SlideShare a Scribd company logo
1 of 23
SAFETY
PRECAUTION
DURING
OHE MAINTENANCE
25 kV AC Traction Safety Requirements
• Major Track Maintenance Works:
An authorised OHE staff should invariably be present, when
relaying work or any major work on track is carried out, in
order to ensure the following points:
(i) Power block is correctly taken and permit to work is issued;
(ii) The structure bonds, track bonds, cross bonds, longitudinal
rail bonds etc. are not disturbed and if disconnected for the
work, they are reconnected properly when the work is
completed.
(iii) The return feeder connections to the rails at the feeding
posts are proper and not disturbed.
(iv) The setting distance of the structure do not affected during
slewing.
25 kV AC Traction Safety Requirements
• Major Track Maintenance Works:
(v) The track level is not raised beyond the permissible limits
during the work;
(vi) Excavation or digging near a mast foundation is done in such a
manner that the foundation is not exposed;
(vii) The clearance particularly at over line structure is maintained
to the required standards; (viii) Precautions for the safety of staff
working under the OHE are taken correctly.
(viii)The Engineering officials in charge of such major work shall
ensure that intimation to their counterparts for OHE maintenance
work is given with adequate notice.
25 kV AC Traction Safety Requirements
• Major Track Maintenance Works:
(ix)Voltages are induced in conductive lines, rails and fence
running parallel to the traction lines. With the use of underground
cables and OFC the induced voltage/interference problem in the
communication circuits is practically resolved.
(x)The value of induced voltage depends on various factors such as
length of parallelism between the cable and electrified track, soil
conductivity, screening efficiency of cable sheath, return current,
through the rails and return conductor where provided, mutual
inductance between catenary and cable conductors, current carried
by the OHE.
Major Track Maintenance Works:
(xi) Appropriate precautions to overcome the effects of the
induced voltage, therefore, have to be taken by S&T department.
(xii) Other aspects where S&T equipment is affected are:
i) OHE masts and fittings may come in the way of visibility of
signals to some extent and may come in the way of signal.
ii) Restrictions in the path of traction currents on section provided
with track circuits.
25 kV AC Traction Safety Requirements
25 kV AC Traction Protection
• The protection of 25 kV ac traction equipment is achieved by
using different types of protection relays provided at the
Traction Substations.
• The protection relays protect traction equipment like
transformers, OHE, Capacitor banks etc. in case of faults
(short circuits).
• Maximum no. of faults occur on the OHE because of its wide
spread geometry and maximum exposure to external objects
(birds, monkeys, snakes, clothes, kites, pollution and weather
conditions etc.).
25 kV AC Traction Protection
• In order to avoid disruption of traction supply to OHE in case
of transient faults an auto recloser arrangement is adopted
which automatically closes CB after 500 ms.
• Only in case of permanent faults on OHE relays trip the CB
again and then TPC has to identify the faulty subsector by a
well defined logic and finally segregate it using SCADA
system.
• The relay status are also monitored by SCADA system.
25 kV AC Traction Protection
• Reliable, high speed and accurate protection systems
are required.
• Diverse range of rolling stocks(rectifier based to 3-
phase drives having regenerative braking features)
and poor traction power quality at TSS.
• Safe working depends on properly designed
protection system.
GENERAL SAFETY OHE
 No work shall be done above or within a distance of 2 meters
from the live OHE without a ‘‘Permit to work’’.
 Inductive effects occur on large metallic structural steel of
platforms running parallel to the track. They will gave to be
earthed suitably to afford safety.
 Whenever there is a doubt in description , the person asking
for power block shall state clearly the track and OHE structure
numbers between which work is to be done.
 When anybody deputed to RRI/Stations for taking power
block is not sure about switching alternations, movements of
trains during power block mainly in yards he should clearly
tell their JE/SSE that I have confusion regarding the same so
that the accidents can be avoided. It is important that staff who
ask for power block should know the correct method of
identifying and describing any section of OHE where
shutdown is required.
 The permit-to-work shall be obtained prior to commencing
work to make sure that power supply has been switched off.
GENERAL SAFETY OHE
 All message relating to shutdown and restoration of power
supply, permit to work etc. issued over the telephone shall
invariably be supported by exchange of private numbers and
repeated twice.
 Men should be posted on both sides of the site of work to warn
the working party of any approaching train on the same track
and adjacent track(s)
 Isolator shall not be opened when current is passing through it.
 Isolator switches on the main line may only be opened
provided the corresponding sub-sector is first made dead by
TPC.
GENERAL SAFETY OHE
 For providing earth on the OHE, fix the earthing clamp
securely to a mast at least one span away after making sure
that the mast to earth rail bond of this mast is intact.
 Earthing clamp should always be fixed to the traction rail first
and then the top clamp should be hooked to the OHE to be
earthed after touching to RT.
 For removing the earthing , first remove the hook on the OHE
and then clamp fixed to the rail or mast.
 Each working party shall be protected by at least two
independent earths, one on each side of a working party.
GENERAL SAFETY OHE
 If the distance between the working parties exceeds 1000
meters, intermediate earths shall be provided in such a manner
as to ensure that the distance between earths does not exceeds
1000 meters.
 All staff should wear helmets to protect their heads againsts
aginst any tool or equipment which may drop down accidently.
 Staff should protect themselves against an inadvertent fall by
wearing a safety belt for supporting themselves by a rope
sling.
GENERAL SAFETY OHE
 Ropes used with ladders should be cotton or jute. A ladder should
be held by one person on the ground to prevent slipping, while
the top end should be tied to the supporting structure or
conductor to keep it in position and prevent it sliding away.
 Ladder should never be allowed to fall on or rest against the
contact wire.
 More than one person shall not normally be allowed on a ladder
as far as possible.
GENERAL SAFETY OHE
 Climbing on a ladder with wet or slipery foot wear is forbidden.
 A rope should be used to pass tools or any equipment to the men
working on a ladder.
 No one should stand directly below a work spot under a ladder.
 Do not tie the rope on rail without taking traffic block.
 Two sections of conductors or ends of conductors which may
have snapped should be separately earthed at two points after
switching off supply to both parts of OHE. This precaution
should also be observed when working in the vicinity of a
sectioning point and cut-in-insulators.
GENERAL SAFETY OHE
 In electrified tracks ,steel tape or metallic tape or tape with
woven metal reinforcement should not be used.
 Ropes, come along clamps, tirfor, pull lifts should be tested once
in a month.
 The continuity of the cable connection between the top clamp
and the earthling clamp should be checked once a fortnight.
 Cable should be renewed if more than 20% strands are broken.
During use, cable should be continually examined for fraying and
breakage of strands.
GENERAL SAFETY OHE
 Neutral section should be treated as live equipment and
earthed separately at two points on either side of the work
party before commencing work.
 When work is to be carried out on isolator , both sides of
the isolator should be earthed at two points.
 No fallen wires should be touched unless power has been
switced off and the wires suitably earthed.
GENERAL SAFETY OHE
 The attention of all railway staff is drawn to the fact
that under 25 kV ac 50 Hz single phase traction, there
is heavy induction on all metallic structures and
conductors in the vicinity of the track.
 The induction is two-fold:
a) Electro-static, which results from the high
potential of 25 kV on the OHE system.
Safety.pptx
Safety.pptx
Safety.pptx
Safety.pptx

More Related Content

Similar to Safety.pptx

Construction safety pocket guide osha3252
Construction safety pocket guide osha3252Construction safety pocket guide osha3252
Construction safety pocket guide osha3252
zul husni
 
Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...
thanh phuoc bui
 
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
anishdani
 

Similar to Safety.pptx (20)

Related RE work (LT, 11kV & 33kV)
Related RE work (LT, 11kV & 33kV)Related RE work (LT, 11kV & 33kV)
Related RE work (LT, 11kV & 33kV)
 
electrical cable crossing.pdf
electrical cable crossing.pdfelectrical cable crossing.pdf
electrical cable crossing.pdf
 
194 adss cable-installationguide
194 adss cable-installationguide194 adss cable-installationguide
194 adss cable-installationguide
 
Overhead-Power-Cables classroom presentation
Overhead-Power-Cables classroom presentationOverhead-Power-Cables classroom presentation
Overhead-Power-Cables classroom presentation
 
work safety for RME
work safety for RMEwork safety for RME
work safety for RME
 
electrical regulation ppt 0123321123333333
electrical regulation ppt 0123321123333333electrical regulation ppt 0123321123333333
electrical regulation ppt 0123321123333333
 
Modern substation design 2
Modern substation design 2Modern substation design 2
Modern substation design 2
 
Modern substation design
Modern substation designModern substation design
Modern substation design
 
Electrical Saftey.pptx
Electrical Saftey.pptxElectrical Saftey.pptx
Electrical Saftey.pptx
 
2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines
 
6a_ELECTRIC SAFETY.ppt
6a_ELECTRIC SAFETY.ppt6a_ELECTRIC SAFETY.ppt
6a_ELECTRIC SAFETY.ppt
 
Reprint3
Reprint3Reprint3
Reprint3
 
22 electrical safety
22 electrical safety22 electrical safety
22 electrical safety
 
Construction safety pocket guide osha3252
Construction safety pocket guide osha3252Construction safety pocket guide osha3252
Construction safety pocket guide osha3252
 
Module-4-Electrical Safety in industrial safety
Module-4-Electrical Safety in industrial safetyModule-4-Electrical Safety in industrial safety
Module-4-Electrical Safety in industrial safety
 
Presentation water way journey by jmv lps
Presentation water way journey by jmv lpsPresentation water way journey by jmv lps
Presentation water way journey by jmv lps
 
13 l m100-150,cl13m10-15,14ml10
13 l m100-150,cl13m10-15,14ml1013 l m100-150,cl13m10-15,14ml10
13 l m100-150,cl13m10-15,14ml10
 
Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...
 
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
 
Safety in Erection of Steel Structures
Safety in Erection of Steel StructuresSafety in Erection of Steel Structures
Safety in Erection of Steel Structures
 

Recently uploaded

Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
IJECEIAES
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
MaherOthman7
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
Kira Dess
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
rahulmanepalli02
 

Recently uploaded (20)

Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
 
Insurance management system project report.pdf
Insurance management system project report.pdfInsurance management system project report.pdf
Insurance management system project report.pdf
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Students
 
Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...
 
Filters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility ApplicationsFilters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility Applications
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentation
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
 
21scheme vtu syllabus of visveraya technological university
21scheme vtu syllabus of visveraya technological university21scheme vtu syllabus of visveraya technological university
21scheme vtu syllabus of visveraya technological university
 
History of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & ModernizationHistory of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & Modernization
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 
handbook on reinforce concrete and detailing
handbook on reinforce concrete and detailinghandbook on reinforce concrete and detailing
handbook on reinforce concrete and detailing
 
Intro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney UniIntro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney Uni
 

Safety.pptx

  • 2. 25 kV AC Traction Safety Requirements • Major Track Maintenance Works: An authorised OHE staff should invariably be present, when relaying work or any major work on track is carried out, in order to ensure the following points: (i) Power block is correctly taken and permit to work is issued; (ii) The structure bonds, track bonds, cross bonds, longitudinal rail bonds etc. are not disturbed and if disconnected for the work, they are reconnected properly when the work is completed. (iii) The return feeder connections to the rails at the feeding posts are proper and not disturbed. (iv) The setting distance of the structure do not affected during slewing.
  • 3. 25 kV AC Traction Safety Requirements • Major Track Maintenance Works: (v) The track level is not raised beyond the permissible limits during the work; (vi) Excavation or digging near a mast foundation is done in such a manner that the foundation is not exposed; (vii) The clearance particularly at over line structure is maintained to the required standards; (viii) Precautions for the safety of staff working under the OHE are taken correctly. (viii)The Engineering officials in charge of such major work shall ensure that intimation to their counterparts for OHE maintenance work is given with adequate notice.
  • 4. 25 kV AC Traction Safety Requirements • Major Track Maintenance Works: (ix)Voltages are induced in conductive lines, rails and fence running parallel to the traction lines. With the use of underground cables and OFC the induced voltage/interference problem in the communication circuits is practically resolved. (x)The value of induced voltage depends on various factors such as length of parallelism between the cable and electrified track, soil conductivity, screening efficiency of cable sheath, return current, through the rails and return conductor where provided, mutual inductance between catenary and cable conductors, current carried by the OHE.
  • 5. Major Track Maintenance Works: (xi) Appropriate precautions to overcome the effects of the induced voltage, therefore, have to be taken by S&T department. (xii) Other aspects where S&T equipment is affected are: i) OHE masts and fittings may come in the way of visibility of signals to some extent and may come in the way of signal. ii) Restrictions in the path of traction currents on section provided with track circuits. 25 kV AC Traction Safety Requirements
  • 6. 25 kV AC Traction Protection • The protection of 25 kV ac traction equipment is achieved by using different types of protection relays provided at the Traction Substations. • The protection relays protect traction equipment like transformers, OHE, Capacitor banks etc. in case of faults (short circuits). • Maximum no. of faults occur on the OHE because of its wide spread geometry and maximum exposure to external objects (birds, monkeys, snakes, clothes, kites, pollution and weather conditions etc.).
  • 7. 25 kV AC Traction Protection • In order to avoid disruption of traction supply to OHE in case of transient faults an auto recloser arrangement is adopted which automatically closes CB after 500 ms. • Only in case of permanent faults on OHE relays trip the CB again and then TPC has to identify the faulty subsector by a well defined logic and finally segregate it using SCADA system. • The relay status are also monitored by SCADA system.
  • 8. 25 kV AC Traction Protection • Reliable, high speed and accurate protection systems are required. • Diverse range of rolling stocks(rectifier based to 3- phase drives having regenerative braking features) and poor traction power quality at TSS. • Safe working depends on properly designed protection system.
  • 9. GENERAL SAFETY OHE  No work shall be done above or within a distance of 2 meters from the live OHE without a ‘‘Permit to work’’.  Inductive effects occur on large metallic structural steel of platforms running parallel to the track. They will gave to be earthed suitably to afford safety.  Whenever there is a doubt in description , the person asking for power block shall state clearly the track and OHE structure numbers between which work is to be done.
  • 10.  When anybody deputed to RRI/Stations for taking power block is not sure about switching alternations, movements of trains during power block mainly in yards he should clearly tell their JE/SSE that I have confusion regarding the same so that the accidents can be avoided. It is important that staff who ask for power block should know the correct method of identifying and describing any section of OHE where shutdown is required.  The permit-to-work shall be obtained prior to commencing work to make sure that power supply has been switched off. GENERAL SAFETY OHE
  • 11.  All message relating to shutdown and restoration of power supply, permit to work etc. issued over the telephone shall invariably be supported by exchange of private numbers and repeated twice.  Men should be posted on both sides of the site of work to warn the working party of any approaching train on the same track and adjacent track(s)  Isolator shall not be opened when current is passing through it.  Isolator switches on the main line may only be opened provided the corresponding sub-sector is first made dead by TPC. GENERAL SAFETY OHE
  • 12.  For providing earth on the OHE, fix the earthing clamp securely to a mast at least one span away after making sure that the mast to earth rail bond of this mast is intact.  Earthing clamp should always be fixed to the traction rail first and then the top clamp should be hooked to the OHE to be earthed after touching to RT.  For removing the earthing , first remove the hook on the OHE and then clamp fixed to the rail or mast.  Each working party shall be protected by at least two independent earths, one on each side of a working party. GENERAL SAFETY OHE
  • 13.  If the distance between the working parties exceeds 1000 meters, intermediate earths shall be provided in such a manner as to ensure that the distance between earths does not exceeds 1000 meters.  All staff should wear helmets to protect their heads againsts aginst any tool or equipment which may drop down accidently.  Staff should protect themselves against an inadvertent fall by wearing a safety belt for supporting themselves by a rope sling. GENERAL SAFETY OHE
  • 14.  Ropes used with ladders should be cotton or jute. A ladder should be held by one person on the ground to prevent slipping, while the top end should be tied to the supporting structure or conductor to keep it in position and prevent it sliding away.  Ladder should never be allowed to fall on or rest against the contact wire.  More than one person shall not normally be allowed on a ladder as far as possible. GENERAL SAFETY OHE
  • 15.  Climbing on a ladder with wet or slipery foot wear is forbidden.  A rope should be used to pass tools or any equipment to the men working on a ladder.  No one should stand directly below a work spot under a ladder.  Do not tie the rope on rail without taking traffic block.  Two sections of conductors or ends of conductors which may have snapped should be separately earthed at two points after switching off supply to both parts of OHE. This precaution should also be observed when working in the vicinity of a sectioning point and cut-in-insulators. GENERAL SAFETY OHE
  • 16.  In electrified tracks ,steel tape or metallic tape or tape with woven metal reinforcement should not be used.  Ropes, come along clamps, tirfor, pull lifts should be tested once in a month.  The continuity of the cable connection between the top clamp and the earthling clamp should be checked once a fortnight.  Cable should be renewed if more than 20% strands are broken. During use, cable should be continually examined for fraying and breakage of strands. GENERAL SAFETY OHE
  • 17.  Neutral section should be treated as live equipment and earthed separately at two points on either side of the work party before commencing work.  When work is to be carried out on isolator , both sides of the isolator should be earthed at two points.  No fallen wires should be touched unless power has been switced off and the wires suitably earthed. GENERAL SAFETY OHE
  • 18.
  • 19.  The attention of all railway staff is drawn to the fact that under 25 kV ac 50 Hz single phase traction, there is heavy induction on all metallic structures and conductors in the vicinity of the track.  The induction is two-fold: a) Electro-static, which results from the high potential of 25 kV on the OHE system.