“ Gerrard Street Watermain”
Oscar A Orellana / September 22, 2016,
11:45 AM @ Metro Hall Room 303
Agenda (proposed)
• Background / Project Description – Rationale / Problem description
• The project Class Environmental Assessment (EA)
• Pre-design, Detail Design and Services During Construction
• Gerrard St Watermain Construction
• Issues / Opportunities / innovations (what went wrong / what went right?)
• Accomplishments / Lessons learned (what did we learn / change?)
• Next Steps (how is this changing the way we do things?). Conclusion.
• Questions (post a couple of FAQs and have answers ready in case there aren’t a
lot of takers at the beginning of Q& A session)
Background
• The Gerrard St Watermain was initiated by Toronto Water’s, Water Supply Unit, as
part of the Cast Iron Watermain Replacement Program. As a result of the Joint
Optimization Study (JOS), a City of Toronto – York Region Study, Toronto Water
identified major watermains that needed to be replaced to increase capacity and
maintain the safety and reliability of the watermain network.
• The existing watermain to be replaced was a 900mm cast iron watermain that run
from Spadina Avenue to Sumach Street, along D’Arcy St, Mc Caul St, Elm St,
Elizabeth St, Gerrard St, ending at Sumach St.
The project Class Environmental Assessment (EA).
• The project EA, Pre-design, Design and Construction was managed by the
Engineering & Construction Services (formerly Technical Services Division)
• The Class Environmental Assessment was started with an REOI in February 2005,
through which four consultants were short-listed: McViro, R. V. Anderson, Earth
Tech and Chisholm Flemings & Associates.
• An RFP was issued in 2005 to the above noted consultants and the Class EA
project was awarded to Chisholm, Flemings & Associates in January 2006. The
Class EA Study was completed in January 2008.
• A preferred route was identified along the same route as the existing 900mm
watermain. The new watermain diameter was upsized to 1650mm, as a result of
JOS and Toronto Water Hydraulic Modelling.
Gerrard Watermain EA study Area
Gerrard Watermain EA Alternative Routes
Pre-design, Detail Design and Services During Construction
• In April 2008, an RFP was issued for Pre-design, Detail Design and Services
During Construction. The project was awarded to Trow Associates Inc. (now exp
Services Inc.) in August 2008.
• The project design was carried out by Trow Associates from November 2008 to
November 2010.
• The design produced a 1650mm diameter steel watermain, 14mm in thickness, 3.9
kms in length, internally cement mortar lined, to be constructed all in tunnel 25
metres below the surface, with a total of 6 large shafts (6m x 12m in size, 25m in
depth) for launching and retrieval of the Tunnel Boring Machine (TBM). The design
also proposed a 2.5 m diameter tunnel with 10mm thick steel liner plates, which
was later changed by the contractor C & M McNally to steel rib and lagging primary
liner.
Gerrard Watermain Final Design
Gerrard Watermain Design
Gerrard Watermain Construction
• The Construction Contract was tendered in December 2010 and awarded to C & M
McNally by the Public Works and Infrastructure Committee in September 2011.
• The award was delayed to late 2011 (due to insufficient funding that year), so we
could start construction in 2012. The value of the contract was $80,276,112.00
excluding HST
• An Order to Commence Work was issued in December 2011 and construction
actually started in January 2012.
• The contract duration was set in the contractor’s bid at 175 weeks or roughly 3.5
years. The contract completion date was determined as June 2015.
• The watermain construction was completed on time and under budget. Six months
were added for extra work to fill the abandoned 900mm watermain with cellular
grout, which was not part of the original contract. The new 1650mm watermain was
fully commissioned in December 2015.
Shaft No. 4 at Allan Gardens
Tunnel Boring Machine
1350mm Riser pipe at Jarvis St
1350mm Horizontal Butterfly valve at Jarvis St
Issues / Opportunities / innovations (what went wrong / what
went right?) 2 slides
• Issues – In 2011, a new City Council was elected. We had obtained a permit to use the Allan
Gardens Park from the previous City Councillor. The new Councillor initially opposed the plan and
ask to find an alternate location. It took a month to resolve this issue with assistance from the senior
management.
• Opportunities – Upon request from the Councillor, the shaft hoarding at Allen Gardens were painted
by the first nations artists and these murals were one of the longest piece of such art in Canada .
• Innovations –In the Tender, Schedule of Price Savings, the contractor proposed a change of the
tunnel liner from 10mm steel to galvanized steel rib and lagging and offered the City $6,200,000 in
savings, which was accepted by the City.
• Upon award, the contractor offered a further change from galvanized steel rib and lagging to black
steel rib and lagging which was accepted and resulted in further savings of $1,387,214
• A change in method of joining the steel pipes, from butt welded joints to lap (bell and spigot) welded
joints, resulted in further savings of $952,000.
• What went wrong – The contractor applied cement mortar lining in their shop, contravening the
contract specifications that called for in-situ cement mortar lining. Bracing of the pipes was required
for Transportation back to the job site to minimize damage to the lining. Defective lining had to be
repaired on site. The contractor assumed the cost of the above.
Mural around the construction site
Accomplishments / Lessons learned (what did we learn /
change?) 2 slides
• Accomplishments - Overall, the contract completed on time and under budget. Upon
completion $6 million in contingency and provisional amounts were not spent. A Certificate
of Substantial Completion was issued on November 17, 2015. There was a contract
extension from June to December-2015, as filling the abandoned 900mm watermain with
grout was added to the scope.
• Lessons learned – Maintaining good communications and professional relation with the
contractor, consultant, and the operating division staff was the key to success. Fairness
and good faith can help achieve strong bonding among all parties involved.
• The contractor offered to change the 20MPa sand-cement grout, in the tunnel annular
space, to 0.5 MPa cellular grout, including a $1 Million dollars credit, which was rejected
despite consultant’s recommendation, on the basis that the change would drastically
reduce the external load bearing capacity of the watermain cross-section. It took strength
to say “NO” to the contractor and the consultant. But, we cannot introduce risk for long
term as a result of cost savings. All cost savings offered by the contractor have to be
analyzed for the 100+ year of life of the infrastructure.
Next Steps (how is this changing the way we do things?)
Conclusion
• Trunk Watermain construction, all in tunnel, drastically minimizes excavations and
traffic disruptions. However there is an added cost, on average double the cost of
open cut construction.
• In the case of the Gerrard Street Watermain, the cost was justifiable because an
open cut construction would have created huge traffic issues in the downtown
corridor. It would have blocked the south access to the emergency entrances to
Princess Margaret Hospital, Mount Sinai Hospital and the Toronto Re-habilitation
Institute, on Murray Street. It would have also completely blocked the emergency
entrance to The Hospital for Sick Children on Elm Street, west of Elizabeth Street.
• Tunnel construction prevented the above noted traffic problems. Construction of
trunk watermains, all in tunnel, is recommended in areas with high volumes of
traffic.
Questions
• What type of TBM’s were used ?
• The contractor used two types of TBM’s:
A brand new 2550mm (102 inches) diameter, LOVAT TBM and an old 3000mm (120
inches) diameter, Robbins TBM, fabricated in Ohio, USA. Both TBM’s were open face
TBM’s for rock tunneling.
• What type of soil was encountered?
The 3.9 km of tunnel is in rock (shale). The watermain profile was designed to be
in the rock layer, which begins approximately 18 m below the surface, with at least 2
metres of rock cover. Transition between different layers of rock and soil is not
preferred in tunneling.
• Was there any subway crossings ?
Yes, the tunnel crossed the University/Spadina Subway Line and the Yonge Subway
Line. The road surface is approx. at 96 m of elevation, at University Ave. The Subway
invert is approx. at 82 m. The watermain invert is approx. at 71 m. The road surface is
approx. at 95 m of elevation at Yonge St. The subway invert is approx. at 86 m. The
watermain invert is approx. at 72 m. Approximately 8 m and 11 m of clearance
respectively.

More Related Content

What's hot

2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For WebACECSDES
 
Lane ave bridge report
Lane ave bridge reportLane ave bridge report
Lane ave bridge reportJohn Mangini
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideChukwuma Anyanwu, PMP, CCP
 
Engineers Club Of Memphis V2
Engineers Club Of Memphis V2Engineers Club Of Memphis V2
Engineers Club Of Memphis V2dgonano
 
Fort indraprastha-egm v1.0
Fort  indraprastha-egm v1.0Fort  indraprastha-egm v1.0
Fort indraprastha-egm v1.0Dwarak Ethiraj
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionSuresh Zanwar
 
Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...
Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...
Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...Communications Branding
 
Pervious Concrete Pilot Project COT 042413
Pervious Concrete Pilot Project COT 042413Pervious Concrete Pilot Project COT 042413
Pervious Concrete Pilot Project COT 042413Mary Kell
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDeltares
 
Project Description - Ben Oaks Sewage Pumping Station
Project Description - Ben Oaks Sewage Pumping StationProject Description - Ben Oaks Sewage Pumping Station
Project Description - Ben Oaks Sewage Pumping StationJahonn Naimi
 

What's hot (16)

2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For Web
 
Cv asif mahmood
Cv asif mahmoodCv asif mahmood
Cv asif mahmood
 
Lane ave bridge report
Lane ave bridge reportLane ave bridge report
Lane ave bridge report
 
DVCV060715
DVCV060715DVCV060715
DVCV060715
 
Infrared heaters
Infrared heatersInfrared heaters
Infrared heaters
 
Poster
PosterPoster
Poster
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guide
 
Engineers Club Of Memphis V2
Engineers Club Of Memphis V2Engineers Club Of Memphis V2
Engineers Club Of Memphis V2
 
Reflex notable projects
Reflex notable projectsReflex notable projects
Reflex notable projects
 
Fort indraprastha-egm v1.0
Fort  indraprastha-egm v1.0Fort  indraprastha-egm v1.0
Fort indraprastha-egm v1.0
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline construction
 
Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...
Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...
Keep it Running! – Surface Drainage 201 – Design Basics for Modular Trench Dr...
 
Pervious Concrete Pilot Project COT 042413
Pervious Concrete Pilot Project COT 042413Pervious Concrete Pilot Project COT 042413
Pervious Concrete Pilot Project COT 042413
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
 
Project Description - Ben Oaks Sewage Pumping Station
Project Description - Ben Oaks Sewage Pumping StationProject Description - Ben Oaks Sewage Pumping Station
Project Description - Ben Oaks Sewage Pumping Station
 

Viewers also liked

Brilliant equity tips
Brilliant equity tipsBrilliant equity tips
Brilliant equity tipsNiharika Jain
 
Muslim style chicken biryani recipe
Muslim style chicken biryani recipeMuslim style chicken biryani recipe
Muslim style chicken biryani recipesaikuppannagari
 
Lecture 6
Lecture 6Lecture 6
Lecture 6hunglq
 
The Health Care Poly Clinic
The Health Care Poly ClinicThe Health Care Poly Clinic
The Health Care Poly ClinicApnaZon
 
Why dont animals have wheels
Why dont animals have wheelsWhy dont animals have wheels
Why dont animals have wheelsHarsh Dod
 
Patientenverfügung, Vorsorgevollmacht und Betreuungsvollmacht
Patientenverfügung, Vorsorgevollmacht und BetreuungsvollmachtPatientenverfügung, Vorsorgevollmacht und Betreuungsvollmacht
Patientenverfügung, Vorsorgevollmacht und BetreuungsvollmachtDaniel, Hagelskamp & Kollegen
 
Problems and Fixes with Progressives!
Problems and Fixes with Progressives!Problems and Fixes with Progressives!
Problems and Fixes with Progressives!mabest
 
Ranking Factors Infographics: Card deck and correlations
Ranking Factors Infographics: Card deck and correlationsRanking Factors Infographics: Card deck and correlations
Ranking Factors Infographics: Card deck and correlationsDigital Strategist
 
La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...
La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...
La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...DrupalDay
 
España del siglo XVII
España del siglo XVIIEspaña del siglo XVII
España del siglo XVIIartesonado
 

Viewers also liked (16)

Brilliant equity tips
Brilliant equity tipsBrilliant equity tips
Brilliant equity tips
 
Muslim style chicken biryani recipe
Muslim style chicken biryani recipeMuslim style chicken biryani recipe
Muslim style chicken biryani recipe
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 
The Health Care Poly Clinic
The Health Care Poly ClinicThe Health Care Poly Clinic
The Health Care Poly Clinic
 
Why dont animals have wheels
Why dont animals have wheelsWhy dont animals have wheels
Why dont animals have wheels
 
Patientenverfügung, Vorsorgevollmacht und Betreuungsvollmacht
Patientenverfügung, Vorsorgevollmacht und BetreuungsvollmachtPatientenverfügung, Vorsorgevollmacht und Betreuungsvollmacht
Patientenverfügung, Vorsorgevollmacht und Betreuungsvollmacht
 
Flora and fauna
Flora and faunaFlora and fauna
Flora and fauna
 
Informe final-de-suelos
Informe final-de-suelosInforme final-de-suelos
Informe final-de-suelos
 
Herakleidon
HerakleidonHerakleidon
Herakleidon
 
Problems and Fixes with Progressives!
Problems and Fixes with Progressives!Problems and Fixes with Progressives!
Problems and Fixes with Progressives!
 
Web 2.0-2013
Web 2.0-2013Web 2.0-2013
Web 2.0-2013
 
Ranking Factors Infographics: Card deck and correlations
Ranking Factors Infographics: Card deck and correlationsRanking Factors Infographics: Card deck and correlations
Ranking Factors Infographics: Card deck and correlations
 
La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...
La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...
La piattaforma web di CNA: Istanze Drupal replicabili integrate con Alfresco ...
 
Los orígenes del arte occidental
Los orígenes del arte occidentalLos orígenes del arte occidental
Los orígenes del arte occidental
 
España del siglo XVII
España del siglo XVIIEspaña del siglo XVII
España del siglo XVII
 
La Segunda Republica
La Segunda RepublicaLa Segunda Republica
La Segunda Republica
 

Similar to Gerrard Street Watermain Project Overview

Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologyLTDH2013
 
Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction Chris Myers
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Soumalya Bag
 
Carbon Fiber - FRP
Carbon Fiber - FRPCarbon Fiber - FRP
Carbon Fiber - FRPdewcraig
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowMark Oberschmidt
 
The Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdfThe Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdffreezefreeze2
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsIRJET Journal
 
Carbon Fiber
Carbon FiberCarbon Fiber
Carbon Fiberjamieram
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015ILIAS MICHALIS
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
 
Foundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic RepairsFoundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic Repairsjamieram
 

Similar to Gerrard Street Watermain Project Overview (20)

Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technology
 
Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
Carbon Fiber - FRP
Carbon Fiber - FRPCarbon Fiber - FRP
Carbon Fiber - FRP
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 
The Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdfThe Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdf
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
attcofinal
attcofinalattcofinal
attcofinal
 
SOME OF THE PROJECTS HANDLED
SOME OF THE PROJECTS HANDLEDSOME OF THE PROJECTS HANDLED
SOME OF THE PROJECTS HANDLED
 
Alan sutton
Alan suttonAlan sutton
Alan sutton
 
Carbon Fiber
Carbon FiberCarbon Fiber
Carbon Fiber
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
CC Intro
CC IntroCC Intro
CC Intro
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Foundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic RepairsFoundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic Repairs
 

Gerrard Street Watermain Project Overview

  • 1. “ Gerrard Street Watermain” Oscar A Orellana / September 22, 2016, 11:45 AM @ Metro Hall Room 303
  • 2. Agenda (proposed) • Background / Project Description – Rationale / Problem description • The project Class Environmental Assessment (EA) • Pre-design, Detail Design and Services During Construction • Gerrard St Watermain Construction • Issues / Opportunities / innovations (what went wrong / what went right?) • Accomplishments / Lessons learned (what did we learn / change?) • Next Steps (how is this changing the way we do things?). Conclusion. • Questions (post a couple of FAQs and have answers ready in case there aren’t a lot of takers at the beginning of Q& A session)
  • 3. Background • The Gerrard St Watermain was initiated by Toronto Water’s, Water Supply Unit, as part of the Cast Iron Watermain Replacement Program. As a result of the Joint Optimization Study (JOS), a City of Toronto – York Region Study, Toronto Water identified major watermains that needed to be replaced to increase capacity and maintain the safety and reliability of the watermain network. • The existing watermain to be replaced was a 900mm cast iron watermain that run from Spadina Avenue to Sumach Street, along D’Arcy St, Mc Caul St, Elm St, Elizabeth St, Gerrard St, ending at Sumach St.
  • 4. The project Class Environmental Assessment (EA). • The project EA, Pre-design, Design and Construction was managed by the Engineering & Construction Services (formerly Technical Services Division) • The Class Environmental Assessment was started with an REOI in February 2005, through which four consultants were short-listed: McViro, R. V. Anderson, Earth Tech and Chisholm Flemings & Associates. • An RFP was issued in 2005 to the above noted consultants and the Class EA project was awarded to Chisholm, Flemings & Associates in January 2006. The Class EA Study was completed in January 2008. • A preferred route was identified along the same route as the existing 900mm watermain. The new watermain diameter was upsized to 1650mm, as a result of JOS and Toronto Water Hydraulic Modelling.
  • 5. Gerrard Watermain EA study Area
  • 6. Gerrard Watermain EA Alternative Routes
  • 7. Pre-design, Detail Design and Services During Construction • In April 2008, an RFP was issued for Pre-design, Detail Design and Services During Construction. The project was awarded to Trow Associates Inc. (now exp Services Inc.) in August 2008. • The project design was carried out by Trow Associates from November 2008 to November 2010. • The design produced a 1650mm diameter steel watermain, 14mm in thickness, 3.9 kms in length, internally cement mortar lined, to be constructed all in tunnel 25 metres below the surface, with a total of 6 large shafts (6m x 12m in size, 25m in depth) for launching and retrieval of the Tunnel Boring Machine (TBM). The design also proposed a 2.5 m diameter tunnel with 10mm thick steel liner plates, which was later changed by the contractor C & M McNally to steel rib and lagging primary liner.
  • 10. Gerrard Watermain Construction • The Construction Contract was tendered in December 2010 and awarded to C & M McNally by the Public Works and Infrastructure Committee in September 2011. • The award was delayed to late 2011 (due to insufficient funding that year), so we could start construction in 2012. The value of the contract was $80,276,112.00 excluding HST • An Order to Commence Work was issued in December 2011 and construction actually started in January 2012. • The contract duration was set in the contractor’s bid at 175 weeks or roughly 3.5 years. The contract completion date was determined as June 2015. • The watermain construction was completed on time and under budget. Six months were added for extra work to fill the abandoned 900mm watermain with cellular grout, which was not part of the original contract. The new 1650mm watermain was fully commissioned in December 2015.
  • 11. Shaft No. 4 at Allan Gardens
  • 13. 1350mm Riser pipe at Jarvis St
  • 14. 1350mm Horizontal Butterfly valve at Jarvis St
  • 15. Issues / Opportunities / innovations (what went wrong / what went right?) 2 slides • Issues – In 2011, a new City Council was elected. We had obtained a permit to use the Allan Gardens Park from the previous City Councillor. The new Councillor initially opposed the plan and ask to find an alternate location. It took a month to resolve this issue with assistance from the senior management. • Opportunities – Upon request from the Councillor, the shaft hoarding at Allen Gardens were painted by the first nations artists and these murals were one of the longest piece of such art in Canada . • Innovations –In the Tender, Schedule of Price Savings, the contractor proposed a change of the tunnel liner from 10mm steel to galvanized steel rib and lagging and offered the City $6,200,000 in savings, which was accepted by the City. • Upon award, the contractor offered a further change from galvanized steel rib and lagging to black steel rib and lagging which was accepted and resulted in further savings of $1,387,214 • A change in method of joining the steel pipes, from butt welded joints to lap (bell and spigot) welded joints, resulted in further savings of $952,000. • What went wrong – The contractor applied cement mortar lining in their shop, contravening the contract specifications that called for in-situ cement mortar lining. Bracing of the pipes was required for Transportation back to the job site to minimize damage to the lining. Defective lining had to be repaired on site. The contractor assumed the cost of the above.
  • 16. Mural around the construction site
  • 17. Accomplishments / Lessons learned (what did we learn / change?) 2 slides • Accomplishments - Overall, the contract completed on time and under budget. Upon completion $6 million in contingency and provisional amounts were not spent. A Certificate of Substantial Completion was issued on November 17, 2015. There was a contract extension from June to December-2015, as filling the abandoned 900mm watermain with grout was added to the scope. • Lessons learned – Maintaining good communications and professional relation with the contractor, consultant, and the operating division staff was the key to success. Fairness and good faith can help achieve strong bonding among all parties involved. • The contractor offered to change the 20MPa sand-cement grout, in the tunnel annular space, to 0.5 MPa cellular grout, including a $1 Million dollars credit, which was rejected despite consultant’s recommendation, on the basis that the change would drastically reduce the external load bearing capacity of the watermain cross-section. It took strength to say “NO” to the contractor and the consultant. But, we cannot introduce risk for long term as a result of cost savings. All cost savings offered by the contractor have to be analyzed for the 100+ year of life of the infrastructure.
  • 18. Next Steps (how is this changing the way we do things?) Conclusion • Trunk Watermain construction, all in tunnel, drastically minimizes excavations and traffic disruptions. However there is an added cost, on average double the cost of open cut construction. • In the case of the Gerrard Street Watermain, the cost was justifiable because an open cut construction would have created huge traffic issues in the downtown corridor. It would have blocked the south access to the emergency entrances to Princess Margaret Hospital, Mount Sinai Hospital and the Toronto Re-habilitation Institute, on Murray Street. It would have also completely blocked the emergency entrance to The Hospital for Sick Children on Elm Street, west of Elizabeth Street. • Tunnel construction prevented the above noted traffic problems. Construction of trunk watermains, all in tunnel, is recommended in areas with high volumes of traffic.
  • 19. Questions • What type of TBM’s were used ? • The contractor used two types of TBM’s: A brand new 2550mm (102 inches) diameter, LOVAT TBM and an old 3000mm (120 inches) diameter, Robbins TBM, fabricated in Ohio, USA. Both TBM’s were open face TBM’s for rock tunneling. • What type of soil was encountered? The 3.9 km of tunnel is in rock (shale). The watermain profile was designed to be in the rock layer, which begins approximately 18 m below the surface, with at least 2 metres of rock cover. Transition between different layers of rock and soil is not preferred in tunneling. • Was there any subway crossings ? Yes, the tunnel crossed the University/Spadina Subway Line and the Yonge Subway Line. The road surface is approx. at 96 m of elevation, at University Ave. The Subway invert is approx. at 82 m. The watermain invert is approx. at 71 m. The road surface is approx. at 95 m of elevation at Yonge St. The subway invert is approx. at 86 m. The watermain invert is approx. at 72 m. Approximately 8 m and 11 m of clearance respectively.