Cutover Strategy
(with details becomes Cutover Kickoff)
2
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
1. Cutover Strategy
2. Timeline
3. Go Live Acceptance Criteria
4. Cutover Organization and Responsibilities
o Legacy Team
o Migration Team
o Business Team
5. Cutover Schedule
6. Cutover Simulations
7. Cutover Communications
8. Contingency Plan
9. Implementation Support
10. Logistics
Agenda
3
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Cutover Strategy
• Time constraints?
• Big bang or phased?
• Sequence?
• Parallel system with legacy?
4
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
High Level Cutover Timeline
Mo October November December January
W
k
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Business
Preparation
2 Production
Environment
Preparation
3 Project Team
Preparation
4 Master Data
Migration
5 Cutover Preparation
6 Legacy Changes and
Shutdown
7 Transaction Data
Migration
8 Key Processes
Execution
9 Legacy Shutdown
10 Security access
enabled
11 Go Live
12 Go Live Support –
Hyper Care
13 Go Live Support –
Long Term
Cutover Simulations
5
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
• The business identifies the acceptance criteria during Realization in order to:
• Maintain the focus on going live on time
• Focus project team efforts on criteria tasks
• Acceptance criteria needed for major milestones
• To begin Production Cutover, for example:
• Acceptable levels of passing for Integration Tests
• Acceptable levels of trained and certified users
• Acceptable levels of open issues
• Acceptable performance criteria
• To accept Master Data, for example:
• Planned accuracy percent of data load by object
• To accept Transactional Data, for example:
• Planned accuracy percent of data load by object
• Key processes that execute correctly in Production post migration
• Meeting acceptance criteria allows move to next steps
Go Live Acceptance Criteria
6
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Cutover Organization
Cutover Manager
Data Migration
Team Lead
Functional
Team Lead
Site coordinators
Key users
Legacy
Team Lead
Business
Team Member
Data Migration
Team
OCM
Team Lead
Legacy
Team
7
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Roles and Responsibility
Cutover Manager  Creates and maintains master cutover schedule
 Defines organization and logistics for cutover
 Manages cutover issues and their resolution
 Ensures communication to all stakeholders
OCM Team Lead  Provides formal communications
Team Leads  Create cutover schedule for team as input to the master cutover schedule
Legacy Team  Extract data
 Provide reports to aid in validation
Data Migration Team Lead  Creates cutover schedule for data migrations as input to the master cutover schedule
 Manages data loads prior to cutover
 Documents results of each data load
Data Migration Team  Execute migrations
 Provide aid in validation
Business Team Members  Validate converted data and resolve errors
 Identify and execute key process tests
Project Team  Hyper care period support
Site Coordinators  Manages site readiness
 Manages site issues and their resolution
Key Users  First line support
8
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Long Term Responsibility
• Inventory of legacy systems
• Identify systems to sunset
• Identify any modifications needed
• Inventory of batch processes to reschedule or cancel
• Identification of security access requirements
• During cutover
• Post Go Live
9
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Migration Team Responsibility
• Determine whether migration is:
• One time
• Multiples for a file with deltas
• Determine approach to dual maintenance, as required
• Determine sequence of migrations
• Document migration quality tracking in Migration Quality Tracking spreadsheet
• Track record counts, validation works, and time requirements
• Create an individual spreadsheet for each data load including unit test, simulation loads, training
migration, etc.
• Aid the business to cleanse and validate the data
10
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Migration Team Responsibility
• Purpose
• Objectives & Goal
• Migration Plan Strategy & Methods
• Planning & Accelerated SAP (SAP Activate) Phases
• Migration Planning High Level Activities
• Go-Live Scope of Activities & Migration
• Key Team Members Worksheet
• Migration/Cutover Schedules
• Top Assumptions
11
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Purpose
• The Migration Plan identifies the activities to be performed during the cutover process from
getting started through execution of all related tasks: Planning, Acceptance and Execution.
• The plan further defines the activities required to facilitate a smooth transition into production
for additional SAP functionality.
• The major activities of Migration are the migration of master data and getting the Production
SAP system functionally and technically ready.
• The Migration Plan template is to be re-usable for each separate Migration effort (release
schedule).
12
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Objectives and Goals
Objectives
• Establish the Process for the Actual Go-Live
Transition
• Define the Approach and Framework for
executing the Cutover
• Establish Approval Criteria for Formal Cutover
Acceptance
• Define Project Team Activities, Roles, &
Responsibilities
• Define Organization Team Activities, Roles &
Responsibilities
• Define Project Management Activities, Roles
and Responsibilities
Goal
The Goal is plan to ensure a smooth transition to
production
Production
Technical
Infrastructure
System
Design
Security
Data
Training
Organization
Deployment
IT
Driven
Items
Business
Driven
Items
13
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Migration Plan Strategy & Methods
• For each SAP Project Schedule, (release) there will be a separate set of Migration documents
created using the following Migration templates:
• Cutover Schedule
• Cutover Checklist
• Final Cutover Checklist
• A Cutover Schedule will be maintained for each release schedule tracking all key area
milestone dates to ensure all areas are coming together for the individual Migration effort.
• A Cutover Checklist will be created with all necessary detail and dependencies and
tested/updated via the cutover simulations and lessons learned process.
• Acceptance criteria by key area will be defined for each Migration effort using the Final
Cutover Acceptance Checklist template.
• Lessons Learned from each Migration effort are to be evaluated and included as updates to the
Migration Plan going forward.
14
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Migration Planning & Accelerated SAP Phases
Create Initial
Migration
Plan
Go-Live &
Support
Solution Validation Phase Realization Phase Final Preparation Phase Go-Live
Revise & Finalize
Migration Plan
Execute
Migration Plan
15
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Migration Planning High Level (Activities)
Test/Re-Test Data
Migration
Programs & Files
Test/Re-Test Data
Migration
Files
Finalize Data
Migration
Files
Go-Live
Ongoing
System
Maintenance
Test Cutover Activities, Execute
Volume & Stress Testing
(Repeat 3X min), Payroll
Interface Testing w/Customer Data
Move Transports into
Production, Data migration
& Validation in Production,
(Execute All Cutover Activities)
Create & Load
Data
Migration
Files
Develop Volume
& Stress Test Scenarios
Apply Latest Support
Packs to DEV/QA/Prod
Production
Support
Organization Readiness Planning
Create End-User
Training Plans
Create SAP Training Materials,
Customer Acceptance
(CAT), Regression &
Security Roles & Rights Testing
Conduct
End-User
Training
Realization Phase Final Preparation PhaseGo-Live
16
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Go-Live Scope of Activities
Migration
Plan Key
Components
• Technical,
(Infrastructure)
• Functional
(System Design)
• Development
(System Design)
• Authorizations
(Security Roles &
Rights))
• Data Cleansing
• Data migration
• Training
• Organization
Change
Management
• Project
Management
• Infrastructure
• System Design
• Security
• Data
• Training
• Organizational
• Deployment
Key Areas Acceptan
ce Criteria
Legacy Source
Data for migration
• Cutover Strategy
• Cutover Schedule
• Cutover Checklist
• Final Cutover
Acceptance
Checklist)
Legend:
1. Items highlighted in blue are “directly” related to Migration &
are tested via the Migration process.
2. Items highlighted in black are “indirectly” related to Migration
with the final outcome of the testing being incorporated into the
Migration effort.
3. Items highlighted in grey are not part of the Migration effort and
are tracked to ensure the overall success of the
implementation.
17
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Top Assumptions
• System design work (configuration and enhancements) in scope have been completed and integration tested end-
to-end.
• Interfaces from SAP to external Customer systems in scope have been completed and integration tested end-to-
end (with new data set), with receiving system resources confirming both receipt and acceptance. (Requires
downstream systems (including those connected to XI) to be locked into SAP integration testing and acceptance
schedule.)
• Additional development work (authorizations, reports, forms, migrations, etc.) in scope have been completed and
tested.
• Data to be converted into the new SAP environment has been cleansed, validated and approved for migration into
SAP.
• The cutover approval process is timely and is based on the approval criteria defined as part of the Migration plan
for both the Business owners and Information Technology areas involved.
• Pre-requisite and parallel activities are completed and approved prior to the go-live (security roles and rights
testing, customer acceptance testing, end-user training, organizational change management activities, etc.).
• Resource constraints will be managed based on priority, criticality and urgency.
• Each team involved retains the resources and skill sets required to complete the tasks related to their respective
areas in the time needed.
• No historical data is part of migration/cutover process into SAP for the go-live.
18
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Business Responsibilities
• The business identifies:
• Key personnel and staffing plans
• New data requirements
• Preparation for cutover
• Business preparation activities
• Process cut off milestones
• Alternative business processes for transition periods
• Acceptable business shut-down window
• Key processes to execute in production after data migration
• End user requirements
• Training or certification requirements
• Log on distribution logistics and requirements
• Start up procedures
• Business resources for cutover:
• Key Users
• Site Coordinators
• The business is responsible for the data
• Cleansing
• Validating
• Determine dual maintenance requirements, if any
19
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Cutover Schedule
• Each functional, data, and technical team lead to maintain a list of cutover activities in Team
Cutover Schedule
• Created before migration to QA box
• Provided to Cutover Manager for use in QA build
• Once provided to Cutover Manager, the Team schedules are no longer maintained, as there is
only one Master Cutover Schedule
• Cutover Manager merges the Team Schedules into the Master Cutover Schedule
• Executes merged schedule to build QA box, Prod box, simulation cutovers, and cutover to
production
• Updates schedule as needed to provide the most error-free cutover to production
• Re-uses the schedule for each
• The Master Cutover Schedule leverages MS Project’s predecessor and successor functionality
to enable forecasting of time requirements for cutover
20
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Cutover Communications
21
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Contingency Plan
• Risks and mitigations for cutover
• Time required to restore legacy
• Position decision points for proceeding with next steps
• Identify acceptance requirements for each decision point
22
PUBLIC
© 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Implementation Support
• Hyper care period
• Project team staffs cutover room for 2 weeks
• Schedule developed for 24 x 7 support
• Help Desk phone line coordination
• Long Term
• Handover to Help Desk after 2 weeks
Partner logo
Contact information:
F name L name
Title
Address
Phone number
Thank you.

More Related Content

What's hot

Oracle ERP Implementation_Genpact_V7.pptx
Oracle ERP Implementation_Genpact_V7.pptxOracle ERP Implementation_Genpact_V7.pptx
Oracle ERP Implementation_Genpact_V7.pptxAshokKumar705948
 
SAP INTRO
SAP INTROSAP INTRO
SAP INTRODr.Ravi
 
SAP S/4HANA Migration Cockpit
SAP S/4HANA Migration CockpitSAP S/4HANA Migration Cockpit
SAP S/4HANA Migration CockpitEdwin Weijers
 
Sap Hr Presentation 08052002
Sap Hr Presentation 08052002Sap Hr Presentation 08052002
Sap Hr Presentation 08052002Anand Shanmugam
 
Cutover strategy - Legacy to new billing, invoicing engine
Cutover strategy - Legacy to new billing, invoicing engineCutover strategy - Legacy to new billing, invoicing engine
Cutover strategy - Legacy to new billing, invoicing engineAjay Kumar Uppal
 
SAP Roll Out - An Introduction and Advantages
SAP Roll Out - An Introduction and AdvantagesSAP Roll Out - An Introduction and Advantages
SAP Roll Out - An Introduction and Advantagesanjalirao366
 
An Overview of SAP S4/HANA
An Overview of SAP S4/HANAAn Overview of SAP S4/HANA
An Overview of SAP S4/HANADebajit Banerjee
 
Production-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.pptProduction-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.pptJohnRichard90
 
SAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptxSAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptxSingbBablu
 
Transition to SAP S/4HANA System Conversion: A step-by-step guide
Transition to SAP S/4HANA System Conversion: A step-by-step guide Transition to SAP S/4HANA System Conversion: A step-by-step guide
Transition to SAP S/4HANA System Conversion: A step-by-step guide Kellton Tech Solutions Ltd
 
SAP Project Management: Major Responsibilities And Key Task
SAP Project Management: Major Responsibilities And Key TaskSAP Project Management: Major Responsibilities And Key Task
SAP Project Management: Major Responsibilities And Key TaskAnjali Rao
 
SAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdf
SAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdfSAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdf
SAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdfssuserf6d533
 
SAP S4HANA Migration Cockpit.pdf
SAP S4HANA Migration Cockpit.pdfSAP S4HANA Migration Cockpit.pdf
SAP S4HANA Migration Cockpit.pdfKrishnaAkula4
 
SAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementationSAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementationBluefin Solutions
 
SAP Activate Methodology for S/4HANA Implementation
SAP Activate Methodology for S/4HANA ImplementationSAP Activate Methodology for S/4HANA Implementation
SAP Activate Methodology for S/4HANA ImplementationKellton Tech Solutions Ltd
 
Sap for beginners
Sap for beginnersSap for beginners
Sap for beginnersRohit Verma
 

What's hot (20)

Oracle ERP Implementation_Genpact_V7.pptx
Oracle ERP Implementation_Genpact_V7.pptxOracle ERP Implementation_Genpact_V7.pptx
Oracle ERP Implementation_Genpact_V7.pptx
 
SAP INTRO
SAP INTROSAP INTRO
SAP INTRO
 
SAP S/4HANA Migration Cockpit
SAP S/4HANA Migration CockpitSAP S/4HANA Migration Cockpit
SAP S/4HANA Migration Cockpit
 
Sap Hr Presentation 08052002
Sap Hr Presentation 08052002Sap Hr Presentation 08052002
Sap Hr Presentation 08052002
 
Cutover strategy - Legacy to new billing, invoicing engine
Cutover strategy - Legacy to new billing, invoicing engineCutover strategy - Legacy to new billing, invoicing engine
Cutover strategy - Legacy to new billing, invoicing engine
 
Sap implementation
Sap implementationSap implementation
Sap implementation
 
SAP Roll Out - An Introduction and Advantages
SAP Roll Out - An Introduction and AdvantagesSAP Roll Out - An Introduction and Advantages
SAP Roll Out - An Introduction and Advantages
 
An Overview of SAP S4/HANA
An Overview of SAP S4/HANAAn Overview of SAP S4/HANA
An Overview of SAP S4/HANA
 
Production-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.pptProduction-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.ppt
 
SAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptxSAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptx
 
Transition to SAP S/4HANA System Conversion: A step-by-step guide
Transition to SAP S/4HANA System Conversion: A step-by-step guide Transition to SAP S/4HANA System Conversion: A step-by-step guide
Transition to SAP S/4HANA System Conversion: A step-by-step guide
 
SAP Project Management: Major Responsibilities And Key Task
SAP Project Management: Major Responsibilities And Key TaskSAP Project Management: Major Responsibilities And Key Task
SAP Project Management: Major Responsibilities And Key Task
 
SAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdf
SAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdfSAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdf
SAP S_4HANA Migration Cockpit - Deep Dive LTMOM for Direct Transfer.pdf
 
SAP HR - PPT
SAP HR - PPTSAP HR - PPT
SAP HR - PPT
 
Sap activate overview
Sap activate overviewSap activate overview
Sap activate overview
 
SAP S4HANA Migration Cockpit.pdf
SAP S4HANA Migration Cockpit.pdfSAP S4HANA Migration Cockpit.pdf
SAP S4HANA Migration Cockpit.pdf
 
SAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementationSAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementation
 
SAP Activate Methodology for S/4HANA Implementation
SAP Activate Methodology for S/4HANA ImplementationSAP Activate Methodology for S/4HANA Implementation
SAP Activate Methodology for S/4HANA Implementation
 
Oracle Fusion Application
Oracle Fusion ApplicationOracle Fusion Application
Oracle Fusion Application
 
Sap for beginners
Sap for beginnersSap for beginners
Sap for beginners
 

Similar to FP_45 Cutover Strategy.pptx

Transition_Roadmap__Overview_23Q1.pdf
Transition_Roadmap__Overview_23Q1.pdfTransition_Roadmap__Overview_23Q1.pdf
Transition_Roadmap__Overview_23Q1.pdfSrinivasan N
 
Savic executive summary sm
Savic executive summary smSavic executive summary sm
Savic executive summary smSupriya SAVIC
 
Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4DevOps.com
 
S4H_399 2 SL _Onboarding Presentation (2).pptx
S4H_399 2  SL _Onboarding Presentation (2).pptxS4H_399 2  SL _Onboarding Presentation (2).pptx
S4H_399 2 SL _Onboarding Presentation (2).pptxchandramohan431817
 
Seerene for SAP S/4HANA Migrations
Seerene for SAP S/4HANA MigrationsSeerene for SAP S/4HANA Migrations
Seerene for SAP S/4HANA MigrationsFranz Schubert
 
Training on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptTraining on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptAshwaniKumar207236
 
S4H_747 How to Approach Remote Cutover (2).pptx
S4H_747 How to Approach Remote Cutover (2).pptxS4H_747 How to Approach Remote Cutover (2).pptx
S4H_747 How to Approach Remote Cutover (2).pptxSreeGe1
 
Deep Dive. How to Transition SAP Payroll to HR Cloud
Deep Dive. How to Transition SAP Payroll to HR CloudDeep Dive. How to Transition SAP Payroll to HR Cloud
Deep Dive. How to Transition SAP Payroll to HR CloudNGA Human Resources
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.pptAshwaniKumar207236
 
Kanban India 2023 | Seshabhargavan R and Shobha Kumari | Project Ignite
Kanban India 2023 | Seshabhargavan R and Shobha Kumari | Project IgniteKanban India 2023 | Seshabhargavan R and Shobha Kumari | Project Ignite
Kanban India 2023 | Seshabhargavan R and Shobha Kumari | Project IgniteLeanKanbanIndia
 
CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...
CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...
CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...TheConnectedCause
 
Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...
Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...
Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...CA Technologies
 
Kickoff meeting template
Kickoff meeting templateKickoff meeting template
Kickoff meeting templateVan Chau
 
Resume of Mohamed Sajid Maqba_2016
Resume of Mohamed Sajid Maqba_2016Resume of Mohamed Sajid Maqba_2016
Resume of Mohamed Sajid Maqba_2016Mohamed Sajid Maqba
 
S4HANA_Roadmap_General_Information.pdf
S4HANA_Roadmap_General_Information.pdfS4HANA_Roadmap_General_Information.pdf
S4HANA_Roadmap_General_Information.pdfmail2cnivas1
 
Putting the Ops in DataOps: Orchestrate the Flow of Data Across Data Pipelines
Putting the Ops in DataOps: Orchestrate the Flow of Data Across Data PipelinesPutting the Ops in DataOps: Orchestrate the Flow of Data Across Data Pipelines
Putting the Ops in DataOps: Orchestrate the Flow of Data Across Data PipelinesDATAVERSITY
 

Similar to FP_45 Cutover Strategy.pptx (20)

Transition_Roadmap__Overview_23Q1.pdf
Transition_Roadmap__Overview_23Q1.pdfTransition_Roadmap__Overview_23Q1.pdf
Transition_Roadmap__Overview_23Q1.pdf
 
Savic executive summary sm
Savic executive summary smSavic executive summary sm
Savic executive summary sm
 
Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4
 
S4H_399 2 SL _Onboarding Presentation (2).pptx
S4H_399 2  SL _Onboarding Presentation (2).pptxS4H_399 2  SL _Onboarding Presentation (2).pptx
S4H_399 2 SL _Onboarding Presentation (2).pptx
 
Seerene for SAP S/4HANA Migrations
Seerene for SAP S/4HANA MigrationsSeerene for SAP S/4HANA Migrations
Seerene for SAP S/4HANA Migrations
 
Training on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptTraining on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.ppt
 
S4H_747 How to Approach Remote Cutover (2).pptx
S4H_747 How to Approach Remote Cutover (2).pptxS4H_747 How to Approach Remote Cutover (2).pptx
S4H_747 How to Approach Remote Cutover (2).pptx
 
Deep Dive. How to Transition SAP Payroll to HR Cloud
Deep Dive. How to Transition SAP Payroll to HR CloudDeep Dive. How to Transition SAP Payroll to HR Cloud
Deep Dive. How to Transition SAP Payroll to HR Cloud
 
Sap migration to cloud
Sap migration to cloudSap migration to cloud
Sap migration to cloud
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.ppt
 
Kanban India 2023 | Seshabhargavan R and Shobha Kumari | Project Ignite
Kanban India 2023 | Seshabhargavan R and Shobha Kumari | Project IgniteKanban India 2023 | Seshabhargavan R and Shobha Kumari | Project Ignite
Kanban India 2023 | Seshabhargavan R and Shobha Kumari | Project Ignite
 
0916 resume
0916  resume0916  resume
0916 resume
 
Jagan
JaganJagan
Jagan
 
CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...
CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...
CRMready Webinar Series - Part 3 - How to Make Your Nonprofit’s CRM Implement...
 
Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...
Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...
Technology Primer: Save Money and Improve Service by Replacing "Free" Native ...
 
Kickoff meeting template
Kickoff meeting templateKickoff meeting template
Kickoff meeting template
 
AnakpalSandhuMaster1
AnakpalSandhuMaster1AnakpalSandhuMaster1
AnakpalSandhuMaster1
 
Resume of Mohamed Sajid Maqba_2016
Resume of Mohamed Sajid Maqba_2016Resume of Mohamed Sajid Maqba_2016
Resume of Mohamed Sajid Maqba_2016
 
S4HANA_Roadmap_General_Information.pdf
S4HANA_Roadmap_General_Information.pdfS4HANA_Roadmap_General_Information.pdf
S4HANA_Roadmap_General_Information.pdf
 
Putting the Ops in DataOps: Orchestrate the Flow of Data Across Data Pipelines
Putting the Ops in DataOps: Orchestrate the Flow of Data Across Data PipelinesPutting the Ops in DataOps: Orchestrate the Flow of Data Across Data Pipelines
Putting the Ops in DataOps: Orchestrate the Flow of Data Across Data Pipelines
 

Recently uploaded

My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 

Recently uploaded (20)

E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 

FP_45 Cutover Strategy.pptx

  • 1. PUBLIC SAP February 14, 2023 Cutover Strategy (with details becomes Cutover Kickoff)
  • 2. 2 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ 1. Cutover Strategy 2. Timeline 3. Go Live Acceptance Criteria 4. Cutover Organization and Responsibilities o Legacy Team o Migration Team o Business Team 5. Cutover Schedule 6. Cutover Simulations 7. Cutover Communications 8. Contingency Plan 9. Implementation Support 10. Logistics Agenda
  • 3. 3 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Cutover Strategy • Time constraints? • Big bang or phased? • Sequence? • Parallel system with legacy?
  • 4. 4 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ High Level Cutover Timeline Mo October November December January W k 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 Business Preparation 2 Production Environment Preparation 3 Project Team Preparation 4 Master Data Migration 5 Cutover Preparation 6 Legacy Changes and Shutdown 7 Transaction Data Migration 8 Key Processes Execution 9 Legacy Shutdown 10 Security access enabled 11 Go Live 12 Go Live Support – Hyper Care 13 Go Live Support – Long Term Cutover Simulations
  • 5. 5 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ • The business identifies the acceptance criteria during Realization in order to: • Maintain the focus on going live on time • Focus project team efforts on criteria tasks • Acceptance criteria needed for major milestones • To begin Production Cutover, for example: • Acceptable levels of passing for Integration Tests • Acceptable levels of trained and certified users • Acceptable levels of open issues • Acceptable performance criteria • To accept Master Data, for example: • Planned accuracy percent of data load by object • To accept Transactional Data, for example: • Planned accuracy percent of data load by object • Key processes that execute correctly in Production post migration • Meeting acceptance criteria allows move to next steps Go Live Acceptance Criteria
  • 6. 6 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Cutover Organization Cutover Manager Data Migration Team Lead Functional Team Lead Site coordinators Key users Legacy Team Lead Business Team Member Data Migration Team OCM Team Lead Legacy Team
  • 7. 7 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Roles and Responsibility Cutover Manager  Creates and maintains master cutover schedule  Defines organization and logistics for cutover  Manages cutover issues and their resolution  Ensures communication to all stakeholders OCM Team Lead  Provides formal communications Team Leads  Create cutover schedule for team as input to the master cutover schedule Legacy Team  Extract data  Provide reports to aid in validation Data Migration Team Lead  Creates cutover schedule for data migrations as input to the master cutover schedule  Manages data loads prior to cutover  Documents results of each data load Data Migration Team  Execute migrations  Provide aid in validation Business Team Members  Validate converted data and resolve errors  Identify and execute key process tests Project Team  Hyper care period support Site Coordinators  Manages site readiness  Manages site issues and their resolution Key Users  First line support
  • 8. 8 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Long Term Responsibility • Inventory of legacy systems • Identify systems to sunset • Identify any modifications needed • Inventory of batch processes to reschedule or cancel • Identification of security access requirements • During cutover • Post Go Live
  • 9. 9 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Migration Team Responsibility • Determine whether migration is: • One time • Multiples for a file with deltas • Determine approach to dual maintenance, as required • Determine sequence of migrations • Document migration quality tracking in Migration Quality Tracking spreadsheet • Track record counts, validation works, and time requirements • Create an individual spreadsheet for each data load including unit test, simulation loads, training migration, etc. • Aid the business to cleanse and validate the data
  • 10. 10 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Migration Team Responsibility • Purpose • Objectives & Goal • Migration Plan Strategy & Methods • Planning & Accelerated SAP (SAP Activate) Phases • Migration Planning High Level Activities • Go-Live Scope of Activities & Migration • Key Team Members Worksheet • Migration/Cutover Schedules • Top Assumptions
  • 11. 11 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Purpose • The Migration Plan identifies the activities to be performed during the cutover process from getting started through execution of all related tasks: Planning, Acceptance and Execution. • The plan further defines the activities required to facilitate a smooth transition into production for additional SAP functionality. • The major activities of Migration are the migration of master data and getting the Production SAP system functionally and technically ready. • The Migration Plan template is to be re-usable for each separate Migration effort (release schedule).
  • 12. 12 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Objectives and Goals Objectives • Establish the Process for the Actual Go-Live Transition • Define the Approach and Framework for executing the Cutover • Establish Approval Criteria for Formal Cutover Acceptance • Define Project Team Activities, Roles, & Responsibilities • Define Organization Team Activities, Roles & Responsibilities • Define Project Management Activities, Roles and Responsibilities Goal The Goal is plan to ensure a smooth transition to production Production Technical Infrastructure System Design Security Data Training Organization Deployment IT Driven Items Business Driven Items
  • 13. 13 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Migration Plan Strategy & Methods • For each SAP Project Schedule, (release) there will be a separate set of Migration documents created using the following Migration templates: • Cutover Schedule • Cutover Checklist • Final Cutover Checklist • A Cutover Schedule will be maintained for each release schedule tracking all key area milestone dates to ensure all areas are coming together for the individual Migration effort. • A Cutover Checklist will be created with all necessary detail and dependencies and tested/updated via the cutover simulations and lessons learned process. • Acceptance criteria by key area will be defined for each Migration effort using the Final Cutover Acceptance Checklist template. • Lessons Learned from each Migration effort are to be evaluated and included as updates to the Migration Plan going forward.
  • 14. 14 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Migration Planning & Accelerated SAP Phases Create Initial Migration Plan Go-Live & Support Solution Validation Phase Realization Phase Final Preparation Phase Go-Live Revise & Finalize Migration Plan Execute Migration Plan
  • 15. 15 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Migration Planning High Level (Activities) Test/Re-Test Data Migration Programs & Files Test/Re-Test Data Migration Files Finalize Data Migration Files Go-Live Ongoing System Maintenance Test Cutover Activities, Execute Volume & Stress Testing (Repeat 3X min), Payroll Interface Testing w/Customer Data Move Transports into Production, Data migration & Validation in Production, (Execute All Cutover Activities) Create & Load Data Migration Files Develop Volume & Stress Test Scenarios Apply Latest Support Packs to DEV/QA/Prod Production Support Organization Readiness Planning Create End-User Training Plans Create SAP Training Materials, Customer Acceptance (CAT), Regression & Security Roles & Rights Testing Conduct End-User Training Realization Phase Final Preparation PhaseGo-Live
  • 16. 16 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Go-Live Scope of Activities Migration Plan Key Components • Technical, (Infrastructure) • Functional (System Design) • Development (System Design) • Authorizations (Security Roles & Rights)) • Data Cleansing • Data migration • Training • Organization Change Management • Project Management • Infrastructure • System Design • Security • Data • Training • Organizational • Deployment Key Areas Acceptan ce Criteria Legacy Source Data for migration • Cutover Strategy • Cutover Schedule • Cutover Checklist • Final Cutover Acceptance Checklist) Legend: 1. Items highlighted in blue are “directly” related to Migration & are tested via the Migration process. 2. Items highlighted in black are “indirectly” related to Migration with the final outcome of the testing being incorporated into the Migration effort. 3. Items highlighted in grey are not part of the Migration effort and are tracked to ensure the overall success of the implementation.
  • 17. 17 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Top Assumptions • System design work (configuration and enhancements) in scope have been completed and integration tested end- to-end. • Interfaces from SAP to external Customer systems in scope have been completed and integration tested end-to- end (with new data set), with receiving system resources confirming both receipt and acceptance. (Requires downstream systems (including those connected to XI) to be locked into SAP integration testing and acceptance schedule.) • Additional development work (authorizations, reports, forms, migrations, etc.) in scope have been completed and tested. • Data to be converted into the new SAP environment has been cleansed, validated and approved for migration into SAP. • The cutover approval process is timely and is based on the approval criteria defined as part of the Migration plan for both the Business owners and Information Technology areas involved. • Pre-requisite and parallel activities are completed and approved prior to the go-live (security roles and rights testing, customer acceptance testing, end-user training, organizational change management activities, etc.). • Resource constraints will be managed based on priority, criticality and urgency. • Each team involved retains the resources and skill sets required to complete the tasks related to their respective areas in the time needed. • No historical data is part of migration/cutover process into SAP for the go-live.
  • 18. 18 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Business Responsibilities • The business identifies: • Key personnel and staffing plans • New data requirements • Preparation for cutover • Business preparation activities • Process cut off milestones • Alternative business processes for transition periods • Acceptable business shut-down window • Key processes to execute in production after data migration • End user requirements • Training or certification requirements • Log on distribution logistics and requirements • Start up procedures • Business resources for cutover: • Key Users • Site Coordinators • The business is responsible for the data • Cleansing • Validating • Determine dual maintenance requirements, if any
  • 19. 19 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Cutover Schedule • Each functional, data, and technical team lead to maintain a list of cutover activities in Team Cutover Schedule • Created before migration to QA box • Provided to Cutover Manager for use in QA build • Once provided to Cutover Manager, the Team schedules are no longer maintained, as there is only one Master Cutover Schedule • Cutover Manager merges the Team Schedules into the Master Cutover Schedule • Executes merged schedule to build QA box, Prod box, simulation cutovers, and cutover to production • Updates schedule as needed to provide the most error-free cutover to production • Re-uses the schedule for each • The Master Cutover Schedule leverages MS Project’s predecessor and successor functionality to enable forecasting of time requirements for cutover
  • 20. 20 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Cutover Communications
  • 21. 21 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Contingency Plan • Risks and mitigations for cutover • Time required to restore legacy • Position decision points for proceeding with next steps • Identify acceptance requirements for each decision point
  • 22. 22 PUBLIC © 2023 SAP SE or an SAP affiliate company. All rights reserved. ǀ Implementation Support • Hyper care period • Project team staffs cutover room for 2 weeks • Schedule developed for 24 x 7 support • Help Desk phone line coordination • Long Term • Handover to Help Desk after 2 weeks
  • 23. Partner logo Contact information: F name L name Title Address Phone number Thank you.