SlideShare a Scribd company logo
1 of 77
GUIDE TO OVERALL
OVERHEAD LINE DESIGN
• AC LINE DESIGN
• ELECTRICAL CHARACTERISTICS
• MECHANICAL CHARACTERISTICS
• THERMAL RATING
• PLANNERS REQUIREMENTS
• OBJECTIVE INDICATOR
• DC LINE DESIGN
• ELECTRICAL CHARACTERISTICS
• OBJECTIVE INDICATOR
• COST OF LINES
• EXAMPLES OF OPTIMISATION
Table of contents
GUIDE TO OVERALL
OVERHEAD LINE
DESIGN
GUIDE TO OVERHEAD OHL DESIGN TB 638
AC LINE DESIGN
AC LINE DESIGN
GUIDE TO OVERHEAD OHL DESIGN TB 638
ELECTRICAL CHARACTERISTICS
What is a power line?
• A device to transmit power over distances.
• Design of the line can be tailor made to meet planner’s requirements.
• Load flow depends on R, X and B values.
5
LINE MODEL
• Reduce R and L (resistance and inductance)
• Increase C (capacitance)
6
Maximise Power Transfer
• Zs is surge impedance
• SIL is the surge impedance loading
• Reduce L and increase C to maximise transfer
L is series
inductance
C is shunt
capacitance
7
VLL is phase to phase
voltage
Determination of R, X and B
8
• Resistance is a function of
− Conductor construction material and line length
o Lay ratio, ACSR,AAAC, number of layers, diameter of strands.
− Temperature
o The higher the temperature the higher the resistance
− Current and frequency
o Transformer effect
o Eddy currents.
Variation with current
Penguin(1+6)
Tcond=80°C
1.04
1.02
1.00
1.14
1.12
1.10
1.08
1.06
0 100 200 300 400 500 600 700 800
I(A)
Rac/Rdc
Falcon(19+54)
Tcond=80°C
1.02
1.00
1.10
1.08
1.06
1.04
0 1000 2000 3000 4000 5000 6000 7000 8000 I(A)
Rac/Rd
c
107 mm2
9
800 mm2
Determination of L
10
• L is a function of Geometric mean radius (GMR) and Geometric mean Distance
(GMD)
• Larger bundle radius and closer phase spacing gives lower L
Determination of C
11
• To increase capacitance
keep phases closer together.
Summary
12
• SIL (L and C) can be varied by
− varying phase spacing closer is better
− Increasing bundle size larger is better
• Resistance can be improved by
− Varying lay ratios per layer (not practical)
− Different materials
− Homogeneous conductors
Corona limitations
13
• Corona can produce audible noise under certain weather conditions. This is very
difficult to mitigate. It is desirable to avoid corona inception.
− Smaller bundle radius will reduce corona up to a point.
− Wider phase spacing better
− More sub conductor bundles better.
AC LINE DESIGN
MECHANICAL CHARACTERISTICS
GUIDE TO OVERHEAD OHL DESIGN TB 638
Mechanical considerations
• Wind load is major consideration in tower design
− Less conductors in the bundle the better
− Less ultimate tensile strength (UTS) the better (Lighter strain towers). Higher
tension to increase height.
• Vibration is a function of tension
− Need to design to the recommended T/m ratio
− Small bundle sizes (twin triple), need more care in vibration damping design
• Galloping mitigation needs to be taken into account
− Includes phase configuration
− Pendulum dampers, interphase spacers
15
Tower top Geometry
• Tower top geometry design applies to conventional towers with metal surrounded
center phase (tower window) as well as three phases in the same window as is
the case with the cross rope suspension.
• The interaction between the phases as well as the shielding angle for the
conductors needs to be carefully designed to ensure optimal insulation co-
ordination providing the required level of reliability.
AC LINE DESIGN
THERMAL RATING
GUIDE TO OVERHEAD OHL DESIGN TB 638
Thermal loading
• Load at which the safety or annealing criteria of the line is met
− Current at which the height above the ground is in line with regulation
− Height determined by voltage and flashover distance
• Heat Balance equation used.
18
Joule and magnetic heating
• Joule dependent on AC resistance and temperature
• Magnetic heating dependent on current and conductor layers.
19
Solar heating
• Darkness of conductor
• Diameter of conductor
• Solar radiation
20
Convective cooling
21
• Dependent on
− the conductor diameter (bigger is better)
− Wind speed
− Temperature difference (bigger is better)
− Roughness
Templating temperature
22
• Templating temperature is the conductor temperature at which the height above
ground is in accordance with regulation
Conductor
Templating
temperature deg C
Normal
Amps
Emergency
Amps
TERN 50 611 814
TERN 60 784 991
TERN 70 911 1138
TERN 80 1023 1257
ZEBRA 50 642 859
ZEBRA 60 818 1049
ZEBRA 70 963 1203
ZEBRA 80 1080 1325
SUMMARY
SIL Corona Mechanical
loading
Thermal
rating
Phase spacing
decrease
Good Bad Good Neutral
Large al
area/cond (less
conductors)
Bad Bad Good Bad
Diameter
Bundle
increase
Good Bad Bad Neutral
High steel
content
Neutral Neutral Bad Good
23
AC LINE DESIGN
PLANNING REQUIREMENTS
GUIDE TO OVERHEAD OHL DESIGN TB 638
Planning requirements
25
• Planners need to specify the following
− Load transfer requirements
− Load profile daily, annual
− Impedance parameters, high and low
− Line Voltage for AC
− Length of line
− Location, start and end points
− Reliability requirements
Conductor size and temp
26
Conductor type
27
TACSR (Thermal resistant)
XTACSIR (Thermal resistant with
invar core)
GTACSR (Thermal resistant
aluminium with gapped core)
ACSS (Steel supported)
Selection of conductor
28
INSULATOR SELECTION
• Location of conductor bundle determined to meet insulation co-ordination
requirements
• Insulator creepage, dry arching distance, basic insulation level (BIL) determined.
− Depends on pollution levels in the line route
• Insulator configuration depends on tower selection, I or V or other.
• Material depends on pollution, vandalism, maintenance.
• Hardware depends on material (corona rings for composite), live line
requirements
• For cross rope towers I string permits less pollution accretion especially from
birds.
LIGHTNING CONSIDERATIONS
• Shield angle determination depends on tower type.
− Negative shield angles generally give better performance.
• Tower footing resistance needs to be determined and reduced on the line
− “crows foot”, buried earthwire, bentonite mix
• Note towers with large footprints generally give lower tower footing resistances.
− Cross rope suspensions provide excellent results
• If tower footing resistance still high may consider line surge arresters installed on
certain towers.
• Shield or earth wires are now often OPGW.
− Care to be taken for fault current in the earth wire.
AC LINE DESIGN
OBJECTIVE INDICATOR
GUIDE TO OVERHEAD OHL DESIGN TB 638
Indicator to determine best design
32
• Need to combine
− SIL
− Thermal rating
− Cost initial and life cycle
o (Taking into account corona, magnetic fields, mech loading etc)
FACTOR 1 Life Cycle Cost (k1)
33
• Covers determination of optimum aluminium area required. (Kelvin’s law)
• Cost of maintenance (estimate)
• Cost of losses – use system losses not line losses. (Due to power flow in
interconnected system)
FACTOR 2 THERMAL (k2)
34
• Cost is directly proportional to Thermal rating
− Higher rating higher initial cost
• A ratio is therefore needed
− Initial cost/MVA thermal (emergency or normal)
• The lower the ratio the better.
FACTOR 3 SIL (k3)
35
• The higher the SIL the higher the initial cost (normally)
• Ratio is therefore also required
− Initial cost/MVAsil
COMBINATION OF THE FACTORS
36
• Objective Matrix method
− Present practice is given 3/10
− 0 or 10 level is determined (normally trial and error) and a linear
interpolation used.
• ATI = w1k1+w2k2+w3k3
− wn are weighting factors
DETERMINING SCORE – NEG SLOPE
Ratio value
S
c
o
r
e
Ratio of current practice
Provides score of 3
3
10
(x1;y1)
(x2;y2)
Assume ratio
value that is ideal.
Score of ideal ratio is 10
Ratio of optionA
Score of
optionA
Y=mx+c
1. For the ratio (LCC, IC/MVA etc),
allocate a score of 3 for the
current practice. This gives point
x1;y1.
2. Assume an ideal ratio that will not
be exceeded. Allocate a score of
10 for this ratio value. This will
provide point x2; y2.
3. Calculate the straight line
equation using these two points.
4. Use the straight line equation to
determine the scores for the
different design options.
5. You now have dimensionless
scores which can be added.
CALCULATION OF SCORE FOR
SITUATIONS WHERE THE LOWER
THE RATIO THE BETTER THE
DESIGN
DETERMINING SCORE – POSITIVE SLOPE
Ratio value
S
c
o
r
e 3
10
x1;y1
x2;y2
y=mx+c
Ratio value of current practice
allocated score of 3
Ratio value of ideal design.
Allocated score of 10
Ratio value of optionA
Score of
optionA
1. Calculate the ratio of the current
design option. Allocate it a score of 3
2. Assume an ideal design value and
allocate it a score of 10
3. This provides two points. Calculate
the straight line (y=mx+c) graph
equation from points x1;y1 and x2;y2
4. Using the equation determine the
scores for the other design options.
5. This provides a dimensionless score
which can be added.
CALCULATION OF SCORES WHERE
THE HIGHER THE RATIO THE
BETTER THE DESIGN
CONDUCTOR SELECTION
CONDUCTOR OPTIMISATION
0.00
100.00
200.00
300.00
400.00
500.00
900.00
800.00
700.00
600.00
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400
Pmean(MVA)
LCC(Rmil)
2 X IEC800
4 X KINGBIRD
3 X BERSFORT
3 X TERN
3 X YEW
4 X TERN3 x Bersfort
39
4 x Tern
4 x Kingbird
3 x Tern
TOWER SELECTION
40
EXAMPLE LINE
41
− Quad “Zebra” guyed Vee tower
− Triple “Bunting” conductor guyed Vee tower
− Quad “Bunting” cross rope suspension (CRS) tower phase spacing of 6,5m.
− Quad “Rail” conductor with a CRS tower with a 6,5m phase spacing.
− Triple “Bittern” conductor with a CRS tower with a 6,5m phase spacing.
− Quad “Boblink” conductor with a CRS tower with a 6,5m phase spacing.
− Triple “Bersfort” conductor with a CRS tower with a 8,2m phase spacing.
ATI SCORES
42
CASE AL AREA
mm2
DESCRIPTION K1 (LCC) K2
(CI/MVAth)
K3
(CI/MVAsil)
1 1715 4XZEB V 103,53
[3,30]
28,13
[3,07]
7,43
[3,19]
2 1817 3XBUNT V 84,4
[6,25]
19.48
[5,20]
6,31
[5,38]
3 2423 4XBUNT
CRS 6.5m
88,36
[5,64]
13.27
[6,73]
7,02
[3,96]
4 1935 4XRAIL
CRS 6.5m
87,76
[5,73]
14.32
[6,47]
5,94
[6,12]
5 1933 3xBIT
CRS 6.5m
82,91
[6,48]
17.86
[5,60]
6,31
[5,38]
6 2901 4Xbob CRS
6.5m
93,33
[4,87]
17.04
[5,80
8,06
[1,88]
7 2059 3xBers CRS
8.2m
80,41
[6,81]
16.23
[6,00]
6,30
[5,40]
ATI WEIGHTING
43
CASE W1;W2;W3 W1;W2;W3 W1;W2;W3 W1;W2;W3
0,8;0,1;0,1 0,6;0,2;0,2 0,4;0,3;0,3 0,2;0,4;0,4
1 2,82 [7] 2,89 [7] 2,96 [7] 3,03 [7]
2 5,80 [3] 5,67 [4] 5,55 [4] 5,42 [4]
3 5,23 [5] 5,18 [5] 5,14 [5] 5,09 [5]
4 5,56 [4] 5,74 [3] 5,93 [2] 6,11 [1]
5 6,04 [2] 5,90 [2] 5,77 [3] 5,63 [3]
6 4,33 [6] 4,21 [6] 4,08 [6] 3,96 [6]
7 6,42 [1] 6,24 [1] 6,06 [1] 5,88 [2]
FINDINGS/BENEFITS
44
• Tower, foundation, hardware, electrical designers work together with planners
(iterative process)
• Indicator very sensitive and detects errors rapidly
• Line optimisation is possible looking at overall line design.
• Reliability is assumed constant for options
• Cost system is critical
• Most aspects of the line design are taken into account
CONCLUSIONS
45
• Line design options can be objectively determined
• ATI is a guide from which options can be finalised.
• Alignment with Planners requirements
GUIDE TO OVERALL
LINE DESIGN
GUIDE TO OVERHEAD OHL DESIGN TB 638
DC LINE DESIGN
DC LINE DESIGN
GUIDE TO OVERHEAD OHL DESIGN TB 638
ELECTRICAL CHARACTERISTICS
Power Transfer
x
Pmax
V 2
 vd%
100R L
where vd% is the voltage drop expressed as a % of V,
and the equation applies for both 10% and 15% volt drop. {1/sqrt(44) is an approximation of 15/100} and the format
removes the generality of the basic and simple equation.
V=Sending end voltage, pole to ground in kV
Rx=DC Resistance of the conductor in ohm/km
L=Distance in kilometres.
DC resistance
• DC resistance not dependent on current
• Dependent on conductor geometry and conductivity of material.
• Dependent on temperature.
Effect of conductor radius (TB388)
The higher the conductor diameter and the more sub-conductors in the bundle the more resistant the bundle is to
corona and therefore the designer is more able to raise the voltage to ground and hence increase the power capability
of the line.
Corona power loss
    





 225 3 3.05
 20log
 25 
 15log n  10log HS dE
P  11 40log mas
Where P is the corona loss is dB above 1 W/m, Emax is the positive polarity maximum bundle gradient in kV/cm, d is the
sub-conductor diameter in cm, n is the number of sub-conductors in the bundle, H is the average conductor height in m
and S is the pole spacing in m.
INSULATOR CONSIDERATIONS
• Similar requirements to AC as far as tower window design.
• For glass insulators need germanium glass as normal glass will shatter
− Zinc collar also required
• Creepage larger than for AC
• Space charge considerations as well as uneven pollution on insulator to be
taken into account.
• Composite insulators can be used for AC and DC lighter weight often suit
long insulator installation.
• Porcelain disc are also successfully used.
Summary of options
Action Parameter Voltage drop Corona Mechanical loading Thermal rating
+ and - pole spacing
decrease
Neutral Bad Good Neutral
Large Al area/cond (less
conductors)
Good Bad Good Bad
Diameter bundle
increase
Neutral Bad Bad Neutral
High steel content Neutral Neutral Bad Good
Voltage selection (TB 388)
DC LINE DESIGN
OBJECTIVE INDICATOR
GUIDE TO OVERHEAD OHL DESIGN TB 638
Optimisation process
• Select voltage (TB388)
• Determine range of conductor, bundle diameter and number of sub-conductors as
well as height above ground and pole spacings that will meet corona limitations
and power flow.
• Determine range of tower, foundation and conductor configurations.
• Finalise by further analysis the most suitable tower, foundation, conductor bundle
option. Recheck with power flow requirements, converter cost and technology.
Objective indicator
th
IC
3
MVA
ATIDC  w1LCC  w2IC* Posscoronal  w
ATIdc Appropriate Technology Index for DC lines
LCC is the life cycle cost expressed in terms of a score from 1 to 10 and IC is the initial cost.
Plosscorona is the power loss due tocorona.
IC is the initial cost.
MVAthermal is the thermal rating of the line and depends, as in the AC case, to the templating temperature of theline.
Line requirements
• DC voltage (V) 600;700;800 kV
• Number of sub-conductors per pole (N) 4; 5; 6
• Conductor type ACSR
• Line length 1750 km
• Transmitted Power 3000 MW (bipolar)
• Cost of the losses 60 U$/MWh; loss factor =0,5
• Life= 30 years; yearly interest rate= 10%
• Interest during construction 10%; maintenance 2% per year (of initial cost)
Alternate designs
Scores
ATIdc weighted scores
GUIDE TO OVERALL
LINE DESIGN
COST OF LINES
GUIDE TO OVERHEAD OHL DESIGN TB 638
Purpose
• The purpose of the questionnaire was to compare the work done by WG09
in 1990 to the latest figures as many component costs may have changed.
• The questionnaire was in two parts, the first to compare component costs
of existing projects, the second to compare costs of an actual line with
given parameters.
• The response was generally poor with around 13 respondents compared
with over 100 in 1990.
North America
Europe
Africa
Asia
Cost per km comparison
Competitive line costs
• From the graphs, if the conductor cost as a percentage of total line cost is greater
than 10% the cost is likely to be relatively low. The range of percentages in the
examples received indicated that the conductor cost for relatively low cost per km
lines, should vary between 10 and 15%.
• In the previous survey it was found that the conductor cost was 32% of the
material cost which was 63%. This results in 20% of the total line cost. It could
be concluded that the cost/km of lines has increased from 1990 to 2014 in real
terms mainly due to cost of labour and environmental issues.
• A good target for a competitive cost per km line would be that the conductor cost
should be between 15 and 20% in 2014.
COMPARISON TO 1991
YEAR
MATERIAL
COSTS
CONSTRUCTION
COSTS
CONDUCTORS SHIELD WIRE INSULATORS TOWERS FOUNDATIONS
For all lines and voltages 1991 63.7 36.3 32.7 3.8 8.1 36.2 19.2
2013 42.4 57.6 31.8 2.7 7.6 46.3 11.6
For all lines up to 150kV 1991 64.3 35.7 31.6 4.1 8.8 36.0 19.5
2013 46.4 53.6 28.6 2.0 7.9 49.6 11.9
For all lines over300kV 1991 62.6 37.4 34.1 3.9 6.9 36.4 18.7
2013 46.8 53.2 35.7 3.0 7.2 42.7 11.4
All single circuit lines 1991 63.6 36.4 33.1 4.2 8.2 35.6 18.8
2013 42.8 57.2 33.4 2.8 6.9 43.7 13.3
All double circuit lines 1991 63.8 36.2 32.0 3.3 7.9 37.1 19.7
2013 31.0 69.0 24.7 2.3 10.6 58.1 4.3
Guyed structure lines 1991 59.6 40.4 32.8 3.2 8.3 36.0 19.8
2013 55.0 45.0 36.5 3.2 6.3 41.3 12.7
Lines with 1 conductor/phase 1991 64.4 35.6 32.2 4.2 8.5 36.3 18.8
2013 38.7 61.3 28.3 2.0 7.8 45.1 16.9
Lines with 2 conductors/phase 1991 64.6 35.4 32.3 4.0 8.1 36.2 19.4
2013 38.0 62.0 32.3 2.3 10.6 48.4 6.3
Lines with 3 conductors/phase 1991 60.8 39.2 35.1 3.7 7.0 40.3 13.8
2013 41.5 58.5 36.6 4.6 6.6 42.6 9.6
Lines with 4 conductors/phase 1991 61.4 38.6 33.4 2.7 7.6 33.4 22.9
2013 56.5 43.5 34.2 3.4 7.9 37.9 16.7
Conductor, shield wire etc % as a function of material costs.
Percentage comparisons with 1991
YEAR
MATERIAL
COSTS
CONSTRUCTION
COSTS
COND
SHIELD
WIRE
INSUL TOWERS FNDN
For all lines and
voltages 1991 63.7 36.3 32.7 3.8 8.1 36.2 19.2
2013 42.4 57.6 31.8 2.7 7.6 46.3 11.6
For all lines up to
150kV 1991 64.3 35.7 31.6 4.1 8.8 36.0 19.5
2013 46.4 53.6 28.6 2.0 7.9 49.6 11.9
For all lines over
300kV 1991 62.6 37.4 34.1 3.9 6.9 36.4 18.7
2013 46.8 53.2 35.7 3.0 7.2 42.7 11.4
All single circuit
lines 1991 63.6 36.4 33.1 4.2 8.2 35.6 18.8
2013 42.8 57.2 33.4 2.8 6.9 43.7 13.3
All double circuit
lines 1991 63.8 36.2 32.0 3.3 7.9 37.1 19.7
2013 31.0 69.0 24.7 2.3 10.6 58.1 4.3
Guyed structure
lines 1991 59.6 40.4 32.8 3.2 8.3 36.0 19.8
2013 55.0 45.0 36.5 3.2 6.3 41.3 12.7
Lines with 1
conductor/phase 1991 64.4 35.6 32.2 4.2 8.5 36.3 18.8
2013 38.7 61.3 28.3 2.0 7.8 45.1 16.9
Lines with 2
conductors/phase 1991 64.6 35.4 32.3 4.0 8.1 36.2 19.4
2013 38.0 62.0 32.3 2.3 10.6 48.4 6.3
Lines with 3
conductors/phase 1991 60.8 39.2 35.1 3.7 7.0 40.3 13.8
2013 41.5 58.5 36.6 4.6 6.6 42.6 9.6
Lines with 4
conductors/phase 1991 61.4 38.6 33.4 2.7 7.6 33.4 22.9
2013 56.5 43.5 34.2 3.4 7.9 37.9 16.7
Summary of Trends
• Material and construction costs – the trend appears to be that the material cost has reduced as a function of
total cost with the construction cost being the more prevalent cost. This appears to be the case over the entire
range of lines investigated.
• Conductors – in the 2013 cases the steel shield wire is included in the conductor cost. Even with this inclusion,
it appears the conductor cost is generally the same or lower percentage of the total cost as compared to 1991.
• Shield wire – this cost is related to the OPGW cost for 2013 and the steel wire cost for 1991. The sample for
double circuit and single circuit lines for 2013 is very small and therefore cannot be considered to be
representative. However it indicates a similar percentage to the 1991 costs even though the shield wire is more
complicated and expensive in real terms in 2013.
• Insulators – the percentage of total cost spent on insulators seem to be slightly lower than in 1991. This could
be due to the advent of composite insulators which have dropped in price considerably over the years as well as
glass being more competitive with merger of manufacturers.
• Towers – The percentage of the total cost spent on towers seem to be higher than in 1991. This cost includes
the erection cost which could indicate the higher cost of labour which is reflected in the construction cost
compared to material cost. As mentioned previously the environmental constraints on current lines could have
resulted in more angle or strain towers as well as more aesthetically pleasing towers such as the Wintrack
towers.
• Foundations – The percentage of the total cost spent on foundations seems to be lower than is 1991.
This may be due to the higher level of mechanisation and perhaps use of more pile foundations
but this is not confirmed.
GUIDE TO OVERALL
LINE DESIGN
EXAMPLES OF OPTIMISATION
GUIDE TO OVERHEAD OHL DESIGN TB 638
Tower development
Proposed CRS 6%
saving on line cost
74
Existing guyed V
Cost Savings
750-15 degree structures 15-30 degree structures
R0
R75,000
R150,000
R225,000
R300,000
R450,000
R375,000
Misc Costs
Insulation
Hardware
Tower Erection
Tower Supply
Foundations
52%
Saving
46%
Saving
705A tower at NETFA
76
REFERENCES/
ACKNOWLEDGEMENTS
77
[Stephen 2004] Stephen R. “Use of indicators to optimise design of overhead transmission lines”. Paper330-1
Shanghai Symposium, Cigré 2003. (Held in Lubljana April 4-62004)
[Stephen 2011] Stephen R “Objective detetermination of Optimal power line designs” PhD thesis submitted in 2011
University of Cape Town.
[Muftic]. Muftic D, Bisnath S, Britten A, Cretchley DH, Pillay T,Vajeth R “The Planning design and constructionof
overhead power lines” Published by Crown publications 2005 ISBN 9780620330428
[Southwire] Overhead Conductor Manual First edition copyright1994.
Prof. C.T.Gaunt (UCT) acknowledged for comments andinput.
J. Lindquist AC/DC conversion TB583
Nolasco, Jardini, TB 388

More Related Content

What's hot

Power cables
Power cablesPower cables
Power cablescollege
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scadaHemendra Kumar Rajput
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical powerpriyanka1432
 
UNDERGROUND CABLES PRESENTATION
UNDERGROUND CABLES  PRESENTATIONUNDERGROUND CABLES  PRESENTATION
UNDERGROUND CABLES PRESENTATIONPANKAJ KUMAR
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxJeffrey Dorsey
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...Thorne & Derrick International
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculationsPankaj Chavan
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationsharique_64
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable SelectionLeonardo ENERGY
 
Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chartvishalgohel12195
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmissionSumit Kumar
 

What's hot (20)

Power cables
Power cablesPower cables
Power cables
 
Underground cables (1)
Underground cables  (1)Underground cables  (1)
Underground cables (1)
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scada
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
 
Circuit breakers
Circuit breakers Circuit breakers
Circuit breakers
 
UNDERGROUND CABLES PRESENTATION
UNDERGROUND CABLES  PRESENTATIONUNDERGROUND CABLES  PRESENTATION
UNDERGROUND CABLES PRESENTATION
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docx
 
Underground cable
Underground cableUnderground cable
Underground cable
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
 
INSULATORS & TYPES
INSULATORS & TYPES INSULATORS & TYPES
INSULATORS & TYPES
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
 
Ehv substation
Ehv substationEhv substation
Ehv substation
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable Selection
 
Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chart
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
Sag and tension
Sag and tensionSag and tension
Sag and tension
 
INSULATORS AND ITS TYPES
INSULATORS AND ITS TYPESINSULATORS AND ITS TYPES
INSULATORS AND ITS TYPES
 

Similar to Guide to Optimizing Overhead Power Line Design

Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology wessam alaslmi
 
Design_of_Power_Transformers.ppt
Design_of_Power_Transformers.pptDesign_of_Power_Transformers.ppt
Design_of_Power_Transformers.pptSelvaPriyaAEEE2020
 
Transformer design-and-design-parameters
Transformer design-and-design-parametersTransformer design-and-design-parameters
Transformer design-and-design-parametersMubarak Suliman
 
Getting the Most out of your Electrical Room
Getting the Most out of your Electrical RoomGetting the Most out of your Electrical Room
Getting the Most out of your Electrical Roommichaeljmack
 
Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission linesShivagee Raj
 
IRJET- Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...
IRJET-  	  Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...IRJET-  	  Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...
IRJET- Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...IRJET Journal
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 
strain insulator must have considerable mechanical strength as well as the ne...
strain insulator must have considerable mechanical strength as well as the ne...strain insulator must have considerable mechanical strength as well as the ne...
strain insulator must have considerable mechanical strength as well as the ne...Karthikkumar Shanmugam
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.pptssuserc3b807
 
Presentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformerPresentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformerSMDDTech
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission linesfiraoltemesgen1
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing Praveen Sharma
 
wireless charging of an electrical vechicle 2
wireless charging of an electrical vechicle 2wireless charging of an electrical vechicle 2
wireless charging of an electrical vechicle 2hari prasad
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisPower System Operation
 
Lecture24 clockpower routing
Lecture24 clockpower routingLecture24 clockpower routing
Lecture24 clockpower routingfreeloadtailieu
 

Similar to Guide to Optimizing Overhead Power Line Design (20)

Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology
 
Design_of_Power_Transformers.ppt
Design_of_Power_Transformers.pptDesign_of_Power_Transformers.ppt
Design_of_Power_Transformers.ppt
 
Transformer design-and-design-parameters
Transformer design-and-design-parametersTransformer design-and-design-parameters
Transformer design-and-design-parameters
 
Getting the Most out of your Electrical Room
Getting the Most out of your Electrical RoomGetting the Most out of your Electrical Room
Getting the Most out of your Electrical Room
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission lines
 
IRJET- Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...
IRJET-  	  Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...IRJET-  	  Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...
IRJET- Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
Cabos_5.1.pdf
Cabos_5.1.pdfCabos_5.1.pdf
Cabos_5.1.pdf
 
strain insulator must have considerable mechanical strength as well as the ne...
strain insulator must have considerable mechanical strength as well as the ne...strain insulator must have considerable mechanical strength as well as the ne...
strain insulator must have considerable mechanical strength as well as the ne...
 
Dc voltage
Dc voltageDc voltage
Dc voltage
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.ppt
 
Presentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformerPresentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformer
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 
wireless charging of an electrical vechicle 2
wireless charging of an electrical vechicle 2wireless charging of an electrical vechicle 2
wireless charging of an electrical vechicle 2
 
1228808532(2)
1228808532(2)1228808532(2)
1228808532(2)
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash Analysis
 
Lecture24 clockpower routing
Lecture24 clockpower routingLecture24 clockpower routing
Lecture24 clockpower routing
 

More from Power System Operation

Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panelsPower System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsPower System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemePower System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePower System Operation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & PartsPower System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Recently uploaded

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Guide to Optimizing Overhead Power Line Design

  • 2. • AC LINE DESIGN • ELECTRICAL CHARACTERISTICS • MECHANICAL CHARACTERISTICS • THERMAL RATING • PLANNERS REQUIREMENTS • OBJECTIVE INDICATOR • DC LINE DESIGN • ELECTRICAL CHARACTERISTICS • OBJECTIVE INDICATOR • COST OF LINES • EXAMPLES OF OPTIMISATION Table of contents
  • 3. GUIDE TO OVERALL OVERHEAD LINE DESIGN GUIDE TO OVERHEAD OHL DESIGN TB 638 AC LINE DESIGN
  • 4. AC LINE DESIGN GUIDE TO OVERHEAD OHL DESIGN TB 638 ELECTRICAL CHARACTERISTICS
  • 5. What is a power line? • A device to transmit power over distances. • Design of the line can be tailor made to meet planner’s requirements. • Load flow depends on R, X and B values. 5
  • 6. LINE MODEL • Reduce R and L (resistance and inductance) • Increase C (capacitance) 6
  • 7. Maximise Power Transfer • Zs is surge impedance • SIL is the surge impedance loading • Reduce L and increase C to maximise transfer L is series inductance C is shunt capacitance 7 VLL is phase to phase voltage
  • 8. Determination of R, X and B 8 • Resistance is a function of − Conductor construction material and line length o Lay ratio, ACSR,AAAC, number of layers, diameter of strands. − Temperature o The higher the temperature the higher the resistance − Current and frequency o Transformer effect o Eddy currents.
  • 9. Variation with current Penguin(1+6) Tcond=80°C 1.04 1.02 1.00 1.14 1.12 1.10 1.08 1.06 0 100 200 300 400 500 600 700 800 I(A) Rac/Rdc Falcon(19+54) Tcond=80°C 1.02 1.00 1.10 1.08 1.06 1.04 0 1000 2000 3000 4000 5000 6000 7000 8000 I(A) Rac/Rd c 107 mm2 9 800 mm2
  • 10. Determination of L 10 • L is a function of Geometric mean radius (GMR) and Geometric mean Distance (GMD) • Larger bundle radius and closer phase spacing gives lower L
  • 11. Determination of C 11 • To increase capacitance keep phases closer together.
  • 12. Summary 12 • SIL (L and C) can be varied by − varying phase spacing closer is better − Increasing bundle size larger is better • Resistance can be improved by − Varying lay ratios per layer (not practical) − Different materials − Homogeneous conductors
  • 13. Corona limitations 13 • Corona can produce audible noise under certain weather conditions. This is very difficult to mitigate. It is desirable to avoid corona inception. − Smaller bundle radius will reduce corona up to a point. − Wider phase spacing better − More sub conductor bundles better.
  • 14. AC LINE DESIGN MECHANICAL CHARACTERISTICS GUIDE TO OVERHEAD OHL DESIGN TB 638
  • 15. Mechanical considerations • Wind load is major consideration in tower design − Less conductors in the bundle the better − Less ultimate tensile strength (UTS) the better (Lighter strain towers). Higher tension to increase height. • Vibration is a function of tension − Need to design to the recommended T/m ratio − Small bundle sizes (twin triple), need more care in vibration damping design • Galloping mitigation needs to be taken into account − Includes phase configuration − Pendulum dampers, interphase spacers 15
  • 16. Tower top Geometry • Tower top geometry design applies to conventional towers with metal surrounded center phase (tower window) as well as three phases in the same window as is the case with the cross rope suspension. • The interaction between the phases as well as the shielding angle for the conductors needs to be carefully designed to ensure optimal insulation co- ordination providing the required level of reliability.
  • 17. AC LINE DESIGN THERMAL RATING GUIDE TO OVERHEAD OHL DESIGN TB 638
  • 18. Thermal loading • Load at which the safety or annealing criteria of the line is met − Current at which the height above the ground is in line with regulation − Height determined by voltage and flashover distance • Heat Balance equation used. 18
  • 19. Joule and magnetic heating • Joule dependent on AC resistance and temperature • Magnetic heating dependent on current and conductor layers. 19
  • 20. Solar heating • Darkness of conductor • Diameter of conductor • Solar radiation 20
  • 21. Convective cooling 21 • Dependent on − the conductor diameter (bigger is better) − Wind speed − Temperature difference (bigger is better) − Roughness
  • 22. Templating temperature 22 • Templating temperature is the conductor temperature at which the height above ground is in accordance with regulation Conductor Templating temperature deg C Normal Amps Emergency Amps TERN 50 611 814 TERN 60 784 991 TERN 70 911 1138 TERN 80 1023 1257 ZEBRA 50 642 859 ZEBRA 60 818 1049 ZEBRA 70 963 1203 ZEBRA 80 1080 1325
  • 23. SUMMARY SIL Corona Mechanical loading Thermal rating Phase spacing decrease Good Bad Good Neutral Large al area/cond (less conductors) Bad Bad Good Bad Diameter Bundle increase Good Bad Bad Neutral High steel content Neutral Neutral Bad Good 23
  • 24. AC LINE DESIGN PLANNING REQUIREMENTS GUIDE TO OVERHEAD OHL DESIGN TB 638
  • 25. Planning requirements 25 • Planners need to specify the following − Load transfer requirements − Load profile daily, annual − Impedance parameters, high and low − Line Voltage for AC − Length of line − Location, start and end points − Reliability requirements
  • 27. Conductor type 27 TACSR (Thermal resistant) XTACSIR (Thermal resistant with invar core) GTACSR (Thermal resistant aluminium with gapped core) ACSS (Steel supported)
  • 29. INSULATOR SELECTION • Location of conductor bundle determined to meet insulation co-ordination requirements • Insulator creepage, dry arching distance, basic insulation level (BIL) determined. − Depends on pollution levels in the line route • Insulator configuration depends on tower selection, I or V or other. • Material depends on pollution, vandalism, maintenance. • Hardware depends on material (corona rings for composite), live line requirements • For cross rope towers I string permits less pollution accretion especially from birds.
  • 30. LIGHTNING CONSIDERATIONS • Shield angle determination depends on tower type. − Negative shield angles generally give better performance. • Tower footing resistance needs to be determined and reduced on the line − “crows foot”, buried earthwire, bentonite mix • Note towers with large footprints generally give lower tower footing resistances. − Cross rope suspensions provide excellent results • If tower footing resistance still high may consider line surge arresters installed on certain towers. • Shield or earth wires are now often OPGW. − Care to be taken for fault current in the earth wire.
  • 31. AC LINE DESIGN OBJECTIVE INDICATOR GUIDE TO OVERHEAD OHL DESIGN TB 638
  • 32. Indicator to determine best design 32 • Need to combine − SIL − Thermal rating − Cost initial and life cycle o (Taking into account corona, magnetic fields, mech loading etc)
  • 33. FACTOR 1 Life Cycle Cost (k1) 33 • Covers determination of optimum aluminium area required. (Kelvin’s law) • Cost of maintenance (estimate) • Cost of losses – use system losses not line losses. (Due to power flow in interconnected system)
  • 34. FACTOR 2 THERMAL (k2) 34 • Cost is directly proportional to Thermal rating − Higher rating higher initial cost • A ratio is therefore needed − Initial cost/MVA thermal (emergency or normal) • The lower the ratio the better.
  • 35. FACTOR 3 SIL (k3) 35 • The higher the SIL the higher the initial cost (normally) • Ratio is therefore also required − Initial cost/MVAsil
  • 36. COMBINATION OF THE FACTORS 36 • Objective Matrix method − Present practice is given 3/10 − 0 or 10 level is determined (normally trial and error) and a linear interpolation used. • ATI = w1k1+w2k2+w3k3 − wn are weighting factors
  • 37. DETERMINING SCORE – NEG SLOPE Ratio value S c o r e Ratio of current practice Provides score of 3 3 10 (x1;y1) (x2;y2) Assume ratio value that is ideal. Score of ideal ratio is 10 Ratio of optionA Score of optionA Y=mx+c 1. For the ratio (LCC, IC/MVA etc), allocate a score of 3 for the current practice. This gives point x1;y1. 2. Assume an ideal ratio that will not be exceeded. Allocate a score of 10 for this ratio value. This will provide point x2; y2. 3. Calculate the straight line equation using these two points. 4. Use the straight line equation to determine the scores for the different design options. 5. You now have dimensionless scores which can be added. CALCULATION OF SCORE FOR SITUATIONS WHERE THE LOWER THE RATIO THE BETTER THE DESIGN
  • 38. DETERMINING SCORE – POSITIVE SLOPE Ratio value S c o r e 3 10 x1;y1 x2;y2 y=mx+c Ratio value of current practice allocated score of 3 Ratio value of ideal design. Allocated score of 10 Ratio value of optionA Score of optionA 1. Calculate the ratio of the current design option. Allocate it a score of 3 2. Assume an ideal design value and allocate it a score of 10 3. This provides two points. Calculate the straight line (y=mx+c) graph equation from points x1;y1 and x2;y2 4. Using the equation determine the scores for the other design options. 5. This provides a dimensionless score which can be added. CALCULATION OF SCORES WHERE THE HIGHER THE RATIO THE BETTER THE DESIGN
  • 39. CONDUCTOR SELECTION CONDUCTOR OPTIMISATION 0.00 100.00 200.00 300.00 400.00 500.00 900.00 800.00 700.00 600.00 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 Pmean(MVA) LCC(Rmil) 2 X IEC800 4 X KINGBIRD 3 X BERSFORT 3 X TERN 3 X YEW 4 X TERN3 x Bersfort 39 4 x Tern 4 x Kingbird 3 x Tern
  • 41. EXAMPLE LINE 41 − Quad “Zebra” guyed Vee tower − Triple “Bunting” conductor guyed Vee tower − Quad “Bunting” cross rope suspension (CRS) tower phase spacing of 6,5m. − Quad “Rail” conductor with a CRS tower with a 6,5m phase spacing. − Triple “Bittern” conductor with a CRS tower with a 6,5m phase spacing. − Quad “Boblink” conductor with a CRS tower with a 6,5m phase spacing. − Triple “Bersfort” conductor with a CRS tower with a 8,2m phase spacing.
  • 42. ATI SCORES 42 CASE AL AREA mm2 DESCRIPTION K1 (LCC) K2 (CI/MVAth) K3 (CI/MVAsil) 1 1715 4XZEB V 103,53 [3,30] 28,13 [3,07] 7,43 [3,19] 2 1817 3XBUNT V 84,4 [6,25] 19.48 [5,20] 6,31 [5,38] 3 2423 4XBUNT CRS 6.5m 88,36 [5,64] 13.27 [6,73] 7,02 [3,96] 4 1935 4XRAIL CRS 6.5m 87,76 [5,73] 14.32 [6,47] 5,94 [6,12] 5 1933 3xBIT CRS 6.5m 82,91 [6,48] 17.86 [5,60] 6,31 [5,38] 6 2901 4Xbob CRS 6.5m 93,33 [4,87] 17.04 [5,80 8,06 [1,88] 7 2059 3xBers CRS 8.2m 80,41 [6,81] 16.23 [6,00] 6,30 [5,40]
  • 43. ATI WEIGHTING 43 CASE W1;W2;W3 W1;W2;W3 W1;W2;W3 W1;W2;W3 0,8;0,1;0,1 0,6;0,2;0,2 0,4;0,3;0,3 0,2;0,4;0,4 1 2,82 [7] 2,89 [7] 2,96 [7] 3,03 [7] 2 5,80 [3] 5,67 [4] 5,55 [4] 5,42 [4] 3 5,23 [5] 5,18 [5] 5,14 [5] 5,09 [5] 4 5,56 [4] 5,74 [3] 5,93 [2] 6,11 [1] 5 6,04 [2] 5,90 [2] 5,77 [3] 5,63 [3] 6 4,33 [6] 4,21 [6] 4,08 [6] 3,96 [6] 7 6,42 [1] 6,24 [1] 6,06 [1] 5,88 [2]
  • 44. FINDINGS/BENEFITS 44 • Tower, foundation, hardware, electrical designers work together with planners (iterative process) • Indicator very sensitive and detects errors rapidly • Line optimisation is possible looking at overall line design. • Reliability is assumed constant for options • Cost system is critical • Most aspects of the line design are taken into account
  • 45. CONCLUSIONS 45 • Line design options can be objectively determined • ATI is a guide from which options can be finalised. • Alignment with Planners requirements
  • 46. GUIDE TO OVERALL LINE DESIGN GUIDE TO OVERHEAD OHL DESIGN TB 638 DC LINE DESIGN
  • 47. DC LINE DESIGN GUIDE TO OVERHEAD OHL DESIGN TB 638 ELECTRICAL CHARACTERISTICS
  • 48. Power Transfer x Pmax V 2  vd% 100R L where vd% is the voltage drop expressed as a % of V, and the equation applies for both 10% and 15% volt drop. {1/sqrt(44) is an approximation of 15/100} and the format removes the generality of the basic and simple equation. V=Sending end voltage, pole to ground in kV Rx=DC Resistance of the conductor in ohm/km L=Distance in kilometres.
  • 49. DC resistance • DC resistance not dependent on current • Dependent on conductor geometry and conductivity of material. • Dependent on temperature.
  • 50. Effect of conductor radius (TB388) The higher the conductor diameter and the more sub-conductors in the bundle the more resistant the bundle is to corona and therefore the designer is more able to raise the voltage to ground and hence increase the power capability of the line.
  • 51. Corona power loss            225 3 3.05  20log  25   15log n  10log HS dE P  11 40log mas Where P is the corona loss is dB above 1 W/m, Emax is the positive polarity maximum bundle gradient in kV/cm, d is the sub-conductor diameter in cm, n is the number of sub-conductors in the bundle, H is the average conductor height in m and S is the pole spacing in m.
  • 52. INSULATOR CONSIDERATIONS • Similar requirements to AC as far as tower window design. • For glass insulators need germanium glass as normal glass will shatter − Zinc collar also required • Creepage larger than for AC • Space charge considerations as well as uneven pollution on insulator to be taken into account. • Composite insulators can be used for AC and DC lighter weight often suit long insulator installation. • Porcelain disc are also successfully used.
  • 53. Summary of options Action Parameter Voltage drop Corona Mechanical loading Thermal rating + and - pole spacing decrease Neutral Bad Good Neutral Large Al area/cond (less conductors) Good Bad Good Bad Diameter bundle increase Neutral Bad Bad Neutral High steel content Neutral Neutral Bad Good
  • 55. DC LINE DESIGN OBJECTIVE INDICATOR GUIDE TO OVERHEAD OHL DESIGN TB 638
  • 56. Optimisation process • Select voltage (TB388) • Determine range of conductor, bundle diameter and number of sub-conductors as well as height above ground and pole spacings that will meet corona limitations and power flow. • Determine range of tower, foundation and conductor configurations. • Finalise by further analysis the most suitable tower, foundation, conductor bundle option. Recheck with power flow requirements, converter cost and technology.
  • 57. Objective indicator th IC 3 MVA ATIDC  w1LCC  w2IC* Posscoronal  w ATIdc Appropriate Technology Index for DC lines LCC is the life cycle cost expressed in terms of a score from 1 to 10 and IC is the initial cost. Plosscorona is the power loss due tocorona. IC is the initial cost. MVAthermal is the thermal rating of the line and depends, as in the AC case, to the templating temperature of theline.
  • 58. Line requirements • DC voltage (V) 600;700;800 kV • Number of sub-conductors per pole (N) 4; 5; 6 • Conductor type ACSR • Line length 1750 km • Transmitted Power 3000 MW (bipolar) • Cost of the losses 60 U$/MWh; loss factor =0,5 • Life= 30 years; yearly interest rate= 10% • Interest during construction 10%; maintenance 2% per year (of initial cost)
  • 62. GUIDE TO OVERALL LINE DESIGN COST OF LINES GUIDE TO OVERHEAD OHL DESIGN TB 638
  • 63. Purpose • The purpose of the questionnaire was to compare the work done by WG09 in 1990 to the latest figures as many component costs may have changed. • The questionnaire was in two parts, the first to compare component costs of existing projects, the second to compare costs of an actual line with given parameters. • The response was generally poor with around 13 respondents compared with over 100 in 1990.
  • 67. Asia
  • 68. Cost per km comparison
  • 69. Competitive line costs • From the graphs, if the conductor cost as a percentage of total line cost is greater than 10% the cost is likely to be relatively low. The range of percentages in the examples received indicated that the conductor cost for relatively low cost per km lines, should vary between 10 and 15%. • In the previous survey it was found that the conductor cost was 32% of the material cost which was 63%. This results in 20% of the total line cost. It could be concluded that the cost/km of lines has increased from 1990 to 2014 in real terms mainly due to cost of labour and environmental issues. • A good target for a competitive cost per km line would be that the conductor cost should be between 15 and 20% in 2014.
  • 70. COMPARISON TO 1991 YEAR MATERIAL COSTS CONSTRUCTION COSTS CONDUCTORS SHIELD WIRE INSULATORS TOWERS FOUNDATIONS For all lines and voltages 1991 63.7 36.3 32.7 3.8 8.1 36.2 19.2 2013 42.4 57.6 31.8 2.7 7.6 46.3 11.6 For all lines up to 150kV 1991 64.3 35.7 31.6 4.1 8.8 36.0 19.5 2013 46.4 53.6 28.6 2.0 7.9 49.6 11.9 For all lines over300kV 1991 62.6 37.4 34.1 3.9 6.9 36.4 18.7 2013 46.8 53.2 35.7 3.0 7.2 42.7 11.4 All single circuit lines 1991 63.6 36.4 33.1 4.2 8.2 35.6 18.8 2013 42.8 57.2 33.4 2.8 6.9 43.7 13.3 All double circuit lines 1991 63.8 36.2 32.0 3.3 7.9 37.1 19.7 2013 31.0 69.0 24.7 2.3 10.6 58.1 4.3 Guyed structure lines 1991 59.6 40.4 32.8 3.2 8.3 36.0 19.8 2013 55.0 45.0 36.5 3.2 6.3 41.3 12.7 Lines with 1 conductor/phase 1991 64.4 35.6 32.2 4.2 8.5 36.3 18.8 2013 38.7 61.3 28.3 2.0 7.8 45.1 16.9 Lines with 2 conductors/phase 1991 64.6 35.4 32.3 4.0 8.1 36.2 19.4 2013 38.0 62.0 32.3 2.3 10.6 48.4 6.3 Lines with 3 conductors/phase 1991 60.8 39.2 35.1 3.7 7.0 40.3 13.8 2013 41.5 58.5 36.6 4.6 6.6 42.6 9.6 Lines with 4 conductors/phase 1991 61.4 38.6 33.4 2.7 7.6 33.4 22.9 2013 56.5 43.5 34.2 3.4 7.9 37.9 16.7 Conductor, shield wire etc % as a function of material costs.
  • 71. Percentage comparisons with 1991 YEAR MATERIAL COSTS CONSTRUCTION COSTS COND SHIELD WIRE INSUL TOWERS FNDN For all lines and voltages 1991 63.7 36.3 32.7 3.8 8.1 36.2 19.2 2013 42.4 57.6 31.8 2.7 7.6 46.3 11.6 For all lines up to 150kV 1991 64.3 35.7 31.6 4.1 8.8 36.0 19.5 2013 46.4 53.6 28.6 2.0 7.9 49.6 11.9 For all lines over 300kV 1991 62.6 37.4 34.1 3.9 6.9 36.4 18.7 2013 46.8 53.2 35.7 3.0 7.2 42.7 11.4 All single circuit lines 1991 63.6 36.4 33.1 4.2 8.2 35.6 18.8 2013 42.8 57.2 33.4 2.8 6.9 43.7 13.3 All double circuit lines 1991 63.8 36.2 32.0 3.3 7.9 37.1 19.7 2013 31.0 69.0 24.7 2.3 10.6 58.1 4.3 Guyed structure lines 1991 59.6 40.4 32.8 3.2 8.3 36.0 19.8 2013 55.0 45.0 36.5 3.2 6.3 41.3 12.7 Lines with 1 conductor/phase 1991 64.4 35.6 32.2 4.2 8.5 36.3 18.8 2013 38.7 61.3 28.3 2.0 7.8 45.1 16.9 Lines with 2 conductors/phase 1991 64.6 35.4 32.3 4.0 8.1 36.2 19.4 2013 38.0 62.0 32.3 2.3 10.6 48.4 6.3 Lines with 3 conductors/phase 1991 60.8 39.2 35.1 3.7 7.0 40.3 13.8 2013 41.5 58.5 36.6 4.6 6.6 42.6 9.6 Lines with 4 conductors/phase 1991 61.4 38.6 33.4 2.7 7.6 33.4 22.9 2013 56.5 43.5 34.2 3.4 7.9 37.9 16.7
  • 72. Summary of Trends • Material and construction costs – the trend appears to be that the material cost has reduced as a function of total cost with the construction cost being the more prevalent cost. This appears to be the case over the entire range of lines investigated. • Conductors – in the 2013 cases the steel shield wire is included in the conductor cost. Even with this inclusion, it appears the conductor cost is generally the same or lower percentage of the total cost as compared to 1991. • Shield wire – this cost is related to the OPGW cost for 2013 and the steel wire cost for 1991. The sample for double circuit and single circuit lines for 2013 is very small and therefore cannot be considered to be representative. However it indicates a similar percentage to the 1991 costs even though the shield wire is more complicated and expensive in real terms in 2013. • Insulators – the percentage of total cost spent on insulators seem to be slightly lower than in 1991. This could be due to the advent of composite insulators which have dropped in price considerably over the years as well as glass being more competitive with merger of manufacturers. • Towers – The percentage of the total cost spent on towers seem to be higher than in 1991. This cost includes the erection cost which could indicate the higher cost of labour which is reflected in the construction cost compared to material cost. As mentioned previously the environmental constraints on current lines could have resulted in more angle or strain towers as well as more aesthetically pleasing towers such as the Wintrack towers. • Foundations – The percentage of the total cost spent on foundations seems to be lower than is 1991. This may be due to the higher level of mechanisation and perhaps use of more pile foundations but this is not confirmed.
  • 73. GUIDE TO OVERALL LINE DESIGN EXAMPLES OF OPTIMISATION GUIDE TO OVERHEAD OHL DESIGN TB 638
  • 74. Tower development Proposed CRS 6% saving on line cost 74 Existing guyed V
  • 75. Cost Savings 750-15 degree structures 15-30 degree structures R0 R75,000 R150,000 R225,000 R300,000 R450,000 R375,000 Misc Costs Insulation Hardware Tower Erection Tower Supply Foundations 52% Saving 46% Saving
  • 76. 705A tower at NETFA 76
  • 77. REFERENCES/ ACKNOWLEDGEMENTS 77 [Stephen 2004] Stephen R. “Use of indicators to optimise design of overhead transmission lines”. Paper330-1 Shanghai Symposium, Cigré 2003. (Held in Lubljana April 4-62004) [Stephen 2011] Stephen R “Objective detetermination of Optimal power line designs” PhD thesis submitted in 2011 University of Cape Town. [Muftic]. Muftic D, Bisnath S, Britten A, Cretchley DH, Pillay T,Vajeth R “The Planning design and constructionof overhead power lines” Published by Crown publications 2005 ISBN 9780620330428 [Southwire] Overhead Conductor Manual First edition copyright1994. Prof. C.T.Gaunt (UCT) acknowledged for comments andinput. J. Lindquist AC/DC conversion TB583 Nolasco, Jardini, TB 388