SlideShare a Scribd company logo
1 of 3
Download to read offline
November 2017
26 NORTH AMERICA
T
o say that Deep Founda-
tions Contractors (Deep)
was drilling in a confined
space within an extraction shaft on
the Eglinton Crosstown Light Rail
Transit Project (Crosstown) would
be an understatement.
It was the first of many chal-
lenges the firm would overcome
while working above and below
the buzzing streets of Midtown
Toronto, Canada. The epicentre of
the action, however, was a 32.5m
(107ft)-deep extraction shaft,
where two massive tunnel boring
machines (TBMs) would be lifted
from the ground at the end of
a long subterranean journey.
While Deep has extensive
experience working in Toronto,
there is nothing simple about
drilling in a crowded urban
environment. The Canadian
foundation contractor’s challenges
included inconsistent soil condi-
tions, low-clearance drilling,
unmovable utilities, maintaining
traffic and darkened confined
working spaces.
TRANSIT EXPANSION
Crosstown is a C$8.4 billion
(US$6.6 billion) infrastructure
project with a 19km corridor,
10km of which is underground.
Phase 2 includes the easternmost
tunnel. Come 2021, Metrolinx
projects that 5,500 passengers
per hour will benefit from this
project – the largest transit
expansion in Toronto history.
The Phase 2 contract was
awarded to the Aecon/ACS
Dragados Joint Venture in Novem-
ber 2013. Its scope entailed
3.25km of 6.5m-diameter twin
tunnels, precast concrete tunnel
lining segments, launch and
retrieval shafts, headwalls associ-
ated with future stations, two
emergency exit buildings, three
cross passages, utility relocations,
traffic staging, ground and
building settlement monitoring,
and site restoration.
Deep specialises in shoring for
a wide cross-section of building
and infrastructure projects. The
contractor was a natural fit having
worked on large transportation
projects, the most recent of which
was a subway extension for the
Toronto Transit Commission. The
Aecon/ACS Dragados JV awarded
Deep a roughly C$21 million
contract to excavate and shore
launch extraction shafts for two
TBMs, build two emergency exits
for the TBMs, and construct head
walls for two future stations. Its
work started in April 2014 and
concluded in March 2017.
KEEP THE TBMS BORING
Deep’s work would allow the two
TBMs, known as Don and Humber,
to continue underground uninter-
rupted. Stopping their progress
would be prohibitively expensive;
failure was not an option.
The Caterpillar TBMs – named
after two of Toronto’s rivers –
began tunnelling on September
30, 2015. The pair would crawl
westbound, digging 3.5km from
the launch shaft at Eglinton and
Leslie Streets before reaching
their destination. The TBMs would
eventually be hoisted out of
Extraction Shaft 3 (ES-3), which
sits at Yonge and Eglinton Streets,
Midtown Toronto’s busiest
intersection. Deep’s goal was to
prepare the shaft for their arrival.
FLEET OF BAUER RIGS
The ace Deep held in its pocket
was Canada’s largest fleet of
Bauer drilling rigs, all of which
were acquired from Equipment
Corporation of America (ECA).
Deep purchased the BG 55 –
one of the most powerful rotary
drilling rigs on the market at the
time with 553kNm of torque – in
September 2016. The contractor
then acquired one of the small-
est, a BG 11 H, in August 2017.
ECA also sold Deep seven Klemm
drilling rigs.
“We have the biggest fleet of
Bauers in Canada,” says Conor
Foy, Deep’s supervisor on the
Crosstown. According to ECA
Canada’s branch manager Ray
Kemppainen, Deep geared up
by purchasing five more rigs from
late 2015 to early 2016, including
a BG 46, two BG 39s, a BG 40 and
a BG 30.
In the early 2000s, Deep
analysed the drill-rig manufactur-
ing market and made a calculated
decision to acquire Bauer rigs.
Kemppainen recalls the 1970s
when the firm was buying
foundation equipment from his
former employer, Special Con-
struction Machines, known today
as ECA Canada. Deep is now
ECA’s largest Canadian client.
Deep was using conventional
crane-mounted drilling equipment
combined with vibratory hammers
to drive and extract casing in
urban environments, which is
more disruptive to residents and
motorists. Bauer technology
allows contractors to install and
remove sectional casings using its
rigs’ powerful hydraulic rotaries.
ECA was instrumental in
matching equipment to the
complexities of the Crosstown,
according to Foy. “There was a lot
of back and forth,” he says. “We
had to provide a lot of information
and work with them to get the
right equipment.”
Keep on boring
Deep Foundations drills to keep tunnel boring machines
crawling on Canada’s largest transit expansion
Deep used a
crane to lower
the BAUER BG
11 H drilling rig
into Extraction
Shaft 3
The mast of
the BG 11 H
was within
inches of the
lowest utility
support
27
November 2017
FEATURE NAME 27NORTH AMERICA
The back and forth Foy refers
to revolves around service,
parts and training, according to
Kemppainen. He adds that Deep’s
managers were given authority to
order parts directly from the job
site, given the unforgiving
schedule and critical need to keep
the rigs drilling.
GROUND CONDITIONS
Midtown Toronto is notorious for
its troublesome ground condi-
tions. This reality sunk in as Deep
began drilling ES-3. The first 10m
included granular and silty sands.
Deep then hit the water table
and encountered flowing silt,
which went down 16m. A layer of
dense glacial till stretched from
26m to 32.5m below the surface.
The contractor overcame the soil
conditions with careful drilling
techniques and an assortment
of drilling buckets and tooling.
One challenge was unstable
soil. “The problem when it got
wet was the silty sand,” Foy
recalls. “It was very fluid, so you
had to follow proper procedures
to make sure the drilling was
consistent and you didn’t have
any cave-ins.” Deep relied
primarily on Bauer drilling buckets
to conquer the material. Augers
were used as a back-up and
bailers helped to remove water.
SHAFT WITHIN A SHAFT
Deep’s decision during the
tender process to tap Ontario-
based Isherwood Geostructural
Engineers as a shoring engineer
paid off. Working with Deep,
Isherwood engineered a creative
solution whereby a shaft could be
deepened just enough to allow
the Bauer BG 11 to go below
street level to install a secant wall
from within. After establishing
the dimensions of the rig and
surveying the lowest utility
supports, Deep determined that
lowering the grade to 15.5m and
pouring a temporary slab would
allow the BG 11 H to finish off
the secant wall.
Deep built ES-3 in two sections:
north and south. Each presented
a unique set of challenges.
The conflicting utilities in the
northern half were relocatable,
which allowed Deep to build a
secant pile wall by drilling from
the surface with one of its five
Bauer BG 40 drilling rigs. Fibre-
glass pile sections were used
on the east wall to prepare for
breakthrough by the TBMs.
Deep kept traffic flowing on
Eglinton Avenue by building a
temporary bridge deck over the
northern half once drilling was
completed. It consisted of timber
mats supported by steel beams
and bracing, and locked in place
with steel angle.
Once utilities were surveyed
and protected with steel sheeting,
Deep relocated its Bauer BG 40 to
start drilling in the southern half. It
was important to compare pile
and utility locations to avoid any
conflicts. The challenges with
confined space and drilling depths
faced in the northern half
remained, but all holes were
completed safely and efficiently.
Supporting utilities was Deep’s
top priority when excavating the
southern half of ES-3. The crew
built a lattice of steel support
beams to support the utility ducts/
conduits and mains running across
the shaft before commencing
work on the deck. Following a
rigorous inspection, this deck was
opened to traffic and the north
deck was removed. The north
would now remain open to allow
for removal of spoils, and eventu-
ally, the two TBMs.
Deep installed an internal waler
and lagging design to continue
shoring below the utilities, so that
The conflicting utilities in
the northern half were
relocatable, which allowed
Deep to build a secant
pile wall by drilling from
the surface with one of its
five Bauer BG 40s
The BG 11 came
as standard with
the ability to
remove the
upper section
for low-
headroom
applications
Wilsonville, Oregon USA
Tel +1 (503) 682-1001
info@rockmore-intl.com
Judenburg, Austria
Tel +43 3572-86300
austria@rockmore-intl.com
DrillMore
Mining
Construction
Quarrying
Tunneling
Water-well
with RockMore
R o c k M o r e
I n t e r n a t i o n a l
  ¡ ¢ £ ¤ ¥ ¦ § § ¦ ¨ ©  ¡ ¡ § 


Bits
Rods
Couplings
Shanks
DTH
Visit us at
in Reno, NV, USA,
Booth# 760
November 2017
28 NORTH AMERICA
the slab could be poured for the
BG 11 H. The system, designed by
Isherwood Geostructural Engi-
neers, allowed the excavation to
be lowered enough for a compact
air track drill to drive soil nails. The
crew worked within a confined
space to install the nails and spray
shotcrete in a panel sequence to
keep the ground stable as
excavation continued. Alternating
panels allowed Deep to vertically
excavate up to 1.2m of material
every week. External dewatering
was required for the final two
levels, below the water table.
Most secant piles were accom-
plished from street level, but three
windows remained in the southern
half where that was not an option.
Closing them during the remain-
der of the excavation proved to
be the greatest challenge of the
complex ES-3 shaft construction.
The client dewatered ES-3 to
lower the water table by one
metre, so that the working
platform could be poured at the
correct elevation. The equipment
ran until the secant wall was
finished to keep the water at bay.
CONFINED SPACE
One of the most interesting
spectacles for passers-by was the
sight of a Bauer BG 11 H dan-
gling from the end of a crane line
as it slowly descended below
street level. Drilling within the
cavernous ES-3 was also one of
the more complex engineering
challenges Deep overcame.
“You barely had room to
breathe, especially inside the
shaft,” Foy says of ES-3, adding
that the mast of the BG 11 H was
within inches of the lowest utility
support. The height from the
drilling slab to the underside of
the utilities was 9.8m. “You had
to put in the preparation work
and make sure everyone knew
what they were doing and had
clear procedures for what was
happening.”
The compact rig excelled at
drilling in a confined space due
to its lower header configuration,
according to Kemppainen. Deep
was renting the rig from ECA
at the time, but converted to a
purchase because it was suited for
this operation.
Kemppainen explains: “The BG
11 comes standard with the ability
to remove the upper section for
low-headroom applications.
Deep removed the upper section
themselves, and ECA Canada
provided a shorter kelly bar for
the low-headroom application.”
“The BG 11 H was the only rig
that could fit under the decking
and utilities and still be able to
drill the required depth to
complete that wall,” Foy adds.
“This machine was dropped in
15m below ground surface, but it
still had to drill holes from inside
the shaft down another 17.8m.”
There were other selling points
for the BG 11 H too. At 35,000kg,
it could be safely lowered into
the excavation by a crane. The
rig’s ability to deliver 110kNm
(81,130ft-lb) of torque down
to a depth of 40m was a bonus.
Even though the BG 11 H was
compact enough to work beneath
the utilities, it was incapable of
using casing to drill the remaining
17.8m-long piles. Deep needed a
high-quality, water-tight secant
wall to keep the shaft dry.
The contractor chose a polymer
drilling fluid to keep the holes
open. A liner was inserted to keep
the top of the excavation open
and the fluid was pumped for the
remainder of the shaft. These
steps, with dewatering, created
enough head pressure to keep the
flowing silt from caving in.
The slurry bubbled in the tanks
at street level while being mixed
and agitated. Deep regularly
tested it for pH and viscosity
before turning on the constant
flow required during drilling.
Once the drill bit hit the
founding elevation, a drilling
bucket scooped out any leftover
chunks of earth. It was critical for
the slurry to keep the hole open
and clean, while Deep’s crews
built sectional piles in preparation
for concrete pouring.
LARGE PILES
The size of the piles forced Deep
to improvise. At 18m in length
and weighing 8,400kg, they were
too long to hoist in one piece and
too heavy for the BG 11 H to lift.
Deep designed a hoisting
device above each pile location
that could lower each of the three
six-metre sections to be bolted
together before eventually being
moved down to their founding
elevations. The hoist could lift
three 6m sections together.
Once the piles were installed to
the correct elevation, the concrete
was placed under polymer slurry
using the tremie method. The
crew poured each pile with a
flexible hose connected to a
sectional tremie pipe fed by a
pump above the shaft. The pipe
was then lowered to the bottom
of each hole. As the concrete was
placed, the slurry in each hole was
displaced.
Deep’s crews persevered 24
hours a day, six days a week to
complete the 29 secant piles
under a rigorous schedule. By this
time the northbound TBM had
already broken through. The
southbound TBM and a 50-person
crew were crawling quickly toward
ES-3. Deep had to be out of the
shaft before breakthrough.
On March 13, 2017, the lower
drilling came to a conclusion. The
project was completed success-
fully to the satisfaction of all
parties involved, bringing the City
of Toronto about 3.5km closer to
increased mobility.
This article was written by Brian M. Fraley, Fraley Construction Marketing
The Deep team
celebrates the
breakthrough
of a TBM
Deep regularly
tested polymer
drilling slurry for
pH and viscosity
before turning
on the constant
flow required
during drilling

More Related Content

What's hot

Henn, Ray (LONG) w-o PhD 2014 (NEW)
Henn, Ray  (LONG) w-o PhD 2014 (NEW)Henn, Ray  (LONG) w-o PhD 2014 (NEW)
Henn, Ray (LONG) w-o PhD 2014 (NEW)Raymond Henn
 
Case Study Brighton Pier 2012
Case Study   Brighton Pier 2012Case Study   Brighton Pier 2012
Case Study Brighton Pier 2012gavinrixon
 
Kansas City Collapse
Kansas City CollapseKansas City Collapse
Kansas City CollapseDon W. Lewis
 
PowerPoint report of Hyatt Regency Walkway Collapse of 1981
PowerPoint report of Hyatt Regency Walkway Collapse of 1981PowerPoint report of Hyatt Regency Walkway Collapse of 1981
PowerPoint report of Hyatt Regency Walkway Collapse of 1981Ash Bista
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters DubaiNeha Rampuria
 
Lofted Final Report
Lofted Final ReportLofted Final Report
Lofted Final ReportCarlos Vega
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipmentsR VIJAYAKUMAR
 
Foundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj KhalifaFoundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj Khalifaastoria104
 
Seismic Upgrade of Alcatraz Quatermaster Building
Seismic Upgrade of Alcatraz Quatermaster Building  Seismic Upgrade of Alcatraz Quatermaster Building
Seismic Upgrade of Alcatraz Quatermaster Building Muneer Merchant
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...Michal Krzeminski
 

What's hot (20)

Henn, Ray (LONG) w-o PhD 2014 (NEW)
Henn, Ray  (LONG) w-o PhD 2014 (NEW)Henn, Ray  (LONG) w-o PhD 2014 (NEW)
Henn, Ray (LONG) w-o PhD 2014 (NEW)
 
Case Study Brighton Pier 2012
Case Study   Brighton Pier 2012Case Study   Brighton Pier 2012
Case Study Brighton Pier 2012
 
Fallingwater Residence
Fallingwater ResidenceFallingwater Residence
Fallingwater Residence
 
Edward Rice House
Edward Rice HouseEdward Rice House
Edward Rice House
 
Kansas City Collapse
Kansas City CollapseKansas City Collapse
Kansas City Collapse
 
PowerPoint report of Hyatt Regency Walkway Collapse of 1981
PowerPoint report of Hyatt Regency Walkway Collapse of 1981PowerPoint report of Hyatt Regency Walkway Collapse of 1981
PowerPoint report of Hyatt Regency Walkway Collapse of 1981
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Al dar hq
Al dar hqAl dar hq
Al dar hq
 
Final EIS Appendix E
Final EIS Appendix EFinal EIS Appendix E
Final EIS Appendix E
 
Lofted Final Report
Lofted Final ReportLofted Final Report
Lofted Final Report
 
Dam engineering i 5
Dam engineering i 5Dam engineering i 5
Dam engineering i 5
 
1115
11151115
1115
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipments
 
Foundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj KhalifaFoundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj Khalifa
 
Seismic Upgrade of Alcatraz Quatermaster Building
Seismic Upgrade of Alcatraz Quatermaster Building  Seismic Upgrade of Alcatraz Quatermaster Building
Seismic Upgrade of Alcatraz Quatermaster Building
 
trial 1
trial 1trial 1
trial 1
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
 
AR Gunnar Birkerts
AR Gunnar BirkertsAR Gunnar Birkerts
AR Gunnar Birkerts
 
Dam engineering i 2
Dam engineering i 2Dam engineering i 2
Dam engineering i 2
 
Possible flood adaptation strategies for Catskill, NY
Possible flood adaptation strategies for Catskill, NYPossible flood adaptation strategies for Catskill, NY
Possible flood adaptation strategies for Catskill, NY
 

Similar to Deep Foundations Contractors Overcomes Challenges Drilling Extraction Shaft for Toronto Transit Project

CTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdfCTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdfPramodLimbore
 
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)Hamed Zarei
 
The Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdfThe Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdffreezefreeze2
 
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINALJoe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINALJoseph Kaufman
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineFilipe Mello
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdfSaqib Imran
 
Underwater Tunnels
Underwater TunnelsUnderwater Tunnels
Underwater TunnelsIshan Parekh
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Ryan Johnson
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuVishweshwar Rao Narla
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationAmir Amdani
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewR K DHIMAN
 

Similar to Deep Foundations Contractors Overcomes Challenges Drilling Extraction Shaft for Toronto Transit Project (20)

CTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdfCTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdf
 
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
 
06 bridge
06 bridge06 bridge
06 bridge
 
Bigdig project
Bigdig projectBigdig project
Bigdig project
 
The Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdfThe Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdf
 
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINALJoe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazine
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Ranjitha.S.H
Ranjitha.S.HRanjitha.S.H
Ranjitha.S.H
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdf
 
Underwater Tunnels
Underwater TunnelsUnderwater Tunnels
Underwater Tunnels
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15
 
coalpreppic
coalpreppiccoalpreppic
coalpreppic
 
Linn Cove Viaduct
Linn Cove ViaductLinn Cove Viaduct
Linn Cove Viaduct
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
Construction site
Construction siteConstruction site
Construction site
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over view
 

More from Fraley Construction Marketing

E.J. Breneman Cold In-Place Recycling Constructioneer Job Story
E.J. Breneman Cold In-Place Recycling Constructioneer Job StoryE.J. Breneman Cold In-Place Recycling Constructioneer Job Story
E.J. Breneman Cold In-Place Recycling Constructioneer Job StoryFraley Construction Marketing
 
Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019
Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019
Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019Fraley Construction Marketing
 
deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...
deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...
deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...Fraley Construction Marketing
 
ECA Among First to Support AED's Technician Certification Program
ECA Among First to Support AED's Technician Certification ProgramECA Among First to Support AED's Technician Certification Program
ECA Among First to Support AED's Technician Certification ProgramFraley Construction Marketing
 
ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing
ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing
ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing Fraley Construction Marketing
 
RTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark III
RTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark IIIRTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark III
RTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark IIIFraley Construction Marketing
 
Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.
Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.
Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.Fraley Construction Marketing
 
11th Annual Hoppenville Antique Truck, Tractor & Car Show
11th Annual Hoppenville Antique Truck, Tractor & Car Show11th Annual Hoppenville Antique Truck, Tractor & Car Show
11th Annual Hoppenville Antique Truck, Tractor & Car ShowFraley Construction Marketing
 
Marketing: Just as Important in the Construction Industry
Marketing: Just as Important in the Construction IndustryMarketing: Just as Important in the Construction Industry
Marketing: Just as Important in the Construction IndustryFraley Construction Marketing
 

More from Fraley Construction Marketing (20)

E.J. Breneman Cold In-Place Recycling Constructioneer Job Story
E.J. Breneman Cold In-Place Recycling Constructioneer Job StoryE.J. Breneman Cold In-Place Recycling Constructioneer Job Story
E.J. Breneman Cold In-Place Recycling Constructioneer Job Story
 
Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019
Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019
Pile Buck Magazine Cover Story Burke seawall story pile buck vol. 35 no. 6 2019
 
R.A.M. Breaks State Records Pound by Pound
R.A.M. Breaks State Records Pound by PoundR.A.M. Breaks State Records Pound by Pound
R.A.M. Breaks State Records Pound by Pound
 
BAUER BGs Bore Boulders Below Brooklyn Cover Story
BAUER BGs Bore Boulders Below Brooklyn Cover StoryBAUER BGs Bore Boulders Below Brooklyn Cover Story
BAUER BGs Bore Boulders Below Brooklyn Cover Story
 
ECA 100 Year Anniversary Piling Canada Cover Story
ECA 100 Year Anniversary Piling Canada Cover StoryECA 100 Year Anniversary Piling Canada Cover Story
ECA 100 Year Anniversary Piling Canada Cover Story
 
ECA 1921 Rebuilding Brochure
ECA 1921 Rebuilding BrochureECA 1921 Rebuilding Brochure
ECA 1921 Rebuilding Brochure
 
deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...
deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...
deep Foundations Drills to Keep TBs Crawling on Canada's Largest Transit Expa...
 
ECA Among First to Support AED's Technician Certification Program
ECA Among First to Support AED's Technician Certification ProgramECA Among First to Support AED's Technician Certification Program
ECA Among First to Support AED's Technician Certification Program
 
Picking the Rockefeller Center Christmas Tree
Picking the Rockefeller Center Christmas TreePicking the Rockefeller Center Christmas Tree
Picking the Rockefeller Center Christmas Tree
 
Second Chance Line Restraint Advertorial
Second Chance Line Restraint Advertorial Second Chance Line Restraint Advertorial
Second Chance Line Restraint Advertorial
 
ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing
ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing
ECA Sponsors and Attends the 6th Annual ADSC Carolinas Golf Outing
 
PennDOT Embraces GPS Technology Column
PennDOT Embraces GPS Technology ColumnPennDOT Embraces GPS Technology Column
PennDOT Embraces GPS Technology Column
 
Big Cats Chew Through Rocky Terrain
Big Cats Chew Through Rocky Terrain Big Cats Chew Through Rocky Terrain
Big Cats Chew Through Rocky Terrain
 
RTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark III
RTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark IIIRTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark III
RTG Pile Driving Rigs Pay Off Big for PA's PKF-Mark III
 
Pennsylvania Turnpike/I-95 Interchange Project
Pennsylvania Turnpike/I-95 Interchange ProjectPennsylvania Turnpike/I-95 Interchange Project
Pennsylvania Turnpike/I-95 Interchange Project
 
Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.
Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.
Change of Pace: PKF's Bet on RTG Pile Driving Rigs Pays Off in the U.S.
 
PKF's Bet on RTG Pile Driving Rigs Pays Off Big
PKF's Bet on RTG Pile Driving Rigs Pays Off BigPKF's Bet on RTG Pile Driving Rigs Pays Off Big
PKF's Bet on RTG Pile Driving Rigs Pays Off Big
 
11th Annual Hoppenville Antique Truck, Tractor & Car Show
11th Annual Hoppenville Antique Truck, Tractor & Car Show11th Annual Hoppenville Antique Truck, Tractor & Car Show
11th Annual Hoppenville Antique Truck, Tractor & Car Show
 
Marketing: Just as Important in the Construction Industry
Marketing: Just as Important in the Construction IndustryMarketing: Just as Important in the Construction Industry
Marketing: Just as Important in the Construction Industry
 
Rebuilding a Historic Viaduct
Rebuilding a Historic ViaductRebuilding a Historic Viaduct
Rebuilding a Historic Viaduct
 

Recently uploaded

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

Deep Foundations Contractors Overcomes Challenges Drilling Extraction Shaft for Toronto Transit Project

  • 1. November 2017 26 NORTH AMERICA T o say that Deep Founda- tions Contractors (Deep) was drilling in a confined space within an extraction shaft on the Eglinton Crosstown Light Rail Transit Project (Crosstown) would be an understatement. It was the first of many chal- lenges the firm would overcome while working above and below the buzzing streets of Midtown Toronto, Canada. The epicentre of the action, however, was a 32.5m (107ft)-deep extraction shaft, where two massive tunnel boring machines (TBMs) would be lifted from the ground at the end of a long subterranean journey. While Deep has extensive experience working in Toronto, there is nothing simple about drilling in a crowded urban environment. The Canadian foundation contractor’s challenges included inconsistent soil condi- tions, low-clearance drilling, unmovable utilities, maintaining traffic and darkened confined working spaces. TRANSIT EXPANSION Crosstown is a C$8.4 billion (US$6.6 billion) infrastructure project with a 19km corridor, 10km of which is underground. Phase 2 includes the easternmost tunnel. Come 2021, Metrolinx projects that 5,500 passengers per hour will benefit from this project – the largest transit expansion in Toronto history. The Phase 2 contract was awarded to the Aecon/ACS Dragados Joint Venture in Novem- ber 2013. Its scope entailed 3.25km of 6.5m-diameter twin tunnels, precast concrete tunnel lining segments, launch and retrieval shafts, headwalls associ- ated with future stations, two emergency exit buildings, three cross passages, utility relocations, traffic staging, ground and building settlement monitoring, and site restoration. Deep specialises in shoring for a wide cross-section of building and infrastructure projects. The contractor was a natural fit having worked on large transportation projects, the most recent of which was a subway extension for the Toronto Transit Commission. The Aecon/ACS Dragados JV awarded Deep a roughly C$21 million contract to excavate and shore launch extraction shafts for two TBMs, build two emergency exits for the TBMs, and construct head walls for two future stations. Its work started in April 2014 and concluded in March 2017. KEEP THE TBMS BORING Deep’s work would allow the two TBMs, known as Don and Humber, to continue underground uninter- rupted. Stopping their progress would be prohibitively expensive; failure was not an option. The Caterpillar TBMs – named after two of Toronto’s rivers – began tunnelling on September 30, 2015. The pair would crawl westbound, digging 3.5km from the launch shaft at Eglinton and Leslie Streets before reaching their destination. The TBMs would eventually be hoisted out of Extraction Shaft 3 (ES-3), which sits at Yonge and Eglinton Streets, Midtown Toronto’s busiest intersection. Deep’s goal was to prepare the shaft for their arrival. FLEET OF BAUER RIGS The ace Deep held in its pocket was Canada’s largest fleet of Bauer drilling rigs, all of which were acquired from Equipment Corporation of America (ECA). Deep purchased the BG 55 – one of the most powerful rotary drilling rigs on the market at the time with 553kNm of torque – in September 2016. The contractor then acquired one of the small- est, a BG 11 H, in August 2017. ECA also sold Deep seven Klemm drilling rigs. “We have the biggest fleet of Bauers in Canada,” says Conor Foy, Deep’s supervisor on the Crosstown. According to ECA Canada’s branch manager Ray Kemppainen, Deep geared up by purchasing five more rigs from late 2015 to early 2016, including a BG 46, two BG 39s, a BG 40 and a BG 30. In the early 2000s, Deep analysed the drill-rig manufactur- ing market and made a calculated decision to acquire Bauer rigs. Kemppainen recalls the 1970s when the firm was buying foundation equipment from his former employer, Special Con- struction Machines, known today as ECA Canada. Deep is now ECA’s largest Canadian client. Deep was using conventional crane-mounted drilling equipment combined with vibratory hammers to drive and extract casing in urban environments, which is more disruptive to residents and motorists. Bauer technology allows contractors to install and remove sectional casings using its rigs’ powerful hydraulic rotaries. ECA was instrumental in matching equipment to the complexities of the Crosstown, according to Foy. “There was a lot of back and forth,” he says. “We had to provide a lot of information and work with them to get the right equipment.” Keep on boring Deep Foundations drills to keep tunnel boring machines crawling on Canada’s largest transit expansion Deep used a crane to lower the BAUER BG 11 H drilling rig into Extraction Shaft 3 The mast of the BG 11 H was within inches of the lowest utility support
  • 2. 27 November 2017 FEATURE NAME 27NORTH AMERICA The back and forth Foy refers to revolves around service, parts and training, according to Kemppainen. He adds that Deep’s managers were given authority to order parts directly from the job site, given the unforgiving schedule and critical need to keep the rigs drilling. GROUND CONDITIONS Midtown Toronto is notorious for its troublesome ground condi- tions. This reality sunk in as Deep began drilling ES-3. The first 10m included granular and silty sands. Deep then hit the water table and encountered flowing silt, which went down 16m. A layer of dense glacial till stretched from 26m to 32.5m below the surface. The contractor overcame the soil conditions with careful drilling techniques and an assortment of drilling buckets and tooling. One challenge was unstable soil. “The problem when it got wet was the silty sand,” Foy recalls. “It was very fluid, so you had to follow proper procedures to make sure the drilling was consistent and you didn’t have any cave-ins.” Deep relied primarily on Bauer drilling buckets to conquer the material. Augers were used as a back-up and bailers helped to remove water. SHAFT WITHIN A SHAFT Deep’s decision during the tender process to tap Ontario- based Isherwood Geostructural Engineers as a shoring engineer paid off. Working with Deep, Isherwood engineered a creative solution whereby a shaft could be deepened just enough to allow the Bauer BG 11 to go below street level to install a secant wall from within. After establishing the dimensions of the rig and surveying the lowest utility supports, Deep determined that lowering the grade to 15.5m and pouring a temporary slab would allow the BG 11 H to finish off the secant wall. Deep built ES-3 in two sections: north and south. Each presented a unique set of challenges. The conflicting utilities in the northern half were relocatable, which allowed Deep to build a secant pile wall by drilling from the surface with one of its five Bauer BG 40 drilling rigs. Fibre- glass pile sections were used on the east wall to prepare for breakthrough by the TBMs. Deep kept traffic flowing on Eglinton Avenue by building a temporary bridge deck over the northern half once drilling was completed. It consisted of timber mats supported by steel beams and bracing, and locked in place with steel angle. Once utilities were surveyed and protected with steel sheeting, Deep relocated its Bauer BG 40 to start drilling in the southern half. It was important to compare pile and utility locations to avoid any conflicts. The challenges with confined space and drilling depths faced in the northern half remained, but all holes were completed safely and efficiently. Supporting utilities was Deep’s top priority when excavating the southern half of ES-3. The crew built a lattice of steel support beams to support the utility ducts/ conduits and mains running across the shaft before commencing work on the deck. Following a rigorous inspection, this deck was opened to traffic and the north deck was removed. The north would now remain open to allow for removal of spoils, and eventu- ally, the two TBMs. Deep installed an internal waler and lagging design to continue shoring below the utilities, so that The conflicting utilities in the northern half were relocatable, which allowed Deep to build a secant pile wall by drilling from the surface with one of its five Bauer BG 40s The BG 11 came as standard with the ability to remove the upper section for low- headroom applications Wilsonville, Oregon USA Tel +1 (503) 682-1001 info@rockmore-intl.com Judenburg, Austria Tel +43 3572-86300 austria@rockmore-intl.com DrillMore Mining Construction Quarrying Tunneling Water-well with RockMore R o c k M o r e I n t e r n a t i o n a l   ¡ ¢ £ ¤ ¥ ¦ § § ¦ ¨ © ¡ ¡ § Bits Rods Couplings Shanks DTH Visit us at in Reno, NV, USA, Booth# 760
  • 3. November 2017 28 NORTH AMERICA the slab could be poured for the BG 11 H. The system, designed by Isherwood Geostructural Engi- neers, allowed the excavation to be lowered enough for a compact air track drill to drive soil nails. The crew worked within a confined space to install the nails and spray shotcrete in a panel sequence to keep the ground stable as excavation continued. Alternating panels allowed Deep to vertically excavate up to 1.2m of material every week. External dewatering was required for the final two levels, below the water table. Most secant piles were accom- plished from street level, but three windows remained in the southern half where that was not an option. Closing them during the remain- der of the excavation proved to be the greatest challenge of the complex ES-3 shaft construction. The client dewatered ES-3 to lower the water table by one metre, so that the working platform could be poured at the correct elevation. The equipment ran until the secant wall was finished to keep the water at bay. CONFINED SPACE One of the most interesting spectacles for passers-by was the sight of a Bauer BG 11 H dan- gling from the end of a crane line as it slowly descended below street level. Drilling within the cavernous ES-3 was also one of the more complex engineering challenges Deep overcame. “You barely had room to breathe, especially inside the shaft,” Foy says of ES-3, adding that the mast of the BG 11 H was within inches of the lowest utility support. The height from the drilling slab to the underside of the utilities was 9.8m. “You had to put in the preparation work and make sure everyone knew what they were doing and had clear procedures for what was happening.” The compact rig excelled at drilling in a confined space due to its lower header configuration, according to Kemppainen. Deep was renting the rig from ECA at the time, but converted to a purchase because it was suited for this operation. Kemppainen explains: “The BG 11 comes standard with the ability to remove the upper section for low-headroom applications. Deep removed the upper section themselves, and ECA Canada provided a shorter kelly bar for the low-headroom application.” “The BG 11 H was the only rig that could fit under the decking and utilities and still be able to drill the required depth to complete that wall,” Foy adds. “This machine was dropped in 15m below ground surface, but it still had to drill holes from inside the shaft down another 17.8m.” There were other selling points for the BG 11 H too. At 35,000kg, it could be safely lowered into the excavation by a crane. The rig’s ability to deliver 110kNm (81,130ft-lb) of torque down to a depth of 40m was a bonus. Even though the BG 11 H was compact enough to work beneath the utilities, it was incapable of using casing to drill the remaining 17.8m-long piles. Deep needed a high-quality, water-tight secant wall to keep the shaft dry. The contractor chose a polymer drilling fluid to keep the holes open. A liner was inserted to keep the top of the excavation open and the fluid was pumped for the remainder of the shaft. These steps, with dewatering, created enough head pressure to keep the flowing silt from caving in. The slurry bubbled in the tanks at street level while being mixed and agitated. Deep regularly tested it for pH and viscosity before turning on the constant flow required during drilling. Once the drill bit hit the founding elevation, a drilling bucket scooped out any leftover chunks of earth. It was critical for the slurry to keep the hole open and clean, while Deep’s crews built sectional piles in preparation for concrete pouring. LARGE PILES The size of the piles forced Deep to improvise. At 18m in length and weighing 8,400kg, they were too long to hoist in one piece and too heavy for the BG 11 H to lift. Deep designed a hoisting device above each pile location that could lower each of the three six-metre sections to be bolted together before eventually being moved down to their founding elevations. The hoist could lift three 6m sections together. Once the piles were installed to the correct elevation, the concrete was placed under polymer slurry using the tremie method. The crew poured each pile with a flexible hose connected to a sectional tremie pipe fed by a pump above the shaft. The pipe was then lowered to the bottom of each hole. As the concrete was placed, the slurry in each hole was displaced. Deep’s crews persevered 24 hours a day, six days a week to complete the 29 secant piles under a rigorous schedule. By this time the northbound TBM had already broken through. The southbound TBM and a 50-person crew were crawling quickly toward ES-3. Deep had to be out of the shaft before breakthrough. On March 13, 2017, the lower drilling came to a conclusion. The project was completed success- fully to the satisfaction of all parties involved, bringing the City of Toronto about 3.5km closer to increased mobility. This article was written by Brian M. Fraley, Fraley Construction Marketing The Deep team celebrates the breakthrough of a TBM Deep regularly tested polymer drilling slurry for pH and viscosity before turning on the constant flow required during drilling