector
2. 34 nos stakeholders have started factory construction
activities out of which 9 nos have started production after
obtaining all statutory clearances
3. Foundries and units manufacturing Light Engineering
Products are being set up
Plot Status
Source of Power :
220 KV sub-station set-up within the Park. FCDA provided
approximately 15 acres of Land to WBSETCL/WBSEDCL for
setting up the sub-station. The sub-station supplies
uninterrupted quality power to meet the entire requirement
Foundry Park.
There is provision of 3 Nos 33 KV substation out of which one is
operational and another one is under construction.
Status of approvals of Foundry Park under SAIP
‘Final Approval’ in favour of Foundry Park was accorded on 20.04.2022.
Now he has requested for for the release of ‘1st installment of Incentives’
of the said Industrial Park.
Checklist according to parameter for 1st Incentive payment
Sl
No
Criteria as per guideline Comments of PMU, WBSIDCL
1 Mutation, conversion & registration of
the land in SPV’s name
Mutation has already been done for total lands but conversion is
yet to be done. It also attracts the memo no. 796-GE(M)/3M-
68/11; dated 25.02.2021.
2 Formation of the SPV and obtaining
final approval of the AIP from the
SLEC
SPV already formed and obtained final approval of the AIP from
the SLEC on 20.04.2022.
This Park has been visited on 14th July, 2022 by the PMU Team of WBSIDCL in presence of Mr. Mukul
Maity, Site Engineer, Foundry Cluster Development Association along with his team and after
inspection & checking of the project it has been found that all basic and essential infrastructures
have been completed as per SAIP 2020 Guideline but, the SPV has developed the Park with the
assistance of Government funds.
Accordingly WBSIDCL has not recommended for release of ‘incentive’ in favour of Foundry
Park. SPV has also applied for reimbursement of stamp duty and registration fees and the
reimbursement of said fees has been recommended.
….cont’d
Sl Criteria as per
guideline
Comments of PMU, WBSIDCL
3 Completion of
construction of Boundary
Wall, Land filling and
Internal Roads
Land filling Work is almost completed (95%).
The total length of Boundary Wall executed at site is 3400m (approx). So the
Construction of Boundary Wall is almost completed.
Internal Road Work has been completed and the total length of about 7760m. As
informed by FCDA, total thickness of the internal road is 580mm consisting of
230mm GSB, 250mm WMM, 60mm DBM & 40mm BC. Two (02) nos Culvert have been
constructed.
Drainage System is done comprises with RCC Wall and the total length of about
7760m. Many portions of drain are choked & damaged. Irrigation Deptt has
initiated the work of improvement of drainage congestion. Copy of all documents
relating to KMDA work is attached.
Regarding Electric Connection, FCDA informed WBSEDCL will set up a 220KVA
substations from which power will be drawn for the project by two 33KVA
substations. Twenty Four (24) nos Street Light have been installed along the road.
Setting up of 0.80MLD CETP is under going on at the end of KMDA.
….cont’d
RECOMMENDATIONS BY WBSIDCL
Since the SPV has developed the Park with the assistance of Government funds, hence WBSIDCL
has not been recommended for release of ‘incentive’ in favour of Foundry Park as per section
8(F)* of SAIP 2020.
SPV has also applied for reimbursement of stamp duty and registration fees and the
reimbursement of said fees has been recommended by WBSIDCL as per guideline of SAIP 2020.
*As per section 8(F) of SAIP 2020 it is stated that the SPV availing of incentives under the Scheme shall be
eligible to avail incentives under any other scheme of the State Government / Government of India
except for the same item and excluding the cluster infrastructure development assistance as available in
MSME Policy of the State Government. Individual Units coming up in the AIP shall be eligible to avail
incentives under various schemes of the State Government/Central Government as per their eligibility.
Main Entrance of the Complex
Road Network and Other Facilities
Weigh Bridge
Road and Sewerage Construction
Operational units at Foundry Park
ITI & Tool Room Building
Vivekananda Industrial Training Institute
Collaborated with Paschim Banga Society of Skill Development (PBSSD)
under the aegis of Ministry of Technical Education & Skill Development,
Govt. of West Bengal for:
Foundry courses including Melting, Moulding and Core making.
Theoretical Class Practical Training Class
Hostel facility for Students
Library & reading Room
Administrative Office
Conference Room with Projector
Infrastructure
Facilities in Training
Institute
Thank You!

More Related Content

What's hot

Proposed Bus Terminal At Rajiv Chowk, Gurgaon, Haryana
Proposed Bus Terminal At Rajiv Chowk, Gurgaon, HaryanaProposed Bus Terminal At Rajiv Chowk, Gurgaon, Haryana
Proposed Bus Terminal At Rajiv Chowk, Gurgaon, HaryanaRamnet Kaur
 
Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...
Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...
Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...Kethees Waran
 
Jamshedpur- Planning History
Jamshedpur- Planning HistoryJamshedpur- Planning History
Jamshedpur- Planning HistorySomnath Bhui
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Avirup Ghosh
 
Classification of Gwalior based town planning parameters
Classification of Gwalior based town planning parametersClassification of Gwalior based town planning parameters
Classification of Gwalior based town planning parametersAmrata Yadav
 
VG check list for OHE bonding and earthing 002
VG check list for OHE bonding and earthing    002 VG check list for OHE bonding and earthing    002
VG check list for OHE bonding and earthing 002 Varadharajalu Gopal
 
M.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systemsM.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systemsMohamed Azzam
 
ppt on industrial training of final year studen from ptcul 132kv substation ...
ppt on industrial training of final year studen  from ptcul 132kv substation ...ppt on industrial training of final year studen  from ptcul 132kv substation ...
ppt on industrial training of final year studen from ptcul 132kv substation ...surendra rawat
 
Local authority of lumut, perak
Local authority of lumut, perakLocal authority of lumut, perak
Local authority of lumut, perakEraz
 
Indian railway final report
Indian railway  final reportIndian railway  final report
Indian railway final reportashwani kumar
 
Case study KSRTC terminal calicut
Case study KSRTC terminal calicutCase study KSRTC terminal calicut
Case study KSRTC terminal calicutHmd
 
East kidwai nagar, new delhi
East kidwai nagar, new delhiEast kidwai nagar, new delhi
East kidwai nagar, new delhiShamitha Reddy
 

What's hot (20)

Proposed Bus Terminal At Rajiv Chowk, Gurgaon, Haryana
Proposed Bus Terminal At Rajiv Chowk, Gurgaon, HaryanaProposed Bus Terminal At Rajiv Chowk, Gurgaon, Haryana
Proposed Bus Terminal At Rajiv Chowk, Gurgaon, Haryana
 
Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...
Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...
Human settlement and planning 9th sem B.Arch 2013 anna univ regulation unit 5...
 
Jamshedpur- Planning History
Jamshedpur- Planning HistoryJamshedpur- Planning History
Jamshedpur- Planning History
 
Taxila
TaxilaTaxila
Taxila
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
 
Mysuru District profile
Mysuru District profileMysuru District profile
Mysuru District profile
 
A study of reconstruction in India
A study of reconstruction in IndiaA study of reconstruction in India
A study of reconstruction in India
 
Classification of Gwalior based town planning parameters
Classification of Gwalior based town planning parametersClassification of Gwalior based town planning parameters
Classification of Gwalior based town planning parameters
 
VG check list for OHE bonding and earthing 002
VG check list for OHE bonding and earthing    002 VG check list for OHE bonding and earthing    002
VG check list for OHE bonding and earthing 002
 
M.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systemsM.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systems
 
Army School Support Services Directory
Army School Support Services Directory Army School Support Services Directory
Army School Support Services Directory
 
ppt on industrial training of final year studen from ptcul 132kv substation ...
ppt on industrial training of final year studen  from ptcul 132kv substation ...ppt on industrial training of final year studen  from ptcul 132kv substation ...
ppt on industrial training of final year studen from ptcul 132kv substation ...
 
Local authority of lumut, perak
Local authority of lumut, perakLocal authority of lumut, perak
Local authority of lumut, perak
 
Indian railway final report
Indian railway  final reportIndian railway  final report
Indian railway final report
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
Case study KSRTC terminal calicut
Case study KSRTC terminal calicutCase study KSRTC terminal calicut
Case study KSRTC terminal calicut
 
Aiims flyover presentation
Aiims flyover presentationAiims flyover presentation
Aiims flyover presentation
 
Building regualations-for-noida 0
Building regualations-for-noida 0Building regualations-for-noida 0
Building regualations-for-noida 0
 
Stations as Places - designing & planning rail stations
Stations as Places - designing & planning rail stationsStations as Places - designing & planning rail stations
Stations as Places - designing & planning rail stations
 
East kidwai nagar, new delhi
East kidwai nagar, new delhiEast kidwai nagar, new delhi
East kidwai nagar, new delhi
 

Similar to FOUNDRY PARK PPT_2023.02.24.ppt

Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
Virat Vanijya_  Vishwakarma Industrial Park_r.pptxVirat Vanijya_  Vishwakarma Industrial Park_r.pptx
Virat Vanijya_ Vishwakarma Industrial Park_r.pptxSomSaha1
 
Scheme for Improving Industrial Infrastructure
Scheme for Improving Industrial InfrastructureScheme for Improving Industrial Infrastructure
Scheme for Improving Industrial InfrastructureOur Vibrant Gujarat
 
Project on expense booking in the service and stores section of F&A dept. of ...
Project on expense booking in the service and stores section of F&A dept. of ...Project on expense booking in the service and stores section of F&A dept. of ...
Project on expense booking in the service and stores section of F&A dept. of ...CA Abhimanyu Chakraborty
 
Gidc corporate presentation june 2011
Gidc corporate presentation june 2011Gidc corporate presentation june 2011
Gidc corporate presentation june 2011Outlook Menia
 
ASCC-Presentation-Coatec.pdf
ASCC-Presentation-Coatec.pdfASCC-Presentation-Coatec.pdf
ASCC-Presentation-Coatec.pdfDaljeetSaluja
 
Bihar Industrial Policy. 2011
Bihar Industrial Policy. 2011Bihar Industrial Policy. 2011
Bihar Industrial Policy. 2011Bakul Haria
 
SSL PROJECT PROFILE
SSL PROJECT PROFILESSL PROJECT PROFILE
SSL PROJECT PROFILEKhaled Hasan
 
Gidc corporate presentation jan 2011
Gidc corporate presentation jan 2011 Gidc corporate presentation jan 2011
Gidc corporate presentation jan 2011 Outlook Menia
 
Presentation 11 06-2013 changes
Presentation 11 06-2013 changesPresentation 11 06-2013 changes
Presentation 11 06-2013 changesGhazanfar Amin
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsDr. Oliver Massmann
 
Lag 305 siddiqsons generation lic 14-09-2015-13666-71
Lag 305 siddiqsons generation lic 14-09-2015-13666-71Lag 305 siddiqsons generation lic 14-09-2015-13666-71
Lag 305 siddiqsons generation lic 14-09-2015-13666-71zubeditufail
 
Odisha industrial policy 2007 for finance, subsidy & project related suppor...
Odisha industrial policy 2007   for finance, subsidy & project related suppor...Odisha industrial policy 2007   for finance, subsidy & project related suppor...
Odisha industrial policy 2007 for finance, subsidy & project related suppor...Radha Krishna Sahoo
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVHarish Sharma
 
Pcpir presentation jan 2011
Pcpir presentation jan 2011Pcpir presentation jan 2011
Pcpir presentation jan 2011Outlook Menia
 
Rice husk power plant project design document for finance, subsidy & projec...
Rice husk power plant project design document   for finance, subsidy & projec...Rice husk power plant project design document   for finance, subsidy & projec...
Rice husk power plant project design document for finance, subsidy & projec...Radha Krishna Sahoo
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptSrikanthTirluka1
 
MNRE_Conclave-CP-ppt-Final.pptx
MNRE_Conclave-CP-ppt-Final.pptxMNRE_Conclave-CP-ppt-Final.pptx
MNRE_Conclave-CP-ppt-Final.pptxVinodBabhale2
 
MNRE_Conclave-CP-presentation-solar.pptx
MNRE_Conclave-CP-presentation-solar.pptxMNRE_Conclave-CP-presentation-solar.pptx
MNRE_Conclave-CP-presentation-solar.pptxJigneshKadia
 

Similar to FOUNDRY PARK PPT_2023.02.24.ppt (20)

Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
Virat Vanijya_  Vishwakarma Industrial Park_r.pptxVirat Vanijya_  Vishwakarma Industrial Park_r.pptx
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
 
Scheme for Improving Industrial Infrastructure
Scheme for Improving Industrial InfrastructureScheme for Improving Industrial Infrastructure
Scheme for Improving Industrial Infrastructure
 
Project on expense booking in the service and stores section of F&A dept. of ...
Project on expense booking in the service and stores section of F&A dept. of ...Project on expense booking in the service and stores section of F&A dept. of ...
Project on expense booking in the service and stores section of F&A dept. of ...
 
Gidc corporate presentation june 2011
Gidc corporate presentation june 2011Gidc corporate presentation june 2011
Gidc corporate presentation june 2011
 
ASCC-Presentation-Coatec.pdf
ASCC-Presentation-Coatec.pdfASCC-Presentation-Coatec.pdf
ASCC-Presentation-Coatec.pdf
 
Bihar Industrial Policy. 2011
Bihar Industrial Policy. 2011Bihar Industrial Policy. 2011
Bihar Industrial Policy. 2011
 
SSL PROJECT PROFILE
SSL PROJECT PROFILESSL PROJECT PROFILE
SSL PROJECT PROFILE
 
Gidc corporate presentation jan 2011
Gidc corporate presentation jan 2011 Gidc corporate presentation jan 2011
Gidc corporate presentation jan 2011
 
PROJECT PROFILE AKWAN
PROJECT PROFILE AKWANPROJECT PROFILE AKWAN
PROJECT PROFILE AKWAN
 
Presentation 11 06-2013 changes
Presentation 11 06-2013 changesPresentation 11 06-2013 changes
Presentation 11 06-2013 changes
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
 
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
 
Lag 305 siddiqsons generation lic 14-09-2015-13666-71
Lag 305 siddiqsons generation lic 14-09-2015-13666-71Lag 305 siddiqsons generation lic 14-09-2015-13666-71
Lag 305 siddiqsons generation lic 14-09-2015-13666-71
 
Odisha industrial policy 2007 for finance, subsidy & project related suppor...
Odisha industrial policy 2007   for finance, subsidy & project related suppor...Odisha industrial policy 2007   for finance, subsidy & project related suppor...
Odisha industrial policy 2007 for finance, subsidy & project related suppor...
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
 
Pcpir presentation jan 2011
Pcpir presentation jan 2011Pcpir presentation jan 2011
Pcpir presentation jan 2011
 
Rice husk power plant project design document for finance, subsidy & projec...
Rice husk power plant project design document   for finance, subsidy & projec...Rice husk power plant project design document   for finance, subsidy & projec...
Rice husk power plant project design document for finance, subsidy & projec...
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.ppt
 
MNRE_Conclave-CP-ppt-Final.pptx
MNRE_Conclave-CP-ppt-Final.pptxMNRE_Conclave-CP-ppt-Final.pptx
MNRE_Conclave-CP-ppt-Final.pptx
 
MNRE_Conclave-CP-presentation-solar.pptx
MNRE_Conclave-CP-presentation-solar.pptxMNRE_Conclave-CP-presentation-solar.pptx
MNRE_Conclave-CP-presentation-solar.pptx
 

Recently uploaded

TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....rightmanforbloodline
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Design and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data ScienceDesign and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data SciencePaolo Missier
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusZilliz
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
AI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by AnitarajAI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by AnitarajAnitaRaj43
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseWSO2
 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingWSO2
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
Simplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptxSimplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptxMarkSteadman7
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard37
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxRemote DBA Services
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdfSandro Moreira
 
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...WSO2
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 

Recently uploaded (20)

TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Design and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data ScienceDesign and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data Science
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
AI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by AnitarajAI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by Anitaraj
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern Enterprise
 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation Computing
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Simplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptxSimplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptx
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 

FOUNDRY PARK PPT_2023.02.24.ppt

  • 1. Foundry Park Ranihati-Amta Road, Howrah, West Bengal developed by Foundry Cluster Development Association Department of MSME&T, Govt. of West Bengal Nodal Organization:WBSIDCL State Approved Industrial Park (SAIP) State Approved Industrial Park (SAIP)
  • 2. LOCATED IN :- HAULIBAGAN SAMANTI, JALABISWANATHPUR & SUVARAH MOUZA), HOWRAH DISTRICT, WEST BENGAL SITE POTENTIAL :-  THE SITE IS LOCATED IN THE HEART OF FOUNDRY INDUSTRY IN EASTERN INDIA  THE APPROACH TO SITE IS FROM HOWRAH- AMTA ROAD CONNECTED TO NH-6 Site Location
  • 3.  Registered under Section 8 of Companies Act on 29th March, 2005 with approval of WBIDC and WBPCB.  Project being implemented with partial grant for infrastructural development from Govt. of India under the Industrial Infrastructure Upgradation Scheme (IIUS), Department of Promotion of Industry and Internal Trade (DPIIT), Ministry of Commerce & Industry, GoI.  State Govt has also contributed by way of setting up of STP and upgradation of local sewarage and drainage system  Phase-I of around 600 acres with 150 foundries and allied units to be accommodated. Total area of the project envisaged is 924 acres About Foundry Park
  • 4. Project Feature Information Total Number of Units Planned Foundry Units:  100 nos. in total in 600 acres Allied (Core making, pattern making, fettling, painting, fabrication and machining shops, raw material banks etc.): 50 nos. Total Envisaged Castings Output  By end of 5th year of Commercial Operations: 5 lakh tonnes per annum. Total Envisaged Investment by Foundry Units Rs. 2500 crores Employment Potential Direct Employment: 10,000 people (approx.) Indirect Employment: 30,000 people About Foundry Park
  • 5. Land Parcel for LTS Coverage
  • 6. Sl No Major Items of Work Scope 1 ROAD WORK 11840 M 2 STORM WATER DRAIN WORK 18225 M 3 EXTERNAL WATER SUPPLY WORK 13000 M 4 WATER WORKS UGR 3 nos OHT 3 nos PH 3 nos TUBE WELLS 4 nos 5 SEWER NETWORK 12800 M 6 POWER DISTRIBUTION SYSTEM 33/11kv substation 2 nos Major Scope of Work 7 Common Facility Buildings I T I building Testing laboratory & Tool room building Information, Marketing, HRD & Management upgradation centre Pump house & its UGR for CFB units Sub-station building for CFB units Boundary wall around CFB units
  • 7. Stakeholders Contribution Contribution from Govt. of West Bengal Grant from Department of Promotion of Industry and Internal Trade (DPIIT) Govt. of India Total Project Cost Rs 95.02 Cr
  • 8. 1. 129 plots already allotted to stakeholders all from MSME sector 2. 34 nos stakeholders have started factory construction activities out of which 9 nos have started production after obtaining all statutory clearances 3. Foundries and units manufacturing Light Engineering Products are being set up Plot Status
  • 9. Source of Power : 220 KV sub-station set-up within the Park. FCDA provided approximately 15 acres of Land to WBSETCL/WBSEDCL for setting up the sub-station. The sub-station supplies uninterrupted quality power to meet the entire requirement Foundry Park. There is provision of 3 Nos 33 KV substation out of which one is operational and another one is under construction.
  • 10. Status of approvals of Foundry Park under SAIP ‘Final Approval’ in favour of Foundry Park was accorded on 20.04.2022. Now he has requested for for the release of ‘1st installment of Incentives’ of the said Industrial Park.
  • 11. Checklist according to parameter for 1st Incentive payment Sl No Criteria as per guideline Comments of PMU, WBSIDCL 1 Mutation, conversion & registration of the land in SPV’s name Mutation has already been done for total lands but conversion is yet to be done. It also attracts the memo no. 796-GE(M)/3M- 68/11; dated 25.02.2021. 2 Formation of the SPV and obtaining final approval of the AIP from the SLEC SPV already formed and obtained final approval of the AIP from the SLEC on 20.04.2022. This Park has been visited on 14th July, 2022 by the PMU Team of WBSIDCL in presence of Mr. Mukul Maity, Site Engineer, Foundry Cluster Development Association along with his team and after inspection & checking of the project it has been found that all basic and essential infrastructures have been completed as per SAIP 2020 Guideline but, the SPV has developed the Park with the assistance of Government funds. Accordingly WBSIDCL has not recommended for release of ‘incentive’ in favour of Foundry Park. SPV has also applied for reimbursement of stamp duty and registration fees and the reimbursement of said fees has been recommended.
  • 12. ….cont’d Sl Criteria as per guideline Comments of PMU, WBSIDCL 3 Completion of construction of Boundary Wall, Land filling and Internal Roads Land filling Work is almost completed (95%). The total length of Boundary Wall executed at site is 3400m (approx). So the Construction of Boundary Wall is almost completed. Internal Road Work has been completed and the total length of about 7760m. As informed by FCDA, total thickness of the internal road is 580mm consisting of 230mm GSB, 250mm WMM, 60mm DBM & 40mm BC. Two (02) nos Culvert have been constructed. Drainage System is done comprises with RCC Wall and the total length of about 7760m. Many portions of drain are choked & damaged. Irrigation Deptt has initiated the work of improvement of drainage congestion. Copy of all documents relating to KMDA work is attached. Regarding Electric Connection, FCDA informed WBSEDCL will set up a 220KVA substations from which power will be drawn for the project by two 33KVA substations. Twenty Four (24) nos Street Light have been installed along the road. Setting up of 0.80MLD CETP is under going on at the end of KMDA.
  • 13. ….cont’d RECOMMENDATIONS BY WBSIDCL Since the SPV has developed the Park with the assistance of Government funds, hence WBSIDCL has not been recommended for release of ‘incentive’ in favour of Foundry Park as per section 8(F)* of SAIP 2020. SPV has also applied for reimbursement of stamp duty and registration fees and the reimbursement of said fees has been recommended by WBSIDCL as per guideline of SAIP 2020. *As per section 8(F) of SAIP 2020 it is stated that the SPV availing of incentives under the Scheme shall be eligible to avail incentives under any other scheme of the State Government / Government of India except for the same item and excluding the cluster infrastructure development assistance as available in MSME Policy of the State Government. Individual Units coming up in the AIP shall be eligible to avail incentives under various schemes of the State Government/Central Government as per their eligibility.
  • 14. Main Entrance of the Complex
  • 15. Road Network and Other Facilities Weigh Bridge
  • 16. Road and Sewerage Construction
  • 17. Operational units at Foundry Park
  • 18. ITI & Tool Room Building
  • 19. Vivekananda Industrial Training Institute Collaborated with Paschim Banga Society of Skill Development (PBSSD) under the aegis of Ministry of Technical Education & Skill Development, Govt. of West Bengal for: Foundry courses including Melting, Moulding and Core making. Theoretical Class Practical Training Class Hostel facility for Students
  • 20. Library & reading Room Administrative Office Conference Room with Projector Infrastructure Facilities in Training Institute