SlideShare a Scribd company logo
1 of 16
Download to read offline
WELCOMEPMP Preparation Course [PMBOK V.6]
Conduct Procurements
Sherif Sabri, PMP®
With
Sherif Sabri, PMP®
 Overview
Conduct Procurements
 Conduct Procurements - Inputs
 Conduct Procurements - Tools & Techniques
 Conduct Procurements - Outputs
Sherif Sabri, PMP®
OVERVIEW
Procurement
Process No. (2)
Executing
Process No. (9)
performed
throughout
the project as
needed
The process of obtaining seller responses, selecting a seller, and awarding a contract.
The key benefit of this process is that
- it selects a qualified seller and implements the legal agreement for delivery. The end results of the process
are the established agreements including formal contracts.
CONDUCT PROCUREMENTS
Inputs Tools & Techniques Outputs
.1 Project management plan
• Scope management plan
• Requirements management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Configuration management plan
• Cost baseline
.2 Project documents
• Lessons learned register
• Project schedule
• Requirements documentation
• Risk register
• Stakeholder register
.3 Procurement documentation
.4 Seller proposals
.5 EEF
.6 OPA
.1 Expert judgment
.2 Advertising
.3 Bidder conferences
.4 Data analysis
• Proposal evaluation
.5 Interpersonal and team skills
• Negotiation
.1 Selected sellers
.2 Agreements
.3 Change requests
.4 Project management plan updates
• Requirements management plan
• Quality management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Scope baseline
• Schedule baseline
• Cost baseline
.5 Project documents updates
• Lessons learned register
• Requirements documentation
• Requirements traceability matrix
• Resource calendars
• Risk register
• Stakeholder register
.6 OPA updates
OVERVIEW
1-PROJECT MANAGEMENT PLAN
 Scope management plan: describes how the overall scope of work will be managed, including the scope
performed by sellers.
 Requirements management plan: describes how requirements will be analyzed, documented, and
managed. The requirements management plan may include how sellers will manage the requirements
they are under agreement to satisfy.
 Communications management plan: describes how communications between buyers and sellers will be
conducted.
 Risk management plan: describes how risk management activities will be structured and performed for
the project.
 Procurement management plan: contains the activities to be undertaken during the Conduct
Procurements process.
 Configuration management plan: defines those items that are configurable, those items that require
formal change control, and the process for controlling changes to such items. It includes formats and
processes for how sellers will provide configuration management in a way that is consistent with the
buyer’s approach.
 Cost baseline: includes the budget for the procurement as well as costs associated with managing the
procurement process and sellers.
Conduct Procurements - Inputs
2-PROJECT DOCUMENTS
 Lessons learned register: Lessons learned earlier in the project with regard to conducting procurement
can be applied to later phases in the project to improve the efficiency of this process.
 Project schedule: identifies the start and end dates of project activities, including procurement
activities. It also defines when contractor deliverables are due.
 Requirements documentation include:
 Technical requirements the seller is required to satisfy, and
 Requirements with contractual and legal implications that may include:
 health, safety, security, performance, environmental, insurance, intellectual property rights,
equal employment opportunity, licenses, permits, and other nontechnical requirements.
 Risk register: Each approved seller comes with its own unique set of risks, depending on the seller’s
organization, the duration of the contract, the external environment, the project delivery method, the
type of contracting vehicle chosen, and the final agreed-upon price.
 Stakeholder register: This document contains all of the details about the identified stakeholders.
Conduct Procurements - Inputs
3-PROCUREMENT DOCUMENTATION
 Bid documents: Procurement documents include the RFI, RFP, RFQ, or other documents sent to sellers so
they can develop a bid response.
 Procurement statement of work (SOW) : provides sellers with a clearly stated set of goals, requirements,
and outcomes from which they can provide a quantifiable response.
 Independent cost estimates: are developed either internally or by using external resources and provide a
reasonableness check against the proposals submitted by bidders.
 Source selection criteria: These criteria describe how bidder proposals will be evaluated, including
evaluation criteria and weights. For risk mitigation, the buyer may decide to sign agreements with more than
one seller to mitigate damage caused by a single seller having problems that impact the overall project.
Conduct Procurements - Inputs
4-SELLER PROPOSALS
Seller proposals, prepared in response to a procurement document package, form the basic information
that will be used by an evaluation body to select one or more successful bidders (sellers). If the seller is
going to submit a price proposal, good practice is to require that it be separate from the technical proposal.
The evaluation body reviews each submitted proposal according to the source selection criteria and selects
the seller that can best satisfy the buying organization’s requirements.
5- EEF
 Local laws and regulations regarding procurements;
 Local laws and regulations ensuring that the major procurements involve local sellers;
 External economic environment constraining procurement processes;
 Marketplace conditions;
 Information on relevant past experience with sellers, both good and bad;
 Prior agreements already in place;
 Contract management systems.
6- OPA
 List of preferred sellers that have been prequalified,
 Organizational policies that influence the selection of a seller,
 Specific organizational templates or guidelines that will determine the way agreements are drafted and built,
 Financial policies and procedures regarding invoicing and payment processes..
Conduct Procurements - Inputs
1-EXPERT JUDGMENT
For this process, expertise should be considered from individuals or groups with specialized
knowledge of or training in the following topics:
 Proposal evaluation;
 Technical or subject matter;
 Relevant functional areas such as finance, engineering, design, development, supply chain management, etc.;
 Industry regulatory environment;
 Laws, regulations, and compliance requirements; and
 Negotiation.
Conduct Procurements - Tools & Techniques
2-ADVERTISING
 Is communicating with users or potential users of a product, service, or result. Existing lists of potential sellers often can be
expanded by placing advertisements in general circulation publications such as selected newspapers or in specialty trade
publications. Most government jurisdictions require public advertising or online posting of pending government contracts.
3-BIDDER CONFERENCES = (contractor conferences, vendor conferences, and pre-bid conferences)
 Are meetings between the buyer and prospective sellers prior to proposal submittal. They are used to ensure that all
prospective bidders have a clear and common understanding of the procurement and no bidders receive preferential
treatment.
4-DATA ANALYSIS
 Proposal Evaluation: Proposals are evaluated to ensure they are complete and respond in full to the bid documents,
procurement statement of work, source selection criteria, and any other documents that went out in the bid package.
Conduct Procurements - Tools & Techniques
5-INTERPERSONAL AND TEAM SKILLS
 Negotiation: is a discussion aimed at reaching an agreement.
 Procurement negotiation clarifies the structure, rights, and obligations of the parties and other terms of the purchases so
that mutual agreement can be reached prior to signing the contract.
 Final document language reflects all agreements reached.
 Negotiation concludes with a signed contract document or other formal agreement that can be executed by both buyer
and seller.
 The negotiation should be led by a member of the procurement team that has the authority to sign contracts.
 The project manager and other members of the project management team may be present during negotiation to provide
assistance as needed.
Conduct Procurements - Tools & Techniques
1-SELECTED SELLERS
 Are those who have been judged to be in a competitive range based on the outcome of the proposal or bid evaluation.
Final approval of complex, high-value, high-risk procurements will generally require organizational senior management
approval prior to award.
2-AGREEMENTS
A contract is a mutually binding agreement that obligates the seller to provide the specified products, services, or results;
obligates the buyer to compensate the seller; and represents a legal relationship that is subject to remedy in the courts.
The major components in an agreement document include:
 Procurement statement of work or major deliverables;
 Schedule, milestones, or date by which a schedule is required;
 Performance reporting;
 Pricing and payment terms;
 Inspection, quality, and acceptance criteria;
 Warranty and future product support;
 Incentives and penalties;
 Insurance and performance bonds;
 Subordinate subcontractor approvals;
 General terms and conditions;
 Change request handling; and
 Termination clause and alternative dispute resolution mechanisms.
Conduct Procurements - Outputs
3-CHANGE REQUESTS
 Change requests to the project management plan, its subsidiary plans, and other components are processed for review
and disposition through the Perform Integrated Change Control process
4-PROJECT MANAGEMENT PLAN UPDATES
 Requirements management plan: There may be changes to project requirements due to changes identified by sellers.
 Quality management plan: Sellers may offer alternative quality standards or alternative solutions that impact the quality approaches
defined in the quality management plan.
 Communications management plan: As sellers are hired, the communications management plan is updated to incorporate their
communications needs and approaches.
 Risk management plan: Each agreement and seller has its own set of risks that may require updates to the risk management plan. Specific
risks are incorporated into the risk register.
 Procurement management plan: Updates may be required depending on the results of the contracting and negotiations processes.
 Scope baseline: The project WBS and deliverables documented in the scope baseline are considered when performing procurement
activities. Any one or all of these may change during the procurement process.
 Schedule baseline: If there are delivery changes created by sellers that impact overall project schedule performance, the baseline
schedule may need to be updated and approved to reflect the current expectations.
 Cost baseline: Contractor and materials prices can change frequently during the delivery of a project. These changes can occur because of
fluctuating materials and labor prices created by the external economic environment and need to be incorporated into the cost baseline.
Conduct Procurements - Outputs
5-PROJECT DOCUMENTS UPDATES
 Lessons learned register: is updated with information on challenges encountered while conducting
procurements and how they could have been avoided as well as approaches that worked well.
 Risk register: Each approved seller comes with its own unique set of risks, depending on the seller’s organization, the
duration of the contract, the external environment, the project delivery method, the type of contracting vehicle chosen, and
the final agreed-upon price. Changes are made to the risk register during the contracting process, which reflect the specific
risks of each seller.
 Requirements documentation include:
 Technical requirements the seller is required to satisfy, and
 Requirements with contractual and legal implications that may include:
 health, safety, security, performance, environmental, insurance, intellectual property rights,
equal employment opportunity, licenses, permits, and other nontechnical requirements.
 Requirements traceability matrix: As sellers are incorporated into the project’s plan, the
requirements register and the traceability matrix may change depending on the capabilities of the
specific seller.
 Stakeholder register: The stakeholder register is updated as agreements are made with specific sellers.
 Resource calendars: Schedule resource calendars may need to be updated depending on the
availabilities of the sellers.
Conduct Procurements - Outputs
6-ORGANIZATIONAL PROCESS ASSETS UPDATES
 Listings of prospective and prequalified sellers; and
 Information on relevant experience with sellers, both good and bad
Conduct Procurements - Outputs
T H A N K S F O R W A T C H I N G
Together We will get it done
Sherif Sabri, PMP®

More Related Content

What's hot

Project Management-Project procurement Management
Project Management-Project procurement ManagementProject Management-Project procurement Management
Project Management-Project procurement ManagementYogender Singh Rana
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPMMudassir Iqbal
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementSarah Fox
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management Serdar Temiz
 
Procurement Mgmt Supplement1
Procurement Mgmt Supplement1Procurement Mgmt Supplement1
Procurement Mgmt Supplement1zfr71
 
Procurement management by- Prateek kumar
Procurement management by- Prateek kumarProcurement management by- Prateek kumar
Procurement management by- Prateek kumarPrateek Kumar
 
Public procurement roadshow presentation
Public procurement roadshow presentationPublic procurement roadshow presentation
Public procurement roadshow presentationBlake Morgan LLP
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment ManagementSaad Al Jabri
 
Training _ZK _Rev3_Final
Training _ZK _Rev3_FinalTraining _ZK _Rev3_Final
Training _ZK _Rev3_FinalZiad Khleif
 
Raffles International Institute_Procurement methods
Raffles International  Institute_Procurement methodsRaffles International  Institute_Procurement methods
Raffles International Institute_Procurement methodsSandra Draskovic
 
procurement plan details
procurement plan detailsprocurement plan details
procurement plan detailsManjul Shrestha
 
IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008IFAD Vietnam
 
Streamlined Tender Evaluation Presentation
Streamlined Tender Evaluation PresentationStreamlined Tender Evaluation Presentation
Streamlined Tender Evaluation PresentationNigel_Moore
 
Project Procurement - Principles and Case Study
Project Procurement - Principles and Case StudyProject Procurement - Principles and Case Study
Project Procurement - Principles and Case StudyKiran Radhakrishnan
 

What's hot (20)

Chap12 project procurement management
Chap12 project procurement managementChap12 project procurement management
Chap12 project procurement management
 
Project Management-Project procurement Management
Project Management-Project procurement ManagementProject Management-Project procurement Management
Project Management-Project procurement Management
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
 
12 procurement
12 procurement12 procurement
12 procurement
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on Procurement
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management
 
Procurement Mgmt Supplement1
Procurement Mgmt Supplement1Procurement Mgmt Supplement1
Procurement Mgmt Supplement1
 
Procurement management by- Prateek kumar
Procurement management by- Prateek kumarProcurement management by- Prateek kumar
Procurement management by- Prateek kumar
 
Pm session11
Pm session11Pm session11
Pm session11
 
Public procurement roadshow presentation
Public procurement roadshow presentationPublic procurement roadshow presentation
Public procurement roadshow presentation
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment Management
 
12 project procurement management
12 project procurement management12 project procurement management
12 project procurement management
 
Session 19 4th edition PMP
Session  19 4th edition PMPSession  19 4th edition PMP
Session 19 4th edition PMP
 
Training _ZK _Rev3_Final
Training _ZK _Rev3_FinalTraining _ZK _Rev3_Final
Training _ZK _Rev3_Final
 
Raffles International Institute_Procurement methods
Raffles International  Institute_Procurement methodsRaffles International  Institute_Procurement methods
Raffles International Institute_Procurement methods
 
procurement plan details
procurement plan detailsprocurement plan details
procurement plan details
 
IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008
 
Streamlined Tender Evaluation Presentation
Streamlined Tender Evaluation PresentationStreamlined Tender Evaluation Presentation
Streamlined Tender Evaluation Presentation
 
Project Procurement - Principles and Case Study
Project Procurement - Principles and Case StudyProject Procurement - Principles and Case Study
Project Procurement - Principles and Case Study
 

Similar to Conduct procurements

L7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfL7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfMUST
 
Control procurement
Control procurement Control procurement
Control procurement Shereef Sabri
 
Lecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptxLecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptxMuhammadAftab89
 
2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]Firly Zulkifli
 
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docxCONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docxaidaclewer
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahidashahida quraishi
 
Procurement ops450
Procurement ops450Procurement ops450
Procurement ops450kahogan62
 
purchasing and contracting for projects
 purchasing and contracting for projects purchasing and contracting for projects
purchasing and contracting for projectsSomashekar S.M
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxtienmixon
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 ProjectManagementDocs.comProcurement Management Plan Temp.docx ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxgertrudebellgrove
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan templateVivek Srivastava
 
Chapter 2 procurment process
Chapter 2 procurment processChapter 2 procurment process
Chapter 2 procurment processYonasSisayAragie
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid Daoud
 
Part Three - The Role of Strategy in PPM - 2022.pptx
Part Three - The Role of Strategy in PPM - 2022.pptxPart Three - The Role of Strategy in PPM - 2022.pptx
Part Three - The Role of Strategy in PPM - 2022.pptxGetanehMulualemGelaw
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015SONU61709
 

Similar to Conduct procurements (20)

L7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfL7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdf
 
Control procurement
Control procurement Control procurement
Control procurement
 
Project procurement management PMBOK Sixth Edition
Project procurement management PMBOK Sixth EditionProject procurement management PMBOK Sixth Edition
Project procurement management PMBOK Sixth Edition
 
Pmp procurement rev
Pmp procurement revPmp procurement rev
Pmp procurement rev
 
Lecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptxLecture-10-10052021-030135pm-29092022-070414pm.pptx
Lecture-10-10052021-030135pm-29092022-070414pm.pptx
 
2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]2 asca 2- purcasing [compatibility mode]
2 asca 2- purcasing [compatibility mode]
 
Procurement management
Procurement managementProcurement management
Procurement management
 
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docxCONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahida
 
Procurement ops450
Procurement ops450Procurement ops450
Procurement ops450
 
Project Procurement Management
Project Procurement ManagementProject Procurement Management
Project Procurement Management
 
purchasing and contracting for projects
 purchasing and contracting for projects purchasing and contracting for projects
purchasing and contracting for projects
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 ProjectManagementDocs.comProcurement Management Plan Temp.docx ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan template
 
Chapter 2 procurment process
Chapter 2 procurment processChapter 2 procurment process
Chapter 2 procurment process
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016
 
Part Three - The Role of Strategy in PPM - 2022.pptx
Part Three - The Role of Strategy in PPM - 2022.pptxPart Three - The Role of Strategy in PPM - 2022.pptx
Part Three - The Role of Strategy in PPM - 2022.pptx
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015
 
research.pptx
research.pptxresearch.pptx
research.pptx
 

More from Shereef Sabri

Project risk management overview
Project risk management overviewProject risk management overview
Project risk management overviewShereef Sabri
 
Plan risk management
Plan risk management Plan risk management
Plan risk management Shereef Sabri
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis Shereef Sabri
 
Perform qualitative risk analysis
Perform qualitative risk analysis Perform qualitative risk analysis
Perform qualitative risk analysis Shereef Sabri
 
Implement risk responses
Implement risk responses Implement risk responses
Implement risk responses Shereef Sabri
 
Project procurement management overview
Project procurement management overviewProject procurement management overview
Project procurement management overviewShereef Sabri
 
Develop project charter
Develop project charterDevelop project charter
Develop project charterShereef Sabri
 

More from Shereef Sabri (10)

Project risk management overview
Project risk management overviewProject risk management overview
Project risk management overview
 
Plan risk responses
Plan risk responsesPlan risk responses
Plan risk responses
 
Plan risk management
Plan risk management Plan risk management
Plan risk management
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis
 
Perform qualitative risk analysis
Perform qualitative risk analysis Perform qualitative risk analysis
Perform qualitative risk analysis
 
Monitor risks
Monitor risks Monitor risks
Monitor risks
 
Implement risk responses
Implement risk responses Implement risk responses
Implement risk responses
 
Identify risks
Identify risksIdentify risks
Identify risks
 
Project procurement management overview
Project procurement management overviewProject procurement management overview
Project procurement management overview
 
Develop project charter
Develop project charterDevelop project charter
Develop project charter
 

Recently uploaded

Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...
Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...
Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...CIOWomenMagazine
 
Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Lilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptxLilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptxABMWeaklings
 
E J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxE J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxJackieSparrow3
 
办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改
办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改
办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改atducpo
 
Dhule Call Girls #9907093804 Contact Number Escorts Service Dhule
Dhule Call Girls #9907093804 Contact Number Escorts Service DhuleDhule Call Girls #9907093804 Contact Number Escorts Service Dhule
Dhule Call Girls #9907093804 Contact Number Escorts Service Dhulesrsj9000
 
Call Girls In Andheri East Call US Pooja📞 9892124323 Book Hot And
Call Girls In Andheri East Call US Pooja📞 9892124323 Book Hot AndCall Girls In Andheri East Call US Pooja📞 9892124323 Book Hot And
Call Girls In Andheri East Call US Pooja📞 9892124323 Book Hot AndPooja Nehwal
 
Breath, Brain & Beyond_A Holistic Approach to Peak Performance.pdf
Breath, Brain & Beyond_A Holistic Approach to Peak Performance.pdfBreath, Brain & Beyond_A Holistic Approach to Peak Performance.pdf
Breath, Brain & Beyond_A Holistic Approach to Peak Performance.pdfJess Walker
 
《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...
《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...
《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...ur8mqw8e
 
Postal Ballot procedure for employees to utilise
Postal Ballot procedure for employees to utilisePostal Ballot procedure for employees to utilise
Postal Ballot procedure for employees to utiliseccsubcollector
 
Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ Escorts
(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ Escorts(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ Escorts
(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ EscortsDelhi Escorts Service
 
Call Girls Anjuna beach Mariott Resort ₰8588052666
Call Girls Anjuna beach Mariott Resort ₰8588052666Call Girls Anjuna beach Mariott Resort ₰8588052666
Call Girls Anjuna beach Mariott Resort ₰8588052666nishakur201
 
办理西悉尼大学毕业证成绩单、制作假文凭
办理西悉尼大学毕业证成绩单、制作假文凭办理西悉尼大学毕业证成绩单、制作假文凭
办理西悉尼大学毕业证成绩单、制作假文凭o8wvnojp
 
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...anilsa9823
 
Cheap Rate ➥8448380779 ▻Call Girls In Mg Road Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Mg Road GurgaonCheap Rate ➥8448380779 ▻Call Girls In Mg Road Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Mg Road GurgaonDelhi Call girls
 
social media chat application main ppt.pptx
social media chat application main ppt.pptxsocial media chat application main ppt.pptx
social media chat application main ppt.pptxsprasad829829
 
REFLECTIONS Newsletter Jan-Jul 2024.pdf.pdf
REFLECTIONS Newsletter Jan-Jul 2024.pdf.pdfREFLECTIONS Newsletter Jan-Jul 2024.pdf.pdf
REFLECTIONS Newsletter Jan-Jul 2024.pdf.pdfssusere8ea60
 

Recently uploaded (20)

Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...
Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...
Understanding Relationship Anarchy: A Guide to Liberating Love | CIO Women Ma...
 
Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Kalyan Vihar Delhi 💯 Call Us 🔝8264348440🔝
 
Lilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptxLilac Illustrated Social Psychology Presentation.pptx
Lilac Illustrated Social Psychology Presentation.pptx
 
escort service sasti (*~Call Girls in Paschim Vihar Metro❤️9953056974
escort service  sasti (*~Call Girls in Paschim Vihar Metro❤️9953056974escort service  sasti (*~Call Girls in Paschim Vihar Metro❤️9953056974
escort service sasti (*~Call Girls in Paschim Vihar Metro❤️9953056974
 
Model Call Girl in Lado Sarai Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Lado Sarai Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Lado Sarai Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Lado Sarai Delhi reach out to us at 🔝9953056974🔝
 
E J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxE J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptx
 
办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改
办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改
办理国外毕业证学位证《原版美国montana文凭》蒙大拿州立大学毕业证制作成绩单修改
 
Dhule Call Girls #9907093804 Contact Number Escorts Service Dhule
Dhule Call Girls #9907093804 Contact Number Escorts Service DhuleDhule Call Girls #9907093804 Contact Number Escorts Service Dhule
Dhule Call Girls #9907093804 Contact Number Escorts Service Dhule
 
Call Girls In Andheri East Call US Pooja📞 9892124323 Book Hot And
Call Girls In Andheri East Call US Pooja📞 9892124323 Book Hot AndCall Girls In Andheri East Call US Pooja📞 9892124323 Book Hot And
Call Girls In Andheri East Call US Pooja📞 9892124323 Book Hot And
 
Breath, Brain & Beyond_A Holistic Approach to Peak Performance.pdf
Breath, Brain & Beyond_A Holistic Approach to Peak Performance.pdfBreath, Brain & Beyond_A Holistic Approach to Peak Performance.pdf
Breath, Brain & Beyond_A Holistic Approach to Peak Performance.pdf
 
《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...
《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...
《塔夫斯大学毕业证成绩单购买》做Tufts文凭毕业证成绩单/伪造美国假文凭假毕业证书图片Q微信741003700《塔夫斯大学毕业证购买》《Tufts毕业文...
 
Postal Ballot procedure for employees to utilise
Postal Ballot procedure for employees to utilisePostal Ballot procedure for employees to utilise
Postal Ballot procedure for employees to utilise
 
Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Govindpuri Delhi 💯Call Us 🔝8264348440🔝
 
(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ Escorts
(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ Escorts(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ Escorts
(No.1)↠Young Call Girls in Sikanderpur (Gurgaon) ꧁❤ 9711911712 ❤꧂ Escorts
 
Call Girls Anjuna beach Mariott Resort ₰8588052666
Call Girls Anjuna beach Mariott Resort ₰8588052666Call Girls Anjuna beach Mariott Resort ₰8588052666
Call Girls Anjuna beach Mariott Resort ₰8588052666
 
办理西悉尼大学毕业证成绩单、制作假文凭
办理西悉尼大学毕业证成绩单、制作假文凭办理西悉尼大学毕业证成绩单、制作假文凭
办理西悉尼大学毕业证成绩单、制作假文凭
 
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
Lucknow 💋 High Class Call Girls Lucknow 10k @ I'm VIP Independent Escorts Gir...
 
Cheap Rate ➥8448380779 ▻Call Girls In Mg Road Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Mg Road GurgaonCheap Rate ➥8448380779 ▻Call Girls In Mg Road Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Mg Road Gurgaon
 
social media chat application main ppt.pptx
social media chat application main ppt.pptxsocial media chat application main ppt.pptx
social media chat application main ppt.pptx
 
REFLECTIONS Newsletter Jan-Jul 2024.pdf.pdf
REFLECTIONS Newsletter Jan-Jul 2024.pdf.pdfREFLECTIONS Newsletter Jan-Jul 2024.pdf.pdf
REFLECTIONS Newsletter Jan-Jul 2024.pdf.pdf
 

Conduct procurements

  • 1. WELCOMEPMP Preparation Course [PMBOK V.6] Conduct Procurements Sherif Sabri, PMP® With Sherif Sabri, PMP®
  • 2.  Overview Conduct Procurements  Conduct Procurements - Inputs  Conduct Procurements - Tools & Techniques  Conduct Procurements - Outputs Sherif Sabri, PMP®
  • 3. OVERVIEW Procurement Process No. (2) Executing Process No. (9) performed throughout the project as needed
  • 4. The process of obtaining seller responses, selecting a seller, and awarding a contract. The key benefit of this process is that - it selects a qualified seller and implements the legal agreement for delivery. The end results of the process are the established agreements including formal contracts. CONDUCT PROCUREMENTS Inputs Tools & Techniques Outputs .1 Project management plan • Scope management plan • Requirements management plan • Communications management plan • Risk management plan • Procurement management plan • Configuration management plan • Cost baseline .2 Project documents • Lessons learned register • Project schedule • Requirements documentation • Risk register • Stakeholder register .3 Procurement documentation .4 Seller proposals .5 EEF .6 OPA .1 Expert judgment .2 Advertising .3 Bidder conferences .4 Data analysis • Proposal evaluation .5 Interpersonal and team skills • Negotiation .1 Selected sellers .2 Agreements .3 Change requests .4 Project management plan updates • Requirements management plan • Quality management plan • Communications management plan • Risk management plan • Procurement management plan • Scope baseline • Schedule baseline • Cost baseline .5 Project documents updates • Lessons learned register • Requirements documentation • Requirements traceability matrix • Resource calendars • Risk register • Stakeholder register .6 OPA updates OVERVIEW
  • 5. 1-PROJECT MANAGEMENT PLAN  Scope management plan: describes how the overall scope of work will be managed, including the scope performed by sellers.  Requirements management plan: describes how requirements will be analyzed, documented, and managed. The requirements management plan may include how sellers will manage the requirements they are under agreement to satisfy.  Communications management plan: describes how communications between buyers and sellers will be conducted.  Risk management plan: describes how risk management activities will be structured and performed for the project.  Procurement management plan: contains the activities to be undertaken during the Conduct Procurements process.  Configuration management plan: defines those items that are configurable, those items that require formal change control, and the process for controlling changes to such items. It includes formats and processes for how sellers will provide configuration management in a way that is consistent with the buyer’s approach.  Cost baseline: includes the budget for the procurement as well as costs associated with managing the procurement process and sellers. Conduct Procurements - Inputs
  • 6. 2-PROJECT DOCUMENTS  Lessons learned register: Lessons learned earlier in the project with regard to conducting procurement can be applied to later phases in the project to improve the efficiency of this process.  Project schedule: identifies the start and end dates of project activities, including procurement activities. It also defines when contractor deliverables are due.  Requirements documentation include:  Technical requirements the seller is required to satisfy, and  Requirements with contractual and legal implications that may include:  health, safety, security, performance, environmental, insurance, intellectual property rights, equal employment opportunity, licenses, permits, and other nontechnical requirements.  Risk register: Each approved seller comes with its own unique set of risks, depending on the seller’s organization, the duration of the contract, the external environment, the project delivery method, the type of contracting vehicle chosen, and the final agreed-upon price.  Stakeholder register: This document contains all of the details about the identified stakeholders. Conduct Procurements - Inputs
  • 7. 3-PROCUREMENT DOCUMENTATION  Bid documents: Procurement documents include the RFI, RFP, RFQ, or other documents sent to sellers so they can develop a bid response.  Procurement statement of work (SOW) : provides sellers with a clearly stated set of goals, requirements, and outcomes from which they can provide a quantifiable response.  Independent cost estimates: are developed either internally or by using external resources and provide a reasonableness check against the proposals submitted by bidders.  Source selection criteria: These criteria describe how bidder proposals will be evaluated, including evaluation criteria and weights. For risk mitigation, the buyer may decide to sign agreements with more than one seller to mitigate damage caused by a single seller having problems that impact the overall project. Conduct Procurements - Inputs
  • 8. 4-SELLER PROPOSALS Seller proposals, prepared in response to a procurement document package, form the basic information that will be used by an evaluation body to select one or more successful bidders (sellers). If the seller is going to submit a price proposal, good practice is to require that it be separate from the technical proposal. The evaluation body reviews each submitted proposal according to the source selection criteria and selects the seller that can best satisfy the buying organization’s requirements. 5- EEF  Local laws and regulations regarding procurements;  Local laws and regulations ensuring that the major procurements involve local sellers;  External economic environment constraining procurement processes;  Marketplace conditions;  Information on relevant past experience with sellers, both good and bad;  Prior agreements already in place;  Contract management systems. 6- OPA  List of preferred sellers that have been prequalified,  Organizational policies that influence the selection of a seller,  Specific organizational templates or guidelines that will determine the way agreements are drafted and built,  Financial policies and procedures regarding invoicing and payment processes.. Conduct Procurements - Inputs
  • 9. 1-EXPERT JUDGMENT For this process, expertise should be considered from individuals or groups with specialized knowledge of or training in the following topics:  Proposal evaluation;  Technical or subject matter;  Relevant functional areas such as finance, engineering, design, development, supply chain management, etc.;  Industry regulatory environment;  Laws, regulations, and compliance requirements; and  Negotiation. Conduct Procurements - Tools & Techniques
  • 10. 2-ADVERTISING  Is communicating with users or potential users of a product, service, or result. Existing lists of potential sellers often can be expanded by placing advertisements in general circulation publications such as selected newspapers or in specialty trade publications. Most government jurisdictions require public advertising or online posting of pending government contracts. 3-BIDDER CONFERENCES = (contractor conferences, vendor conferences, and pre-bid conferences)  Are meetings between the buyer and prospective sellers prior to proposal submittal. They are used to ensure that all prospective bidders have a clear and common understanding of the procurement and no bidders receive preferential treatment. 4-DATA ANALYSIS  Proposal Evaluation: Proposals are evaluated to ensure they are complete and respond in full to the bid documents, procurement statement of work, source selection criteria, and any other documents that went out in the bid package. Conduct Procurements - Tools & Techniques
  • 11. 5-INTERPERSONAL AND TEAM SKILLS  Negotiation: is a discussion aimed at reaching an agreement.  Procurement negotiation clarifies the structure, rights, and obligations of the parties and other terms of the purchases so that mutual agreement can be reached prior to signing the contract.  Final document language reflects all agreements reached.  Negotiation concludes with a signed contract document or other formal agreement that can be executed by both buyer and seller.  The negotiation should be led by a member of the procurement team that has the authority to sign contracts.  The project manager and other members of the project management team may be present during negotiation to provide assistance as needed. Conduct Procurements - Tools & Techniques
  • 12. 1-SELECTED SELLERS  Are those who have been judged to be in a competitive range based on the outcome of the proposal or bid evaluation. Final approval of complex, high-value, high-risk procurements will generally require organizational senior management approval prior to award. 2-AGREEMENTS A contract is a mutually binding agreement that obligates the seller to provide the specified products, services, or results; obligates the buyer to compensate the seller; and represents a legal relationship that is subject to remedy in the courts. The major components in an agreement document include:  Procurement statement of work or major deliverables;  Schedule, milestones, or date by which a schedule is required;  Performance reporting;  Pricing and payment terms;  Inspection, quality, and acceptance criteria;  Warranty and future product support;  Incentives and penalties;  Insurance and performance bonds;  Subordinate subcontractor approvals;  General terms and conditions;  Change request handling; and  Termination clause and alternative dispute resolution mechanisms. Conduct Procurements - Outputs
  • 13. 3-CHANGE REQUESTS  Change requests to the project management plan, its subsidiary plans, and other components are processed for review and disposition through the Perform Integrated Change Control process 4-PROJECT MANAGEMENT PLAN UPDATES  Requirements management plan: There may be changes to project requirements due to changes identified by sellers.  Quality management plan: Sellers may offer alternative quality standards or alternative solutions that impact the quality approaches defined in the quality management plan.  Communications management plan: As sellers are hired, the communications management plan is updated to incorporate their communications needs and approaches.  Risk management plan: Each agreement and seller has its own set of risks that may require updates to the risk management plan. Specific risks are incorporated into the risk register.  Procurement management plan: Updates may be required depending on the results of the contracting and negotiations processes.  Scope baseline: The project WBS and deliverables documented in the scope baseline are considered when performing procurement activities. Any one or all of these may change during the procurement process.  Schedule baseline: If there are delivery changes created by sellers that impact overall project schedule performance, the baseline schedule may need to be updated and approved to reflect the current expectations.  Cost baseline: Contractor and materials prices can change frequently during the delivery of a project. These changes can occur because of fluctuating materials and labor prices created by the external economic environment and need to be incorporated into the cost baseline. Conduct Procurements - Outputs
  • 14. 5-PROJECT DOCUMENTS UPDATES  Lessons learned register: is updated with information on challenges encountered while conducting procurements and how they could have been avoided as well as approaches that worked well.  Risk register: Each approved seller comes with its own unique set of risks, depending on the seller’s organization, the duration of the contract, the external environment, the project delivery method, the type of contracting vehicle chosen, and the final agreed-upon price. Changes are made to the risk register during the contracting process, which reflect the specific risks of each seller.  Requirements documentation include:  Technical requirements the seller is required to satisfy, and  Requirements with contractual and legal implications that may include:  health, safety, security, performance, environmental, insurance, intellectual property rights, equal employment opportunity, licenses, permits, and other nontechnical requirements.  Requirements traceability matrix: As sellers are incorporated into the project’s plan, the requirements register and the traceability matrix may change depending on the capabilities of the specific seller.  Stakeholder register: The stakeholder register is updated as agreements are made with specific sellers.  Resource calendars: Schedule resource calendars may need to be updated depending on the availabilities of the sellers. Conduct Procurements - Outputs
  • 15. 6-ORGANIZATIONAL PROCESS ASSETS UPDATES  Listings of prospective and prequalified sellers; and  Information on relevant experience with sellers, both good and bad Conduct Procurements - Outputs
  • 16. T H A N K S F O R W A T C H I N G Together We will get it done Sherif Sabri, PMP®