SlideShare a Scribd company logo
1 of 24
IN PLANT TRAINING
Report
By,
SHIVAM JAIN
10BEC0482
INTRODUCTION
ABOUT NTPC
• India’s largest power company, NTPC was set up in 1975 to
accelerate power development in India.
• NTPC became a Maharatna company in May, 2010, one of
the only four companies to be awarded this status.
• The total installed capacity of the company is 39,174 MW
(including JVs) with 16 coal based and 7 gas based
stations, located across the country.
• In addition under JVs, 7 stations are coal based & another
station uses naptha/LNG as fuel.
• The company has set a target to have an installed power
generating capacity of 1,28,000 MW by the year 2032.
About BTPS
•
•
•
•
•
•
•
•

BADARPUR THERMAL POWER STATION was established on 1973 and it was the
part of Central Government.
On 01/04/1978 is was given to NTPC.
Since then operating performance of NTPC has been considerably above the
national average.
Badarpur thermal power station started with a single 95 mw unit.
There were 2 more units (95 MW each) installed in next 2 consecutive years.
Now it has total five units with total capacity of 720 MW. Ownership of BTPS was
transferred to NTPC with effect from 01.06.2006
The power is supplied to a 220 KV network that is a part of the northern grid.
The ten circuits through which the power is evacuated from the plant are:
o
o
o
o
o
o

1. Mehrauli
2. Okhla
3. Ballabgarh
4. Indraprastha
5. UP (Noida)
6. Jaipur
Installed Capacity
OPERATION MECHANISM
•
•
•
•

•
•
•
•

The coal is brought and crushed to
powder. This is feed to boiler for
producing heat .
In Boiler the water is converted to
steam.
In super heater the moisture content is
removed from the steam and that
steam is called super heated steam.
The superheated steam rotates the
shaft of the High pressure turbine.
The exhausted steam is sent to
preheater and the steam then rotates
the intermediate pressure (IP) turbine.
The steam from the IP Turbine is then
feed to low pressure turbine.
The turbine shaft is connected to the
Generator, which produces electric
Power.
The power generated is then
transmitted .
OPERATION AND MAINTAINANCE
• This control &
instrumentation is the
brain of the plant
because from the
relays to transmitters
followed by the
electronic computation
chipsets and recorders
and lastly the
controlling circuitry, all
fall under this.
LVDT
(Linear Variable Differential Transducers)
• An electro-mechanical device that produces
electrical output linearly proportional to
displacement of moveable core.
• play integral part in C&I lab as for pressure
measurement
• Convert minute pressure drops by virtue of
movement of plunger which causes emf to be
induced which is coverted to digital values to read.
Working :•
•

•

•

When the primary coil is energized
by an AC current, source voltage
are induced in two secondary coils.
The arrangement shown produces
net zero signal output from the
secondary's when induced voltage
are equal in each coil when core is
in center.
A movement of core leads to an
increase in magnetic coupling to
the coil in direction of movement
and reduction in other coil
producing a net output signal.
Similarly in opposite direction
produces an identical signal in
opposite phase.
Important Features :• Advantage is that moving core does not make contact with other
electrical components of the assembly.
• Offers high reliability and long life.
• Positive Over-Pressure – protected from damage by over pressure.
• Shock loading – diaphragms are not made from brittle materials
and so failures due to shock loads are rare.
• Transmitter Electronics – LVDT pressure and level transmitters
enable the user to adjust zero and span settings.
o Analogue transmitter provide only zero and span adjustment, square
root option and other
o Digital type can be configures via integral communication port.
o Thus submersible type LVDT sensor use digital signal processing.
Data Acquisition System
• A lot of Data is coming from process due to lot
of instrumentation involved.
• Target is to acquire this data at lower cost and
less complex instruments.
• To maintain line safe operation, data is
analyzed to :o Increase efficiency, reliability and availability
o Provide historical records for review
• A computerized DAS is a real time system thus
computer must have a proven and efficient
real time operating system as :o
o
o
o
o
o
o

Memory cycle time < 1 microseconds
Multiple external interrupts
Fast access disk in order of 20 millisecond
Multi memory banks and expandability to at least 64K words
Floating point hardware
Internal Interrupts for various trap conditions
Real time clocks and etc.

The actual performance of a computer system for the same hardware depends upon
the configuration , operating system and software design.
Data logging system
• Another function of system is data logging for operator
understanding.
o
o
o
o
o
o
o

Turbine run on log – start turbine roll off
Boiler starts up log
Hourly log
Summary log
Maintenance log
Performance log
Shut down log and etc.

• The plant monitoring is done by constantly scanning the
inputs and checking them against the alarm limits, if any is
out of limits then a message is printed or a light or alarm is
activated
Memory management system
• Also called as “ dynamic memory allocation “
• OS searches for an area in memory large
enough to run a program.
• OS should not do more I/O’s for memory
management than it is necessary.
• The software design and priority structure
should be thought out carefully with the
objective of minimizing access to bulk
memory.
Programmable Logic Controller (PLC)
• A digital computer for automation of electromechanical processes.

• PROGRAMMABLE LOGIC CONTROLLER is a solid state control
system that continuously monitors the status of devices connected
as inputs. Based upon a user written program, stored in memory, it
controls the status of devices connected as outputs.
• Control of machinery as in factory assembly lines, amusement rides
or light fixtures.
• PLC is designed for multiple inputs and outputs, extended
temperature ranges , immunity to electrical noise and resistance to
vibration and impact
• Programs are stored in battery-backed-up or non volatile memory.
• Automotive industry is still one of the largest users of PLCs
Need of PLC
References :• Reading material from Mr. Ashish Agrawal
(senior superintendent) and other C&I officials
• Nalanda library at NTPC
• Various links used :
o http://ntpc.co.in
o http://en.wikipedia.org/wiki/Linear_variable_differential_transformer and etc.
THANKYOU

More Related Content

What's hot

Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC pptkirbadh
 
Ntpc badarpur training ppt
Ntpc badarpur training pptNtpc badarpur training ppt
Ntpc badarpur training pptanuj_kumar57
 
Industrial summer training at ntpc,badarpur
Industrial summer training at ntpc,badarpurIndustrial summer training at ntpc,badarpur
Industrial summer training at ntpc,badarpurMadhur Sharma
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar Dilip kumar
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt nilesh choubey
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipatpratikguptateddy
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivankshivank Kumar
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpurShrey Dhasmana
 
NTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingNTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingAbhitendra Singh
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT94600banti
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli Ram Narayan Shah
 
DADRI GAS POWER PLANT report
DADRI GAS POWER PLANT reportDADRI GAS POWER PLANT report
DADRI GAS POWER PLANT report94600banti
 

What's hot (20)

Report ntpc
Report ntpcReport ntpc
Report ntpc
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
Ntpc report
Ntpc reportNtpc report
Ntpc report
 
Ntpc badarpur training ppt
Ntpc badarpur training pptNtpc badarpur training ppt
Ntpc badarpur training ppt
 
Industrial summer training at ntpc,badarpur
Industrial summer training at ntpc,badarpurIndustrial summer training at ntpc,badarpur
Industrial summer training at ntpc,badarpur
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivank
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
NTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingNTPC Auraiya Industrial Training
NTPC Auraiya Industrial Training
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
 
NTPC Seminar
NTPC SeminarNTPC Seminar
NTPC Seminar
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
 
DADRI GAS POWER PLANT report
DADRI GAS POWER PLANT reportDADRI GAS POWER PLANT report
DADRI GAS POWER PLANT report
 

Similar to Ntpc badarpur summer training

MECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .ppt
MECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .pptMECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .ppt
MECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .pptCHANDRA KUMAR S
 
UNIT IV PROGRAMMABLE LOGIC CONTROLLER
UNIT IV PROGRAMMABLE LOGIC CONTROLLER UNIT IV PROGRAMMABLE LOGIC CONTROLLER
UNIT IV PROGRAMMABLE LOGIC CONTROLLER ravis205084
 
20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.ppt20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.pptMohanumar S
 
Programmable logic Controlller ppt
Programmable logic Controlller pptProgrammable logic Controlller ppt
Programmable logic Controlller pptkarthik R
 
Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS
Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS
Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS Mohanumar S
 
PresentationGGSSTP_Atul
PresentationGGSSTP_AtulPresentationGGSSTP_Atul
PresentationGGSSTP_AtulAtul Kataria
 
catalog Frenic AQUA catalog - www.haophuong.com
catalog Frenic AQUA catalog - www.haophuong.comcatalog Frenic AQUA catalog - www.haophuong.com
catalog Frenic AQUA catalog - www.haophuong.comCTY TNHH HẠO PHƯƠNG
 
Programmable Logic Controller
Programmable Logic ControllerProgrammable Logic Controller
Programmable Logic ControllerArul Kumar
 
Control and instrumentation
Control and instrumentationControl and instrumentation
Control and instrumentationVSRAGHU
 
Industrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod applicationIndustrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod applicationAvinash Vemula
 
Distributed control system presentation
Distributed control system presentationDistributed control system presentation
Distributed control system presentationAYUSH VARSHNEY
 
Bangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewBangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewRidwanul Hoque
 
PLC Introduction Details
PLC Introduction DetailsPLC Introduction Details
PLC Introduction Detailssuhaskhadake
 
Introduction_to_Mechatronics_Chapter4.pdf
Introduction_to_Mechatronics_Chapter4.pdfIntroduction_to_Mechatronics_Chapter4.pdf
Introduction_to_Mechatronics_Chapter4.pdfBereket Walle
 
DATA LOGER GSM MODULATOR
DATA LOGER GSM MODULATORDATA LOGER GSM MODULATOR
DATA LOGER GSM MODULATORsikandar8233
 
Lecture+9+-+SCADA+Systems.pptx
Lecture+9+-+SCADA+Systems.pptxLecture+9+-+SCADA+Systems.pptx
Lecture+9+-+SCADA+Systems.pptxsurangagw
 

Similar to Ntpc badarpur summer training (20)

MECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .ppt
MECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .pptMECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .ppt
MECHATRONICS-UNIT 4-PROGRAMMABLE LOGIC CONTROLLER .ppt
 
UNIT IV PROGRAMMABLE LOGIC CONTROLLER
UNIT IV PROGRAMMABLE LOGIC CONTROLLER UNIT IV PROGRAMMABLE LOGIC CONTROLLER
UNIT IV PROGRAMMABLE LOGIC CONTROLLER
 
20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.ppt20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.ppt
 
Programmable logic Controlller ppt
Programmable logic Controlller pptProgrammable logic Controlller ppt
Programmable logic Controlller ppt
 
Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS
Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS
Unit 4-PROGRAMMABLE LOGIC INTERFACE-ME6702– MECHATRONICS
 
C&i systems
C&i systemsC&i systems
C&i systems
 
PresentationGGSSTP_Atul
PresentationGGSSTP_AtulPresentationGGSSTP_Atul
PresentationGGSSTP_Atul
 
INTERNSHIP DHEERAJ.pptx
INTERNSHIP DHEERAJ.pptxINTERNSHIP DHEERAJ.pptx
INTERNSHIP DHEERAJ.pptx
 
catalog Frenic AQUA catalog - www.haophuong.com
catalog Frenic AQUA catalog - www.haophuong.comcatalog Frenic AQUA catalog - www.haophuong.com
catalog Frenic AQUA catalog - www.haophuong.com
 
Programmable Logic Controller
Programmable Logic ControllerProgrammable Logic Controller
Programmable Logic Controller
 
Control and instrumentation
Control and instrumentationControl and instrumentation
Control and instrumentation
 
Industrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod applicationIndustrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod application
 
BHAVESH AGRAWAL.pptx
BHAVESH AGRAWAL.pptxBHAVESH AGRAWAL.pptx
BHAVESH AGRAWAL.pptx
 
Distributed control system presentation
Distributed control system presentationDistributed control system presentation
Distributed control system presentation
 
Bangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewBangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants Overview
 
PLC Introduction Details
PLC Introduction DetailsPLC Introduction Details
PLC Introduction Details
 
Introduction_to_Mechatronics_Chapter4.pdf
Introduction_to_Mechatronics_Chapter4.pdfIntroduction_to_Mechatronics_Chapter4.pdf
Introduction_to_Mechatronics_Chapter4.pdf
 
DATA LOGER GSM MODULATOR
DATA LOGER GSM MODULATORDATA LOGER GSM MODULATOR
DATA LOGER GSM MODULATOR
 
PLC - Programmable Logic Controller
PLC - Programmable Logic ControllerPLC - Programmable Logic Controller
PLC - Programmable Logic Controller
 
Lecture+9+-+SCADA+Systems.pptx
Lecture+9+-+SCADA+Systems.pptxLecture+9+-+SCADA+Systems.pptx
Lecture+9+-+SCADA+Systems.pptx
 

Recently uploaded

Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 

Recently uploaded (20)

TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 

Ntpc badarpur summer training

  • 3. ABOUT NTPC • India’s largest power company, NTPC was set up in 1975 to accelerate power development in India. • NTPC became a Maharatna company in May, 2010, one of the only four companies to be awarded this status. • The total installed capacity of the company is 39,174 MW (including JVs) with 16 coal based and 7 gas based stations, located across the country. • In addition under JVs, 7 stations are coal based & another station uses naptha/LNG as fuel. • The company has set a target to have an installed power generating capacity of 1,28,000 MW by the year 2032.
  • 4. About BTPS • • • • • • • • BADARPUR THERMAL POWER STATION was established on 1973 and it was the part of Central Government. On 01/04/1978 is was given to NTPC. Since then operating performance of NTPC has been considerably above the national average. Badarpur thermal power station started with a single 95 mw unit. There were 2 more units (95 MW each) installed in next 2 consecutive years. Now it has total five units with total capacity of 720 MW. Ownership of BTPS was transferred to NTPC with effect from 01.06.2006 The power is supplied to a 220 KV network that is a part of the northern grid. The ten circuits through which the power is evacuated from the plant are: o o o o o o 1. Mehrauli 2. Okhla 3. Ballabgarh 4. Indraprastha 5. UP (Noida) 6. Jaipur
  • 6.
  • 7. OPERATION MECHANISM • • • • • • • • The coal is brought and crushed to powder. This is feed to boiler for producing heat . In Boiler the water is converted to steam. In super heater the moisture content is removed from the steam and that steam is called super heated steam. The superheated steam rotates the shaft of the High pressure turbine. The exhausted steam is sent to preheater and the steam then rotates the intermediate pressure (IP) turbine. The steam from the IP Turbine is then feed to low pressure turbine. The turbine shaft is connected to the Generator, which produces electric Power. The power generated is then transmitted .
  • 8.
  • 9.
  • 10. OPERATION AND MAINTAINANCE • This control & instrumentation is the brain of the plant because from the relays to transmitters followed by the electronic computation chipsets and recorders and lastly the controlling circuitry, all fall under this.
  • 11. LVDT (Linear Variable Differential Transducers) • An electro-mechanical device that produces electrical output linearly proportional to displacement of moveable core. • play integral part in C&I lab as for pressure measurement • Convert minute pressure drops by virtue of movement of plunger which causes emf to be induced which is coverted to digital values to read.
  • 12. Working :• • • • When the primary coil is energized by an AC current, source voltage are induced in two secondary coils. The arrangement shown produces net zero signal output from the secondary's when induced voltage are equal in each coil when core is in center. A movement of core leads to an increase in magnetic coupling to the coil in direction of movement and reduction in other coil producing a net output signal. Similarly in opposite direction produces an identical signal in opposite phase.
  • 13. Important Features :• Advantage is that moving core does not make contact with other electrical components of the assembly. • Offers high reliability and long life. • Positive Over-Pressure – protected from damage by over pressure. • Shock loading – diaphragms are not made from brittle materials and so failures due to shock loads are rare. • Transmitter Electronics – LVDT pressure and level transmitters enable the user to adjust zero and span settings. o Analogue transmitter provide only zero and span adjustment, square root option and other o Digital type can be configures via integral communication port. o Thus submersible type LVDT sensor use digital signal processing.
  • 14. Data Acquisition System • A lot of Data is coming from process due to lot of instrumentation involved. • Target is to acquire this data at lower cost and less complex instruments. • To maintain line safe operation, data is analyzed to :o Increase efficiency, reliability and availability o Provide historical records for review
  • 15. • A computerized DAS is a real time system thus computer must have a proven and efficient real time operating system as :o o o o o o o Memory cycle time < 1 microseconds Multiple external interrupts Fast access disk in order of 20 millisecond Multi memory banks and expandability to at least 64K words Floating point hardware Internal Interrupts for various trap conditions Real time clocks and etc. The actual performance of a computer system for the same hardware depends upon the configuration , operating system and software design.
  • 16. Data logging system • Another function of system is data logging for operator understanding. o o o o o o o Turbine run on log – start turbine roll off Boiler starts up log Hourly log Summary log Maintenance log Performance log Shut down log and etc. • The plant monitoring is done by constantly scanning the inputs and checking them against the alarm limits, if any is out of limits then a message is printed or a light or alarm is activated
  • 17. Memory management system • Also called as “ dynamic memory allocation “ • OS searches for an area in memory large enough to run a program. • OS should not do more I/O’s for memory management than it is necessary. • The software design and priority structure should be thought out carefully with the objective of minimizing access to bulk memory.
  • 18. Programmable Logic Controller (PLC) • A digital computer for automation of electromechanical processes. • PROGRAMMABLE LOGIC CONTROLLER is a solid state control system that continuously monitors the status of devices connected as inputs. Based upon a user written program, stored in memory, it controls the status of devices connected as outputs. • Control of machinery as in factory assembly lines, amusement rides or light fixtures. • PLC is designed for multiple inputs and outputs, extended temperature ranges , immunity to electrical noise and resistance to vibration and impact • Programs are stored in battery-backed-up or non volatile memory. • Automotive industry is still one of the largest users of PLCs
  • 19.
  • 20.
  • 22.
  • 23. References :• Reading material from Mr. Ashish Agrawal (senior superintendent) and other C&I officials • Nalanda library at NTPC • Various links used : o http://ntpc.co.in o http://en.wikipedia.org/wiki/Linear_variable_differential_transformer and etc.