SlideShare a Scribd company logo
1 of 1
Download to read offline
24	 July 2014 • Water & Wastes Digest Water & Wastes Digest • Www.wwdmag.com 25
By Janet Rummel
Colorado utility nears
the end of construction
of 50-mile pipeline
B
efore the end of 2014, Colorado Springs
Utilities will lay the final piece of pipe for
one of the largest water projects currently
being built in the western U.S.
The Southern Delivery System (SDS) is a
regional water project in southern Colorado that
will bring Arkansas River water stored in Pueblo
Dam to Colorado Springs, the state’s second larg-
est city, and its partner communities, Fountain,
Security and Pueblo West. Colorado Springs
Utilities is completing SDS at a time when the fre-
quency and volatility of drought is growing in the
arid American West, while the economy is improv-
ing and water demand is increasing.
Fifty miles of predominantly 66-in.-diameter
welded steel pipe serve as the artery of SDS, travel-
ling up 1,500 ft in elevation via three new pump-
ing stations and eventually arriving at a new water
treatment plant north of the dam.
To finish SDS on time and under budget, the
municipally owned utility and its program man-
ager, MWH Global, divided the pipeline into sev-
eral different work packages. Separate packages
facilitated competitive private industry bidding,
which is among the reasons that the project is pro-
jected to come in significantly under budget at
completion, reducing the final projected cost from
almost $1 billion to $841 million.
“The program team has been innovative in
how we have approached SDS—starting with the
design and engineering to contracting and con-
struction,” said John Fredell, SDS program direc-
tor. “We also have extended this ‘outside the box’
approach to how we communicate and inform
interested stakeholders, local residents and busi-
nesses impacted by construction activities.”
The following are a few highlights of the creative
approaches the SDS team used to install the pipeline
in often challenging physical and social conditions.
Ascending From Pueblo Reservoir
The southernmost section of the pipeline, a
4.3-mile section known as South Pipeline 1 (S1),
stood out as one of the most difficult sections to con-
struct due to technical and geological conditions.
Much like a stair step, S1 needed to rise 150 feet
from the reservoir basin and surmount the sur-
rounding embankment in order to level out and
begin its gradual ascent northward. This journey
was complicated by the presence of a railroad line
cut into the surrounding bluff.
The design engineer chose a route between
a drainage way on one side and two 80-ft hills.
After examining multiple options, the SDS
project team determined that the best design was
a 308-ft-long, 10-ft-diameter tunnel at an approx-
imately 3% slope underneath the railroad. A 90-ft
vertical riser shaft situated within the bluff sup-
ported the pipe and tunnel.
Subsurface conditions proved complicated.
The bluff is located just a few hundred yards from
one of the globally recognized sections of the
Cretaceous-Paleogene boundary, the marker bed
of the geologic period approximately 65.5 mil-
lion years ago. Geologically, the bed hosts layers
of limestone and shale, providing both very strong
and very weak subsurface soils.
Construction engineers began work by drilling
a vertical tunnel and installing a riser shaft, rest-
ing it in sand bedding. Then came the arduous
work of digging through limestone. Because of the
slope, tunnel methods such as auger boring and
jack and bore were ruled out. Methods that called
for conveyor discharge or muck cars also were not
practical due to the slope.
Instead, the main tunnel was completed with
the use of a 27-ton road header. Mucking was com-
pleted using a skip bucket attached to a tracked
skid-steer loader.
At the opposite end of the tunnel, engineers con-
structed an approximately 12-ft-wide final cavern
section in the shale, and supported it using rock
bolts at a staggered pattern, steel mesh and shot-
crete. The roof of the cavern intersected the previ-
ously installed sand bedding of the north riser pipe.
Despite such difficult soil and technical con-
ditions, the S1 tunnel crossing was completed
successfully, on time, under budget and to the rail-
road owner’s specifications.
Traversing an ATV Area
After leaving Pueblo Reservoir, S1 pipeline tra-
verses through one of the most well-used motor
sports areas in southern Colorado. Construction
was underway during spring and summer—prime
season for motor sports enthusiasts to ride.
The conventional approach would have been to
establish a linear work area multiple miles long,
stage the pipe sections (66 in. in diameter and 50 ft
long) end to end, and fence off the linear construc-
tion site. That approach would have prohibited
the public from using the many ATV trails that
traversed the pipeline alignment. But because the
SDS team sought to minimize disruption to local
residents, they took a different approach.
Prior to the two-month-long trenching project,
the SDS public involvement team distributed infor-
mational materials to enthusiasts who frequented
the area, and coordinated with both the city of
Pueblo Parks and Recreation Department and
State of Colorado Division of Parks and Wildlife—
the two agencies that co-manage the area. Then,
rather than laying one continuous line of pipe, the
contractor staged the pipe above-ground in islands
and then built several crossings using gates and
fences between the islands of pipe to allow safe
passage through the construction zone.
These passageways were left open until the
actual pipe laying was at each crossing and con-
struction was too intense to keep them open. Signs
were put up encouraging individuals to
use the crossing, but to stay out of the con-
struction areas. This gave off-road motor-
ists the opportunity to enjoy the area. As a
result, there were no complaints from ATV
enthusiasts, and the measures helped pro-
tect public and worker safety by creating
designated safe corridors to cross through
the construction zone.
Engaging Residents in
Pueblo West
Another community engagement chal-
lenge arose in Pueblo West, a community
of 30,000 residents. The 6.4-mile South
Pipeline 2 (S2) section needed to travel
through 125 residential yards and required
the purchase and removal of six houses and
the relocation of their owners.
To keep residents safe and informed and
minimize disruption, SDS staff aimed to be
good neighbors.
Two full-time “construction facilita-
tors” continuously were on site at the
construction areas and served as daily
touch points for residents and businesses.
Through door-to-door visits, meetings
and a 24-hour staffed hotline, the facilita-
tors explained the project and occurrences
that residents could expect. As work pro-
gressed, residents received ongoing visits,
letters, e-mails and newsletters to keep them
apprised of issues ranging from road closures to
plans for yard revegetation.
Even the six homes acquired for demolition
became a community asset. After the project paid
for the owners to relocate, the SDS team offered reus-
able items—such as plumbing fixtures, cabinets and
doors—to the local Habitat for Humanity office to
resell or install in their homes. Local fire and police
departments were invited to use the houses to con-
duct drills and practice simulated firefighting.
By utilizing creative approaches to construction,
coupled with a commitment to communication
and community relations, SDS is advancing a criti-
cal water infrastructure project for four southern
Colorado communities, creating a more certain
water future for its customers. WWD
Janet Rummel is senior public affairs specialist for
Colorado Springs Utilities. Rummel can be reached at
jrummel@csu.org or 719.668.3030.
For more information, write in 1109 on this issue’s reader
service form on page 42.
pipe  distribution systems
Finishing Strong
The 6.4-mile pipeline in the Pueblo
West neighborhood had to travel
through 125 residential yards.
Installation of the shaft riser
Several crossings were built using gates and fences to allow
ATV riders to safely pass through the construction zone.
specialsection
MUNCH?
1936 was a good year for progressing cavity (PC) pumps. We started
manufacturing PC pumps in the United States, and since then, Moyno has
added industrial grinders providing reliable, effective maceration of solids to
protect downstream equipment from blockages. We’re pround of the new,
innovative designs like the EZstrip TR Muncher–quick, simple, maintain-in-place
solution making your job easier.
www.moyno.com/EZstrip
TR Muncher
offers different
cutter thickness
to match the
required particle
size for application.
A quick release
access port allows
in-place inspection
and cutter stack
replacement.
Write in 116Write in 115

More Related Content

What's hot

Martin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project OverviewMartin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project OverviewWaterfrontTO
 
Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01geographystudents
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Fairfax County
 
Clifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersClifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersJake Henderson
 
CPAC Meeting 9-22-03
CPAC Meeting 9-22-03CPAC Meeting 9-22-03
CPAC Meeting 9-22-03HartTWI
 
Innovations Within Our Means, Presentation 2
Innovations Within Our Means, Presentation 2Innovations Within Our Means, Presentation 2
Innovations Within Our Means, Presentation 2Trailnet
 
Roberto Clemente State Park Revitalization Plan
Roberto Clemente State Park Revitalization PlanRoberto Clemente State Park Revitalization Plan
Roberto Clemente State Park Revitalization Plancwestory
 
Lin Xue Portfolio
Lin Xue PortfolioLin Xue Portfolio
Lin Xue Portfoliolionetxue
 
Dam construction
Dam constructionDam construction
Dam constructionalizay41
 
Draft Scenario 5 16-13
Draft Scenario 5 16-13Draft Scenario 5 16-13
Draft Scenario 5 16-13Roar Media
 
Damges to MKHP Sept, 2015
Damges to MKHP Sept, 2015Damges to MKHP Sept, 2015
Damges to MKHP Sept, 2015Binay Chipalu
 
Chapter 7 dams and reservoirs
Chapter 7 dams and reservoirsChapter 7 dams and reservoirs
Chapter 7 dams and reservoirsMohammed Salahat
 
Introduction of dams
Introduction of damsIntroduction of dams
Introduction of damstausif_k
 

What's hot (19)

Martin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project OverviewMartin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project Overview
 
Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01
 
Small dam projects in pakistan
Small dam projects in pakistanSmall dam projects in pakistan
Small dam projects in pakistan
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016
 
Jason Abendroth Resume_10_2015
Jason Abendroth Resume_10_2015Jason Abendroth Resume_10_2015
Jason Abendroth Resume_10_2015
 
Clifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersClifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - Posters
 
CPAC Meeting 9-22-03
CPAC Meeting 9-22-03CPAC Meeting 9-22-03
CPAC Meeting 9-22-03
 
Innovations Within Our Means, Presentation 2
Innovations Within Our Means, Presentation 2Innovations Within Our Means, Presentation 2
Innovations Within Our Means, Presentation 2
 
Roberto Clemente State Park Revitalization Plan
Roberto Clemente State Park Revitalization PlanRoberto Clemente State Park Revitalization Plan
Roberto Clemente State Park Revitalization Plan
 
Lin Xue Portfolio
Lin Xue PortfolioLin Xue Portfolio
Lin Xue Portfolio
 
Dam construction
Dam constructionDam construction
Dam construction
 
Draft Scenario 5 16-13
Draft Scenario 5 16-13Draft Scenario 5 16-13
Draft Scenario 5 16-13
 
Damges to MKHP Sept, 2015
Damges to MKHP Sept, 2015Damges to MKHP Sept, 2015
Damges to MKHP Sept, 2015
 
dam
damdam
dam
 
Final
FinalFinal
Final
 
Chapter 7 dams and reservoirs
Chapter 7 dams and reservoirsChapter 7 dams and reservoirs
Chapter 7 dams and reservoirs
 
Introduction of dams
Introduction of damsIntroduction of dams
Introduction of dams
 
NA
NANA
NA
 
Dams%20report
Dams%20reportDams%20report
Dams%20report
 

Similar to Finishing Strong_July 2014_Water & Wastes Digest

Cowlitz falls paper naes power contractors lewis county pud-final
Cowlitz falls paper   naes power contractors lewis county pud-finalCowlitz falls paper   naes power contractors lewis county pud-final
Cowlitz falls paper naes power contractors lewis county pud-finalNAES Corporation
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence AwardsACECSDES
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For WebACECSDES
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACECSDES
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence AwardsACECSDES
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdfSaqib Imran
 
D1 Newsletter_2016 vol1
D1 Newsletter_2016 vol1D1 Newsletter_2016 vol1
D1 Newsletter_2016 vol1Jose Moreno
 
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15Dario Gnoato
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows MeanderTony Smith
 
Sp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 finalSp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 finalcityofevanston
 
Srdc bartrams to passyunk final_report
Srdc bartrams to passyunk final_reportSrdc bartrams to passyunk final_report
Srdc bartrams to passyunk final_reportPaul Vernon
 
Citizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River JewelCitizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River JewelR Ray Saikus
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowMark Oberschmidt
 
Sp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 finalSp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 finalcityofevanston
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Ryan Johnson
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects City of Corona
 

Similar to Finishing Strong_July 2014_Water & Wastes Digest (20)

Cowlitz falls paper naes power contractors lewis county pud-final
Cowlitz falls paper   naes power contractors lewis county pud-finalCowlitz falls paper   naes power contractors lewis county pud-final
Cowlitz falls paper naes power contractors lewis county pud-final
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence Awards
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For Web
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence Awards
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence Awards
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdf
 
SDS Whitepaper
SDS WhitepaperSDS Whitepaper
SDS Whitepaper
 
D1 Newsletter_2016 vol1
D1 Newsletter_2016 vol1D1 Newsletter_2016 vol1
D1 Newsletter_2016 vol1
 
chey 5-29-15
chey 5-29-15chey 5-29-15
chey 5-29-15
 
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows Meander
 
Sp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 finalSp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 final
 
Srdc bartrams to passyunk final_report
Srdc bartrams to passyunk final_reportSrdc bartrams to passyunk final_report
Srdc bartrams to passyunk final_report
 
Senior Project PSR
Senior Project PSRSenior Project PSR
Senior Project PSR
 
Citizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River JewelCitizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River Jewel
 
NW Natural Report
NW Natural ReportNW Natural Report
NW Natural Report
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 
Sp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 finalSp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 final
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
 

More from Philip Tunnah

ENR SDS Article May 2015
ENR SDS Article May 2015ENR SDS Article May 2015
ENR SDS Article May 2015Philip Tunnah
 
Effective communication aids water project in Colorado
Effective communication aids water project in ColoradoEffective communication aids water project in Colorado
Effective communication aids water project in ColoradoPhilip Tunnah
 
UEP Slide Meet n greet
UEP Slide Meet n greetUEP Slide Meet n greet
UEP Slide Meet n greetPhilip Tunnah
 
APWA Florida Proj Award_UEP
APWA Florida Proj Award_UEPAPWA Florida Proj Award_UEP
APWA Florida Proj Award_UEPPhilip Tunnah
 
Government Engineering May June 2013 -- Colorado Springs SDS
Government Engineering May June 2013 -- Colorado Springs SDSGovernment Engineering May June 2013 -- Colorado Springs SDS
Government Engineering May June 2013 -- Colorado Springs SDSPhilip Tunnah
 
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARDENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARDPhilip Tunnah
 

More from Philip Tunnah (9)

ENR SDS Article May 2015
ENR SDS Article May 2015ENR SDS Article May 2015
ENR SDS Article May 2015
 
Effective communication aids water project in Colorado
Effective communication aids water project in ColoradoEffective communication aids water project in Colorado
Effective communication aids water project in Colorado
 
ARH ENR Oct 2015
ARH ENR Oct 2015ARH ENR Oct 2015
ARH ENR Oct 2015
 
UEP Slide Meet n greet
UEP Slide Meet n greetUEP Slide Meet n greet
UEP Slide Meet n greet
 
UIM Jul 09
UIM Jul 09UIM Jul 09
UIM Jul 09
 
UEP Statistics
UEP StatisticsUEP Statistics
UEP Statistics
 
APWA Florida Proj Award_UEP
APWA Florida Proj Award_UEPAPWA Florida Proj Award_UEP
APWA Florida Proj Award_UEP
 
Government Engineering May June 2013 -- Colorado Springs SDS
Government Engineering May June 2013 -- Colorado Springs SDSGovernment Engineering May June 2013 -- Colorado Springs SDS
Government Engineering May June 2013 -- Colorado Springs SDS
 
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARDENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
 

Finishing Strong_July 2014_Water & Wastes Digest

  • 1. 24 July 2014 • Water & Wastes Digest Water & Wastes Digest • Www.wwdmag.com 25 By Janet Rummel Colorado utility nears the end of construction of 50-mile pipeline B efore the end of 2014, Colorado Springs Utilities will lay the final piece of pipe for one of the largest water projects currently being built in the western U.S. The Southern Delivery System (SDS) is a regional water project in southern Colorado that will bring Arkansas River water stored in Pueblo Dam to Colorado Springs, the state’s second larg- est city, and its partner communities, Fountain, Security and Pueblo West. Colorado Springs Utilities is completing SDS at a time when the fre- quency and volatility of drought is growing in the arid American West, while the economy is improv- ing and water demand is increasing. Fifty miles of predominantly 66-in.-diameter welded steel pipe serve as the artery of SDS, travel- ling up 1,500 ft in elevation via three new pump- ing stations and eventually arriving at a new water treatment plant north of the dam. To finish SDS on time and under budget, the municipally owned utility and its program man- ager, MWH Global, divided the pipeline into sev- eral different work packages. Separate packages facilitated competitive private industry bidding, which is among the reasons that the project is pro- jected to come in significantly under budget at completion, reducing the final projected cost from almost $1 billion to $841 million. “The program team has been innovative in how we have approached SDS—starting with the design and engineering to contracting and con- struction,” said John Fredell, SDS program direc- tor. “We also have extended this ‘outside the box’ approach to how we communicate and inform interested stakeholders, local residents and busi- nesses impacted by construction activities.” The following are a few highlights of the creative approaches the SDS team used to install the pipeline in often challenging physical and social conditions. Ascending From Pueblo Reservoir The southernmost section of the pipeline, a 4.3-mile section known as South Pipeline 1 (S1), stood out as one of the most difficult sections to con- struct due to technical and geological conditions. Much like a stair step, S1 needed to rise 150 feet from the reservoir basin and surmount the sur- rounding embankment in order to level out and begin its gradual ascent northward. This journey was complicated by the presence of a railroad line cut into the surrounding bluff. The design engineer chose a route between a drainage way on one side and two 80-ft hills. After examining multiple options, the SDS project team determined that the best design was a 308-ft-long, 10-ft-diameter tunnel at an approx- imately 3% slope underneath the railroad. A 90-ft vertical riser shaft situated within the bluff sup- ported the pipe and tunnel. Subsurface conditions proved complicated. The bluff is located just a few hundred yards from one of the globally recognized sections of the Cretaceous-Paleogene boundary, the marker bed of the geologic period approximately 65.5 mil- lion years ago. Geologically, the bed hosts layers of limestone and shale, providing both very strong and very weak subsurface soils. Construction engineers began work by drilling a vertical tunnel and installing a riser shaft, rest- ing it in sand bedding. Then came the arduous work of digging through limestone. Because of the slope, tunnel methods such as auger boring and jack and bore were ruled out. Methods that called for conveyor discharge or muck cars also were not practical due to the slope. Instead, the main tunnel was completed with the use of a 27-ton road header. Mucking was com- pleted using a skip bucket attached to a tracked skid-steer loader. At the opposite end of the tunnel, engineers con- structed an approximately 12-ft-wide final cavern section in the shale, and supported it using rock bolts at a staggered pattern, steel mesh and shot- crete. The roof of the cavern intersected the previ- ously installed sand bedding of the north riser pipe. Despite such difficult soil and technical con- ditions, the S1 tunnel crossing was completed successfully, on time, under budget and to the rail- road owner’s specifications. Traversing an ATV Area After leaving Pueblo Reservoir, S1 pipeline tra- verses through one of the most well-used motor sports areas in southern Colorado. Construction was underway during spring and summer—prime season for motor sports enthusiasts to ride. The conventional approach would have been to establish a linear work area multiple miles long, stage the pipe sections (66 in. in diameter and 50 ft long) end to end, and fence off the linear construc- tion site. That approach would have prohibited the public from using the many ATV trails that traversed the pipeline alignment. But because the SDS team sought to minimize disruption to local residents, they took a different approach. Prior to the two-month-long trenching project, the SDS public involvement team distributed infor- mational materials to enthusiasts who frequented the area, and coordinated with both the city of Pueblo Parks and Recreation Department and State of Colorado Division of Parks and Wildlife— the two agencies that co-manage the area. Then, rather than laying one continuous line of pipe, the contractor staged the pipe above-ground in islands and then built several crossings using gates and fences between the islands of pipe to allow safe passage through the construction zone. These passageways were left open until the actual pipe laying was at each crossing and con- struction was too intense to keep them open. Signs were put up encouraging individuals to use the crossing, but to stay out of the con- struction areas. This gave off-road motor- ists the opportunity to enjoy the area. As a result, there were no complaints from ATV enthusiasts, and the measures helped pro- tect public and worker safety by creating designated safe corridors to cross through the construction zone. Engaging Residents in Pueblo West Another community engagement chal- lenge arose in Pueblo West, a community of 30,000 residents. The 6.4-mile South Pipeline 2 (S2) section needed to travel through 125 residential yards and required the purchase and removal of six houses and the relocation of their owners. To keep residents safe and informed and minimize disruption, SDS staff aimed to be good neighbors. Two full-time “construction facilita- tors” continuously were on site at the construction areas and served as daily touch points for residents and businesses. Through door-to-door visits, meetings and a 24-hour staffed hotline, the facilita- tors explained the project and occurrences that residents could expect. As work pro- gressed, residents received ongoing visits, letters, e-mails and newsletters to keep them apprised of issues ranging from road closures to plans for yard revegetation. Even the six homes acquired for demolition became a community asset. After the project paid for the owners to relocate, the SDS team offered reus- able items—such as plumbing fixtures, cabinets and doors—to the local Habitat for Humanity office to resell or install in their homes. Local fire and police departments were invited to use the houses to con- duct drills and practice simulated firefighting. By utilizing creative approaches to construction, coupled with a commitment to communication and community relations, SDS is advancing a criti- cal water infrastructure project for four southern Colorado communities, creating a more certain water future for its customers. WWD Janet Rummel is senior public affairs specialist for Colorado Springs Utilities. Rummel can be reached at jrummel@csu.org or 719.668.3030. For more information, write in 1109 on this issue’s reader service form on page 42. pipe distribution systems Finishing Strong The 6.4-mile pipeline in the Pueblo West neighborhood had to travel through 125 residential yards. Installation of the shaft riser Several crossings were built using gates and fences to allow ATV riders to safely pass through the construction zone. specialsection MUNCH? 1936 was a good year for progressing cavity (PC) pumps. We started manufacturing PC pumps in the United States, and since then, Moyno has added industrial grinders providing reliable, effective maceration of solids to protect downstream equipment from blockages. We’re pround of the new, innovative designs like the EZstrip TR Muncher–quick, simple, maintain-in-place solution making your job easier. www.moyno.com/EZstrip TR Muncher offers different cutter thickness to match the required particle size for application. A quick release access port allows in-place inspection and cutter stack replacement. Write in 116Write in 115