Quantitative Project Risk Analysis
1
Agenda
• Introduction
• Part One
– Project Decision Framework
– Quantitative Analysis within Project Risk Management
• Part Two
– Practical Exercises
• Q and A
2
Introduction
Who is Intaver Institute?
• Formed 2002
• Group of risk, economic, and decision analysis experts
• All to some extent were involved in developing software tools for
these fields
3
Problem
• Many IT projects were late or over budget
• No readily available tools for the analysis of project schedules,
the provided similar analysis as the ones they were
developing for other industries
• Decision analysis processes including quantitative analysis
widely used in many industries, but not project management
– Many project manager don’t believe in benefits of quantitative methods
– Most methods and tools remain relatively complex, require special training,
and expensive
4
Vision: Quantitative project
analysis for the rest of us
• Develop application
– No specialist training required to get started
– Easier to use and understand
– Relatively inexpensive
• Provide project decision analysis training and consulting to
support application
5© Intaver Institute 2009
Part One: Project Decisions Framework and
Quantitative Analysis
• Project Decision Analysis
• Quantitative Project Risk Analysis and Management
6
Project Decision Analysis
• Successful projects are the result of good decisions
• Structure decision analysis
– Well defined process founded in decision analysis science
– Applicable to project management
– Provides framework that will improve project decisions
7
Decision Analysis vs. PMBOK
• Decision analysis not in conflict with PMBOK
• Can be easily integrated (as needed) into current PM
Risk Analysis Pyramid
8
Quantitative
Analysis
Qualitative Analysis
Risk Management Planning
© Intaver Institute 2009
8
Quantitative Estimates
• Uncertainties
– 3pt estimates
– Distributions
• Risk events
– Chance
– Outcome
– Result
– Moment of risk
9© Intaver Institute 2009
Types of uncertainties
• Duration
• Cost
• Start and Finish Times
• Lags
• Rates and Resource Allocation
• Entered as 3 pt estimate
10© Intaver Institute 2009
Types of Risk
• Task
• Resource
• Global (project or local)
11© Intaver Institute 2009
Risks or uncertainties?
• Use uncertainties in cases where you have historical data that
is both strong and analogous
• Use uncertainties in cases where you have some historical
data and strong expert opinion (experts have consensus)
• Use risk events when little historical data exists to back up
expert opinion
• Use risk events on higher risk projects
• You can use a combination of risk events and uncertainties
12
Risk or uncertainties
• Risk events are less prone to the effects of human biases and
heuristics
• Easier to recall effect of risk events on projects
13
Event Based Analysis
• Risk event estimates less affected by heuristics and biases
• Risk events estimates easier to obtain via relative frequency analysis
• Event based analysis of causes of project uncertainty
– Sensitivity analysis can be done to identify critical risks
– Uncertainties require additional root cause analysis to identify critical risks
14
Modeling Risk Events
• Chance - % chance that the risk will occur
• Outcome – relative % or fixed (e.g. % cost increase, Fixed
delay)
• Result - 15%
• Example Fire: 20% Chance of a Fixed Delay of 14 days
• Risks can have mutually exclusive alternatives
15
Monte Carlo Analysis
• Statistical sampling
• Runs many simulations of a project that produces probabilistic
distributions of particular results (cost, duration, finish time,
etc.)
• Gaining popularity as size and power of hardware and
software improve
16
Project Risk Analysis
• Create project schedule
• Define project uncertainties
• Define project risks
• Perform Monte Carlo Simulations
• Analyze results
17
RiskyProject Workflow
WBS
Resources
Costs
Risk List
RiskyProject Analysis
Results of Analysis
• Project outcomes with and without risks and uncertainties
• Sensitivity analysis
• Cost analysis
• Identifying critical risks and uncertainties
• Success rates
20
Project Summary
21
Main Project
Parameters with and
without risks
Probabilistic results
Result Gantt Chart
22
White bars represent
original project
schedule (no risks)
Blue bars represent
project schedule with
risks
Because of risks, project duration has
significantly increased
Detailed Results of Analysis
23
Move the slider to determine the chance
that project will be within budget
Get detailed
statistical data You may export this data to
other software it graphic
or text formats
Detailed results can be shown for each tasks or
whole project for cost, duration, start time, finish
time, and income.
Cost Analysis
You may compare cash
flow with (blue line) and
without (red line) risks
Cash flow is generated based on fixed
and variables cost and income
associated with tasks and resources
Crucial Tasks
Crucial tasks have the
most affect on the project
schedule
Green bars represent tasks
uncertainties that have almost no
affect on the project schedule
Crucial tasks for project cost and duration can
be different
Critical Risks
Tornado chart shows the risks that
have the most impact on project costs
Critical risks need to be
mitigated first
Project Dashboard 3x3
3 most important project
parameters (cost, duration, and
finish time)
3 most crucial tasks
3 most critical risks
Project Dashboard 3x3 is a
condensed view for most
important results of
analysis
Risk Chart
The risk chart shows risk uncertainty for tasks versus duration or cost
This task has high cost and
risk
These tasks have balanced risk
versus cost ratio.
Success Rate
The deadline is causing
calculation of the task in 86% of
cases
A task can be canceled if it reaches a task or a project deadline or if it is affected
by risk with a “Cancel task” outcome.
This task is affected by one of many
risks with impact “Cancel task”
Success rate is calculated based on
number of times the task is not
canceled
Tracking
This task is 100% completed (green
bar)
For each task at any moment you may enter how much work has been completed
This task is partially completed
(yellow bar)
Risky project automatically adjust probability of
risks for partially completed tasks
Tracking Results
New project forecast is done each time actual project data is
entered
Original (baseline) project duration
Actual project duration
Low, base, and high
forecast
Intaver Institute
32
Intaver Institute performs project risk management, risk
analysis, and decision analysis training and consulting
Download a trial version of RiskyProject at:
http://www.intaver.com/index-downloads.html (version 2.1)
White papers, presentations : http://www.intaver.com/index-
whitepapers.html
Courses: http://www.intaver.com/riskyproject_training.html
Additional Resources
33
Project Think:
Why Good
Managers Make
Poor Project
Choices
Project Decisions: The
Art and Science
Introduction to
Project Risk
Management and
Decision Analysis
Project Risk Analysis
Made Ridiculously
Simple

More Related Content

What's hot

Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
jisothomas
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
Pankaj K Sinha
 
Introduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptIntroduction to primavera risk analysis ppt
Introduction to primavera risk analysis ppt
p6academy
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
harwoodr
 
Thesis Presentation_LocNguyen
Thesis Presentation_LocNguyenThesis Presentation_LocNguyen
Thesis Presentation_LocNguyen
Loc Nguyen
 

What's hot (20)

Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - Reporting
 
Project Estimation
Project EstimationProject Estimation
Project Estimation
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
 
Introduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptIntroduction to primavera risk analysis ppt
Introduction to primavera risk analysis ppt
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Risk Management by Roger Pressman
Risk Management by Roger PressmanRisk Management by Roger Pressman
Risk Management by Roger Pressman
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
Parametric Estimation in a nutshell
Parametric Estimation in a nutshellParametric Estimation in a nutshell
Parametric Estimation in a nutshell
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
 
Thesis Presentation_LocNguyen
Thesis Presentation_LocNguyenThesis Presentation_LocNguyen
Thesis Presentation_LocNguyen
 
The art of project estimation
The art of project estimationThe art of project estimation
The art of project estimation
 
Qualitative risk analysis
Qualitative risk analysisQualitative risk analysis
Qualitative risk analysis
 

Similar to Quantitative Project Risk Analysis

RICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 MayRICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 May
Saeed Shalbafan
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
p6academy
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
Neenu Babu
 
Essentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev A
Steve Kiester
 
Software project plannings
Software project planningsSoftware project plannings
Software project plannings
Aman Adhikari
 

Similar to Quantitative Project Risk Analysis (20)

Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
 
RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2
 
Project Risk Analysis with Risk Event and Event Chain
Project Risk Analysis with Risk Event and Event ChainProject Risk Analysis with Risk Event and Event Chain
Project Risk Analysis with Risk Event and Event Chain
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis
 
Chapter 2.ppt
Chapter 2.pptChapter 2.ppt
Chapter 2.ppt
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Project management part 3
Project management part 3Project management part 3
Project management part 3
 
RICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 MayRICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 May
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
 
Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
 
Essentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev A
 
RiskyProject Enterprise
RiskyProject EnterpriseRiskyProject Enterprise
RiskyProject Enterprise
 
Software project plannings
Software project planningsSoftware project plannings
Software project plannings
 
Software project plannings
Software project planningsSoftware project plannings
Software project plannings
 
Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 

More from Intaver Insititute

More from Intaver Insititute (19)

Project Cost Analysis
Project Cost AnalysisProject Cost Analysis
Project Cost Analysis
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project Portfolios
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
RiskyProject 7
RiskyProject 7RiskyProject 7
RiskyProject 7
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace Industry
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project Management
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project Management
 
Risky projectpresentation rus
Risky projectpresentation rusRisky projectpresentation rus
Risky projectpresentation rus
 
Risky project Cloud presentation rus
Risky project Cloud presentation rusRisky project Cloud presentation rus
Risky project Cloud presentation rus
 
Risky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementRisky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagement
 
Risky Project Lite vs. Professional
Risky Project Lite vs. ProfessionalRisky Project Lite vs. Professional
Risky Project Lite vs. Professional
 
Enterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProjectEnterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProject
 
Risky projectcloudpresentation
Risky projectcloudpresentationRisky projectcloudpresentation
Risky projectcloudpresentation
 
Adaptive Project Management
Adaptive Project ManagementAdaptive Project Management
Adaptive Project Management
 
Decision Framing in Project Decision-Making
Decision Framing in Project Decision-MakingDecision Framing in Project Decision-Making
Decision Framing in Project Decision-Making
 

Recently uploaded

internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
AllTops
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
SandaliGurusinghe2
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 

Recently uploaded (14)

W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 

Quantitative Project Risk Analysis

  • 2. Agenda • Introduction • Part One – Project Decision Framework – Quantitative Analysis within Project Risk Management • Part Two – Practical Exercises • Q and A 2
  • 3. Introduction Who is Intaver Institute? • Formed 2002 • Group of risk, economic, and decision analysis experts • All to some extent were involved in developing software tools for these fields 3
  • 4. Problem • Many IT projects were late or over budget • No readily available tools for the analysis of project schedules, the provided similar analysis as the ones they were developing for other industries • Decision analysis processes including quantitative analysis widely used in many industries, but not project management – Many project manager don’t believe in benefits of quantitative methods – Most methods and tools remain relatively complex, require special training, and expensive 4
  • 5. Vision: Quantitative project analysis for the rest of us • Develop application – No specialist training required to get started – Easier to use and understand – Relatively inexpensive • Provide project decision analysis training and consulting to support application 5© Intaver Institute 2009
  • 6. Part One: Project Decisions Framework and Quantitative Analysis • Project Decision Analysis • Quantitative Project Risk Analysis and Management 6
  • 7. Project Decision Analysis • Successful projects are the result of good decisions • Structure decision analysis – Well defined process founded in decision analysis science – Applicable to project management – Provides framework that will improve project decisions 7 Decision Analysis vs. PMBOK • Decision analysis not in conflict with PMBOK • Can be easily integrated (as needed) into current PM
  • 8. Risk Analysis Pyramid 8 Quantitative Analysis Qualitative Analysis Risk Management Planning © Intaver Institute 2009 8
  • 9. Quantitative Estimates • Uncertainties – 3pt estimates – Distributions • Risk events – Chance – Outcome – Result – Moment of risk 9© Intaver Institute 2009
  • 10. Types of uncertainties • Duration • Cost • Start and Finish Times • Lags • Rates and Resource Allocation • Entered as 3 pt estimate 10© Intaver Institute 2009
  • 11. Types of Risk • Task • Resource • Global (project or local) 11© Intaver Institute 2009
  • 12. Risks or uncertainties? • Use uncertainties in cases where you have historical data that is both strong and analogous • Use uncertainties in cases where you have some historical data and strong expert opinion (experts have consensus) • Use risk events when little historical data exists to back up expert opinion • Use risk events on higher risk projects • You can use a combination of risk events and uncertainties 12
  • 13. Risk or uncertainties • Risk events are less prone to the effects of human biases and heuristics • Easier to recall effect of risk events on projects 13
  • 14. Event Based Analysis • Risk event estimates less affected by heuristics and biases • Risk events estimates easier to obtain via relative frequency analysis • Event based analysis of causes of project uncertainty – Sensitivity analysis can be done to identify critical risks – Uncertainties require additional root cause analysis to identify critical risks 14
  • 15. Modeling Risk Events • Chance - % chance that the risk will occur • Outcome – relative % or fixed (e.g. % cost increase, Fixed delay) • Result - 15% • Example Fire: 20% Chance of a Fixed Delay of 14 days • Risks can have mutually exclusive alternatives 15
  • 16. Monte Carlo Analysis • Statistical sampling • Runs many simulations of a project that produces probabilistic distributions of particular results (cost, duration, finish time, etc.) • Gaining popularity as size and power of hardware and software improve 16
  • 17. Project Risk Analysis • Create project schedule • Define project uncertainties • Define project risks • Perform Monte Carlo Simulations • Analyze results 17
  • 20. Results of Analysis • Project outcomes with and without risks and uncertainties • Sensitivity analysis • Cost analysis • Identifying critical risks and uncertainties • Success rates 20
  • 21. Project Summary 21 Main Project Parameters with and without risks Probabilistic results
  • 22. Result Gantt Chart 22 White bars represent original project schedule (no risks) Blue bars represent project schedule with risks Because of risks, project duration has significantly increased
  • 23. Detailed Results of Analysis 23 Move the slider to determine the chance that project will be within budget Get detailed statistical data You may export this data to other software it graphic or text formats Detailed results can be shown for each tasks or whole project for cost, duration, start time, finish time, and income.
  • 24. Cost Analysis You may compare cash flow with (blue line) and without (red line) risks Cash flow is generated based on fixed and variables cost and income associated with tasks and resources
  • 25. Crucial Tasks Crucial tasks have the most affect on the project schedule Green bars represent tasks uncertainties that have almost no affect on the project schedule Crucial tasks for project cost and duration can be different
  • 26. Critical Risks Tornado chart shows the risks that have the most impact on project costs Critical risks need to be mitigated first
  • 27. Project Dashboard 3x3 3 most important project parameters (cost, duration, and finish time) 3 most crucial tasks 3 most critical risks Project Dashboard 3x3 is a condensed view for most important results of analysis
  • 28. Risk Chart The risk chart shows risk uncertainty for tasks versus duration or cost This task has high cost and risk These tasks have balanced risk versus cost ratio.
  • 29. Success Rate The deadline is causing calculation of the task in 86% of cases A task can be canceled if it reaches a task or a project deadline or if it is affected by risk with a “Cancel task” outcome. This task is affected by one of many risks with impact “Cancel task” Success rate is calculated based on number of times the task is not canceled
  • 30. Tracking This task is 100% completed (green bar) For each task at any moment you may enter how much work has been completed This task is partially completed (yellow bar) Risky project automatically adjust probability of risks for partially completed tasks
  • 31. Tracking Results New project forecast is done each time actual project data is entered Original (baseline) project duration Actual project duration Low, base, and high forecast
  • 32. Intaver Institute 32 Intaver Institute performs project risk management, risk analysis, and decision analysis training and consulting Download a trial version of RiskyProject at: http://www.intaver.com/index-downloads.html (version 2.1) White papers, presentations : http://www.intaver.com/index- whitepapers.html Courses: http://www.intaver.com/riskyproject_training.html
  • 33. Additional Resources 33 Project Think: Why Good Managers Make Poor Project Choices Project Decisions: The Art and Science Introduction to Project Risk Management and Decision Analysis Project Risk Analysis Made Ridiculously Simple

Editor's Notes

  1. Bring out parking lot questions
  2. So what should we use.
  3. Risks are separated from the schedule and cost. When we use distributions, we set “boundaries” on them. Risk events less effected as we do not know the statistical outcome until Monte Carlo is run. Less conscious or unconscious “gaming” of estimates.