SlideShare a Scribd company logo
1 of 9
Arbitration Cases
Presentation by: Parvez Ahmad Hashmat
Entry#: 2019CET2027
Submitted to: Prof. K.N JHA
Indian Institute of Technology-Delhi- 2020
Case 1:
Haleem Khapalwak Construction Company V/S Ministry of Finance,
2018/Feb/08.
The project of building a DATA Archive for Kandahar Custom was awarded
to Haleem Khapalwak Construction Company on 2018/Jan/01 from the
ministry of finance of Afghanistan with an estimated cost of $53600.
2
Claimant’s (Contractor’s) Case:
i. Clear columns height of the structure is differing in drawings and design,
resulting in a change of 5cum volume of work in the BOQ that costs $900.
ii. Claim for additional expenses incurred toward the stone masonry work for
inside ring beams, which isn’t included in the BOQ that costs
approximately $5000.
Respondent Defense:
The clarity of drawings and specifications are vibrant. The contractor
estimated his bidding from BOQ not observing the drawings accurately; thus,
the specified money shouldn’t be awarded to the claimant.
3
Arbitrator Findings and Resolution:
4
According to the laws of Afghanistan, there is no arbitrator in governmental
projects, but instead, the respective department representative is introduced.
A Monitor engineer of the urban development and housing department of
Kandahar was stated as an arbitrator as per governmental rules to go through
claim identification and resolve the dispute and case.
Arbitrator Findings and Resolution:
5
Resolution Claim 1:
 The claimant should go with the 440 cm clear height of the columns as the
calculations in the BOQ for estimating the work volume were corresponding to it.
Resolution Claim 2:
The arbitrator ended the second claim officially, as the mentioned portion of
estimation was missing due to an error of the estimator of the project.
 Estimation for the stone masonry work for the inside ring beams was prepared by
the department of urban development and housing as per the request of the
Kandahar custom department and the decision of the arbitrator.
 The contractor was awarded $3500 for the stone masonry of inside ring beams
along with a time extension of one month in the contract agreement due to a loss
of time during the dispute.
Case 2:
MW High Tech Projects V Balfour Beatty Kilpatrick Ltd,
2020/June/05
6
Facts of the case:
The claim arose out of a sub-contract (“the Contract”) between the claimant (“MW”) and the
defendant (“BBK”) pursuant to which MW engaged BBK to carry out mechanical and electrical
services in relation to the construction of a new laboratory building at Dansom Lane, Hull for a
contract price of £23,370,077.
The defendant, (BBK) served five notices of delay between March 2018 and February 2019, as
required by clause 2.17 of the parties. The claimant, MW, did not respond to these notices or
request further particulars to support the extension of time (EOT) claimed within the 16-week
period specified in clause 2.18.
Delays occurred to the works and in August 2019, BBK referred to arbitration its claim for an EOT.
On 10 October 2019 the arbitrator published his decision, awarding BBK the full EOT required and
ordering MW to pay the arbitrator’s fees.
7
MW (Claimant’s) Case:
MW argued that the arbitrator did not have the authority to decide the dispute
and the arbitration decision was invalid. (BBK) had served a new delay report (“the
Goodman Report”) on MW eight days before beginning the arbitration.
BBK (Respondent) Defense:
BBK’s case is that the arbitrator had the authority to determine the dispute and the
arbitration decision was valid. BBK gave MW notice of delay and claimed an
extension of time by the letters between March 2018 and February 2019, in
compliance with the contractual requirements. By letter dated 30 July 2019, BBK
provided MW with the Goodman Report in support of its claims and invited MW to
grant the extension of time within seven days. MW failed to respond to the letter.
Judgment (Court’s Decision)
8
i) The arbitrator had the authority to determine the dispute referred to him by the
defendant on 7 August 2019.
ii) The arbitrator’s decision dated 10 October 2019 is valid and binding on the parties.
iii) The Goodman report was not a fresh notification.
iv) The claimant shall pay the defendant the sum of £37,251, being the amount paid
by the defendant to the arbitrator in respect of his fees.
Thank You

More Related Content

What's hot

Chapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame ConstructionChapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame ConstructionDouglas Vail
 
BUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTBUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTJoyeeLee0131
 
Lotus temple case study by Anjali Sethiya
Lotus temple case study by Anjali SethiyaLotus temple case study by Anjali Sethiya
Lotus temple case study by Anjali SethiyaAnjaliSethiya
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYBUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYAgrima Garg
 
Inference from case studies for designing ISBT
Inference from case studies for designing ISBTInference from case studies for designing ISBT
Inference from case studies for designing ISBTMridul Bhandari
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationAditi Garg
 
Lucknow institutional byelaws
Lucknow institutional byelawsLucknow institutional byelaws
Lucknow institutional byelawsAyushi Mehrotra
 
Council of Architecture | Architecture Design Competition Guidelines
Council of Architecture | Architecture Design Competition GuidelinesCouncil of Architecture | Architecture Design Competition Guidelines
Council of Architecture | Architecture Design Competition GuidelinesGOVIND GOPAL NAIR
 
The Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyThe Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyDinesh Kumar
 
STADIUM STUDY - SHARON SHERANI DANIEL.pdf
STADIUM STUDY - SHARON SHERANI DANIEL.pdfSTADIUM STUDY - SHARON SHERANI DANIEL.pdf
STADIUM STUDY - SHARON SHERANI DANIEL.pdfSheraniDaniel
 
Hospital Services (Library & Case Study)
Hospital Services (Library & Case Study)Hospital Services (Library & Case Study)
Hospital Services (Library & Case Study)Mansi Pushpakar
 
presentation on the literature and case study of cricket stadium
presentation on the literature and case study of cricket stadium presentation on the literature and case study of cricket stadium
presentation on the literature and case study of cricket stadium Kathmandu Engineering College
 
ARCHITECTURE THESIS 1
ARCHITECTURE THESIS 1 ARCHITECTURE THESIS 1
ARCHITECTURE THESIS 1 ong93
 

What's hot (20)

Chapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame ConstructionChapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame Construction
 
Kohinoor square
Kohinoor squareKohinoor square
Kohinoor square
 
BUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTBUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORT
 
Lotus temple case study by Anjali Sethiya
Lotus temple case study by Anjali SethiyaLotus temple case study by Anjali Sethiya
Lotus temple case study by Anjali Sethiya
 
Zostel case study
Zostel case studyZostel case study
Zostel case study
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYBUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
 
Inference from case studies for designing ISBT
Inference from case studies for designing ISBTInference from case studies for designing ISBT
Inference from case studies for designing ISBT
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliation
 
Lucknow institutional byelaws
Lucknow institutional byelawsLucknow institutional byelaws
Lucknow institutional byelaws
 
Council of Architecture | Architecture Design Competition Guidelines
Council of Architecture | Architecture Design Competition GuidelinesCouncil of Architecture | Architecture Design Competition Guidelines
Council of Architecture | Architecture Design Competition Guidelines
 
presentation ON TALL BUILDING
 presentation ON TALL BUILDING presentation ON TALL BUILDING
presentation ON TALL BUILDING
 
Office case study
Office case studyOffice case study
Office case study
 
The Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyThe Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case Study
 
STADIUM STUDY - SHARON SHERANI DANIEL.pdf
STADIUM STUDY - SHARON SHERANI DANIEL.pdfSTADIUM STUDY - SHARON SHERANI DANIEL.pdf
STADIUM STUDY - SHARON SHERANI DANIEL.pdf
 
Hospital Services (Library & Case Study)
Hospital Services (Library & Case Study)Hospital Services (Library & Case Study)
Hospital Services (Library & Case Study)
 
presentation on the literature and case study of cricket stadium
presentation on the literature and case study of cricket stadium presentation on the literature and case study of cricket stadium
presentation on the literature and case study of cricket stadium
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
ARCHITECTURE THESIS 1
ARCHITECTURE THESIS 1 ARCHITECTURE THESIS 1
ARCHITECTURE THESIS 1
 

Similar to Arbitration Cases

Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group AssignmentLin Hui
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Adnan Alam
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Alec Rendell [NBPR-2]
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterSeanGibbs12
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - AssignmentQuo Ming
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterSeanGibbs12
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 briefDoreen Yeo
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
 
The best order by an information commissioner under the right to information act
The best order by an information commissioner under the right to information actThe best order by an information commissioner under the right to information act
The best order by an information commissioner under the right to information actRaviforjustice Raviforjustice
 

Similar to Arbitration Cases (20)

Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
UK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 NewsletterUK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 Newsletter
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
UK Adjdudiators Newsletter June 2019
UK Adjdudiators Newsletter June 2019UK Adjdudiators Newsletter June 2019
UK Adjdudiators Newsletter June 2019
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
 
UK Adjudicators September 2019 newsletter
UK Adjudicators September 2019 newsletterUK Adjudicators September 2019 newsletter
UK Adjudicators September 2019 newsletter
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 Newsletter
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 brief
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
The best order by an information commissioner under the right to information act
The best order by an information commissioner under the right to information actThe best order by an information commissioner under the right to information act
The best order by an information commissioner under the right to information act
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Arbitration Cases

  • 1. Arbitration Cases Presentation by: Parvez Ahmad Hashmat Entry#: 2019CET2027 Submitted to: Prof. K.N JHA Indian Institute of Technology-Delhi- 2020
  • 2. Case 1: Haleem Khapalwak Construction Company V/S Ministry of Finance, 2018/Feb/08. The project of building a DATA Archive for Kandahar Custom was awarded to Haleem Khapalwak Construction Company on 2018/Jan/01 from the ministry of finance of Afghanistan with an estimated cost of $53600. 2
  • 3. Claimant’s (Contractor’s) Case: i. Clear columns height of the structure is differing in drawings and design, resulting in a change of 5cum volume of work in the BOQ that costs $900. ii. Claim for additional expenses incurred toward the stone masonry work for inside ring beams, which isn’t included in the BOQ that costs approximately $5000. Respondent Defense: The clarity of drawings and specifications are vibrant. The contractor estimated his bidding from BOQ not observing the drawings accurately; thus, the specified money shouldn’t be awarded to the claimant. 3
  • 4. Arbitrator Findings and Resolution: 4 According to the laws of Afghanistan, there is no arbitrator in governmental projects, but instead, the respective department representative is introduced. A Monitor engineer of the urban development and housing department of Kandahar was stated as an arbitrator as per governmental rules to go through claim identification and resolve the dispute and case.
  • 5. Arbitrator Findings and Resolution: 5 Resolution Claim 1:  The claimant should go with the 440 cm clear height of the columns as the calculations in the BOQ for estimating the work volume were corresponding to it. Resolution Claim 2: The arbitrator ended the second claim officially, as the mentioned portion of estimation was missing due to an error of the estimator of the project.  Estimation for the stone masonry work for the inside ring beams was prepared by the department of urban development and housing as per the request of the Kandahar custom department and the decision of the arbitrator.  The contractor was awarded $3500 for the stone masonry of inside ring beams along with a time extension of one month in the contract agreement due to a loss of time during the dispute.
  • 6. Case 2: MW High Tech Projects V Balfour Beatty Kilpatrick Ltd, 2020/June/05 6 Facts of the case: The claim arose out of a sub-contract (“the Contract”) between the claimant (“MW”) and the defendant (“BBK”) pursuant to which MW engaged BBK to carry out mechanical and electrical services in relation to the construction of a new laboratory building at Dansom Lane, Hull for a contract price of £23,370,077. The defendant, (BBK) served five notices of delay between March 2018 and February 2019, as required by clause 2.17 of the parties. The claimant, MW, did not respond to these notices or request further particulars to support the extension of time (EOT) claimed within the 16-week period specified in clause 2.18. Delays occurred to the works and in August 2019, BBK referred to arbitration its claim for an EOT. On 10 October 2019 the arbitrator published his decision, awarding BBK the full EOT required and ordering MW to pay the arbitrator’s fees.
  • 7. 7 MW (Claimant’s) Case: MW argued that the arbitrator did not have the authority to decide the dispute and the arbitration decision was invalid. (BBK) had served a new delay report (“the Goodman Report”) on MW eight days before beginning the arbitration. BBK (Respondent) Defense: BBK’s case is that the arbitrator had the authority to determine the dispute and the arbitration decision was valid. BBK gave MW notice of delay and claimed an extension of time by the letters between March 2018 and February 2019, in compliance with the contractual requirements. By letter dated 30 July 2019, BBK provided MW with the Goodman Report in support of its claims and invited MW to grant the extension of time within seven days. MW failed to respond to the letter.
  • 8. Judgment (Court’s Decision) 8 i) The arbitrator had the authority to determine the dispute referred to him by the defendant on 7 August 2019. ii) The arbitrator’s decision dated 10 October 2019 is valid and binding on the parties. iii) The Goodman report was not a fresh notification. iv) The claimant shall pay the defendant the sum of £37,251, being the amount paid by the defendant to the arbitrator in respect of his fees.