SlideShare a Scribd company logo
1 of 10
Download to read offline
ranilkumar@quanta-technology.com
21, rue d’Artois, F-75008 PARIS CIGRE US National Committee
http://www.cigre.org 2019 Grid of the Future Symposium
Reliability Impacts of Behind the Meter Distributed Energy Resources on
Transmission Operations
R. ANILKUMAR, A. DANESHPOOY, V. MARATHE
Quanta Technology LLC
USA
SUMMARY
The increasing amounts of customer-owned Distributed Energy Resources (DERs) limit the
control and visibility of local Independent System Operators (ISOs) and utility operators.
Most of these resources are non-curtailable and subject to several aggregation guidelines for
wholesale participation. These units cannot be decoupled from the Transmission-Distribution
(T-D) interface and have a direct impact on the economics and reliability of the grid. This
paper reports the results of a study that investigated realistic dispatch conditions from a
production and power flow co-simulation environment with increased behind-the-meter DER
resources. The objectives of this study include: 1) understanding steady-state and transient
voltage response of the system at the local T-D interface, 2) analyzing impacts on switching
operations, 3) studying the system-wide frequency response of the Western Interconnection,
and 4) examining scenarios that provide insight into the type of control strategies that best
benefit local ISO and utility operations from a reliability perspective.
KEYWORDS
Distributed energy resources, frequency response, production simulation, power flow
simulations, curtailments.
2
1. INTRODUCTION
The recent advancements in technology and policies have driven the growth of Distributed Energy
Resource (DER) into the grid. Several states, including California and New York, have established
Renewable Portfolio Standards (RPSs), which would require close to 50% of their energy procurement
to come directly from renewable resources by the year 2030. Over time, these targets have become
more aggressive, resulting in 100% by the year 2045 [1].
Several potential impacts have been identified by industry and academic researchers that demonstrate
the economic and operational impacts of these resources. The key challenges associated with DERs are
directly attributed to their operating characteristics. This is coupled with state and federal policies
driving the retirement of coal and nuclear plants [2]. The existing fleet of generation would likely need
to operate at lower minimum levels if not already uncommitted. For example, there is an increased
likelihood of over-generation resulting in reverse power flows at the Transmission-Distribution (T-D)
interface, resulting in protection equipment failures. The displacement of large-scale units can severely
impact the system-wide frequency response and NERC BAL-003 requirements [3]. The off-peak hours
(particularly, high ramping) can result in voltage issues that arise from the offset of generation and load
balance. Similarly, there can be scenarios of excessive shunt-capacitor and transformer-tap switching
necessary to maintain scheduled voltages at the T-D interfaces [4]. The focus of this paper is on the
operational reliability impacts of these resources directly associated with local and system-wide
reliability.
DERs are currently divided into three categories, customer-owned/Behind-the-Meter DER (BTM-
DER), Merchant DER, and microgrids. Among the three, most Independent System Operators (ISOs)
have control over their merchant DERs, which are typically larger units that can be curtailed as per the
ISO request. However, BTM units are not within the full visibility of ISO operations. Without visibility
to these resources, ISO’s cannot include them in the state RPS targets as firm procurements, even
though they can impact the transmission grid more indirectly through the T-D interface.
Currently, these BTM-DERs are modified as a load modifier. BTM and Net Energy Metering (NEM)
mask the generation within the available load schedule. However, for accurate modeling, it is
imperative to distinguish load from generation and establish differentiated load and generation data.
This level of accuracy should be included within the market assessment tools and the power-flow-based
tools. In order to capture their response in power-flow studies during fault and outage conditions, it is
essential to establish dynamic models as well.
While several studies have been performed highlighting the impacts of DER penetration into the grid
[4–11], no study has analyzed the operational visibility considerations as they impact market and
reliability aspects of the power system directly at the T-D interface. The thin line between controllable
and non-controllable resources can have several implications on system operations. The objective of
this study is to highlight some of the key aspects of DER penetration into the grid using the state of
California as an example. The study will account for the larger merchant DER (controllable) and
BTM-DER (non-controllable) to better capture all aspects of DER operations. A coupled market and
power-flow simulation has been used to study this in detail; however, the focus of this paper will
remain on the power-flow implications of the problem.
2. MODELING, ASSUMPTIONS AND STUDY METHODOLOGY
2.1. Scenario Description
To study reliability impacts at the T-D interface, two scenarios are considered. The non-participating
scenario, herein referred to as Scenario 1, represents current market operations where distribution-
connected renewables deliver only active power. These units are non-curtailable, do not provide
reactive power support or any form of frequency support, nor are they equipped with intelligent
protection or ride-through settings.
The participating scenario, herein referred to as Scenario 2, considers a model where BTM units can
contribute to reactive power support and frequency regulation within the rated capabilities. The model
further includes ride-through settings and additional protection configurations for these units. These
3
models also include latch/trip ranges for frequency and voltage response. Further, they represent a
future market model evolution to be considered, where the ISO has control over the distribution-
connected resources as well, either in the form of generation resources(energy) or ancillary services.
2.2. Modeling, Assumptions, and Study Methodology
Production simulations were performed using ABB’s GridView software tool. The 2024 Transmission
Expansion Planning Policy Committee (TEPPC) base cases were used, which included the most
current statewide RPS requirements within the Western Electricity Coordinating Council (WECC).
The objective was to mimic market operations and identify the worst-operating days and hours for the
local ISO. These days were evaluated in further detail using power-flow and dynamic-transient
simulations.
The DER penetration levels considered in this study are based on the published California Energy
Commission (CEC) forecasts for self-generation in the year 2024 [12]. Detailed models were built, and
the DER forecast was implemented at distribution and sub-transmission networks. Equivalent
impedances were calculated to represent the distribution network model within commercially available
transmission planning and market operational tools like GE Positive Sequence Load Flow (PSLF) [13]
and ABB GridView [14]. With the models that were built for Scenario 1 and Scenario 2 conditions,
studies were conducted at 100 and 200% CEC renewable penetration levels.
Within the production simulation, a detailed representation of the BTM-DER generation was modeled.
The representation is highlighted by Fig. 1 below. To enable market participation, they were modeled
as aggregations for each local utility within the state and assigned participation factors. A similar
model was built out in the power-flow cases as well.
• The BTM- DER was modeled at several buses ranging from 4.7 kV to 230 kV and includes
PV(residential) and non-PV (commercial generation) units. Based on the CEC forecast, the total
generation added was 4,000 MW, which includes 2,100 MW of PV and 1,900 MW of non-PV
generation for the 100% penetration scenario. For the 200% penetration scenario, the total
generation added was 8,000 MW, which includes 6,100 MW of PV and 1,900 MW of non-PV
generation. Under the assumption that load is being offset by a proportional increase in
self-generation, a total of 4,000 MW of load was added at the locations (similar to the additional
self-generation units added). For accuracy, loads and generations were modeled separately. The
same load was assumed for both 100 and 200% scenarios.
Fig. 1. BTM-Distributed Generation (DG) model for power flow and production simulation.
• PV and non-PV generation was interconnected at appropriate voltage levels through equivalent
impedances and the DG interconnection transformer. The equivalent impedances represent the
aggregate value of distribution and/or sub-transmission lines, as well as substation transformer
impedances, as obtained from the short-circuit capacity of the system.
4
• Generation and load dispatches from production simulation were imported into multiple power-
flow cases to analyze the 100 and 200% penetration levels. In this paper, spring off-peak conditions
for 11 AM and 8 PM are considered. Operationally, these were identified as the most critical hours
of the day.
• For dynamic simulations, “PVD1” model were used for the BTM generation. In Scenario 1, active
power control is a priority and no reactive power support capability is associated with these units;
in Scenario 2 simulations, the PF flag is set to 0, wherein reactive power control is a priority and
reactive power support is provided by these units. Further, Scenario 1 did not include low/high
voltage ride-through and frequency ride-through protection considerations. All loads were replaced
with the WECC composite load model.
• The CEC generation non-PV units represent typical synchronous machine for combined heat and
power (CHP) units. In the dynamic model the unit is represented by a GENROU model with an
Exciter (EXST1), governor (GGOV1) and power system stabilizer (PSS1D). All protection
considerations are applied to these units.
3. POWER FLOW STUDY
The local-area power flow study was conducted to analyze the impact of DER penetration on voltages.
The larger penetration of DER can result in overvoltages, larger transformer tap swings, lower
voltages during off-peak conditions with larger imbalance (generation vs load), while making the
system more sensitive to critical contingencies.
3.1. Steady State Assessment
The region-wide voltage study was used to assess the impact of contingencies on voltages at all buses
in the ISO region of 100 kV and above. The steady-state assessment was performed in adherence to
WECC and regional ISO planning standards [15]. PSLF simulation environment was used for this
study.
Results from the 100 and 200% penetration studies were analyzed for both Scenarios 1 and 2. Two
different hours of the day were considered (11 AM and 8 PM). Several comparisons were drawn
between these operating conditions that provide insight into the operation of the system:
1. Excessive capacitor-bank switching was observed in Scenario 1, without voltage control from
local DER. Further, there were a total of 125 tap-changing operations recorded while moving from
11 AM to 8 PM on the same day (2.48% of tap-up and 6.875% of tap-down operation).
2. In Scenario 1 under 200% CEC penetration, there were reduced tap-down operations between
11 AM to 8 PM of the operating day but an increased percentage of tap-up operations. Several
capacitor banks were at peak capacity by 8 PM in this operating scenario.
3. In Scenario 1, under 100 and 200% penetration, several undervoltages were observed in the
system, with the lowest being 0.92 pu. Additional support from compensation devices is critical to
prevent voltage from being significantly suppressed.
4. In Scenario 2, under 100 and 200% penetration, reduced undervoltages were observed in the
system. Between the two cases, the lowest voltage recorded was 0.94 p.u..
5. Post-contingency responses were observed between both scenarios, and no delta V deviations of
greater than 8% were recorded. Several high voltages were recorded throughout the system, with
the highest being 1.11 p.u. at the 115-kV network.
6. Interestingly in both scenarios, while moving from 11 AM to 8 PM, larger tap-down operations
were recorded in the 100% scenario than in the 200% scenario. The 200% scenario reported
reduced transformer tap-change operations overall.
7. Table 1 presents a high-level overview of the highest and lowest voltages recorded for both
scenarios at a sample substation in the PG&E operating area. The results at the T-D interface
demonstrate that larger deviations are observable under Scenario 1 and at 8 PM. The results
5
indicated that the 230-kV T-D interface interconnections are less impacted by voltage deviations
than the 115-kV network.
Table 1: Pre and post contingency voltage deviations at T-D interfaces
Pre- and Post-Voltage
Deviations @
San Ramon 230 kV
substation
200% - Scenario 1 200% - Scenario 2
11 AM 8 PM Δ V 11 AM 8 PM Δ V
Pre-
Cont.
Base
Case
1.021 1.012 0.01 1.015 1.012 0.003
Post-
Cont.
C2_8 1.008 0.989 0.019 0.993 0.993 0
Δ V 0.013 0.023 0.022 0.019
Post-
Cont.
C2-11 1.015 0.99 0.025 0.993 0.993 0
Δ V 0.006 0.022 0.022 0.019
Pre and Post Voltage
Deviations@ 115 kV
substation
100% - Scenario 1 100% - Scenario 2
11 AM 8 PM Δ V 11 AM 8 PM Δ V
Pre-
Cont.
Base
Case
1.053 1.033 0.01 1.04 1.029 0.011
Post-
Cont.
SL-
10117
1.038 1.018 0.02 1.026 1.024 0.002
Δ V 0.015 0.015 0.014 0.005
Post-
Cont.
SL-
10235
1.041 1.021 0.02 1.028 1.027 0.001
Δ V 0.012 0.012 0.012 0.002
4. TRANSIENT DYNAMIC SIMULATIONS
To perform dynamic simulations, a three-phase-to-ground bolted fault was applied at the remote bus,
followed by an immediate line loss connecting the remote bus to the T-D interface. The logic behind
using a remote bus was to examine the behavior of PV units in scenarios where their tripping is not
always certain. Further, if a three-phase fault was applied at the T-D interface directly, there is
certainty that the PV unit will trip, not providing much ground to explore the exact transient response
from these units. The fault was applied at 0.1 seconds in all simulations and cleared in 6 cycles.
Composite load models were evaluated in detail.
In order to evaluate the transient voltage response at the T-D interface, two substations are presented
below. For, the San Ramon 230-kV T-D interface, a fault was applied at Moraga 230-kV bus, and the
line was cleared after 6 cycles. An average reduction of 2-MW output was observed at all loads in the
composite load model for the 11 AM case, and a reduction of 1-MW output observed at all loads in the
composite load model for the 8 PM case for Scenario 1 with 200% injection. It was observed that the
bus voltage settles down at the nominal value after the fault is cleared and no PV-unit trip was
recorded. The behavior of the composite load for 200% penetration at San Ramon is presented in
Fig. 2.
The voltage overshoot post-fault clearing was more pronounced at 11 AM than 8 PM in both
scenarios. Interaction from neighboring PV units in the system also contribute to the post-fault
clearing voltage overshoot. This is presented in Fig. 3.
Table 2 summarizes the results obtained from the studies in Scenario 1. It includes the MW generation
tripped from the PV unit and the cause for tripping. “N/A” indicates scenarios where no PV-unit trip
was recorded.
6
Fig. 2. Composite load model at San Ramon T-D interface - 200%, Scenario 1.
Fig. 3. Voltages at T-D interface, 11 AM and 8 PM.
Table 2: Select T-D interfaces and cause for PV trip in Scenarios 1 & 2
Bus
Name
Scenario
Scenario 1 Scenario 2
Generation
tripped (MW)
Load Tripped
(MW)
Generation
tripped (MW)
Load Tripped
(MW)
San
Ramon
200% -
11AM
40 8 N/A 4
Huron
200% -
11AM
20 (Frequency) 2 N/A 2
San
Ramon
100% -
11AM
N/A 13 N/A 8
Huron
100% -
11AM
35 7 10 5
In Scenario 2, the CEC generator models were equipped with reactive power capability. Low/High
voltage/frequency ride through configurations were implemented based on distribution consensus
standards. In this scenario, the number of PV units tripped was less than for Scenario 1. This can be
observed in Table 2.
The following observations can be made from the system-wide voltage study and local T-D interface
study.
• It was observed from dynamic simulations that the composite load models recorded a maximum of
10-MW reduction post-fault clearing.
• PV DG tripping recorded due to frequency and voltage swings are more significant in the sub-
transmission network.
• In Scenario 2, voltages at the T-D interface buses are supported by reactive power contribution
from PV and non-PV units. Since no low-voltage/high-voltage scenarios were encountered at the
interface bus in the base case, most of the Q variations in these units were observed in response to
fault conditions.
7
The plots in Fig. 4 demonstrate the dependence of frequency on the MW output of the power-flow
model under Scenario 2. Faults near and downstream from the 115kV network reduce the plant output
significantly until the frequency recovers. Under Scenario 1, the tripping of several PV units was
observed throughout the region. Most of the trips were in response to frequency swings measured at
the bus.
Fig. 4. PV plant output and frequency at T-D interface bus (Huron)
5. SYSTEM WIDE FREQUENCY RESPONSE STUDY
Frequency response has recently gained a lot of attention across the Western Interconnection. The
purpose of this study is to investigate the frequency performance of the California region in response to
events of sudden generation loss , particularly those targeted by NERC standard BAL–003 under near-
future conditions with high levels of renewable generation. This study addresses the overall frequency
response of the Western Grid, with special attention to the response within the local California region.
Some of the major system impacts resulting from increased renewable generation include lower system
inertia and displacement of primary frequency control reserves [16].
The objective was to capture the frequency response of the entire WECC system and California
Independent System Operator (CAISO) region for the Palo Verde double outage; simulation was
performed for 60 seconds. The original production simulation results were used to create the seed case
– herein referred to as Case 1.
A more conservative scenario was developed from Case 1 using reduced headroom in the WECC and
CAISO regions – herein referred to as Case 2. The frequency performance metrics for the two cases
are tabulated in Table 3. The frequency at the Round Mountain 500-kV facility is shown in Figs. 5 and
6 for Case 1 and Case 2, respectively, under Scenario 1. For Scenario 2, with the cases in the study
having the same headroom as shown in Table 4, it was observed that the results obtained are
comparable to the results obtained in Scenario 1 and were not reproduced.
From the performance metrics, it was observed that the frequency performance within WECC for
Scenario 1 and Scenario 2 was acceptable. WECC system response slightly reduced in Scenario 2.
However, for the CAISO the response improved. This is due the marginal differences between
dispatches in Scenario 1 and Scenario 2. This response could also be attributed to a large PV unit’s
frequency self-resettling capability and wider frequency range for Scenario 2.
8
Table 3: Frequency performance metrics
Case 1
Scenario 1 Scenario 2
WECC CA WECC CA
Frequency Nadir (Hz) 59.685 59.68 59.691 59.691
Frequency Nadir time (seconds) 6.94 6.79 6.88 6.8
Settling Frequency (Hz) 59.83 59.83 59.836 59.836
Frequency Response (MW/0.1Hz) 2236 269 2210 278
Case 2
Scenario 1 Scenario 2
WECC CA WECC CA
Frequency Nadir (Hz) 59.54 59.54 59.56 59.55
Frequency Nadir time (seconds) 9.22 9.12 9.18 9.1
Settling Frequency (Hz) 59.751 59.751 59.758 59.758
Frequency Response (MW/0.1Hz) 1324 168 1320 170.9
Fig. 5. Frequency at Round Mountain 500 kV facility for Case 1 Scenario 1
Fig. 6. Frequency at Round Mountain 500 kV facility for Case 2 Scenario 1
9
Table 4: Headroom in study cases
Case
Headroom (GW)
WECC CAISO
Case 1 ~ 19 ~ 3.95
Case 2 ~13.7 ~2.3
6. CONCLUSIONS
This paper evaluated the impact of uncontrolled BTM resources on the T-D interface. A coupled
production/power flow simulation environment was used to capture all aspects of the problem. The
study did not identify any serious concerns at the T-D interface. The reliability of the system can be
successfully ensured with good system planning and power system engineering practices. At a
minimum, local voltage and thermal problems were identified that will require capacity expansion to
accommodate the increased penetration. Scenarios with active participation from BTM resources
demonstrated considerable improvement in system reliability. The system frequency response was
observed to deteriorate without active DER controls allocated to all participating BTM units.
Distribution is not decoupled from transmission and will continue to impact bulk power system
operations, largely from a system-wide frequency-response perspective. From a steady-state and
transient voltage perspective, the issues were largely localized in nature, with the strength of the grid
at the point of interconnection and switching action of compensating devices influencing voltage
response.
10
BIBLIOGRAPHY
[1] Jocelyn Durkay, “State Renewable Portfolio Standards and Goals,” National Conference of
State Legislatures, Jan. 2019, [online] http://www.ncsl.org/research/energy/renewable-portfolio-
standards.aspx.
[2] R. Anderson, S. Gerber, and E. Reid (Feb. 2014). “Distributed Energy Resources Integration,
Summarizing the Challenges and Barriers,” Olivine, Inc., San Ramon, CA.
[3] Standard BAL-003, “Frequency Response and Frequency Bias Setting,” NERC, Nov. 2012.
[4] N. Miller, M. Shao, and S. Venkataraman, “California ISO (CAISO) Frequency Response
Study,” Nov. 2011.
[5] N. Miller, M. Shao, S. Pajic, and R. D'Aquila, “Eastern Frequency Response Study,”
NREL/SR-5500-58077 Subcontractor Report, May 2013.
[6] N. Miller, M. Shao, S. Pajic, and R. D'Aquila, “Western Wind and Solar Integration Study
Phase 3 – Frequency Response and Transient Stability,” NREL/SR-5D00-62906
Subcontractor Report, Dec. 2014.
[7] N. Miller, C. Loutan, M. Shao, and K. Clark, “Emergency Response: U.S. System Frequency
with High Wind Penetration,” IEEE/PES Power and Energy Magazine, vol. 11, no. 6, pp. 63-71,
Nov. 2013.
[8] GE Energy, “Western Wind and Solar Integration Study,” NREL Report No. SR-550-47434,
May 2010.
[9] D. Lew, et al., “The Western Wind and Solar Integration Study Phase 2,” NREL/TP-5500-
55888, Sep. 2013.
[10] GE Energy Consulting, “Stage 2 Oahu – Maui Interconnection Study,” Hawaii Electric
Company, May 2013.
[11] GE Energy Consulting, “Oahu Distributed PV Grid Stability Study. Part 1: System Frequency
Response to Generator Contingency Events,” Hawaii Electric Company, Mar. 2016.
[12] C. Kavalec, “2014-2024 Final Forecast Volume 1: Statewide Electricity,” CEC Report No.
CEC-200-2013-004-V1-CMF, Jan. 2014.
[13] GE Positive Sequence Load Flow (PSLF) [online] http://www.geenergyconsulting.com/practice-
area/software-products/pslf.
[14] GridView [online] http://new.abb.com/enterprise-software/energy-portfolio-
management/market-analysis/gridview.
[15] WECC Regional Planning Standards [online]
https://www.wecc.biz/Standards/Pages/Default.aspx.
[16] S. Sharma, S. Huang, and N.D.R. Sarma, “System Inertial Frequency Response Estimation
and Impact of Renewable Resources in ERCOT Interconnection,” in Proc. IEEE Power and
Energy Society General Meeting, San Diego, CA, Jul. 2011.

More Related Content

What's hot

Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...PromiseBeshel
 
Power distribution planning_reference_book__second_edition__power_engineering...
Power distribution planning_reference_book__second_edition__power_engineering...Power distribution planning_reference_book__second_edition__power_engineering...
Power distribution planning_reference_book__second_edition__power_engineering...sushrut p
 
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural ElectrificationIRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural ElectrificationIRJET Journal
 
A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...eSAT Journals
 
Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant IJECEIAES
 
Indian wind energy status
Indian wind energy statusIndian wind energy status
Indian wind energy statusbazgha khan
 
Introducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR modelIntroducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR modelIJECEIAES
 
Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...davidtrebolle
 
The need for enhanced power system modelling techniques and simulation tools
The need for enhanced power system modelling techniques and simulation toolsThe need for enhanced power system modelling techniques and simulation tools
The need for enhanced power system modelling techniques and simulation toolsPower System Operation
 
ACTIVE DISTRIBUTION SYSTEM MANAGEMENT
ACTIVE DISTRIBUTION SYSTEM MANAGEMENTACTIVE DISTRIBUTION SYSTEM MANAGEMENT
ACTIVE DISTRIBUTION SYSTEM MANAGEMENTdavidtrebolle
 
A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...
A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...
A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...IJERD Editor
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Sifan Welisa
 
Power System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemPower System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemIJECEIAES
 
Martinot_Kristov_Erickson_2015
Martinot_Kristov_Erickson_2015Martinot_Kristov_Erickson_2015
Martinot_Kristov_Erickson_2015Dave Erickson
 
Loss Reduction by Optimal Placement of Distributed Generation on a Radial feeder
Loss Reduction by Optimal Placement of Distributed Generation on a Radial feederLoss Reduction by Optimal Placement of Distributed Generation on a Radial feeder
Loss Reduction by Optimal Placement of Distributed Generation on a Radial feederIDES Editor
 
A Review on Optimization Techniques for Power Quality Improvement using DSTAT...
A Review on Optimization Techniques for Power Quality Improvement using DSTAT...A Review on Optimization Techniques for Power Quality Improvement using DSTAT...
A Review on Optimization Techniques for Power Quality Improvement using DSTAT...ijtsrd
 
Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...IJECEIAES
 

What's hot (20)

Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...
 
Power distribution planning_reference_book__second_edition__power_engineering...
Power distribution planning_reference_book__second_edition__power_engineering...Power distribution planning_reference_book__second_edition__power_engineering...
Power distribution planning_reference_book__second_edition__power_engineering...
 
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural ElectrificationIRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
 
A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...
 
ijess_paper7
ijess_paper7ijess_paper7
ijess_paper7
 
Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant
 
Indian wind energy status
Indian wind energy statusIndian wind energy status
Indian wind energy status
 
Introducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR modelIntroducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR model
 
Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...
 
The need for enhanced power system modelling techniques and simulation tools
The need for enhanced power system modelling techniques and simulation toolsThe need for enhanced power system modelling techniques and simulation tools
The need for enhanced power system modelling techniques and simulation tools
 
ACTIVE DISTRIBUTION SYSTEM MANAGEMENT
ACTIVE DISTRIBUTION SYSTEM MANAGEMENTACTIVE DISTRIBUTION SYSTEM MANAGEMENT
ACTIVE DISTRIBUTION SYSTEM MANAGEMENT
 
A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...
A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...
A NOVEL CONTROL STRATEGY FOR POWER QUALITY IMPROVEMENT USING ANN TECHNIQUE FO...
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
 
Power System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemPower System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power System
 
Martinot_Kristov_Erickson_2015
Martinot_Kristov_Erickson_2015Martinot_Kristov_Erickson_2015
Martinot_Kristov_Erickson_2015
 
Reliability Assesment of Debremarkos Distribution System Found In Ethiopia
Reliability Assesment of Debremarkos Distribution System Found In EthiopiaReliability Assesment of Debremarkos Distribution System Found In Ethiopia
Reliability Assesment of Debremarkos Distribution System Found In Ethiopia
 
Loss Reduction by Optimal Placement of Distributed Generation on a Radial feeder
Loss Reduction by Optimal Placement of Distributed Generation on a Radial feederLoss Reduction by Optimal Placement of Distributed Generation on a Radial feeder
Loss Reduction by Optimal Placement of Distributed Generation on a Radial feeder
 
A Review on Optimization Techniques for Power Quality Improvement using DSTAT...
A Review on Optimization Techniques for Power Quality Improvement using DSTAT...A Review on Optimization Techniques for Power Quality Improvement using DSTAT...
A Review on Optimization Techniques for Power Quality Improvement using DSTAT...
 
Main paper
Main paperMain paper
Main paper
 
Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...
 

Similar to Reliability Impacts of Behind the Meter Distributed Energy Resources on Transmission Operations

Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Power System Operation
 
Study of distributed energy resources
Study of distributed energy resourcesStudy of distributed energy resources
Study of distributed energy resourcesvivatechijri
 
Impact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency controlImpact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency controlIRJET Journal
 
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...IRJET Journal
 
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEMLATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEMijiert bestjournal
 
Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...
Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...
Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...inventy
 
Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...
Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...
Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...IRJET Journal
 
Automatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAutomatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAlexander Decker
 
Congestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesCongestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesIRJET Journal
 
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...Power System Operation
 
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...Power System Operation
 
Optimal dg placement using multiobjective index and its effect on stability 2
Optimal dg placement using multiobjective index and its effect on stability 2Optimal dg placement using multiobjective index and its effect on stability 2
Optimal dg placement using multiobjective index and its effect on stability 2IAEME Publication
 
IRJET-Identification of Weak Bus using Load Variation
IRJET-Identification of Weak Bus using Load VariationIRJET-Identification of Weak Bus using Load Variation
IRJET-Identification of Weak Bus using Load VariationIRJET Journal
 
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
IRJET-  	  Optimization of Renewable Energy Sources for DC MicrogridIRJET-  	  Optimization of Renewable Energy Sources for DC Microgrid
IRJET- Optimization of Renewable Energy Sources for DC MicrogridIRJET Journal
 
Stochastic control for optimal power flow in islanded microgrid
Stochastic control for optimal power flow in islanded microgridStochastic control for optimal power flow in islanded microgrid
Stochastic control for optimal power flow in islanded microgridIJECEIAES
 
System Operational Challenges from the Energy Transition
System Operational Challenges from the Energy TransitionSystem Operational Challenges from the Energy Transition
System Operational Challenges from the Energy TransitionPower System Operation
 
IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...
IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...
IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...IRJET Journal
 
IRJET- A Review on Hybrid AC/DC Microgrid System and its Coordination Con...
IRJET-  	  A Review on Hybrid AC/DC Microgrid System and its Coordination Con...IRJET-  	  A Review on Hybrid AC/DC Microgrid System and its Coordination Con...
IRJET- A Review on Hybrid AC/DC Microgrid System and its Coordination Con...IRJET Journal
 

Similar to Reliability Impacts of Behind the Meter Distributed Energy Resources on Transmission Operations (20)

Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
 
Study of distributed energy resources
Study of distributed energy resourcesStudy of distributed energy resources
Study of distributed energy resources
 
Impact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency controlImpact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency control
 
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
 
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEMLATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
 
Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...
Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...
Optimal Siting And Sizing Of Distributed Generation For Radial Distribution S...
 
Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...
Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...
Power-Sharing of Parallel Inverters in Micro-Grids via Droop control and Virt...
 
Automatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAutomatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systems
 
Congestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesCongestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS Devices
 
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
 
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
Modeling Approaches and Studies of the Impact of Distributed Energy Resources...
 
Optimal dg placement using multiobjective index and its effect on stability 2
Optimal dg placement using multiobjective index and its effect on stability 2Optimal dg placement using multiobjective index and its effect on stability 2
Optimal dg placement using multiobjective index and its effect on stability 2
 
IRJET-Identification of Weak Bus using Load Variation
IRJET-Identification of Weak Bus using Load VariationIRJET-Identification of Weak Bus using Load Variation
IRJET-Identification of Weak Bus using Load Variation
 
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
IRJET-  	  Optimization of Renewable Energy Sources for DC MicrogridIRJET-  	  Optimization of Renewable Energy Sources for DC Microgrid
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
 
Stochastic control for optimal power flow in islanded microgrid
Stochastic control for optimal power flow in islanded microgridStochastic control for optimal power flow in islanded microgrid
Stochastic control for optimal power flow in islanded microgrid
 
System Operational Challenges from the Energy Transition
System Operational Challenges from the Energy TransitionSystem Operational Challenges from the Energy Transition
System Operational Challenges from the Energy Transition
 
Sysc 5302 101079892
Sysc 5302 101079892Sysc 5302 101079892
Sysc 5302 101079892
 
IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...
IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...
IRJET- Automatic Demand Response Controller with Load Shifting Algorithm usin...
 
IRJET- A Review on Hybrid AC/DC Microgrid System and its Coordination Con...
IRJET-  	  A Review on Hybrid AC/DC Microgrid System and its Coordination Con...IRJET-  	  A Review on Hybrid AC/DC Microgrid System and its Coordination Con...
IRJET- A Review on Hybrid AC/DC Microgrid System and its Coordination Con...
 
N020698101
N020698101N020698101
N020698101
 

More from Power System Operation

Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panelsPower System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsPower System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemePower System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePower System Operation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & PartsPower System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 

Reliability Impacts of Behind the Meter Distributed Energy Resources on Transmission Operations

  • 1. ranilkumar@quanta-technology.com 21, rue d’Artois, F-75008 PARIS CIGRE US National Committee http://www.cigre.org 2019 Grid of the Future Symposium Reliability Impacts of Behind the Meter Distributed Energy Resources on Transmission Operations R. ANILKUMAR, A. DANESHPOOY, V. MARATHE Quanta Technology LLC USA SUMMARY The increasing amounts of customer-owned Distributed Energy Resources (DERs) limit the control and visibility of local Independent System Operators (ISOs) and utility operators. Most of these resources are non-curtailable and subject to several aggregation guidelines for wholesale participation. These units cannot be decoupled from the Transmission-Distribution (T-D) interface and have a direct impact on the economics and reliability of the grid. This paper reports the results of a study that investigated realistic dispatch conditions from a production and power flow co-simulation environment with increased behind-the-meter DER resources. The objectives of this study include: 1) understanding steady-state and transient voltage response of the system at the local T-D interface, 2) analyzing impacts on switching operations, 3) studying the system-wide frequency response of the Western Interconnection, and 4) examining scenarios that provide insight into the type of control strategies that best benefit local ISO and utility operations from a reliability perspective. KEYWORDS Distributed energy resources, frequency response, production simulation, power flow simulations, curtailments.
  • 2. 2 1. INTRODUCTION The recent advancements in technology and policies have driven the growth of Distributed Energy Resource (DER) into the grid. Several states, including California and New York, have established Renewable Portfolio Standards (RPSs), which would require close to 50% of their energy procurement to come directly from renewable resources by the year 2030. Over time, these targets have become more aggressive, resulting in 100% by the year 2045 [1]. Several potential impacts have been identified by industry and academic researchers that demonstrate the economic and operational impacts of these resources. The key challenges associated with DERs are directly attributed to their operating characteristics. This is coupled with state and federal policies driving the retirement of coal and nuclear plants [2]. The existing fleet of generation would likely need to operate at lower minimum levels if not already uncommitted. For example, there is an increased likelihood of over-generation resulting in reverse power flows at the Transmission-Distribution (T-D) interface, resulting in protection equipment failures. The displacement of large-scale units can severely impact the system-wide frequency response and NERC BAL-003 requirements [3]. The off-peak hours (particularly, high ramping) can result in voltage issues that arise from the offset of generation and load balance. Similarly, there can be scenarios of excessive shunt-capacitor and transformer-tap switching necessary to maintain scheduled voltages at the T-D interfaces [4]. The focus of this paper is on the operational reliability impacts of these resources directly associated with local and system-wide reliability. DERs are currently divided into three categories, customer-owned/Behind-the-Meter DER (BTM- DER), Merchant DER, and microgrids. Among the three, most Independent System Operators (ISOs) have control over their merchant DERs, which are typically larger units that can be curtailed as per the ISO request. However, BTM units are not within the full visibility of ISO operations. Without visibility to these resources, ISO’s cannot include them in the state RPS targets as firm procurements, even though they can impact the transmission grid more indirectly through the T-D interface. Currently, these BTM-DERs are modified as a load modifier. BTM and Net Energy Metering (NEM) mask the generation within the available load schedule. However, for accurate modeling, it is imperative to distinguish load from generation and establish differentiated load and generation data. This level of accuracy should be included within the market assessment tools and the power-flow-based tools. In order to capture their response in power-flow studies during fault and outage conditions, it is essential to establish dynamic models as well. While several studies have been performed highlighting the impacts of DER penetration into the grid [4–11], no study has analyzed the operational visibility considerations as they impact market and reliability aspects of the power system directly at the T-D interface. The thin line between controllable and non-controllable resources can have several implications on system operations. The objective of this study is to highlight some of the key aspects of DER penetration into the grid using the state of California as an example. The study will account for the larger merchant DER (controllable) and BTM-DER (non-controllable) to better capture all aspects of DER operations. A coupled market and power-flow simulation has been used to study this in detail; however, the focus of this paper will remain on the power-flow implications of the problem. 2. MODELING, ASSUMPTIONS AND STUDY METHODOLOGY 2.1. Scenario Description To study reliability impacts at the T-D interface, two scenarios are considered. The non-participating scenario, herein referred to as Scenario 1, represents current market operations where distribution- connected renewables deliver only active power. These units are non-curtailable, do not provide reactive power support or any form of frequency support, nor are they equipped with intelligent protection or ride-through settings. The participating scenario, herein referred to as Scenario 2, considers a model where BTM units can contribute to reactive power support and frequency regulation within the rated capabilities. The model further includes ride-through settings and additional protection configurations for these units. These
  • 3. 3 models also include latch/trip ranges for frequency and voltage response. Further, they represent a future market model evolution to be considered, where the ISO has control over the distribution- connected resources as well, either in the form of generation resources(energy) or ancillary services. 2.2. Modeling, Assumptions, and Study Methodology Production simulations were performed using ABB’s GridView software tool. The 2024 Transmission Expansion Planning Policy Committee (TEPPC) base cases were used, which included the most current statewide RPS requirements within the Western Electricity Coordinating Council (WECC). The objective was to mimic market operations and identify the worst-operating days and hours for the local ISO. These days were evaluated in further detail using power-flow and dynamic-transient simulations. The DER penetration levels considered in this study are based on the published California Energy Commission (CEC) forecasts for self-generation in the year 2024 [12]. Detailed models were built, and the DER forecast was implemented at distribution and sub-transmission networks. Equivalent impedances were calculated to represent the distribution network model within commercially available transmission planning and market operational tools like GE Positive Sequence Load Flow (PSLF) [13] and ABB GridView [14]. With the models that were built for Scenario 1 and Scenario 2 conditions, studies were conducted at 100 and 200% CEC renewable penetration levels. Within the production simulation, a detailed representation of the BTM-DER generation was modeled. The representation is highlighted by Fig. 1 below. To enable market participation, they were modeled as aggregations for each local utility within the state and assigned participation factors. A similar model was built out in the power-flow cases as well. • The BTM- DER was modeled at several buses ranging from 4.7 kV to 230 kV and includes PV(residential) and non-PV (commercial generation) units. Based on the CEC forecast, the total generation added was 4,000 MW, which includes 2,100 MW of PV and 1,900 MW of non-PV generation for the 100% penetration scenario. For the 200% penetration scenario, the total generation added was 8,000 MW, which includes 6,100 MW of PV and 1,900 MW of non-PV generation. Under the assumption that load is being offset by a proportional increase in self-generation, a total of 4,000 MW of load was added at the locations (similar to the additional self-generation units added). For accuracy, loads and generations were modeled separately. The same load was assumed for both 100 and 200% scenarios. Fig. 1. BTM-Distributed Generation (DG) model for power flow and production simulation. • PV and non-PV generation was interconnected at appropriate voltage levels through equivalent impedances and the DG interconnection transformer. The equivalent impedances represent the aggregate value of distribution and/or sub-transmission lines, as well as substation transformer impedances, as obtained from the short-circuit capacity of the system.
  • 4. 4 • Generation and load dispatches from production simulation were imported into multiple power- flow cases to analyze the 100 and 200% penetration levels. In this paper, spring off-peak conditions for 11 AM and 8 PM are considered. Operationally, these were identified as the most critical hours of the day. • For dynamic simulations, “PVD1” model were used for the BTM generation. In Scenario 1, active power control is a priority and no reactive power support capability is associated with these units; in Scenario 2 simulations, the PF flag is set to 0, wherein reactive power control is a priority and reactive power support is provided by these units. Further, Scenario 1 did not include low/high voltage ride-through and frequency ride-through protection considerations. All loads were replaced with the WECC composite load model. • The CEC generation non-PV units represent typical synchronous machine for combined heat and power (CHP) units. In the dynamic model the unit is represented by a GENROU model with an Exciter (EXST1), governor (GGOV1) and power system stabilizer (PSS1D). All protection considerations are applied to these units. 3. POWER FLOW STUDY The local-area power flow study was conducted to analyze the impact of DER penetration on voltages. The larger penetration of DER can result in overvoltages, larger transformer tap swings, lower voltages during off-peak conditions with larger imbalance (generation vs load), while making the system more sensitive to critical contingencies. 3.1. Steady State Assessment The region-wide voltage study was used to assess the impact of contingencies on voltages at all buses in the ISO region of 100 kV and above. The steady-state assessment was performed in adherence to WECC and regional ISO planning standards [15]. PSLF simulation environment was used for this study. Results from the 100 and 200% penetration studies were analyzed for both Scenarios 1 and 2. Two different hours of the day were considered (11 AM and 8 PM). Several comparisons were drawn between these operating conditions that provide insight into the operation of the system: 1. Excessive capacitor-bank switching was observed in Scenario 1, without voltage control from local DER. Further, there were a total of 125 tap-changing operations recorded while moving from 11 AM to 8 PM on the same day (2.48% of tap-up and 6.875% of tap-down operation). 2. In Scenario 1 under 200% CEC penetration, there were reduced tap-down operations between 11 AM to 8 PM of the operating day but an increased percentage of tap-up operations. Several capacitor banks were at peak capacity by 8 PM in this operating scenario. 3. In Scenario 1, under 100 and 200% penetration, several undervoltages were observed in the system, with the lowest being 0.92 pu. Additional support from compensation devices is critical to prevent voltage from being significantly suppressed. 4. In Scenario 2, under 100 and 200% penetration, reduced undervoltages were observed in the system. Between the two cases, the lowest voltage recorded was 0.94 p.u.. 5. Post-contingency responses were observed between both scenarios, and no delta V deviations of greater than 8% were recorded. Several high voltages were recorded throughout the system, with the highest being 1.11 p.u. at the 115-kV network. 6. Interestingly in both scenarios, while moving from 11 AM to 8 PM, larger tap-down operations were recorded in the 100% scenario than in the 200% scenario. The 200% scenario reported reduced transformer tap-change operations overall. 7. Table 1 presents a high-level overview of the highest and lowest voltages recorded for both scenarios at a sample substation in the PG&E operating area. The results at the T-D interface demonstrate that larger deviations are observable under Scenario 1 and at 8 PM. The results
  • 5. 5 indicated that the 230-kV T-D interface interconnections are less impacted by voltage deviations than the 115-kV network. Table 1: Pre and post contingency voltage deviations at T-D interfaces Pre- and Post-Voltage Deviations @ San Ramon 230 kV substation 200% - Scenario 1 200% - Scenario 2 11 AM 8 PM Δ V 11 AM 8 PM Δ V Pre- Cont. Base Case 1.021 1.012 0.01 1.015 1.012 0.003 Post- Cont. C2_8 1.008 0.989 0.019 0.993 0.993 0 Δ V 0.013 0.023 0.022 0.019 Post- Cont. C2-11 1.015 0.99 0.025 0.993 0.993 0 Δ V 0.006 0.022 0.022 0.019 Pre and Post Voltage Deviations@ 115 kV substation 100% - Scenario 1 100% - Scenario 2 11 AM 8 PM Δ V 11 AM 8 PM Δ V Pre- Cont. Base Case 1.053 1.033 0.01 1.04 1.029 0.011 Post- Cont. SL- 10117 1.038 1.018 0.02 1.026 1.024 0.002 Δ V 0.015 0.015 0.014 0.005 Post- Cont. SL- 10235 1.041 1.021 0.02 1.028 1.027 0.001 Δ V 0.012 0.012 0.012 0.002 4. TRANSIENT DYNAMIC SIMULATIONS To perform dynamic simulations, a three-phase-to-ground bolted fault was applied at the remote bus, followed by an immediate line loss connecting the remote bus to the T-D interface. The logic behind using a remote bus was to examine the behavior of PV units in scenarios where their tripping is not always certain. Further, if a three-phase fault was applied at the T-D interface directly, there is certainty that the PV unit will trip, not providing much ground to explore the exact transient response from these units. The fault was applied at 0.1 seconds in all simulations and cleared in 6 cycles. Composite load models were evaluated in detail. In order to evaluate the transient voltage response at the T-D interface, two substations are presented below. For, the San Ramon 230-kV T-D interface, a fault was applied at Moraga 230-kV bus, and the line was cleared after 6 cycles. An average reduction of 2-MW output was observed at all loads in the composite load model for the 11 AM case, and a reduction of 1-MW output observed at all loads in the composite load model for the 8 PM case for Scenario 1 with 200% injection. It was observed that the bus voltage settles down at the nominal value after the fault is cleared and no PV-unit trip was recorded. The behavior of the composite load for 200% penetration at San Ramon is presented in Fig. 2. The voltage overshoot post-fault clearing was more pronounced at 11 AM than 8 PM in both scenarios. Interaction from neighboring PV units in the system also contribute to the post-fault clearing voltage overshoot. This is presented in Fig. 3. Table 2 summarizes the results obtained from the studies in Scenario 1. It includes the MW generation tripped from the PV unit and the cause for tripping. “N/A” indicates scenarios where no PV-unit trip was recorded.
  • 6. 6 Fig. 2. Composite load model at San Ramon T-D interface - 200%, Scenario 1. Fig. 3. Voltages at T-D interface, 11 AM and 8 PM. Table 2: Select T-D interfaces and cause for PV trip in Scenarios 1 & 2 Bus Name Scenario Scenario 1 Scenario 2 Generation tripped (MW) Load Tripped (MW) Generation tripped (MW) Load Tripped (MW) San Ramon 200% - 11AM 40 8 N/A 4 Huron 200% - 11AM 20 (Frequency) 2 N/A 2 San Ramon 100% - 11AM N/A 13 N/A 8 Huron 100% - 11AM 35 7 10 5 In Scenario 2, the CEC generator models were equipped with reactive power capability. Low/High voltage/frequency ride through configurations were implemented based on distribution consensus standards. In this scenario, the number of PV units tripped was less than for Scenario 1. This can be observed in Table 2. The following observations can be made from the system-wide voltage study and local T-D interface study. • It was observed from dynamic simulations that the composite load models recorded a maximum of 10-MW reduction post-fault clearing. • PV DG tripping recorded due to frequency and voltage swings are more significant in the sub- transmission network. • In Scenario 2, voltages at the T-D interface buses are supported by reactive power contribution from PV and non-PV units. Since no low-voltage/high-voltage scenarios were encountered at the interface bus in the base case, most of the Q variations in these units were observed in response to fault conditions.
  • 7. 7 The plots in Fig. 4 demonstrate the dependence of frequency on the MW output of the power-flow model under Scenario 2. Faults near and downstream from the 115kV network reduce the plant output significantly until the frequency recovers. Under Scenario 1, the tripping of several PV units was observed throughout the region. Most of the trips were in response to frequency swings measured at the bus. Fig. 4. PV plant output and frequency at T-D interface bus (Huron) 5. SYSTEM WIDE FREQUENCY RESPONSE STUDY Frequency response has recently gained a lot of attention across the Western Interconnection. The purpose of this study is to investigate the frequency performance of the California region in response to events of sudden generation loss , particularly those targeted by NERC standard BAL–003 under near- future conditions with high levels of renewable generation. This study addresses the overall frequency response of the Western Grid, with special attention to the response within the local California region. Some of the major system impacts resulting from increased renewable generation include lower system inertia and displacement of primary frequency control reserves [16]. The objective was to capture the frequency response of the entire WECC system and California Independent System Operator (CAISO) region for the Palo Verde double outage; simulation was performed for 60 seconds. The original production simulation results were used to create the seed case – herein referred to as Case 1. A more conservative scenario was developed from Case 1 using reduced headroom in the WECC and CAISO regions – herein referred to as Case 2. The frequency performance metrics for the two cases are tabulated in Table 3. The frequency at the Round Mountain 500-kV facility is shown in Figs. 5 and 6 for Case 1 and Case 2, respectively, under Scenario 1. For Scenario 2, with the cases in the study having the same headroom as shown in Table 4, it was observed that the results obtained are comparable to the results obtained in Scenario 1 and were not reproduced. From the performance metrics, it was observed that the frequency performance within WECC for Scenario 1 and Scenario 2 was acceptable. WECC system response slightly reduced in Scenario 2. However, for the CAISO the response improved. This is due the marginal differences between dispatches in Scenario 1 and Scenario 2. This response could also be attributed to a large PV unit’s frequency self-resettling capability and wider frequency range for Scenario 2.
  • 8. 8 Table 3: Frequency performance metrics Case 1 Scenario 1 Scenario 2 WECC CA WECC CA Frequency Nadir (Hz) 59.685 59.68 59.691 59.691 Frequency Nadir time (seconds) 6.94 6.79 6.88 6.8 Settling Frequency (Hz) 59.83 59.83 59.836 59.836 Frequency Response (MW/0.1Hz) 2236 269 2210 278 Case 2 Scenario 1 Scenario 2 WECC CA WECC CA Frequency Nadir (Hz) 59.54 59.54 59.56 59.55 Frequency Nadir time (seconds) 9.22 9.12 9.18 9.1 Settling Frequency (Hz) 59.751 59.751 59.758 59.758 Frequency Response (MW/0.1Hz) 1324 168 1320 170.9 Fig. 5. Frequency at Round Mountain 500 kV facility for Case 1 Scenario 1 Fig. 6. Frequency at Round Mountain 500 kV facility for Case 2 Scenario 1
  • 9. 9 Table 4: Headroom in study cases Case Headroom (GW) WECC CAISO Case 1 ~ 19 ~ 3.95 Case 2 ~13.7 ~2.3 6. CONCLUSIONS This paper evaluated the impact of uncontrolled BTM resources on the T-D interface. A coupled production/power flow simulation environment was used to capture all aspects of the problem. The study did not identify any serious concerns at the T-D interface. The reliability of the system can be successfully ensured with good system planning and power system engineering practices. At a minimum, local voltage and thermal problems were identified that will require capacity expansion to accommodate the increased penetration. Scenarios with active participation from BTM resources demonstrated considerable improvement in system reliability. The system frequency response was observed to deteriorate without active DER controls allocated to all participating BTM units. Distribution is not decoupled from transmission and will continue to impact bulk power system operations, largely from a system-wide frequency-response perspective. From a steady-state and transient voltage perspective, the issues were largely localized in nature, with the strength of the grid at the point of interconnection and switching action of compensating devices influencing voltage response.
  • 10. 10 BIBLIOGRAPHY [1] Jocelyn Durkay, “State Renewable Portfolio Standards and Goals,” National Conference of State Legislatures, Jan. 2019, [online] http://www.ncsl.org/research/energy/renewable-portfolio- standards.aspx. [2] R. Anderson, S. Gerber, and E. Reid (Feb. 2014). “Distributed Energy Resources Integration, Summarizing the Challenges and Barriers,” Olivine, Inc., San Ramon, CA. [3] Standard BAL-003, “Frequency Response and Frequency Bias Setting,” NERC, Nov. 2012. [4] N. Miller, M. Shao, and S. Venkataraman, “California ISO (CAISO) Frequency Response Study,” Nov. 2011. [5] N. Miller, M. Shao, S. Pajic, and R. D'Aquila, “Eastern Frequency Response Study,” NREL/SR-5500-58077 Subcontractor Report, May 2013. [6] N. Miller, M. Shao, S. Pajic, and R. D'Aquila, “Western Wind and Solar Integration Study Phase 3 – Frequency Response and Transient Stability,” NREL/SR-5D00-62906 Subcontractor Report, Dec. 2014. [7] N. Miller, C. Loutan, M. Shao, and K. Clark, “Emergency Response: U.S. System Frequency with High Wind Penetration,” IEEE/PES Power and Energy Magazine, vol. 11, no. 6, pp. 63-71, Nov. 2013. [8] GE Energy, “Western Wind and Solar Integration Study,” NREL Report No. SR-550-47434, May 2010. [9] D. Lew, et al., “The Western Wind and Solar Integration Study Phase 2,” NREL/TP-5500- 55888, Sep. 2013. [10] GE Energy Consulting, “Stage 2 Oahu – Maui Interconnection Study,” Hawaii Electric Company, May 2013. [11] GE Energy Consulting, “Oahu Distributed PV Grid Stability Study. Part 1: System Frequency Response to Generator Contingency Events,” Hawaii Electric Company, Mar. 2016. [12] C. Kavalec, “2014-2024 Final Forecast Volume 1: Statewide Electricity,” CEC Report No. CEC-200-2013-004-V1-CMF, Jan. 2014. [13] GE Positive Sequence Load Flow (PSLF) [online] http://www.geenergyconsulting.com/practice- area/software-products/pslf. [14] GridView [online] http://new.abb.com/enterprise-software/energy-portfolio- management/market-analysis/gridview. [15] WECC Regional Planning Standards [online] https://www.wecc.biz/Standards/Pages/Default.aspx. [16] S. Sharma, S. Huang, and N.D.R. Sarma, “System Inertial Frequency Response Estimation and Impact of Renewable Resources in ERCOT Interconnection,” in Proc. IEEE Power and Energy Society General Meeting, San Diego, CA, Jul. 2011.