SlideShare a Scribd company logo
1 of 2
Download to read offline
w
78 ucononline.com Underground Construction October 2015
What would you do if your drink-
ing water was discolored and your
water system was more than 100
years old? That is the question resi-
dents in the Town of Scituate, MA,
were faced with when they voted
in favor of a $22 million water pipe
replacement project in November
2013. Today, work continues on
the three-year project to update a
portion of the century-old water
supply system.
The Town of Scituate is located
in Plymouth County and is home
to 18,133 residents, according to
2010 U.S. Census Bureau figures.
The town sits on the Massachu-
setts South Shore and is approxi-
mately 25 miles southeast of Bos-
ton. It was settled 385 years ago
and today retains much of the Irish
ancestry that settled in the area.
As with many other older cities
in the Northeast region, Scituate
faces infrastructure challenges,
namely old underground utilities
that need to be updated. Residents
were in favor of updating their
water pipe system to improve the
water quality and appearance.
According to the Public Works
Department, the old water pipes
were installed between 1901 and
1935, and are made of unlined cast
iron. In summer months, sedi-
ment from the iron pipes causes a
phenomenon referred to as “brown
water.”
Scituate residents voted to
replace a 24-mile portion of the
aged system with an increase in
water rates and water enterprise
revenues. According to the town
website, the water division is
responsible for 100 miles of water
distribution system, 250 fire hy-
drants and 7,200 water meters.
Weston and Sampson Engineers
Inc., an engineering firm from
Peabody, MA, was contracted by
the Scituate officials to review in-
formation about the underground
pipes and valves. The town asked
the firm to confirm which pipes
needed to be replaced and recom-
mend the order in which the work
should be done and prepare the
final bid package for the first
phase. The plan was for the work
to begin in spring 2014 and to be
spread over three years.
Phase 1A of the water main
replacement project included con-
struction of approximately 3,500
feet of new 12-inch and 11,900 feet
of new 8-inch ductile iron water
main in town streets and neighbor-
hoods. The work included installa-
tion of a temporary water main and
services, replacement of all water
services, installation of hydrants
and water main abandonment.
Year2
Following one of the worst winters
on record in the northeast,
When A Town Had Enough Of Its
Brown Water
construction crews were eager to
get back to work this spring.
Employees of R&D Site Develop-
ment, a construction company
based in Groveland, MA, were hired
to complete a $3 million portion of
the water main replacement project
in 2015. According to Public Works
Director Kevin Cafferty, residents
would still have water while the
work continued, although some
road detours would be required.
While a relatively young compa-
ny that started in 2005, co-own-
ers Bill Daley and Steve Reppucci
have built a solid reputation for
themselves in Massachusetts. “We
started our business by doing small
construction sites and small utility
projects,” Daley says. “That got big-
ger and bigger over the years. Now
we do tens of thousands of feet a
year with water and soil projects.”
With 13 dedicated employees,
the company works April through
December, weather permitting.
Jobs like the water main replace-
ment for the Town of Scituate are
a good fit for R&D Site Develop-
ment, which specializes in install-
ing utilities for local municipali-
ties throughout Massachusetts.
Altogether, the company owns 50
pieces of specialized equipment
to best match the job at hand. The
company works with commercial
clients, local airports and munici-
palities to complete a variety of
projects.
According to Daley, the R&D
Site Development portion of the
2015 water main project includes
30,000 feet of water mains, hy-
drants and services. He says work
began in early May and took about
18 weeks to complete their por-
tion. The Town of Scituate is leav-
ing the existing water mains in the
ground, and Daley says his com-
pany is laying a new corridor with
new pipe.
Limitedworkroom
Like a lot of other cities in the
northeast, streets are narrow and
do not provide much room for two-
way traffic and parking, let alone
79ucononline.comOctober 2015 Underground Construction
construction projects. The town re-routed traffic
while Daley, Reppucci and their crew performed
their underground construction tasks. Daley
says they started with a four-foot-wide trench
cut through the asphalt road. A Doosan DX-
235LCR reduced tail swing excavator, purchased
earlier in 2015 from the local Doosan heavy
equipment dealer, Equipment East, was instru-
mental in efficiently excavating dirt from the
trench. The 25.4-metric-ton crawler excavator
has a maximum dig depth of 21 feet 10 inches,
and a maximum reach of 31 feet 7 inches.
With Reppucci seated inside the excavator
cab at the controls, he removed soil from the
trench and left the spoil pile next to it. One area
where R&D Site Development worked in 2015
was along First Parish Road and Maple Street,
where mature trees line both sides of the road.
Daley says his crew installed 12-inch pipe in the
trench with the help of the 166-net-horsepower
DX235LCR excavator and various buckets. The
reduced-tail-swing excavator was the perfect
size for the underground project. Daley says his
company purchased the excavator because of its
size and agility. It is 10 feet 5 inches wide, and
has a tail overhang of just 3 inches over the side.
“Most of our work is in the inner city of Bos-
ton and the surrounding areas, so we really need
a reduced-tail-swing excavator,” he says. “It is
easier for the operator to maneuver and it keeps
the machine looking better over time, too.
“Earlier on the project, we had two pipe sizes
going in the same trench,” Daley says. “We con-
nected the 36-inch trenching bucket to the
Doosan excavator and we were able to put in
two pipes. Then, we went back to one pipe and
we switched to the 24-inch trenching bucket,
eventually converting to the 18-inch trenching
bucket when we were installing smaller pipe.”
Quickchange
It was important for Daley and Reppucci to
change buckets to best match the digging
requirements and not over-dig. “The less dig-
ging, the better for us,” Daley notes. They can
easily switch back and forth between different
trenching buckets because they have a Doosan
hydraulic quick coupler installed on the DX-
235LCR crawler excavator. Reppucci can quickly
change his buckets without leaving his seat,
and each bucket comes standard with teeth to
dig through tough soil conditions. A quick cou-
pler control box in the excavator’s cab makes it
simple to activate the quick coupler to lock or
unlock the attachment connection mechanism.
Once Reppucci removed the soil from the
trench, a worker used an upright compactor to
compact the soil. Meanwhile, Reppucci rotated
the excavator’s house to access and lift a pipe,
turned the unit back to the trench and placed
the 1,000-pound pipe in the open trench. A
Bobcat S650 skid-steer loader with bucket back-
filled the trench with the spoil after the pipe
was put in place.
Work will continue in 2016 as the Town of
Scituate completes its three-year construction
project to replace 24 miles of water pipes,
hoping to improve water quality for decades
to come.
FORMOREINFORMATION
Doosan Equipment
(877) 613-7970, www.DoosanEquipment.com
Bobcat
(866) 823-7898, www.bobcat.com
R&D Site Development
(978) 374-4353,www.rdsitedevelopment.com

More Related Content

What's hot

Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & ResumeRichard Rask
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingVDOT Northern Virginia
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016VDOT Northern Virginia
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Crosstown TO
 
City Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project UpdateCity Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project UpdateCity of San Angelo Texas
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects City of Corona
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowMark Oberschmidt
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017Crosstown TO
 
CPAC Meeting 5-17-05
CPAC Meeting 5-17-05CPAC Meeting 5-17-05
CPAC Meeting 5-17-05HartTWI
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Crosstown TO
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For WebACECSDES
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingVDOT Northern Virginia
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectFairfax County
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
 

What's hot (18)

Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & Resume
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meeting
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
 
City Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project UpdateCity Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project Update
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
CPAC Meeting 5-17-05
CPAC Meeting 5-17-05CPAC Meeting 5-17-05
CPAC Meeting 5-17-05
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For Web
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation Project
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
 

Similar to Town of Scitutate job story Underground Construction 10-1-15

ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)Mark Shanholtzer
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence AwardsACECSDES
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence AwardsACECSDES
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACECSDES
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_knelischer
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_knelischer
 
2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2Ismael Vazquez, LSIT
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - FletcherJade Keswick
 
Finishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes DigestFinishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes DigestPhilip Tunnah
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Fairfax County
 
Water Resources Department 5 Year Capital Improvement Plan
Water Resources Department 5 Year Capital Improvement PlanWater Resources Department 5 Year Capital Improvement Plan
Water Resources Department 5 Year Capital Improvement PlanClermont County, Ohio
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectFairfax County
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitFairfax County
 

Similar to Town of Scitutate job story Underground Construction 10-1-15 (20)

ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)
 
Jentz_Patrick
Jentz_PatrickJentz_Patrick
Jentz_Patrick
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence Awards
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence Awards
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence Awards
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
 
Project report
Project reportProject report
Project report
 
Finishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes DigestFinishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes Digest
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016
 
NA
NANA
NA
 
ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2
 
WET IC brochure
WET IC brochureWET IC brochure
WET IC brochure
 
Construction Job Story in GeoDrilling International
Construction Job Story in GeoDrilling InternationalConstruction Job Story in GeoDrilling International
Construction Job Story in GeoDrilling International
 
Brookwood Parkway Improvement
Brookwood Parkway ImprovementBrookwood Parkway Improvement
Brookwood Parkway Improvement
 
Water Resources Department 5 Year Capital Improvement Plan
Water Resources Department 5 Year Capital Improvement PlanWater Resources Department 5 Year Capital Improvement Plan
Water Resources Department 5 Year Capital Improvement Plan
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality Retrofit
 

More from Ryan Johnson

DoMORE Spring 2015
DoMORE Spring 2015DoMORE Spring 2015
DoMORE Spring 2015Ryan Johnson
 
DoMORE Winter 2015
DoMORE Winter 2015DoMORE Winter 2015
DoMORE Winter 2015Ryan Johnson
 
DoMORE Spring 2014
DoMORE Spring 2014DoMORE Spring 2014
DoMORE Spring 2014Ryan Johnson
 
DoMORE Winter 2016
DoMORE Winter 2016DoMORE Winter 2016
DoMORE Winter 2016Ryan Johnson
 
DoMORE Spring 2016
DoMORE Spring 2016DoMORE Spring 2016
DoMORE Spring 2016Ryan Johnson
 
WorkSaver Fall 2013 issue
WorkSaver Fall 2013 issueWorkSaver Fall 2013 issue
WorkSaver Fall 2013 issueRyan Johnson
 
DoMORE Winter 2012 issue
DoMORE Winter 2012 issueDoMORE Winter 2012 issue
DoMORE Winter 2012 issueRyan Johnson
 
DoMORE Spring 2012 issue.PDF
DoMORE Spring 2012 issue.PDFDoMORE Spring 2012 issue.PDF
DoMORE Spring 2012 issue.PDFRyan Johnson
 
DoMORE Winter 2014 issue
DoMORE Winter 2014 issueDoMORE Winter 2014 issue
DoMORE Winter 2014 issueRyan Johnson
 
DoMORE Winter 2013 issue
DoMORE Winter 2013 issueDoMORE Winter 2013 issue
DoMORE Winter 2013 issueRyan Johnson
 
DoMORE_Spring_2013
DoMORE_Spring_2013DoMORE_Spring_2013
DoMORE_Spring_2013Ryan Johnson
 

More from Ryan Johnson (11)

DoMORE Spring 2015
DoMORE Spring 2015DoMORE Spring 2015
DoMORE Spring 2015
 
DoMORE Winter 2015
DoMORE Winter 2015DoMORE Winter 2015
DoMORE Winter 2015
 
DoMORE Spring 2014
DoMORE Spring 2014DoMORE Spring 2014
DoMORE Spring 2014
 
DoMORE Winter 2016
DoMORE Winter 2016DoMORE Winter 2016
DoMORE Winter 2016
 
DoMORE Spring 2016
DoMORE Spring 2016DoMORE Spring 2016
DoMORE Spring 2016
 
WorkSaver Fall 2013 issue
WorkSaver Fall 2013 issueWorkSaver Fall 2013 issue
WorkSaver Fall 2013 issue
 
DoMORE Winter 2012 issue
DoMORE Winter 2012 issueDoMORE Winter 2012 issue
DoMORE Winter 2012 issue
 
DoMORE Spring 2012 issue.PDF
DoMORE Spring 2012 issue.PDFDoMORE Spring 2012 issue.PDF
DoMORE Spring 2012 issue.PDF
 
DoMORE Winter 2014 issue
DoMORE Winter 2014 issueDoMORE Winter 2014 issue
DoMORE Winter 2014 issue
 
DoMORE Winter 2013 issue
DoMORE Winter 2013 issueDoMORE Winter 2013 issue
DoMORE Winter 2013 issue
 
DoMORE_Spring_2013
DoMORE_Spring_2013DoMORE_Spring_2013
DoMORE_Spring_2013
 

Town of Scitutate job story Underground Construction 10-1-15

  • 1. w 78 ucononline.com Underground Construction October 2015 What would you do if your drink- ing water was discolored and your water system was more than 100 years old? That is the question resi- dents in the Town of Scituate, MA, were faced with when they voted in favor of a $22 million water pipe replacement project in November 2013. Today, work continues on the three-year project to update a portion of the century-old water supply system. The Town of Scituate is located in Plymouth County and is home to 18,133 residents, according to 2010 U.S. Census Bureau figures. The town sits on the Massachu- setts South Shore and is approxi- mately 25 miles southeast of Bos- ton. It was settled 385 years ago and today retains much of the Irish ancestry that settled in the area. As with many other older cities in the Northeast region, Scituate faces infrastructure challenges, namely old underground utilities that need to be updated. Residents were in favor of updating their water pipe system to improve the water quality and appearance. According to the Public Works Department, the old water pipes were installed between 1901 and 1935, and are made of unlined cast iron. In summer months, sedi- ment from the iron pipes causes a phenomenon referred to as “brown water.” Scituate residents voted to replace a 24-mile portion of the aged system with an increase in water rates and water enterprise revenues. According to the town website, the water division is responsible for 100 miles of water distribution system, 250 fire hy- drants and 7,200 water meters. Weston and Sampson Engineers Inc., an engineering firm from Peabody, MA, was contracted by the Scituate officials to review in- formation about the underground pipes and valves. The town asked the firm to confirm which pipes needed to be replaced and recom- mend the order in which the work should be done and prepare the final bid package for the first phase. The plan was for the work to begin in spring 2014 and to be spread over three years. Phase 1A of the water main replacement project included con- struction of approximately 3,500 feet of new 12-inch and 11,900 feet of new 8-inch ductile iron water main in town streets and neighbor- hoods. The work included installa- tion of a temporary water main and services, replacement of all water services, installation of hydrants and water main abandonment. Year2 Following one of the worst winters on record in the northeast, When A Town Had Enough Of Its Brown Water construction crews were eager to get back to work this spring. Employees of R&D Site Develop- ment, a construction company based in Groveland, MA, were hired to complete a $3 million portion of the water main replacement project in 2015. According to Public Works Director Kevin Cafferty, residents would still have water while the work continued, although some road detours would be required. While a relatively young compa- ny that started in 2005, co-own- ers Bill Daley and Steve Reppucci have built a solid reputation for themselves in Massachusetts. “We started our business by doing small construction sites and small utility projects,” Daley says. “That got big- ger and bigger over the years. Now we do tens of thousands of feet a year with water and soil projects.” With 13 dedicated employees, the company works April through December, weather permitting. Jobs like the water main replace- ment for the Town of Scituate are a good fit for R&D Site Develop- ment, which specializes in install- ing utilities for local municipali- ties throughout Massachusetts. Altogether, the company owns 50 pieces of specialized equipment to best match the job at hand. The company works with commercial clients, local airports and munici- palities to complete a variety of projects. According to Daley, the R&D Site Development portion of the 2015 water main project includes 30,000 feet of water mains, hy- drants and services. He says work began in early May and took about 18 weeks to complete their por- tion. The Town of Scituate is leav- ing the existing water mains in the ground, and Daley says his com- pany is laying a new corridor with new pipe. Limitedworkroom Like a lot of other cities in the northeast, streets are narrow and do not provide much room for two- way traffic and parking, let alone
  • 2. 79ucononline.comOctober 2015 Underground Construction construction projects. The town re-routed traffic while Daley, Reppucci and their crew performed their underground construction tasks. Daley says they started with a four-foot-wide trench cut through the asphalt road. A Doosan DX- 235LCR reduced tail swing excavator, purchased earlier in 2015 from the local Doosan heavy equipment dealer, Equipment East, was instru- mental in efficiently excavating dirt from the trench. The 25.4-metric-ton crawler excavator has a maximum dig depth of 21 feet 10 inches, and a maximum reach of 31 feet 7 inches. With Reppucci seated inside the excavator cab at the controls, he removed soil from the trench and left the spoil pile next to it. One area where R&D Site Development worked in 2015 was along First Parish Road and Maple Street, where mature trees line both sides of the road. Daley says his crew installed 12-inch pipe in the trench with the help of the 166-net-horsepower DX235LCR excavator and various buckets. The reduced-tail-swing excavator was the perfect size for the underground project. Daley says his company purchased the excavator because of its size and agility. It is 10 feet 5 inches wide, and has a tail overhang of just 3 inches over the side. “Most of our work is in the inner city of Bos- ton and the surrounding areas, so we really need a reduced-tail-swing excavator,” he says. “It is easier for the operator to maneuver and it keeps the machine looking better over time, too. “Earlier on the project, we had two pipe sizes going in the same trench,” Daley says. “We con- nected the 36-inch trenching bucket to the Doosan excavator and we were able to put in two pipes. Then, we went back to one pipe and we switched to the 24-inch trenching bucket, eventually converting to the 18-inch trenching bucket when we were installing smaller pipe.” Quickchange It was important for Daley and Reppucci to change buckets to best match the digging requirements and not over-dig. “The less dig- ging, the better for us,” Daley notes. They can easily switch back and forth between different trenching buckets because they have a Doosan hydraulic quick coupler installed on the DX- 235LCR crawler excavator. Reppucci can quickly change his buckets without leaving his seat, and each bucket comes standard with teeth to dig through tough soil conditions. A quick cou- pler control box in the excavator’s cab makes it simple to activate the quick coupler to lock or unlock the attachment connection mechanism. Once Reppucci removed the soil from the trench, a worker used an upright compactor to compact the soil. Meanwhile, Reppucci rotated the excavator’s house to access and lift a pipe, turned the unit back to the trench and placed the 1,000-pound pipe in the open trench. A Bobcat S650 skid-steer loader with bucket back- filled the trench with the spoil after the pipe was put in place. Work will continue in 2016 as the Town of Scituate completes its three-year construction project to replace 24 miles of water pipes, hoping to improve water quality for decades to come. FORMOREINFORMATION Doosan Equipment (877) 613-7970, www.DoosanEquipment.com Bobcat (866) 823-7898, www.bobcat.com R&D Site Development (978) 374-4353,www.rdsitedevelopment.com