Pavement Design Report by priyanshu kumar 9608684800
1. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga At Munger Ghat Near
Munger, in the State Of Bihar On EPC Mode
ii
CONTENTS
1. Pavement Design report 1
1.1 General 1
1.2 Design Approach and Methodology 1
1.2.1 Type of Pavement 1
1.2.2 Design Standards 1
1.3 Input Parameters for Pavement Design 1
1.3.1 Design Period and Strategy 1
1.3.2 Design Traffic 1
1.4 Soil Characteristics for OGL Samples 2
1.5 Borrow Area Soil Characteristics for Embankment and Subgrade 3
1.6 Design of New Flexible Pavement 3
1.6.1 Design of Conventional Flexible Pavement for Main Carriageway 4
1.6.2 Design of Conventional Flexible Pavement for Service Road 10
LIST OF TABLES
Table 1-1: Design Traffic in Terms of ESAL 2
Table 1-2: Summary of OGL Sample 2
Table 1-3: Input Parameters for IITPAVE of Conventional Pavement 4
Table 1-4: Calculated Conventional Flexible Pavement Thickness for New Construction: 7
Table 1-5: Recommended Pavement Composition for Service Roads 10
LIST OF FIGURES
Figure 1-1: IITPAVE INPUT File 5
Figure 1-2: IITPAVE OUTPUT File 6
LIST OF ANNEXURES
Annexure 1.1: Detailed Result of test conducted on OGL of soil sample 8
Annexure 1.2: Detailed laboratory test result of borrow area soil sample with
90th
percentile CBR calculation
9
2. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near
Munger, in the State of Bihar On EPC Mode
1/10
1. PAVEMENT DESIGN REPORT
1.1 General
Pavement design basically aims at determining the total thickness of the pavement structure
as well as the thickness of the individual structural components. The approach of the consultant
is to work out the required crust thickness by IRC methods.
1.2 Design Approach and Methodology
1.2.1 Type of Pavement
For Main Carriageway Flexible Pavement shall be executed as per IRC-37: 2012.
1.2.2 Design Standards
The following standards are applicable for new pavement of the project:
New Flexible Pavement Design
IRC: 37-2012 – “Guidelines for the Design of Flexible Pavements”
1.3 Input Parameters for Pavement Design
The performance of pavements is affected by several factors which includes the following
factors which are described as below.
1.3.1 Design Period and Strategy
As per clause 5.1.1 of Schedule-B “Flexible pavement for new pavements road. Shall be
designed for a minimum design period of 15 (Fifteen) years. Stage construction shall not be
permitted.”
1.3.2 Design Traffic
Design Traffic (Cumulative Number of Standard Axles):
The traffic loading in terms of the cumulative number of standard axles for the given period
has been computed using the following relationship as given in IRC: 37-2012:
3 6 5 1 1
n
r
N A D F
r
Where,
N = Cumulative number of standard axles to be catered for the design life
in terms of msa.
r = Annual growth rate of commercial vehicles
n = Design life in years
A = Initial traffic in the year of completion of construction in terms of
number of commercial vehicles per day exceeding 3 tonnes
D = Lane distribution factor
F = Vehicle Damage Factor
3. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near
Munger, in the State of Bihar On EPC Mode
2/10
As per schedule Clause 5.1.2 pavement shall be designed for a minimum design traffic of 30
Million Standard Axles.
Table 1-1: Design Traffic in Terms of ESAL
Sections
Design Traffic (MSA)
Minimum Design Traffic
as per Schedule-B
Recommended
Design Traffic
Munger Km 00+000 to Km 9+394 30 30
Khagaria Km 0+075 to Km 5+198 30 30
1.4 Soil Characteristics for OGL Samples
Investigation has been carried out on the test pit samples taken at the following different
locations
OGL at the toe of embankment.
Representative soil sample were collected on 1st
August 2019 and samples were tested from
2nd
August 2019 to 11th
August 2019.
The following test have been carried out on each of the samples collected from test pits.
a) Atterberg’s Limits – IS:2720 (Part V);
b) Modified Proctor Density – IS: 2720 (Part VIII);
c) Field Moisture Content – IS:2720 (Part II);
d) Four Days Soaked CBR – IS: 2720 (Part XVI);
e) Free Swell Index Test – IS: 2720 (Part XI);
f) Grain Size Analysis – IS: 2720 (Part IV);
g) Soil Classification – IS: 1498.
Test Pits at Toe of Embankment (OGL soil)
To assess the existing OGL properties, test pits were dug at frequent intervals. Representative
samples of OGL were collected from each test pit for laboratory analysis. The results of the test
conducted on existing subgrade soil samples have been summarized in Table 1-2.
Table 1-2: Summary of OGL Sample
Soil Property Average Min Max
Liquid Limit (%) - - 40.80
Plastic Limit (%) - - 25.30
Plasticity Index (%) - N.P. 15.50
MDD (gm/cc) 1.93 1.84 2.05
OMC (%) 12.77 11.00 15.30
Soaked CBR (%) 6.18 4.40 9.40
Free Swell Index (%) - NIL 18.20
4. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near
Munger, in the State of Bihar On EPC Mode
3/10
Detailed results of tests conducted on existing subgrade soil sample are presented in
Annexure 1.
1.5 Borrow Area Soil Characteristics for Embankment and Subgrade
Potential borrow area locations have been identified along the project road for construction of
subgrade and embankment and representative samples of identified sources have been
collected for laboratory testing.
The detailed laboratory investigation has been carried out on borrow area soil samples as per
relevant codes & specifications.
Following test have been carried out on each of the borrow area soil sample collected;
a) Atterberg’s Limits (Liquid Limit and Plastic Limit) – IS:2720 (Part V);
b) Modified Proctor Density – IS: 2720 (Part VIII);
c) Four Days Soaked CBR – IS: 2720 (Part XVI);
d) Free Swell Index Test – IS: 2720 (Part XI);
e) Grain Size Analysis – IS: 2720 (Part IV);
From the borrow area test results, it has been observed that the borrow area soil is non-
plasticity Silty Sand. Laboratory testing indicates that CBR is in the range of 10.29 per cent to
12.94 per cent. Based on the borrow area investigation, it is proposed to use soil only from
sources having CBR value of minimum 8 per cent for subgrade construction. Detailed laboratory
test result of borrow area samples are given in Annexure 2.
Subgrade –
Borrow area Soil shall be used to prepare subgrade and embankment soil.
Out of the prospective borrow area samples, 90th
percentile CBR has been considered as the
representative CBR value for borrow area soil, here 90 percentile refers to the CBR value, which
is lower than 90% values obtained from results.
The detailed calculation for 90th
percentile CBR value for borrow area soil has been provided
below in Annexure 2.
Design CBR Determination for New Construction Stretch:
90th
percentile CBR values of Borrow material was found to be 10.35 % which is higher than
minimum CBR value required i.e. 8 % as per Clause 5.1 of IRC 37-2012, hence borrow areas
are suitable for subgrade and embankment preparation.
For the purpose of flexible pavement design, Effective Subgrade CBR of 8 per cent is considered
for safe and conservation approach.
1.6 Design of New Flexible Pavement
Design of new flexible pavement is applicable for main carriageway sections.
5. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near
Munger, in the State of Bihar On EPC Mode
4/10
1.6.1 Design of Conventional Flexible Pavement for Main Carriageway
Specifications and Input parameters as per IRC: 37-2012
In order to provide scientific design thickness ‘Mechanistic–Empirical pavement design’
procedure is followed as directed in IRC: 37-2012. The input parameters used in the design
are given in Table 1-3.
Table 1-3: Input Parameters for IITPAVE of Conventional Pavement
Sl. No. Description Value considered
1 Wheel Configuration Dual Wheel
2
Spacing Between the wheels
(mm)
310
3 Load of Single Wheel (N) 20000
4 Tire Pressure (MPa) 0.56
5
Bituminous Layer E-Value (MPa)
(DBM and BC layer together)
1700MPa – VG-30
6
Unbound Layers E-Value (MPa)
(GSB and WMM together)
MR_granular = 0.2*h0.45
MR subgrade
= 0.2*4500.45
(66.60)
MR_granular = 208.19
(Eq. 7.3 of IRC:37-2012)
7 Subgrade Layer E-value (MPa)
MR = 17.6*(CBR)0.64
= 17.6*(8)0.64
MR = 66.60
(Eq. 5.2 IRC:37-2012)
8 Poisson’s Ratio
Bituminous Layers: 0.35
WMM/GSB: 0.35
Sub-grade: 0.35
The flexible pavements are designed for two failure models as described in IRC: 37-2012.
i) Fatigue Model:
Fatigue Model has been calibrated in the R-56 (54) studies using the pavement performance
data collected during the R-6 (57) and R-19 (58) studies sponsored by MoRTH;
Nf = 2.21 × 10-04
× [
£
]3.89
× [ ]0.854
…………… Eq 6.1 of IRC:37-2012
Nf = 0.5161 × C × 10-04
× [
£
]3.89
× [ ]0.854
…………… Eq 6.3 of IRC:37-2012
Where,
Nf = Fatigue life in number of standard axles,
£t = Maximum Horizontal Tensile strain at the bottom of the bituminous layer
Mr = Resilient modulus of the bituminous layer.
For design traffic of 30 million standard axel; Eq. 6.1 of IRC: 37-2012 (80 per cent reliability)
and resilient modulus of VG-30 grade bitumen at 35°C is 1700 MPa is used for fatigue analysis:
30×106
= 2.21 × 10-04
× [
£
]3.89
× [ ]0.854
£t = 268.4 × 10-6
(Allowable/Maximum Horizontal Tensile Strain)
6. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near
Munger, in the State of Bihar On EPC Mode
5/10
ii) Rutting Model:
The rutting life of the pavement composition is calculated by using the following equation with
the obtained vertical compressive strains at on top of subgrade through IITPAVE.
Nr = 4.1656 x 10-08 × [
£
]4.5337
……… (Eq. 6.4 of IRC:37-2012)
Nr = 1.41 x 10-08 × [
£
]4.5337
……… (Eq. 6.5 of IRC:37-2012)
Where,
Nr = Number of cumulative standard axles, and
£v = Maximum Compressive Vertical strain in the subgrade
For design traffic of 30 million standard axel; Eq. 6.4 of IRC: 37-2012 (80 per cent reliability)
is used for rutting analysis:
30×106
= 4.1656 x 10-08 × [
£
]4.5337
£v = 528.3 10-6
(Allowable Vertical Compressive Strain)
After Allowable strains are obtained, proposed Pavement thickness is evaluated on IIT PAVE
software using input parameters specified in Table 1-3 and critical strains are obtained. Details
are presented Figure 1-1 & Figure 1-2:
Figure 1-1: IITPAVE INPUT File
7. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near
Munger, in the State of Bihar On EPC Mode
6/10
Figure 1-2: IITPAVE OUTPUT File
8. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near Munger, in the State of Bihar On EPC Mode
Table 1-4: Calculated Conventional Flexible Pavement Thickness for New Construction:
Carriageway
Design
Traffic
(msa)
Allowable Strain
Effective
Subgrade
CBR
(%)
Calculated Pavement
Composition(mm)
Elastic
Modulus
(MPa)
of
DBM
Layers
Obtained Strains
Remarks
Horizontal
Tensile
Strain
(Fatigue)
Vertical
Compressive
Strain
(Rutting)
BC DBM WMM GSB
Horizontal
Tensile
Strain
(Fatigue)
Vertical
Compressive
Strain
(Rutting)
New construction of Main
carriageway from Km
00.000 to Km 9.394 &
Km 0.075 to Km 5.198
30 268.48 x10-6
528.30 x10-6
8.0 40 100 250 200 1700 255 x10-6
359 x10-6
Safe
However, Minimum Pavement thickness that contractor shall provide is specified in schedule B clause 5.2. Therefore, Recommended Pavement thickness
for the project corridor is:
BC 40 mm
DBM 105 mm
WMM 250 mm
GSB 260 mm
11. PAVEMENT DESIGN REPORT
Construction of Road Approaches to Rail-Cum-Road Bridge Across River Ganga at Munger Ghat Near
Munger, in the State of Bihar On EPC Mode
10/10
CBR values for a borrow area samples obtained are as follows:
11.43, 12.6, 10.44, 10.97, 10.29, 10.36, 11.73, 12.94, 11.14, 12.26.
Arranging the above values in ascending order
10.29, 10.36, 10.44, 10.97, 11.14, 11.43, 11.73, 12.26, 12.6, 12.94
Calculating percentage greater than equal to each of the values are as follows:
For CBR of 10.29, percentage of values greater than equal to 10.29 = (14/14) *100 = 100
For CBR of 10.36, percentage of values greater than equal to 10.36 = (13/14) *100 = 92.8
and so on.
Plot between percentage of values greater than equal and the CBR values versus the CBR as
follows.
The 90th
percentile CBR value = 10.353, and 80th
percentile CBR value = 10.425
1.6.2 Design of Conventional Flexible Pavement for Service Road
Service Roads are designed for design traffic of 10 msa as per clause 5.5.8 of IRC: SP:73-2015
and the pavement thickness are determined from catalogues of IRC: 37-2012 and the same is
given in Table 1-5 below: -
Table 1-5: Recommended Pavement Composition for Service Roads
Design Traffic
(msa)
Subgrade
CBR (%)
Recommended Pavement
Composition(mm)
BC DBM WMM GSB
10 8.0 40 60 250 200
0
20
40
60
80
100
120
0 2 4 6 8 10 12 14
%
Equal
to
greater
than
Subgrade CBR
Evaluation of Subgrade CBR for Pavement
Design