SlideShare a Scribd company logo
1 of 10
Download to read offline
International journal of scientific and technical research in engineering (IJSTRE)
www.ijstre.com Volume 1 Issue 1 ǁ April 2016.
Manuscript id. 626565888 www.ijstre.com Page 27
Reliability Assesment of Debremarkos Distribution System Found
In Ethiopia
Demsew Mitiku Teferra1
, Amache Jara Godobo2
Department of Electrical and Computer Engineering
Debre Markos University
Debre Markos, Ethiopia
Abstract- This research presents a method for reliability assessment considering the 23MVA, 230/15 kV
transformer through two 15 kV outgoing transmission lines at Debre Markos substation. It also goes further to
include 139 low voltage 15/0.4 kV distribution transformers. The total load connected to the 15 kV feeders are
varies between 0.33255 and 6.3185 MW. A composite system adequacy and security assessment is done using
Monte Carlo simulation. The basic data and the topology used in the analysis are based on the Institution of
Electrical and Electronics Engineers - Reliability Test System and distribution system for bus two of the IEEE-
Reliability Bus bar Test System. The reliability indices SAIDI, SAIFI, CAIDI, EENS, AENS, ASAI, ASUI, and
expected interruption costs are being assessed and considered. Distribution system reliability information was
obtained from actual data for systems operating in Ethiopia Electric Utility office and Debre Markos substation
recorded data and online SCADA system.
Keywords: Adequacy, DigSILent, Expected Interruption cost, Failure rate, Forced outage, Indices, Interruptions,
Reliability, Repair time, Security.
I. INTRODUCTION
The electric power systems can be divided into generation plant, generation sub-station, transmission
system, sub-transmission and distribution sub-stations. Traditionally, generation is to supply the power to the
transmission system which can be defined as the carrier of power from the generating stations to the sub-
transmission system, at voltage levels of 230 kV or higher. The sub-transmission system then transfers the
power at voltage levels between 66 kV to 132 kV to the distribution substation systems. Finally, the distribution
substation system, at voltages under 33 kV, delivers electricity to the consumer [1].
The case study of radial distribution system reliability assessment is carried out on Debre Markos Substation
system which consists of 66kV, 33kV and 15kV outgoing feeder network in Debre Markos. The reliability
assessment analysis through 230/15KV, 23MVA transformer is done on two 15kV feeders (feeder-3 and feeder-
4) system to assess the performance of existing system to reliability indices analysis considering customer and
system configurations. The alternative technique which shows reliability indices such as SAIDI, SAIFI, CAIDI,
EENS, and EIC are being assessed and considered. Recent and unpublished important information and data have
been collected from Debre Markos Substation. Interviews with respective professionals at substations and
Electric utility office have been considered. The collected data are; fault statics, outage consequences, the
number of interruption, interruption duration, the existing distribution network capacity, the capacity of power
supplied to the network, the number of connected feeders, the minimum, mid-range, maximum demands per
day/month/year, the distance from the transmission line to the distribution, and from distribution to main feeders
of the study area have been collected from Ethiopia electric power and Ethiopia electric utility offices. The
distribution system model for reliability analysis using DIgSILent software tool was developed.
This study considered the two 15kV outgoing feeders (Debre Markos line 3 and line 4) in the town. This is
because the distribution system is the major contributor of the reliability problems in the power system more
than 80% [2].
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 28
Figure 1.1: Basic power system structure.
2. SYSTEM MODEL
2.1. Distribution system Reliability Indices
The most commonly used reliability indices of distribution systems are statistical aggregations of reliability data
for defined loads, components or customers. They are mostly average values of a particular reliability
characteristic for an entire system, operating region, distribution service area or other portion of the system. The
indices can be categorized as customer based and load based indices [3-6].
2.1.1. Customer Based Indices
System Average Interruption Frequency Index: (SAIFI) is measure of how many sustained interruptions on
average customer will experience over the course of a year. For a fixed number of customers, the only way to
improve SAIFI is reduce the number of sustained interruption experienced by customers [3-6].
SAIFI 
Total number of customer interruptions

λi Ni
(1)Total number of cutemer served  Ni
System average interruption duration index: (SAIDI) is a measure of how many interruption hours on
average customer will experience over the course of a year. For a fixed number of customers, SAIDI can be
improved by decreasing the number of interruptions or by decreasing the duration of these interruptions. Since
both of these reflect reliability improvements, a reduction in SAIDI means an improvement in reliability [3-6].
SAIDI 
Sum of customer interruptions durations

 Ui Ni
(2)
Total number of customer  Ni
Customer average interruption duration index: (CAIDI) is a measure of how long an average interruption
lasts, and is used as a measure of utility response time to system incidents. CAIDI can be improved by
decreasing the length of interruptions, but can also be decreased by increasing the number of short interruptions.
As a result, a decrease in CAIDI does not necessarily mean an improvement in reliability [3-6].
CAIDI 
Sum of customer interruptions durations

 Ui Ni
(3)Total number of customer interruptions λi Ni
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 29
Average service availability index: (ASAI) is the customer-weighted availability of the system and provides
the same information as SAIDI. Higher ASAI values means higher level of system reliability [3-6].
ASAI 
Customer hours of available service

8760 
 Ni

 Ui Ni
(4)
Customer hours demand
8760 
 Ni
Average service unavailability index:
ASUI 
Customer hours of unavailable service

 Ui Ni
(5)
Customer hours demand
8760 
 Ni
Where Ni is the number of customers for load point i,U i is the annual outage duration for
load point , λi is the number of occurrence of sustained interruption at load point i and 8760
is the number of hours in a calendar year [3-6].
2.1.2. Load and Energy Based Indices
One of the important parameters required in the evaluation of load and energy based indices is the average load
La  at each load point bus bars, which is given by: [3-6]
La 
Lpeak f
Where;
Lpeak is the peak load demand
f is the corresponding load factor
Expected Energy Not Supplied Index at Load Point:
EENS = Expected total energy not supplied by the system =  Ui La(i)
Average Energy Not Supplied:
Total energy not supplied
 i
AENS  
U La(i)
 i
Total number of customers served
N
2.2. Software Implementation Procedure for Reliability Evaluation
DIgSILent is a computer aided engineering tool for the analysis of industrial, utility, commercial, and residential
electrical power systems. It has been designed as an advanced integrated and interactive software package
dedicated to electrical power system and control analysis in order to achieve the main objectives of planning and
operation optimization.
DIgSILent reliability evaluation software can be used to provide not only the reliability indices for both the
individual load points and the overall power system, but also it can be used to provide the cost of interruptions.
DIgSILent is based on Monte Carlo simulation and enumeration techniques. Figure 2.1 shows the reliability
evaluation procedure taken in DIgSILent to achieve the reliability indices for both load point and the overall
system.
The first step is to analyze all the input data required for power flow analysis and data required for reliability
evaluation. After processing the data and solving the power flow program for the system in order to obtain the
system characteristics in normal condition, the system will be modeled by applying the MCS. The achieved
model will be reduced to the reasonably small model by applying the contingency and ranking or the truncation
of states techniques. But applying such techniques require a deep understanding over practical systems i.e. it is
necessary to know what kind of outages may occur in practical system. In DIgSILent
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 30
the predefined outages events are categorized in two groups’ i.e. first order and second order contingencies.
Process of Distribution Network Data
Creating possible outage events combinations
1st
order outages events 2nd
order outage events
Single stochastic Single deterministic Double stochastic Single stochastic &
outage outage outage deterministic outage
Effect analysis of each outages mode on system performance
Normal√
System
performance
Abnormal?
Alleviating the abnormality of the system
Normal√ System
performance
Abnormal?
Load curtailment
Σ Registering the failure rate
Load point indices, failures frequency, duration, etc
Overall system indices
Figure 2.1: Flow chart for reliability evaluation of the distribution system
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 31
The second step is to create a first order and second order outage combinations. First order contingencies deal
with single stochastic outages and single deterministic outages. Generally the single deterministic group does
not contribute in interruption frequency while it causes no supply interruption to the loads of the system. Single
stochastic outages group includes several modes such as independent single outage, common mode outage,
ground fault and unintended switch opening. The reliability input data for these categories are failure rate and
repair time and the output data are failure frequency and its relevant duration.
2.3. Case Study Reliability Assessment
To get some insight in the problems related to operation of a real distribution network, a case study based on the
distribution system around Debre Markos and 15km South from Debre Markos town has been performed. The
basis for the study is firstly a steady state load flow model of the 15 and 0.4 kV network which has been created
and is maintained by the distribution network operator, and secondly measurements from the supervisory control
and data acquisition system (SCADA) of the distribution system.
The substation supplies 10670 customers. The utility owns the distribution lines at 66, 33, 15 and 0.4 kV levels.
The grid is only connected to the transmission system through the 230/66 kV, 230/33 kV and 230/15 kV
substation. There are two parallel connected 400/230 kV, another 230/33kV and a third three winding
230/66/15kV transformer stations. This research considers only the 230/15 kV transformer through two 15 kV
outgoing feeders and it also 139 total low voltage distribution transformers.
The 66, 33 and 15 kV system consists of overhead transmission lines, but 0.4 kV systems are considered a part
of the loads. A general one line diagram of the 66, 33 and 15 kV grid including the neighboring 230 kV lines
and the 400 kV in feed is shown in Figure 2.3. The 15 kV network is operated as radials and the total capacity
of 230/66/15 kV transformer is 63MVA supply to two 66 kV (FINOTE SELAM and BICHENA) and supply to
four 15kV (AMANUAL line 1, LUMAME line 2, Debre Markos Line 3 and Debre Markos Line 4) outgoing
feeders. The total load connected to the two 15 kV feeders (Debre Markos Line 3 and Debre Markos Line 4) are
varies between 0.33255 and 6.3185222 MW.
Figure 2.2: ETAP-Model Single line diagram of Debre Markos Substation
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 32
2.4. Distribution Substation test system
The base case distribution system modeled with ETAP software is shown in Figure 2.2. The peak loading levels
of the two feeders (feeder-3 and feeder-4) is 6.31852MW and the average load is 2.972MW. It is assume a
100% of reliability performance from generation and transmission of the RBTS. There is one 230KV main bus
that corresponds to bus 2 from Figure 2.3: which is connected to the 15KV supply point through substation
transformer. Though the 15KV feeder the power supply is limited by having only one 23MVA, 230/15KV
transformer capacity, there are four main feeders, Amanuel line 1, Lumame line 2, Debre Markos line 3, and
Debre Markos line 4 at 15 KV, the feeders operate as radial system.
The main feeder names, detail transformers numbers, ratings, connected numbers of customers and remarks of
low voltage outgoing feeders are shown in Table 2.1. The distribution system has 12 load points that supplies
power to different types of costumer’s loads, such as residential, commercial and industrial, the customers,
minimum load, peak load and average load data at each feeder is shown in Table 2.2.
Figure 2.3: The Base Case Distribution Substation Model Using DIgSILent.
The minimum and maximum recorded load profile of feeder-3 and feeder-4 is presented in Figure 2.3 and
Figure 2.4 in the year 2015.
Load(MW)
Peak load Minimum load
3.5
3
2.5
2
1.5
1
0.5
0
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 33
Sept. Oct. Nov. Dec. Jan. Feb. March April May June July Aug.
Months
Figure 2.3: Peak and Minimum Load Profile of Feeder Three (Debre Markos Line-3)
Load(MW)
3.5
3
2.5
2
1.5
1
0.5
0
Peak load Minimum load
Sept. Oct. Nov. Dec. Jan. Feb. March April May June July Aug.
Months
Figure 2.4: Peak and Minimum Load Profile of Feeder Four (Debre Markos line 4)
2.5. Case Study Area Major Source of Power Interruption
From historical data of the past years, major cause of outages, occurrences, and durations in the system is being
evaluated and presented in Table 2.2 and Table 2.3.
Table 2.2: Causes of outage and number of occurrences in Debre Markos line-3 and -4
Feeder 3 Causes DPEF DPSC DTEF DTSC OP Sum
No. of occurrences 116 74 116 64 320 690
Feeder 4 No. of occurrences 57 45 53 49 242 446
Total number of occurrences 173 119 169 113 562 1136
Table 2.3: Causes of outage and interruption duration in Debre Markos line-3 and -4
Feeder 3 Causes DPEF DPSC DTEF DTSC OP Sum
Interrupted hours 134.9167 178.45 4.467 3.167 298 619.001
Feeder 4 Interrupted hours 142.433 118.1 2.7167 2.033 260.0833 525.366
Total interrupted hours 277.3497 296.55 7.1837 5.2 558.0833 1144.367
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 34
3. SIMULATION RESULT AND DISCUSSION
The DIgSILent software simulation result of reliability indices of Debre Markos substation for each feeders are
shown in Table 3.1, as a radial system with no meshed connections the failure rate (λ/yr), the outage durations
(hr) and annual outage durations (hr/yr) and also Figure 3.1 shows outage duration and failure occurrence of
each feeder.
Outage duration (hrs) Frequency
800
700
648.788044
693.6
600
543.8200008
445.2
500
400
300
200
100
0 Feeder
3 Feeder 4
Figure 3.1: Outage duration and failure occurrence of each feeder.
Table 3.1: Radial system reliability indices for each feeder
Substation Outage Frequency Failure rate λ Annual outage
Feeders duration (hrs) (occurrence) (Failures/year) duration U (hrs/yr)
Feeder 3
648.788044 693.6
0.0855112656 55.478687
Feeder 4
543.820001 445.2
0.0541857652 29.467303
In the normal conditions of the circuit, there are no disconnects on the main line. The only protections are the
fuses that connect the main feeders and the lateral distributors. Hence, any fault on the main line will require the
system to be isolated from the main breaker. The reliability assessment of each feeder can be calculated by
considering the impact of each section and load point on the corresponding load point. Let us to examine the
reliability assessment of each feeder.
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 35
First, the impact of each section failure on the load point’s reliability is considered. Any section failure will
result in power outage for load point since there are no disconnects on the main distribution lines. Then the
outage duration r (hours) of each feeder is assessed. Using the failure occurrences of the feeder, its failure rate λ
(f/yr) is determined. Using the failure rate and repair time, the annual outage duration U (hrs/yr) for each feeder
is obtained.
Secondly, the impact of each lateral distributor’s failure on the load point is considered. Since, each lateral is
connected to the main feeder through fuse; a fault on any lateral will be introducing impact on the other load
point. If there is a fault on the load point, the power from the main feeder is shutdown to repair the fault; its
reliability impact will be added to the system. Adding the impact of each section and lateral distributor, the
average failure rate, average outage duration, and annual outage duration for the main feeders can be calculated
as by using equation (9), (10) and (11).
λs

λi (9)
i
Us 
λi ri (10)
rs  Us
(11)
λs
From the above equations the other parameters of each feeder were calculated as shown in the Table 3.2.
Table 3.2: The main feeder availability and unavailability indices
S/Station
Ni
648.788 λi ∗ Ni U i
ASAI (%) ASUI (%)
feeder
ri * N
i
Feeder 3 6541 0.085511 559.3294 362886.092 92.594 7.4063
Feeder 4 4129 0.054186
543.82
223.7332 121670.494 93.792 6.208
Total 10670 93.193 6.807
The costumer load point indices are calculated, related to the unsupplied energy and costs. Those are the
expected Energy Not Supplied (EENS), the Expected interruption Cost (EIC) and the Average Energy Not
Supplied values are shown in Table 3.3. The priority order based on the EIC was used for load curtailment level;
the EIC is the average monetary impact on the customers at a load point. This higher the EIC the higher priority
this load may have, because a load curtailment at that load point will contribute to higher economic cost.
Table 3.3: Expected Energy not supplied and Interruption Costs indices for each feeder.
Substation Expected Energy not Expected Interruption Average Energy Not
Feeders supplied (MW hr/yr) Cost EIC (m$ /yr) Supplied (KW hr/yr. ca.)
Feeder 3 1843.73952 1.58043808 281.87426
Feeder 4 1175.52185 1.00764752 284.69892
Total 3019.26137 2.58808558 283.28659
Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia
Manuscript id. 626565888 www.ijstre.com Page 36
From the above table each index of the main feeder provides different information and some indices are more
important than others. The main feeder indices are useful in assessing the load point impact of system
modifications and provide input to reliability evaluation at the actual customer level. Furthermore, there are the
system reliability indices which provide valuable information on the overall ability of the system to supply the
customer load. The probability of a customer receiving uninterrupted power supply can be accessed from the
indices of Table 3.2 and Table 3.3. The higher the value of the reliability indices the higher is the unreliability at
the corresponding bus. Using the data from the above table, the overall base case reliability indices can be
calculated as shown in Table 3.4:
Table 3.4: DIgSILent Simulation Result of Overall System Indices Values.
4. CONCLUSION
The result of the study concluded that the base case system indices; SAIDI is 597.476 hr/customer year
suggesting that system’s average interruption duration for each customer is 597.476hr during a year, SAIFI is
608.168 inter./customer year suggesting that system’s average interruption frequency for each customer is
608.168 during a year, CAIDI is 0.982 hrs/ customer interruption, suggesting system’s average interruption
duration for the customers that experience interruption is 0.982 hrs during a year and system availability and
unavailability are 93.193% and 6.803% are respectively . Also, the expected energy not supplied (EENS) for the
base case system due to the failures is 2933.692MWh/yr and the energy not supplied per customer is
168.9396kWh/yr. And finally, the expected interruption cost is 1.5333764millions $/yr during a year. The
system reliability indices show that Debre Markos distribution system is unreliable distribution system.
REFERENCES
[1]. A. Von Meier, Electric Power Systems. Wiley Online Library
[2]. R. Billinton and J. E. Billinton, ‘Distribution System Reliability Indices’, IEEE Trans. Power Delivery, Vol.4, No.1, Jan.
1989, pp. 561-568.
[3]. Y. Kumar, B. Das, and J. Sharma. Multi-objective, multi-constraint service restoration of electric power distribution system
with priority customers. IEEE Trans. Power Delivery, 23(1):261-270, Jan 2008.
[4]. D. Zhu, R.P. Broadwater, K.-S. Tam, R.Seguim, and H. Asgeirsson. Impact of DG placement on reliability an Trans. Power
Systems, 21:419-427, Feb 2006.
[5]. Y. M. Atwa and E. F. EI-Saadany. Reliability evaluation for distribution system with renewable DG during islanded
mode of operation. IEEE Tans. Power Systems, 24:572-581, May 2009.
[6]. W. Peng and R. Billinton. Reliability benefits analysis of adding WTG to a distribution system. IEEE Trans. Energy
Conversion, 16(2):134-139, Jun 2001.

More Related Content

What's hot

Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.Shweta Yadav
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault AnalysisSANTOSH GADEKAR
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMerramansaini1947
 
Parallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase TransformerParallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase TransformerRidwanul Hoque
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 6
Principles of Power Systems V.K Mehta Complete Book - Chapter 6Principles of Power Systems V.K Mehta Complete Book - Chapter 6
Principles of Power Systems V.K Mehta Complete Book - Chapter 6Power System Operation
 
Chapter 1 Solution Techniques.pdf
Chapter 1 Solution Techniques.pdfChapter 1 Solution Techniques.pdf
Chapter 1 Solution Techniques.pdfMurugesanKarthi
 
Load factor and demand factor
Load factor and demand factorLoad factor and demand factor
Load factor and demand factordhirajthakkar1
 
Solid State Control of Electric Drive
Solid State Control of Electric DriveSolid State Control of Electric Drive
Solid State Control of Electric DriveSHIMI S L
 
Unified Power Flow Controller(upfc) 2
Unified Power Flow Controller(upfc) 2Unified Power Flow Controller(upfc) 2
Unified Power Flow Controller(upfc) 2JayakalyanReddy
 
Load Frequency Control of two area Power system
Load Frequency Control  of two area Power systemLoad Frequency Control  of two area Power system
Load Frequency Control of two area Power systemAnimesh Sachan
 
Unit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drivesUnit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drivesraviarmugam
 
Overcurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryOvercurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryAreeb Abdullah
 
Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power controlCaner Göksel Sonuzun
 

What's hot (20)

Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault Analysis
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEM
 
Parallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase TransformerParallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase Transformer
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 6
Principles of Power Systems V.K Mehta Complete Book - Chapter 6Principles of Power Systems V.K Mehta Complete Book - Chapter 6
Principles of Power Systems V.K Mehta Complete Book - Chapter 6
 
Distribution System
Distribution SystemDistribution System
Distribution System
 
Chapter 1 Solution Techniques.pdf
Chapter 1 Solution Techniques.pdfChapter 1 Solution Techniques.pdf
Chapter 1 Solution Techniques.pdf
 
Load factor and demand factor
Load factor and demand factorLoad factor and demand factor
Load factor and demand factor
 
Solid State Control of Electric Drive
Solid State Control of Electric DriveSolid State Control of Electric Drive
Solid State Control of Electric Drive
 
Unified Power Flow Controller(upfc) 2
Unified Power Flow Controller(upfc) 2Unified Power Flow Controller(upfc) 2
Unified Power Flow Controller(upfc) 2
 
Load Frequency Control of two area Power system
Load Frequency Control  of two area Power systemLoad Frequency Control  of two area Power system
Load Frequency Control of two area Power system
 
Load flow study
Load flow studyLoad flow study
Load flow study
 
Power flow analysis
Power flow analysisPower flow analysis
Power flow analysis
 
Unit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drivesUnit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drives
 
SYNCHRONOUS MACHINES
SYNCHRONOUS MACHINESSYNCHRONOUS MACHINES
SYNCHRONOUS MACHINES
 
Overcurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryOvercurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactory
 
Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power control
 
Introduction
IntroductionIntroduction
Introduction
 
Power quality improvement using UPQC
Power quality improvement using UPQCPower quality improvement using UPQC
Power quality improvement using UPQC
 
Representation of loads
Representation of loadsRepresentation of loads
Representation of loads
 

Similar to Reliability Assesment of Debremarkos Distribution System Found In Ethiopia

Adequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power SystemAdequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power SystemIOSR Journals
 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET Journal
 
Power System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemPower System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemIJECEIAES
 
Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...
Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...
Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...Radita Apriana
 
Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...eSAT Publishing House
 
On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...idescitation
 
Reliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution FeederReliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution FeederIOSR Journals
 
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...theijes
 
Predicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution FactorsPredicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution FactorsDr. Amarjeet Singh
 
Vagueness concern in bulk power system reliability assessment methodology 2-3-4
Vagueness concern in bulk power system reliability assessment methodology 2-3-4Vagueness concern in bulk power system reliability assessment methodology 2-3-4
Vagueness concern in bulk power system reliability assessment methodology 2-3-4IAEME Publication
 
A Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis SystemA Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis SystemIRJET Journal
 
Power System Contingency Ranking Using Fast Decoupled Load Flow Method
Power System Contingency Ranking Using Fast Decoupled Load Flow MethodPower System Contingency Ranking Using Fast Decoupled Load Flow Method
Power System Contingency Ranking Using Fast Decoupled Load Flow Methodpaperpublications3
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentationAfzal Tiwari
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system slmnsvn
 
Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...
Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...
Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...IRJET Journal
 
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEMLATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEMijiert bestjournal
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...IRJET Journal
 
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...IJERA Editor
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)theijes
 

Similar to Reliability Assesment of Debremarkos Distribution System Found In Ethiopia (20)

Adequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power SystemAdequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power System
 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
 
Power System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemPower System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power System
 
Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...
Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...
Optimal Placement and Sizing of Distributed Generation Units Using Co-Evoluti...
 
Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...
 
On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...
 
Reliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution FeederReliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
 
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
 
Predicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution FactorsPredicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution Factors
 
Vagueness concern in bulk power system reliability assessment methodology 2-3-4
Vagueness concern in bulk power system reliability assessment methodology 2-3-4Vagueness concern in bulk power system reliability assessment methodology 2-3-4
Vagueness concern in bulk power system reliability assessment methodology 2-3-4
 
A Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis SystemA Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis System
 
Power System Contingency Ranking Using Fast Decoupled Load Flow Method
Power System Contingency Ranking Using Fast Decoupled Load Flow MethodPower System Contingency Ranking Using Fast Decoupled Load Flow Method
Power System Contingency Ranking Using Fast Decoupled Load Flow Method
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentation
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...
Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...
Smart Substation with Automatic Monitoring, Smart Controlling and Overload Pr...
 
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEMLATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
 
Power system planing and operation (pce5312) chapter three
Power system planing and operation (pce5312) chapter threePower system planing and operation (pce5312) chapter three
Power system planing and operation (pce5312) chapter three
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
 
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 

More from International journal of scientific and technical research in engineering (IJSTRE)

More from International journal of scientific and technical research in engineering (IJSTRE) (20)

COVID-19 Vaccine And Problematics In Children: A Literature Review
COVID-19 Vaccine And Problematics In Children: A Literature ReviewCOVID-19 Vaccine And Problematics In Children: A Literature Review
COVID-19 Vaccine And Problematics In Children: A Literature Review
 
The Challenges of Handling Dengue Hemorrhagic Fever during the COVID-19 Pande...
The Challenges of Handling Dengue Hemorrhagic Fever during the COVID-19 Pande...The Challenges of Handling Dengue Hemorrhagic Fever during the COVID-19 Pande...
The Challenges of Handling Dengue Hemorrhagic Fever during the COVID-19 Pande...
 
Development of Measuring technique for Electric Power of Wind turbine-Solar P...
Development of Measuring technique for Electric Power of Wind turbine-Solar P...Development of Measuring technique for Electric Power of Wind turbine-Solar P...
Development of Measuring technique for Electric Power of Wind turbine-Solar P...
 
Estimation of Speed Required for Palm Nut Shell Mass-Size Particle Reduction ...
Estimation of Speed Required for Palm Nut Shell Mass-Size Particle Reduction ...Estimation of Speed Required for Palm Nut Shell Mass-Size Particle Reduction ...
Estimation of Speed Required for Palm Nut Shell Mass-Size Particle Reduction ...
 
A comprehensive review of Chronic Kidney Disease of Unknown Etiology
A comprehensive review of Chronic Kidney Disease of Unknown EtiologyA comprehensive review of Chronic Kidney Disease of Unknown Etiology
A comprehensive review of Chronic Kidney Disease of Unknown Etiology
 
EVALUATION OF HEAVY METALS IN SEDIMENT OF SOME SELECTED DAMS FROM KATSINA STA...
EVALUATION OF HEAVY METALS IN SEDIMENT OF SOME SELECTED DAMS FROM KATSINA STA...EVALUATION OF HEAVY METALS IN SEDIMENT OF SOME SELECTED DAMS FROM KATSINA STA...
EVALUATION OF HEAVY METALS IN SEDIMENT OF SOME SELECTED DAMS FROM KATSINA STA...
 
Using Partitioned Design Matrices in Analyzing Nested-Factorial Experiments
Using Partitioned Design Matrices in Analyzing Nested-Factorial ExperimentsUsing Partitioned Design Matrices in Analyzing Nested-Factorial Experiments
Using Partitioned Design Matrices in Analyzing Nested-Factorial Experiments
 
Reasons for High Life Expectancy at Birth with Males in Hambantota District i...
Reasons for High Life Expectancy at Birth with Males in Hambantota District i...Reasons for High Life Expectancy at Birth with Males in Hambantota District i...
Reasons for High Life Expectancy at Birth with Males in Hambantota District i...
 
A Study of the Refractory Properties of Selected Clay deposit in Chavakali, K...
A Study of the Refractory Properties of Selected Clay deposit in Chavakali, K...A Study of the Refractory Properties of Selected Clay deposit in Chavakali, K...
A Study of the Refractory Properties of Selected Clay deposit in Chavakali, K...
 
Cause Investigation of Failure of the Challenge to World Record of Human-Powe...
Cause Investigation of Failure of the Challenge to World Record of Human-Powe...Cause Investigation of Failure of the Challenge to World Record of Human-Powe...
Cause Investigation of Failure of the Challenge to World Record of Human-Powe...
 
Status of Geological Disasters in Jiaozuo City and Countermeasures for Preven...
Status of Geological Disasters in Jiaozuo City and Countermeasures for Preven...Status of Geological Disasters in Jiaozuo City and Countermeasures for Preven...
Status of Geological Disasters in Jiaozuo City and Countermeasures for Preven...
 
Experimental Study on Toxic Gas Produced during Pipeline Gas Explosions
Experimental Study on Toxic Gas Produced during Pipeline Gas ExplosionsExperimental Study on Toxic Gas Produced during Pipeline Gas Explosions
Experimental Study on Toxic Gas Produced during Pipeline Gas Explosions
 
The influence of the entry speed to flow field above water surface on the wat...
The influence of the entry speed to flow field above water surface on the wat...The influence of the entry speed to flow field above water surface on the wat...
The influence of the entry speed to flow field above water surface on the wat...
 
Geological Hazards in Pingdingshan Coal Mine District and Controlling Counter...
Geological Hazards in Pingdingshan Coal Mine District and Controlling Counter...Geological Hazards in Pingdingshan Coal Mine District and Controlling Counter...
Geological Hazards in Pingdingshan Coal Mine District and Controlling Counter...
 
Is There any Change from Magma Mixing in Kelud Characteristics?
Is There any Change from Magma Mixing in Kelud Characteristics? Is There any Change from Magma Mixing in Kelud Characteristics?
Is There any Change from Magma Mixing in Kelud Characteristics?
 
Improving Properties of Black Cotton Soil with Quarry Dust
Improving Properties of Black Cotton Soil with Quarry DustImproving Properties of Black Cotton Soil with Quarry Dust
Improving Properties of Black Cotton Soil with Quarry Dust
 
Study Charge the Floods Evaluated From Morphometry and Mitigasi Arau Padang C...
Study Charge the Floods Evaluated From Morphometry and Mitigasi Arau Padang C...Study Charge the Floods Evaluated From Morphometry and Mitigasi Arau Padang C...
Study Charge the Floods Evaluated From Morphometry and Mitigasi Arau Padang C...
 
Histochemical Characteristics of Ricinodedron Heudelotii (Baill, Pierre Ex Pa...
Histochemical Characteristics of Ricinodedron Heudelotii (Baill, Pierre Ex Pa...Histochemical Characteristics of Ricinodedron Heudelotii (Baill, Pierre Ex Pa...
Histochemical Characteristics of Ricinodedron Heudelotii (Baill, Pierre Ex Pa...
 
Formation Sensitivity Assessment of the Gbaran Field, Niger Delta Basin, Nigeria
Formation Sensitivity Assessment of the Gbaran Field, Niger Delta Basin, NigeriaFormation Sensitivity Assessment of the Gbaran Field, Niger Delta Basin, Nigeria
Formation Sensitivity Assessment of the Gbaran Field, Niger Delta Basin, Nigeria
 
The Optimization of Carbonitriding Process for 1022 Self-drilling Tapping Scr...
The Optimization of Carbonitriding Process for 1022 Self-drilling Tapping Scr...The Optimization of Carbonitriding Process for 1022 Self-drilling Tapping Scr...
The Optimization of Carbonitriding Process for 1022 Self-drilling Tapping Scr...
 

Recently uploaded

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 

Recently uploaded (20)

young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 

Reliability Assesment of Debremarkos Distribution System Found In Ethiopia

  • 1. International journal of scientific and technical research in engineering (IJSTRE) www.ijstre.com Volume 1 Issue 1 ǁ April 2016. Manuscript id. 626565888 www.ijstre.com Page 27 Reliability Assesment of Debremarkos Distribution System Found In Ethiopia Demsew Mitiku Teferra1 , Amache Jara Godobo2 Department of Electrical and Computer Engineering Debre Markos University Debre Markos, Ethiopia Abstract- This research presents a method for reliability assessment considering the 23MVA, 230/15 kV transformer through two 15 kV outgoing transmission lines at Debre Markos substation. It also goes further to include 139 low voltage 15/0.4 kV distribution transformers. The total load connected to the 15 kV feeders are varies between 0.33255 and 6.3185 MW. A composite system adequacy and security assessment is done using Monte Carlo simulation. The basic data and the topology used in the analysis are based on the Institution of Electrical and Electronics Engineers - Reliability Test System and distribution system for bus two of the IEEE- Reliability Bus bar Test System. The reliability indices SAIDI, SAIFI, CAIDI, EENS, AENS, ASAI, ASUI, and expected interruption costs are being assessed and considered. Distribution system reliability information was obtained from actual data for systems operating in Ethiopia Electric Utility office and Debre Markos substation recorded data and online SCADA system. Keywords: Adequacy, DigSILent, Expected Interruption cost, Failure rate, Forced outage, Indices, Interruptions, Reliability, Repair time, Security. I. INTRODUCTION The electric power systems can be divided into generation plant, generation sub-station, transmission system, sub-transmission and distribution sub-stations. Traditionally, generation is to supply the power to the transmission system which can be defined as the carrier of power from the generating stations to the sub- transmission system, at voltage levels of 230 kV or higher. The sub-transmission system then transfers the power at voltage levels between 66 kV to 132 kV to the distribution substation systems. Finally, the distribution substation system, at voltages under 33 kV, delivers electricity to the consumer [1]. The case study of radial distribution system reliability assessment is carried out on Debre Markos Substation system which consists of 66kV, 33kV and 15kV outgoing feeder network in Debre Markos. The reliability assessment analysis through 230/15KV, 23MVA transformer is done on two 15kV feeders (feeder-3 and feeder- 4) system to assess the performance of existing system to reliability indices analysis considering customer and system configurations. The alternative technique which shows reliability indices such as SAIDI, SAIFI, CAIDI, EENS, and EIC are being assessed and considered. Recent and unpublished important information and data have been collected from Debre Markos Substation. Interviews with respective professionals at substations and Electric utility office have been considered. The collected data are; fault statics, outage consequences, the number of interruption, interruption duration, the existing distribution network capacity, the capacity of power supplied to the network, the number of connected feeders, the minimum, mid-range, maximum demands per day/month/year, the distance from the transmission line to the distribution, and from distribution to main feeders of the study area have been collected from Ethiopia electric power and Ethiopia electric utility offices. The distribution system model for reliability analysis using DIgSILent software tool was developed. This study considered the two 15kV outgoing feeders (Debre Markos line 3 and line 4) in the town. This is because the distribution system is the major contributor of the reliability problems in the power system more than 80% [2].
  • 2. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 28 Figure 1.1: Basic power system structure. 2. SYSTEM MODEL 2.1. Distribution system Reliability Indices The most commonly used reliability indices of distribution systems are statistical aggregations of reliability data for defined loads, components or customers. They are mostly average values of a particular reliability characteristic for an entire system, operating region, distribution service area or other portion of the system. The indices can be categorized as customer based and load based indices [3-6]. 2.1.1. Customer Based Indices System Average Interruption Frequency Index: (SAIFI) is measure of how many sustained interruptions on average customer will experience over the course of a year. For a fixed number of customers, the only way to improve SAIFI is reduce the number of sustained interruption experienced by customers [3-6]. SAIFI  Total number of customer interruptions  λi Ni (1)Total number of cutemer served  Ni System average interruption duration index: (SAIDI) is a measure of how many interruption hours on average customer will experience over the course of a year. For a fixed number of customers, SAIDI can be improved by decreasing the number of interruptions or by decreasing the duration of these interruptions. Since both of these reflect reliability improvements, a reduction in SAIDI means an improvement in reliability [3-6]. SAIDI  Sum of customer interruptions durations   Ui Ni (2) Total number of customer  Ni Customer average interruption duration index: (CAIDI) is a measure of how long an average interruption lasts, and is used as a measure of utility response time to system incidents. CAIDI can be improved by decreasing the length of interruptions, but can also be decreased by increasing the number of short interruptions. As a result, a decrease in CAIDI does not necessarily mean an improvement in reliability [3-6]. CAIDI  Sum of customer interruptions durations   Ui Ni (3)Total number of customer interruptions λi Ni
  • 3. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 29 Average service availability index: (ASAI) is the customer-weighted availability of the system and provides the same information as SAIDI. Higher ASAI values means higher level of system reliability [3-6]. ASAI  Customer hours of available service  8760   Ni   Ui Ni (4) Customer hours demand 8760   Ni Average service unavailability index: ASUI  Customer hours of unavailable service   Ui Ni (5) Customer hours demand 8760   Ni Where Ni is the number of customers for load point i,U i is the annual outage duration for load point , λi is the number of occurrence of sustained interruption at load point i and 8760 is the number of hours in a calendar year [3-6]. 2.1.2. Load and Energy Based Indices One of the important parameters required in the evaluation of load and energy based indices is the average load La  at each load point bus bars, which is given by: [3-6] La  Lpeak f Where; Lpeak is the peak load demand f is the corresponding load factor Expected Energy Not Supplied Index at Load Point: EENS = Expected total energy not supplied by the system =  Ui La(i) Average Energy Not Supplied: Total energy not supplied  i AENS   U La(i)  i Total number of customers served N 2.2. Software Implementation Procedure for Reliability Evaluation DIgSILent is a computer aided engineering tool for the analysis of industrial, utility, commercial, and residential electrical power systems. It has been designed as an advanced integrated and interactive software package dedicated to electrical power system and control analysis in order to achieve the main objectives of planning and operation optimization. DIgSILent reliability evaluation software can be used to provide not only the reliability indices for both the individual load points and the overall power system, but also it can be used to provide the cost of interruptions. DIgSILent is based on Monte Carlo simulation and enumeration techniques. Figure 2.1 shows the reliability evaluation procedure taken in DIgSILent to achieve the reliability indices for both load point and the overall system. The first step is to analyze all the input data required for power flow analysis and data required for reliability evaluation. After processing the data and solving the power flow program for the system in order to obtain the system characteristics in normal condition, the system will be modeled by applying the MCS. The achieved model will be reduced to the reasonably small model by applying the contingency and ranking or the truncation of states techniques. But applying such techniques require a deep understanding over practical systems i.e. it is necessary to know what kind of outages may occur in practical system. In DIgSILent
  • 4. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 30 the predefined outages events are categorized in two groups’ i.e. first order and second order contingencies. Process of Distribution Network Data Creating possible outage events combinations 1st order outages events 2nd order outage events Single stochastic Single deterministic Double stochastic Single stochastic & outage outage outage deterministic outage Effect analysis of each outages mode on system performance Normal√ System performance Abnormal? Alleviating the abnormality of the system Normal√ System performance Abnormal? Load curtailment Σ Registering the failure rate Load point indices, failures frequency, duration, etc Overall system indices Figure 2.1: Flow chart for reliability evaluation of the distribution system
  • 5. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 31 The second step is to create a first order and second order outage combinations. First order contingencies deal with single stochastic outages and single deterministic outages. Generally the single deterministic group does not contribute in interruption frequency while it causes no supply interruption to the loads of the system. Single stochastic outages group includes several modes such as independent single outage, common mode outage, ground fault and unintended switch opening. The reliability input data for these categories are failure rate and repair time and the output data are failure frequency and its relevant duration. 2.3. Case Study Reliability Assessment To get some insight in the problems related to operation of a real distribution network, a case study based on the distribution system around Debre Markos and 15km South from Debre Markos town has been performed. The basis for the study is firstly a steady state load flow model of the 15 and 0.4 kV network which has been created and is maintained by the distribution network operator, and secondly measurements from the supervisory control and data acquisition system (SCADA) of the distribution system. The substation supplies 10670 customers. The utility owns the distribution lines at 66, 33, 15 and 0.4 kV levels. The grid is only connected to the transmission system through the 230/66 kV, 230/33 kV and 230/15 kV substation. There are two parallel connected 400/230 kV, another 230/33kV and a third three winding 230/66/15kV transformer stations. This research considers only the 230/15 kV transformer through two 15 kV outgoing feeders and it also 139 total low voltage distribution transformers. The 66, 33 and 15 kV system consists of overhead transmission lines, but 0.4 kV systems are considered a part of the loads. A general one line diagram of the 66, 33 and 15 kV grid including the neighboring 230 kV lines and the 400 kV in feed is shown in Figure 2.3. The 15 kV network is operated as radials and the total capacity of 230/66/15 kV transformer is 63MVA supply to two 66 kV (FINOTE SELAM and BICHENA) and supply to four 15kV (AMANUAL line 1, LUMAME line 2, Debre Markos Line 3 and Debre Markos Line 4) outgoing feeders. The total load connected to the two 15 kV feeders (Debre Markos Line 3 and Debre Markos Line 4) are varies between 0.33255 and 6.3185222 MW. Figure 2.2: ETAP-Model Single line diagram of Debre Markos Substation
  • 6. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 32 2.4. Distribution Substation test system The base case distribution system modeled with ETAP software is shown in Figure 2.2. The peak loading levels of the two feeders (feeder-3 and feeder-4) is 6.31852MW and the average load is 2.972MW. It is assume a 100% of reliability performance from generation and transmission of the RBTS. There is one 230KV main bus that corresponds to bus 2 from Figure 2.3: which is connected to the 15KV supply point through substation transformer. Though the 15KV feeder the power supply is limited by having only one 23MVA, 230/15KV transformer capacity, there are four main feeders, Amanuel line 1, Lumame line 2, Debre Markos line 3, and Debre Markos line 4 at 15 KV, the feeders operate as radial system. The main feeder names, detail transformers numbers, ratings, connected numbers of customers and remarks of low voltage outgoing feeders are shown in Table 2.1. The distribution system has 12 load points that supplies power to different types of costumer’s loads, such as residential, commercial and industrial, the customers, minimum load, peak load and average load data at each feeder is shown in Table 2.2. Figure 2.3: The Base Case Distribution Substation Model Using DIgSILent. The minimum and maximum recorded load profile of feeder-3 and feeder-4 is presented in Figure 2.3 and Figure 2.4 in the year 2015. Load(MW) Peak load Minimum load 3.5 3 2.5 2 1.5 1 0.5 0
  • 7. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 33 Sept. Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Months Figure 2.3: Peak and Minimum Load Profile of Feeder Three (Debre Markos Line-3) Load(MW) 3.5 3 2.5 2 1.5 1 0.5 0 Peak load Minimum load Sept. Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Months Figure 2.4: Peak and Minimum Load Profile of Feeder Four (Debre Markos line 4) 2.5. Case Study Area Major Source of Power Interruption From historical data of the past years, major cause of outages, occurrences, and durations in the system is being evaluated and presented in Table 2.2 and Table 2.3. Table 2.2: Causes of outage and number of occurrences in Debre Markos line-3 and -4 Feeder 3 Causes DPEF DPSC DTEF DTSC OP Sum No. of occurrences 116 74 116 64 320 690 Feeder 4 No. of occurrences 57 45 53 49 242 446 Total number of occurrences 173 119 169 113 562 1136 Table 2.3: Causes of outage and interruption duration in Debre Markos line-3 and -4 Feeder 3 Causes DPEF DPSC DTEF DTSC OP Sum Interrupted hours 134.9167 178.45 4.467 3.167 298 619.001 Feeder 4 Interrupted hours 142.433 118.1 2.7167 2.033 260.0833 525.366 Total interrupted hours 277.3497 296.55 7.1837 5.2 558.0833 1144.367
  • 8. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 34 3. SIMULATION RESULT AND DISCUSSION The DIgSILent software simulation result of reliability indices of Debre Markos substation for each feeders are shown in Table 3.1, as a radial system with no meshed connections the failure rate (λ/yr), the outage durations (hr) and annual outage durations (hr/yr) and also Figure 3.1 shows outage duration and failure occurrence of each feeder. Outage duration (hrs) Frequency 800 700 648.788044 693.6 600 543.8200008 445.2 500 400 300 200 100 0 Feeder 3 Feeder 4 Figure 3.1: Outage duration and failure occurrence of each feeder. Table 3.1: Radial system reliability indices for each feeder Substation Outage Frequency Failure rate λ Annual outage Feeders duration (hrs) (occurrence) (Failures/year) duration U (hrs/yr) Feeder 3 648.788044 693.6 0.0855112656 55.478687 Feeder 4 543.820001 445.2 0.0541857652 29.467303 In the normal conditions of the circuit, there are no disconnects on the main line. The only protections are the fuses that connect the main feeders and the lateral distributors. Hence, any fault on the main line will require the system to be isolated from the main breaker. The reliability assessment of each feeder can be calculated by considering the impact of each section and load point on the corresponding load point. Let us to examine the reliability assessment of each feeder.
  • 9. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 35 First, the impact of each section failure on the load point’s reliability is considered. Any section failure will result in power outage for load point since there are no disconnects on the main distribution lines. Then the outage duration r (hours) of each feeder is assessed. Using the failure occurrences of the feeder, its failure rate λ (f/yr) is determined. Using the failure rate and repair time, the annual outage duration U (hrs/yr) for each feeder is obtained. Secondly, the impact of each lateral distributor’s failure on the load point is considered. Since, each lateral is connected to the main feeder through fuse; a fault on any lateral will be introducing impact on the other load point. If there is a fault on the load point, the power from the main feeder is shutdown to repair the fault; its reliability impact will be added to the system. Adding the impact of each section and lateral distributor, the average failure rate, average outage duration, and annual outage duration for the main feeders can be calculated as by using equation (9), (10) and (11). λs  λi (9) i Us  λi ri (10) rs  Us (11) λs From the above equations the other parameters of each feeder were calculated as shown in the Table 3.2. Table 3.2: The main feeder availability and unavailability indices S/Station Ni 648.788 λi ∗ Ni U i ASAI (%) ASUI (%) feeder ri * N i Feeder 3 6541 0.085511 559.3294 362886.092 92.594 7.4063 Feeder 4 4129 0.054186 543.82 223.7332 121670.494 93.792 6.208 Total 10670 93.193 6.807 The costumer load point indices are calculated, related to the unsupplied energy and costs. Those are the expected Energy Not Supplied (EENS), the Expected interruption Cost (EIC) and the Average Energy Not Supplied values are shown in Table 3.3. The priority order based on the EIC was used for load curtailment level; the EIC is the average monetary impact on the customers at a load point. This higher the EIC the higher priority this load may have, because a load curtailment at that load point will contribute to higher economic cost. Table 3.3: Expected Energy not supplied and Interruption Costs indices for each feeder. Substation Expected Energy not Expected Interruption Average Energy Not Feeders supplied (MW hr/yr) Cost EIC (m$ /yr) Supplied (KW hr/yr. ca.) Feeder 3 1843.73952 1.58043808 281.87426 Feeder 4 1175.52185 1.00764752 284.69892 Total 3019.26137 2.58808558 283.28659
  • 10. Reliability Assesment Of Debremarkos Distribution System Found In Ethiopia Manuscript id. 626565888 www.ijstre.com Page 36 From the above table each index of the main feeder provides different information and some indices are more important than others. The main feeder indices are useful in assessing the load point impact of system modifications and provide input to reliability evaluation at the actual customer level. Furthermore, there are the system reliability indices which provide valuable information on the overall ability of the system to supply the customer load. The probability of a customer receiving uninterrupted power supply can be accessed from the indices of Table 3.2 and Table 3.3. The higher the value of the reliability indices the higher is the unreliability at the corresponding bus. Using the data from the above table, the overall base case reliability indices can be calculated as shown in Table 3.4: Table 3.4: DIgSILent Simulation Result of Overall System Indices Values. 4. CONCLUSION The result of the study concluded that the base case system indices; SAIDI is 597.476 hr/customer year suggesting that system’s average interruption duration for each customer is 597.476hr during a year, SAIFI is 608.168 inter./customer year suggesting that system’s average interruption frequency for each customer is 608.168 during a year, CAIDI is 0.982 hrs/ customer interruption, suggesting system’s average interruption duration for the customers that experience interruption is 0.982 hrs during a year and system availability and unavailability are 93.193% and 6.803% are respectively . Also, the expected energy not supplied (EENS) for the base case system due to the failures is 2933.692MWh/yr and the energy not supplied per customer is 168.9396kWh/yr. And finally, the expected interruption cost is 1.5333764millions $/yr during a year. The system reliability indices show that Debre Markos distribution system is unreliable distribution system. REFERENCES [1]. A. Von Meier, Electric Power Systems. Wiley Online Library [2]. R. Billinton and J. E. Billinton, ‘Distribution System Reliability Indices’, IEEE Trans. Power Delivery, Vol.4, No.1, Jan. 1989, pp. 561-568. [3]. Y. Kumar, B. Das, and J. Sharma. Multi-objective, multi-constraint service restoration of electric power distribution system with priority customers. IEEE Trans. Power Delivery, 23(1):261-270, Jan 2008. [4]. D. Zhu, R.P. Broadwater, K.-S. Tam, R.Seguim, and H. Asgeirsson. Impact of DG placement on reliability an Trans. Power Systems, 21:419-427, Feb 2006. [5]. Y. M. Atwa and E. F. EI-Saadany. Reliability evaluation for distribution system with renewable DG during islanded mode of operation. IEEE Tans. Power Systems, 24:572-581, May 2009. [6]. W. Peng and R. Billinton. Reliability benefits analysis of adding WTG to a distribution system. IEEE Trans. Energy Conversion, 16(2):134-139, Jun 2001.