SlideShare a Scribd company logo
1 of 55
POWER PLANT ENGINEERING
UNIT 5
ECONOMICS , SELECTION CRITERIAS
& ENVIRONMENTAL ISSUES
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
LOAD CURVE
TIME - hours
L
O
A
D
In
M
w
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• BASE LOAD : LOAD BELOW WHICH DEMAND
NEVER FALLS. LOAD REQUIRED TO BE
SUPPLIED 100 %
• PEAK LOAD : MAX. LOAD SUPPLIED – IT MAY
BE 15 – 20 % OF TIME
• INTERMEDIATE LOAD : LOAD SUPPLIED
BETWEEN BASE AND PEAK.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
LOAD CURVE & LOAD DURATION CURVE
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Load duration curve
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
700
• RATED CAPACITY OF UNIT : Installed Capacity
• PEAK LOAD : MAXIMUM LOAD PRODUCED
• AVERAGE LOAD : GENERATED POWER /HOURS
• INSTALLED CAPCITY = 1000 MW
• TOTAL PLANNED SHUT DOWN = 720 Hrs.
• FORCED OUTAGE = 50 Hrs.
• UNIT IN SERVICE = 8760-720-50 =7990 Hrs.
0-6 6-8 8-9 9-17 18-20 20-22 22-24
600 700 800 900 750 700 650
Daily loading pattern of a Power Station (in MWs)
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• MAX LOAD = 900 MW
• MINI LOAD = 600 MW
• AVERAGE LOAD = SUM OF LOAD/TOTAL HOURS
= 6X600+2X700+800+8X900+3X750+2X700+2X650
24
= 17950/24 =747.91 MW
LOAD FACTOR = AVERAGE LOAD/PEAK LOAD
= 747.91/900 = 0.831
CAPACITY FACTOR = AVERAGE LOAD/RATED CAPACITY
= 747.91/1000 = 0.74791
RESERVE FACTOR =LOAD FACTOR/CAPACITY FACTOR
=0.831/0.74791= 1.111
USE FACTOR = AV.LOADX8760/INST.CAP.X HOURS RUN
= 747.91X8760/1000X7990 =0. , Say 0.819S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
DEMAND & DIVERSITY FACTORs
IF LIGHTING LOAD = 35 KW , MACHIENRIES LOAD = 450 KW,
MISC. LOAD = 15 KW are connected
200 Nos of 60 W BULB IN SERVICE FOR 16 Hours. 5 nos. of
M/c of 1500 W and 10 nos. of M/c OF 750 W IN SERVICE for
2 Shifts, 7 hours/Shift.
CONNECTED LOAD : SUM OF RATED CAPACITY OF ALL
EQUIPMENTS AND OUTLETS ON CONSUMER’S CIRCUIT
CONNECTED LOAD =35+ 450+15=500 KW
L.L = 16X60X 200 =19200 W = 19.2 KW
M.L.= 2X7X5X1500+ 2X7X10X750=210000 W = 210 KW
MISC.L= 5 KW
DEMAND FACTOR = ACTUAL MAX. CONSUMPTION
TOTAL CONNECTED LOAD
= 19.2 + 210 +5/500 =234.2/500 =0.4684
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
DIVERSITY FACTOR
= TOTAL LOAD CONNECTED/MAX. CONSUMPTION
DIV. FACTOR (SYSTEM)= 500/234.2 = 2.1349
DIV. FACTOR (L.L.) = 35/19.2 =1.8229
DIV. FACTOR (M.L.) = 450/210 = 2.1428
DIV. FACTOR (Misc. L.) = 15/5 = 3
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• HEAT RATE =Heat Input (I)/Net kW output(L)
• Plant Net Efficiency = Net output(L)/Heat Input (I)
• INCREMENTAL HEAT RATE :Amount of energy
needed to generate additional output at any given
load
• When plant output decreases, heat rate increases,
where as the incremental heat rate decreases.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
COST/PER K.W
• DETERMINED BY
• FIXED COST + O & M COST+ FUEL COST
• COST IS BASED ON POWER EXPORTED YEARLY
• FIXED COST : INTEREST, DEPRECIATION, INSURANCE,
TAXES ON CAPITAL INVESTED.
• CAPITAL COST = CONSTRUCTION COST+ LAND COST
• CONSTRUCTION COST = DESIGN+ PRICE OF EQPTS+
TRANSPORT+ ERECTION + COMMISSIONING
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Total Annual Cost ( Ct )
Cc = Construction cost = 1430 Cr.
I = INTEREST RATE = 12 % = 0.12
D= DEPRECIATION = 100/15 =6.67 % = 0.0667
T= TAXES = 14 % = 0.14
W = TOTAL ANNUAL WAGES = 126 Cr.
M = MTCE. CHARGES = 30 Cr.
Cf = Fuel Cost = Cost of fuel including its trans.
Ct= I + D + T x Cc +(W+M)+ Cf
100
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• Fuel cost : Total fuel required (T) x Cost/T
• Total fuel reqd.= Total Power generated/Fuel Kg/Kwh
• C.F.= 85% Installed = 420 MW
• C.F.= Average load/Installed capacity
• Ave.load = 0.85x420 =357 MW
• Total power generated =0.85x420x103
x8760
=312.732X 107
KWH
Fuel reqd./KWh = 1 Kg. (Net Heat rate = 1Kg/1KWh)
•
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Annual Fuel reqd.=312.732X10 7
Kg.=3127320T
Fuel Cost =3127320X1600 =Rs. 5003712000 =500.03712X10 7
Total cost = (0.12+0.067+0.14)x1450x107
+(120+30) 107
+
fuel cost
= 474.15 X 107
+150 X 107
+500.3712 X 107
= 1124.5212 Cr.
Cost/Unit = Total Cost/Units Generated = 1124.5212/312.732
=3.5958
Cost of Generation = Rs. 3.60/kW
Profit margin = 43 p/unit : Selling price = 3.6 +0.43 =4.03
Auxiliary consumed = 8 %:
Power exported = (1-0.08)x units generated
=0.92x312.732 x107
Units: Revenue=4.03x0.92x312.732 Cr.
= 1159.485163 Cr.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Determine the generating cost per unit of 80 MW power station with the
following data
Capital cost = Rs. 160 x 107
; Annual cost of fuel = Rs. 32 x 106
;
Annual wages and taxes = Rs. 36 x 106
; Interest and depreciation = 10 %
of capital cost : Annual load factor = 45 %
Assume, Maximum load = 80 MW
Load factor = 0.45 = Average load /Maximum load
Average load = 0.45 x 80 = 36 MW
Total energy generated = Average load x 8760 = 36 x 8760 =
315.360 x106
kWH (units)
Generation cost = Fixed cost + Running Cost
Fixed cost = % of (interest + depreciation ) on Capital cost
Fixed cost = 0.1 x 160 x 107
= Rs.160 x 106
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Running cost = Annual fuel cost + Annual wages and taxes
= 32 x 106
+ 36 x 106
= 68 x 106
Generation Cost = 160 x 106
+ 68 x106
= Rs. 228 x 106
Cost of generation of 1 unit
= Total generation cost/Total energy generated (units)
= 228 x106
/315.360 x106
= Rs.0. 7229 = 72.3 paise.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Find the cost of generation per kWh from the following data :
Capacity of the plant = 150 MW ; capital cost = Rs. 20,000 per kW
installed. Interest and depreciation = 10 % on capital ;
Fuel consumption = 1.2 kg/kWh; Fuel cost = Rs. 400 per tone; salaries,
wages, repair and maintenance=Rs.150x106
per year; Max. demand =
120 MW ; load factor = 50 %
Load factor = Average load/max. demand = 0.5
Average load = 0.5 x 120 MW = 60 MW
Total energy produced=Average loadx8760 = 60 x103
x 8760
=525.6 x 106
kWh(units)
Capital cost = 20000 x 150 x 103
=Rs. 300 x 107
Total cost of generation = Fixed cost + Running cost
Fixed cost = % (Interest + depreciation) x Capital cost
= 0.1 x 300 x 107
= Rs. 300 x 106
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Fuel consumption / unit = 1.2 kg/kWh
Fuel requirement for annual generation = 1.2 x 525. 6 x 106
= 630.72x106
kg. = 630.72 x103
T.
Annual fuel cost = 630.72 x 103
x 400 = Rs. 252.288 x 106
Cost on salaries, wages, repair and maintenance = Rs. 150 x 106
Running cost =Rs. 252.288 x 106
+ Rs. 150 x 106
= Rs.402.288 x 106
Total generation cost = Fixed cost + Running cost
= Rs.300x106
+ Rs. 402.288 x 106
= Rs. 702.288 x 106
Cost of generation/unit
= Total generation cost/Total energy produced
= Rs. 702.288 x 106
/ 525.6 x 106
= Rs. 1.34
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
DEPRECIATION
• STRAIGHT LINE METHOD :
• DEPRECIATION OCCURS UNIFORMLY
• MONEY SAVED NEGLECTS ANY INTEREST
• IF ‘A’ = CAPITAL , G= SALVAGE VALUE,
N= YEARS OF USEFUL LIFE
THEN DPRECIATION “D”=(A-G)/N
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
DEPRECIATION
• SINKING FUND METHOD :
• SUM OF MONEY IS SET ASIDE EVERY YEAR & INVESTED TO
EARN COMPOUND INTEREST
• IF “P” IS SUM INVESTED EVERY YEAR FOR ‘N’ YEARS TO
HAVE DPRECIATION AMOUNT ‘S’ AND THE RATE OF
INTEREST IS ‘I’
• VALUE OF MONEY AT END OF 1 YEAR = P
• VALUE AT THE END OF 2 YEAR = (P+Pi) + P
• VALUE AT 3RD
YEAR = (P+Pi)Xi +Pi+P
• VALUE AT N-1 YEAR = P(1+i) (N-1-1)
• VALUE AT N YEAR = P(1+i) (N-1)
• SUM OF INVESTMENT in N YEARS = P+P(1+i)….+P (1+i) (N-1)
• S = P (1+i) (N)
-1) = A – G =A’ : P= A’ i
i (1+i) (N)
-1)
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
PRESENT WORTH
• IFSUMOF“P”ISINVESTEDNOW,
• ITSVALUEWILLGETDECREASE
• GEOMETRICALLYOVERTHEYEARS
• THERATEOFDECREASEIS“i”
• PRESENTWORTHIN“N”YEARS=P/(1+i)
N
• IFP=110:I=10%
• P.W.AFTER1YEAR=110/(1+.1)=110/1.1=100
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Reliability of Power Plant
Total no. of hours a power plant is available for power generation is an
important factor in designing a power Plant.
This factor is called as availability factor or reliability factor.
No. of hours a plant is not in service due to stoppage of units due to
various causes while the unit in service are called as Forced outage
hours. Forced outage hours has to be below 2 % for efficient
operation. Forced outage is a measure of Reliabilty of Unit
In a year a power plant has to be stopped to undertake annual
maintenance works , which may vary to 30 days to 25 days.
In addition to these Plant may not be in service due to stoppage of
units on some causes while in operation , that is called forced outages.
Ratio total no. of hours units in service in a year to Total no. of hours
after deducting annual maintenance hours is availability factor.
Availability factor of a power plant is expected to maintain above 90
% to operate economical.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• As forced outages increase the operation and maintenance
costs, proven reliability of equipment and regular preventive
maintenance are essential not only to guarantee electric
supply but also for overall economical operation of plant
• Costs of power generation can be reduced by
 Selecting equipment of longer life and proper capacities
 Running the Plant at high load factor
 Increasing the efficiency of power plant
 Carrying out proper maintenance of equipments to avoid
breakdowns and forced outages
 Keeping proper supervision and trained manpower so as to
keep lesser break downs and efficient operation
 Using a plant of simple and proven design
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
SELECTION OF CAPACITY
TOTAL CAPACITY REQUIRED BASED ON
MAXIMUM DEMAND EXPECTED
GROWTH OF DEMAND ANTICIPATED
RESERVE CAPACITY REQUIRED
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
SIZE OF UNITS
• VARIATION OF LOAD DURING 24 HOURS
• TOTAL UNITS CONNECTED TO GRID
• MINI. STRAT-UP & SHUTDOWN PERIOD
• MANITEANCE PLANNED
• PLANT EFFICIENCY Vs SIZE
• COST/MW, SPACE /KW Vs SIZE
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
LOCATION OF THERMAL POWER PLANT
• AVAILABLITY OF FUEL
• AVAILABLITY OF
COOLING WATER
• LAND COST
• CHARACTER OF SOIL
• DISPOSAL OF ASH
• WIND DIRECTION &
WATER CURRENT
• RAIL & ROAD
CONNECTION
• ACCOMODATION FOR
STAFF
• ZONE -FREE FROM
EARTH QUAKE
• SECURITY
CONSIDERATIONS.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
HYDRO ELEC. POWER PLANT
• HYDRO : BASED ON AVAILABLITY OF WATER
AND UTILISABLE WATER HEAD
• INITIAL COST WILL BE VERY HIGH
• RUNNING COST WILL BE LESS
• TAKES MORE TIME TO CONSTRUCT
• DIFFICULT TO CONVINCE PEOPLE
• POWER CAN BE PRODUCED BY TAKING LESS TIME
• MOSTLY MULTI PURPOSE LIKE … IRRIGATION,
FLOOD CONTROL , POWER GENERATION,
PUMPING STATION.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Problems
• 1. A Power Plant has the following annual factors :
Load factor = 0.75, Capacity factor= 0.6, Use Factor
=0.65. Max. demand is 60 MW.
• Estimate a) The Annual energy produced,
• b) the reserve capacity and C) hours of operation and
hours during which plant was not in service
Load factor = Average Load/Max. Load
0.75 = Average Load/60 MW
Average load = 60 x 0.75 = 45 MW
a) Annual Energy produced = Average load x 24 x 365
= 45x24x365 = 394200 MWH =394.2 x106
kWh
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Capacity factor = Aver. Load/Installed capacity
0.6 = 45/installed capacity
Installed capacity = 45/0.6 = 75 MW
b) Reserve capacity = Installed – max. Load
= 75 – 60 = 15 MW
Use factor = Energy Produced/Max. energy possible
0.65 = 394.2 x 106
/75 x running hours
c)Running hours = 394.2x 106
/75x0.65 = 8086.154 hrs.
Unit not in service = 8760-8086.154 = 673.846hrs.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
2. A power station of 30 MW capacity has the
annual max. demand of 25 MW. It supplies
loads having max. demands of 10 MW, 8.5
MW,5MW and 4.5 MW. The annual load
factor is 45%. Estimate a) Average load,
b)Energy supplied in a year, c)the diversity
factor and
d) Demand factor.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• Peak Load = 25 MW
• Connected load = 10+ 8.5+5+ 4.5 = 28 MW
• Load factor = Aver.load/Peak load
• 0.45= Aver.Load/Peak load
• Aver.load=peak loadx0.45=25x 0.45=11.25MW
Energy produced=11.25x8760=98.550x 106
units
Demand factor = Peak load /Connected load
= 25/28 =0.8928
Diversity factor = Connected load/Peak load
= 28/25 = 1.12
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• A central power station has annual load factor, capacity factor and use
factor as 60 %, 40 % and 45 % respectively. The maximum load is 15
MW. Estimate (a) the annual energy production and revenue earned if
the cost of energy is Rs. 1 /kWh, (b) the reserve capacity over and above
the peak load and (c) the hours per year the station is not in service.
Load factor = 0.6 ; Capacity factor = 0.4 ; use factor = 0.45 ; peak load =
15 MW
Load factor = Average load/Peak load
Average load = load factor x peak load = 0.6 x 15 = 9 MW
Total power generated in a year = Average load x 8760 hours
= 9 x 8760 = 78840 MWH
=78.84 x106
kWh
Cost of energy /unit = Rs.1
Total revenue earned = Total power generated x cost/unit
= 78.84 x106
x1 = Rs. 78.84 x106
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Capacity factor = 0.4 = Average load/Installed capacity
= 9/installed capacity
Installed capacity = 9/0.4 = 22.5 MW
Reserve capacity = Installed capacity – Maximum load
= 22.5 – 15 = 7.5 MW
Use factor = Total power generated/ ( Installed capacity x Total
running hours)
0.45 = 78.84 x106
/22.5 x total running hours
Total running hours = 78.84 x106
/22.5 x0.45 = 7786 hours
Hours per year not in service = 24 x 365 – running hours
= 8760- 7786 = 974 hours.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
A power station of 30 MW capacity has the maximum annual demand of 25
MW. It supplies loads having maximum demands of 10 MW, 8.5 MW, 5
MW and 4.5 MW. The annual load factor is 45 %. Estimate a) the average
load b) the energy supplied per year c) diversity factor and d) demand
factor.
Given Installed capacity = 30 MW, Maximum demand = 25 MW,
Demands connected loads in MW = 10, 8.5, 5, 4.5; Annual load factor = 0.45
Load factor = 0.45 = Average Load/Maximum load = 0.45
= Average Load/25
Average Load = 25 x 0.45 = 11.25 MW
Energy supplied in a year = Average load x 8760 = 11.25 x 8760 =98.55x106
kWH.
Load connected = 10 + 8.5+ 5 + 4.5 = 28 MW
Demand factor = Maximum load/ Connected load = 25/28 =0.89
Diversity factor = Connected load/Maximum load = 28/25 = 1.12
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
3. A Power Station has a maximum demand of
10,000 kW and the daily load on the Station
is as follows :
Time kW Time kW
6 a.m to 8 a.m. 3500 5 p.m. to 7 p.m. 8500
8 a.m. to 12 noon 8000 7 p.m. to 9 p.m. 10000
12 noon to 1 p.m. 3000 9 p.m. to 11 p.m. 4500
1 p.m. to 5 p.m. 7500 11 p.m. to 6 a.m. 2000
a) Draw the load curve and load duration curve
b) Choose the size and no. of generating Units
c) Draw up the operating schedule of the Units
d) What reserve plant would be necessary
e) Calculate Load factor, Plant capacity factor and Use factor of
the station.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Load (kW) - duration
10000 - 2 hours
8500 - 2 hours
8000 - 4 hours
7500 - 4 hours
4500 - 2 hours
3500 - 2 hours
3000 - 1 hr.
2000 - 7 hrs.
Load requirements and its duration can be had from load
Duration curve
Max. load required = 10000 kW
Minimum load required = 2000 kW
Reserve capacity assumed = 2500 kW
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
4 units of 2500 kW for running and 2500 kW as stand
by , so 5 nos. of 2500 kW are to be selected.
Operating schedule :
1 unit of 2500 kW run for – 24 hours
2 units of 2500 kW run for – 17 hours
3 units of 2500 kW run for - 12 hours
4 units of 2500 kW run for - 8 hours
Instead of 2500 kW unit if 2000 kW is selected,
then no. of units required including reserve
of 2000 kW = 10000+2000/2000 = 6
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Then operating schedule will be
1 unit of 2000 kW run for 24 hours
2 units of 2000 kW run for 17 hours
3 units of 2000 kW run for 14 hours
4 units of 2000 kW run for 8 hours
5 units of 2000 kW run for 4 hours.
Load factor = Average load/Max load
Average load = (10x2+8.5x2+8x4+7.5x4+4.5x2+
3.5x2+3x1+2x7)MWH/24 = 132/24 = 5.5 MWh
Load factor = 5.5/10 = 0.55
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• Capacity factor = Average load /Installed Cap.
• Capacity factor = 5.5/12.5 (or) 5.5/12
=0.44 (or) 0.45833
Use factor = Energy produced/Max. energy possible
= 5.5 x24/12.5 x24 (or) 5.5x24/12 x24
=044 (or) 0.45833
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
4.Determine the Generating cost per unit of 80 MW
Power Station with the following data:
• Capital Cost = Rs.160 Cr.
• Annual fuel Cost = Rs.3.2 Cr.
• Annual wages = Rs. 3.6 cr.
• Interest and Depreciation = 10 %
• Annual load factor = 45 %
Assume capacity = Peak load = 80 MW
Average load = peak load x load factor = 80x0.45
= 36 MW
Energy produced in a year = 36x24x365 = 315.36x106
units
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Generation cost = total cost/Total energy produced
Cost = Fixed cost + Running cost
Fixed Cost = (Int.+ Depreci.) x Constn. Cost
= 160x 107
x 0.1 =Rs. 160 x 106
Running Cost = Annual Fuel cost + Annual Mtce cost =
3.2 + 3.6 = 6.8 Cr.
= Rs. 68 x 106
Total cost = Rs. (160 + 68 ) x 106
Generation Cost = 228 x 106
/ 315.36 x 106
= Rs. 0.7229 = 72.29 paise
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
5. A Plant costing Rs. 65,000 has a useful life of
15 Years. Find the amount which should be
saved annually to replace the equipment at
the end of time
a) by the straight-line method
b) by the sinking fund method , if the annual
rate of compound interest is 5%. Assume
salvage value of the equipment is Rs.5000
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Plant cost = A = Rs. 65000
Salvage Cost = G = Rs. 5000
No. of years = N = 15
Depreciation by straight line method :
Depreciation charge per year = (A-G)/N
= (65000 – 5000)/15
= 60000/15 = Rs.4000
Depreciation by sinking fund method :
•A’ = Capital cost – salvage value = 65000 – 5000 = Rs. 60000
•Rate of compound interest = I = 5 %
•No. of years = N = 15
•Amount to be kept side per year = P
•P = (A’ x i) /{(1+i)N
- 1} = (60000 x 0.05)/ {(1+.05)15
– 1 }
•P=3000/ (1.0515
– 1) = 3000/(2.07893 -1) = 3000/1.07893
= Rs. 2780 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
The incremental fuel costs for two generating units A and B of s power
plant are given by the following relations;
dFA /dPA = 0.06 PA + 11. 4
dFB /dPB = 0.07 PB + 10
where P is the power in MW and F is the fuel cost in rupees per hour.
Find the economic loading of the two units when the total load to be
supplied by the power station is 150 MW.
Find the increase in fuel cost per hour if the load is equally shared by the
two units.
Given dFA /dPA = 0.06 PA + 11. 4
dFB /dPB = 0.07 PB + 10
Total load = PA + PB = 150 MW
PA = 150 – PB
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
The condition for economic loading demands equal
incremental heat rate of the two units which leads to
dFA /dPA = dFB /dPB
0.06 PA + 11. 4 = 0.07 PB + 10
0.06 PA - 0.07 PB = 10 – 11.4 = - 1.4
0.06 (150- PB ) – 0.07 PB = - 1.4
9 -0.06 PB - 0.07 PB = - 1.4
-0.13 PB = - 10.4
0.13 PB = 10.4
PB = 10.4/0.13 = 80 MW : PA = 150 -80 = 70 MW
If load is equally shared by units ie. PA = PB = 150/2 = 75 MW
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Then increase in fuel cost of unit A is given by
75
ƪ70 dFA x dPA = [ 0.06 PA
2
/2 + 11.4 PA ]75
70
dPA
= {( 0.06 x 752
)/2 + 11.4 x 75)} – { (0.06 x 702
)/2 + 11.4 x 70)}
=Rs. 78.75
Then increase in fuel cost of unit B is given by
75
ƪ80 dFB x dPB = [ 0.07 PB
2
/2 + 10 PB ]75
80
dPB
= {( 0.07 x 752
)/2 + 10 x 75)} – { (0.76 x 802
)/2 + 10 x 80)}
= Rs.- 77.125
Net increase in fuel cost = 78.75 – 77.125 = Rs. 1.63
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
The loads on a power plant with respect to time for 24 hours are given
below
Time (hours) :0-6 : 6-8: 8-12:12-14:14-18:18-22:22-24
Load (MW) : 40: 50 : 60 : 50: 70 :80 : 40
Draw the load curve and find out the load factor of the power station. If the
loads above 60 MW are taken by unit of 20 MW capacity, find out the
load factor and the use factor of the standby unit.
Total load in 24 hours = 6x 40 + 2x50+ 4x 60 +2x 50 + 4x 70 + 4x
80 + 2 x40 = 1360 MWH
Average load = 1360/24 =56.67 MW
Load factor of station = Average load/peak load = 56.67/80 =
0.70833=0.71
Loads taken by standby unit (load above 60 MW) are 70-60 =
10 MW between 14 and 18 hours ie for 4 hours, 80-60 = 20
MW between 18 and 22 hours ie for 4 hours.S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Total Loads taken by standby unit = 4 x 10 + 4 x 20 =
120 MWH
Average load = 120/8 = 15 MW
Load factor = average load/peak load = 15/20 = 0.75
Capacity use factor = Total power generated/
(Installed capacity x hours of operation)
=120/(20x8) = 120/160 =0.75
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
A central power station has annual load factor, capacity factor and use
factor as 60 %, 40 % and 45 % respectively. The maximum load is 15 MW.
Estimate (a) the annual energy production and revenue earned if the cost
of energy is Rs. 1 /kWh, (b) the reserve capacity over and above the peak
load and (c) the hours per year the station is not in service.
Load factor = 0.6 ; Capacity factor = 0.4 ; use factor = 0.45 ;
peak load = 15 MW
Load factor = Average load/Peak load
Average load = load factor x peak load = 0.6 x 15 = 9 MW
Total power generated in a year = Average load x 8760 hours
= 9 x 8760 = 78840 MWH =78.84 x106
kWh
Cost of energy /unit = Rs.1
Total revenue earned = Total power generated x cost/unit
= 78.84 x106
x1 = Rs. 78.84 x106
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE
OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Capacity factor = 0.4 = Average load/Installed capacity =
9/installed capacity
Installed capacity = 9/0.4 = 22.5 MW
Reserve capacity = Installed capacity – Maximum load
= 22.5 – 15 = 7.5 MW
Use factor = Total power generated/ ( Installed capacity x Total
running hours)
0.45 = 78.84 x106
/22.5 x total running hours
Total running hours = 78.84 x106
/22.5 x0.45 = 7786 hours
Hours per year not in service = 24 x 365 – running hours
= 8760- 7786 = 974 hours.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
A power station is said to have a use factor of 47 % and capacity factor of
40 %. For how many hours in a year was the power station not in service.
Given use factor = 0.47 ; Capacity factor = 0.4
Use factor = kWH generated in a year / (Installed capacity x
operating hours)
Capacity factor = kWH generated in a year/(Installed capacity x
8760 hours)
0.4/0.47 = (kWH generated in a year/Installed capacityx8760) /
(kWH generated in a year/Installed capacity x running hours )
0.4/0.47 = Operating Hours /8760
Operating Hours = 0.4 x 8760 /0.47 = 7455 hours
Hours not in service = 8760 – operating hours = 8760- 7455
= 1305 hours.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
The following data pertain to a power plant ;
Installed capacity = 200 MW; Capital cost = Rs. 4000 x 106
; Annual cost of
fuel, taxes and salaries =Rs. 600 x106
; Rate of interest = 5 % of the
capital; Rate of depreciation = 6 % of the capital ; Annual load factor =
65 %; Capacity factor = 55 % energy used in running the plant auxiliaries
= 4 % of total units generated. Determine a) the reserve capacity and b)
the cost of power generation
Load factor = Average load/peak load = 0.65
Capacity factor = Peak load / Installed capacity = 0.55
Peak load = 0.55 x Installed capacity = 0.55 x 200 = 110 MW.
Reserve capacity = Installed capacity – Peak load
= 200 -110 = 90 MW
Load factor = 0.65 = Average load / peak load
Average load = 0.65 x 110 MW = 71.5 MW
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
Energy generated = Average load x 8760 hrs. = 626.34x 106
kWH
Power generated used in auxiliaries = 4 %
Total units exported = 0.96 x 626.34 x106
units
= 601.286 x 106
units.
Total generation cost = Fixed Cost + Running Cost
Fixed Cost = % of (Rate of Interest + depreciation) x Capital cost
= % (5 + 6) x 4000x106
= 0.11 x 4000 x 106
= Rs. 440 x 106
Running cost = 600 x 106
Total generation cost = 440 x 106
+ 600 x 106
= Rs. 1040 x 106
Considering total energy produced
Cost of generation = Total generation cost / Energy generated
= 1040 x 106
/626.34 x 106
= Rs. 1.66
Considering auxiliaries consumption total energy exported
Cost of generation = 1040 x 106
/601.286 x 106
= Rs. 1.73S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• A power plant has the following annual factors;
• Load factor = 70%; capacity factor = 50 % ; use factor = 60 %; max.
demand = 20 MW Estimate a) annual energy production; b) reserve
capacity over and above the peak load and c) the hours per year during
which plant is not in service.
Load factor = Average load/Max. demand
Average load = Load factor x Max. demand = 0.7 x 20 MW= 14 MW.
Annual energy produced = Average load x 8760 hours = 122.640 x 106
units.
Capacity factor = Max. demand / Installed capacity = 0.5
Installed capacity = Max. demand/ Capacity factor = 20/0.5 = 40 MW
Reserve capacity = Installed capacity – Max. demand = 40 -20 = 20 MW.
Use factor = Total energy produced/ Installed capacity x Running hours =
0.6
Running hours = 14 x 8760/(40 x 0.6) =5110 hours
Hours per year during which plant is not in service = 8760 – 5110 = 3650
hours.
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
• The connected loads of a consumer consist of 10 electric bulbs of 60 W
each and 2 electric heaters of 1000 W each. His maximum demand is
1500 W. On an average, he uses 8 bulbs for 5 hours a day and one heater
for 3 hours a day. Estimate his average load, monthly energy
consumption and load factor.
Total load in a day = 8 bulbs x 5 hours x 60 W + 1 heater x 3
hours x 1000 W
= 8x 5 x 60 + 1 x 3 x 1000 = 2400 + 3000 = 5400 kWh
Average load = 5400 kWh/24 = 225 kWh
Monthly consumption = 30 days x average load = 30 x 225 kWh
= 6750 kWh
Load factor = Average load/max. demand = 225/1500 = 0. 15
S.PALANIVEL ASSOCIATE PROF./MECH. ENGG
KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)

More Related Content

What's hot

Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plantra m
 
Gas Turbine PPT
Gas Turbine PPTGas Turbine PPT
Gas Turbine PPTA M
 
Wind turbine types
Wind turbine typesWind turbine types
Wind turbine typesTaral Soliya
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plantSatish Taji
 
Doubly fed-induction-generator
Doubly fed-induction-generatorDoubly fed-induction-generator
Doubly fed-induction-generatorHarshad Karmarkar
 
Design of flywheel
Design of flywheelDesign of flywheel
Design of flywheelDhiren Patel
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantYuri Melliza
 
Vertical axis wind turbine
Vertical axis wind turbineVertical axis wind turbine
Vertical axis wind turbineDavisLazarus
 
Modern thermal power plant
Modern thermal power plantModern thermal power plant
Modern thermal power plantTaral Soliya
 
Specific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid MechanicsSpecific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid MechanicsSatish Taji
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam TurbineSumit Sharma
 
Load curve
Load curveLoad curve
Load curveboromama
 
Rankine Cycle & How to increase its efficiency
Rankine Cycle & How to increase its efficiencyRankine Cycle & How to increase its efficiency
Rankine Cycle & How to increase its efficiencyRaja Dolat
 
Betz speed limit and tip speed ratio
Betz speed limit and tip speed ratioBetz speed limit and tip speed ratio
Betz speed limit and tip speed ratioSonuKumarBairwa
 

What's hot (20)

Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
 
Rankine cycle
Rankine cycleRankine cycle
Rankine cycle
 
Gas Turbine PPT
Gas Turbine PPTGas Turbine PPT
Gas Turbine PPT
 
Reaction turbbine
Reaction turbbine Reaction turbbine
Reaction turbbine
 
Wind turbine types
Wind turbine typesWind turbine types
Wind turbine types
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plant
 
Doubly fed-induction-generator
Doubly fed-induction-generatorDoubly fed-induction-generator
Doubly fed-induction-generator
 
Design of flywheel
Design of flywheelDesign of flywheel
Design of flywheel
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Class- 13 Design considerations for wind turbine systems
Class- 13 Design considerations for wind turbine systemsClass- 13 Design considerations for wind turbine systems
Class- 13 Design considerations for wind turbine systems
 
Vertical axis wind turbine
Vertical axis wind turbineVertical axis wind turbine
Vertical axis wind turbine
 
Modern thermal power plant
Modern thermal power plantModern thermal power plant
Modern thermal power plant
 
Specific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid MechanicsSpecific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid Mechanics
 
Gas turbine
Gas turbineGas turbine
Gas turbine
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam Turbine
 
Load curve
Load curveLoad curve
Load curve
 
Francis Turbine
Francis Turbine Francis Turbine
Francis Turbine
 
Rankine Cycle & How to increase its efficiency
Rankine Cycle & How to increase its efficiencyRankine Cycle & How to increase its efficiency
Rankine Cycle & How to increase its efficiency
 
Betz speed limit and tip speed ratio
Betz speed limit and tip speed ratioBetz speed limit and tip speed ratio
Betz speed limit and tip speed ratio
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 

Similar to Unit5ppts

Economics of power plant h.pptx
Economics of power plant   h.pptxEconomics of power plant   h.pptx
Economics of power plant h.pptxMahamad Jawhar
 
Utilization of Exhaust Gas of Vehicle for Electricity Generation
Utilization of Exhaust Gas of Vehicle for Electricity GenerationUtilization of Exhaust Gas of Vehicle for Electricity Generation
Utilization of Exhaust Gas of Vehicle for Electricity GenerationIRJET Journal
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptxXamilMurad
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptxMuradulkabir
 
IRJET- Regenerative Suspension System
IRJET- Regenerative Suspension SystemIRJET- Regenerative Suspension System
IRJET- Regenerative Suspension SystemIRJET Journal
 
OPTIMIZATION AND INNOVATION OF KARTS
OPTIMIZATION AND INNOVATION   OF KARTS OPTIMIZATION AND INNOVATION   OF KARTS
OPTIMIZATION AND INNOVATION OF KARTS Ajay658267
 
Self Generator Free Energy Flywheel
Self Generator Free Energy FlywheelSelf Generator Free Energy Flywheel
Self Generator Free Energy FlywheelIRJET Journal
 
Load characteristics and Economic Aspects
Load characteristics and Economic AspectsLoad characteristics and Economic Aspects
Load characteristics and Economic AspectsAbha Tripathi
 
Project green buildings (be)
Project green buildings (be)Project green buildings (be)
Project green buildings (be)husein
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptxLucasMogaka
 
Tranformer Design
Tranformer DesignTranformer Design
Tranformer DesignArnab Nandi
 
case study on energy conservation and utilization.
case study on energy conservation and utilization.case study on energy conservation and utilization.
case study on energy conservation and utilization.tamboliameer
 
Design of Solar Tricycle for Handicapped People
Design of Solar Tricycle for Handicapped PeopleDesign of Solar Tricycle for Handicapped People
Design of Solar Tricycle for Handicapped PeopleIRJET Journal
 
Design and Development Solar Power Aeration System ppt.pdf
Design and Development Solar Power Aeration System  ppt.pdfDesign and Development Solar Power Aeration System  ppt.pdf
Design and Development Solar Power Aeration System ppt.pdfUtkarshFalak1
 
Design of low weight high speed induction machine
Design of low weight high speed induction machineDesign of low weight high speed induction machine
Design of low weight high speed induction machineDurga Sadasivuni
 
Power Flow Diagram & Efficiency
Power Flow Diagram & EfficiencyPower Flow Diagram & Efficiency
Power Flow Diagram & Efficiencymasum heera
 
IRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student ChassisIRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student ChassisIRJET Journal
 
Ee w05.1 m_ 2. electricity generation _ part 4 (generation technologies)
Ee  w05.1 m_ 2. electricity generation _ part 4 (generation technologies)Ee  w05.1 m_ 2. electricity generation _ part 4 (generation technologies)
Ee w05.1 m_ 2. electricity generation _ part 4 (generation technologies)Silvester Van Koten
 

Similar to Unit5ppts (20)

Economics of power plant h.pptx
Economics of power plant   h.pptxEconomics of power plant   h.pptx
Economics of power plant h.pptx
 
Utilization of Exhaust Gas of Vehicle for Electricity Generation
Utilization of Exhaust Gas of Vehicle for Electricity GenerationUtilization of Exhaust Gas of Vehicle for Electricity Generation
Utilization of Exhaust Gas of Vehicle for Electricity Generation
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptx
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptx
 
IRJET- Regenerative Suspension System
IRJET- Regenerative Suspension SystemIRJET- Regenerative Suspension System
IRJET- Regenerative Suspension System
 
OPTIMIZATION AND INNOVATION OF KARTS
OPTIMIZATION AND INNOVATION   OF KARTS OPTIMIZATION AND INNOVATION   OF KARTS
OPTIMIZATION AND INNOVATION OF KARTS
 
Self Generator Free Energy Flywheel
Self Generator Free Energy FlywheelSelf Generator Free Energy Flywheel
Self Generator Free Energy Flywheel
 
Load characteristics and Economic Aspects
Load characteristics and Economic AspectsLoad characteristics and Economic Aspects
Load characteristics and Economic Aspects
 
Project green buildings (be)
Project green buildings (be)Project green buildings (be)
Project green buildings (be)
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptx
 
Tranformer Design
Tranformer DesignTranformer Design
Tranformer Design
 
case study on energy conservation and utilization.
case study on energy conservation and utilization.case study on energy conservation and utilization.
case study on energy conservation and utilization.
 
Design of Solar Tricycle for Handicapped People
Design of Solar Tricycle for Handicapped PeopleDesign of Solar Tricycle for Handicapped People
Design of Solar Tricycle for Handicapped People
 
Design and Development Solar Power Aeration System ppt.pdf
Design and Development Solar Power Aeration System  ppt.pdfDesign and Development Solar Power Aeration System  ppt.pdf
Design and Development Solar Power Aeration System ppt.pdf
 
LCA-SolarFINAL
LCA-SolarFINALLCA-SolarFINAL
LCA-SolarFINAL
 
GROUP 3.pdf
GROUP 3.pdfGROUP 3.pdf
GROUP 3.pdf
 
Design of low weight high speed induction machine
Design of low weight high speed induction machineDesign of low weight high speed induction machine
Design of low weight high speed induction machine
 
Power Flow Diagram & Efficiency
Power Flow Diagram & EfficiencyPower Flow Diagram & Efficiency
Power Flow Diagram & Efficiency
 
IRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student ChassisIRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
 
Ee w05.1 m_ 2. electricity generation _ part 4 (generation technologies)
Ee  w05.1 m_ 2. electricity generation _ part 4 (generation technologies)Ee  w05.1 m_ 2. electricity generation _ part 4 (generation technologies)
Ee w05.1 m_ 2. electricity generation _ part 4 (generation technologies)
 

More from PALANIVEL SUBBIAH

GE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT HUMAN VALUES
GE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT  HUMAN VALUESGE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT  HUMAN VALUES
GE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT HUMAN VALUESPALANIVEL SUBBIAH
 
Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916PALANIVEL SUBBIAH
 
Unit4 introduction to various renewable energy sources 0916
Unit4 introduction to various renewable energy sources 0916Unit4 introduction to various renewable energy sources 0916
Unit4 introduction to various renewable energy sources 0916PALANIVEL SUBBIAH
 
Unit2 diesel engine power plant
Unit2 diesel engine power plantUnit2 diesel engine power plant
Unit2 diesel engine power plantPALANIVEL SUBBIAH
 
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)PALANIVEL SUBBIAH
 

More from PALANIVEL SUBBIAH (13)

GE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT HUMAN VALUES
GE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT  HUMAN VALUESGE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT  HUMAN VALUES
GE 6075 PROFESSIONALETHICS IN ENGINEERING UNIT HUMAN VALUES
 
Unit1 COALBASEDPOWER PLANTS
Unit1 COALBASEDPOWER PLANTSUnit1 COALBASEDPOWER PLANTS
Unit1 COALBASEDPOWER PLANTS
 
Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916
 
Unit4 introduction to various renewable energy sources 0916
Unit4 introduction to various renewable energy sources 0916Unit4 introduction to various renewable energy sources 0916
Unit4 introduction to various renewable energy sources 0916
 
Unit 3 Nuclear Power Plants
Unit 3 Nuclear Power PlantsUnit 3 Nuclear Power Plants
Unit 3 Nuclear Power Plants
 
Unit 3 nuclear power plants
Unit 3 nuclear power plantsUnit 3 nuclear power plants
Unit 3 nuclear power plants
 
Unit2 diesel engine power plant
Unit2 diesel engine power plantUnit2 diesel engine power plant
Unit2 diesel engine power plant
 
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
 
Unit 5 controlling
Unit 5 controllingUnit 5 controlling
Unit 5 controlling
 
Unit4 directing 120317
Unit4 directing 120317Unit4 directing 120317
Unit4 directing 120317
 
Unit 3 organising-150217
Unit 3 organising-150217Unit 3 organising-150217
Unit 3 organising-150217
 
Unit2 planning
Unit2 planningUnit2 planning
Unit2 planning
 
Pom slide01
Pom slide01Pom slide01
Pom slide01
 

Recently uploaded

ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 

Recently uploaded (20)

ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 

Unit5ppts

  • 1. POWER PLANT ENGINEERING UNIT 5 ECONOMICS , SELECTION CRITERIAS & ENVIRONMENTAL ISSUES S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 2. LOAD CURVE TIME - hours L O A D In M w S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 3. • BASE LOAD : LOAD BELOW WHICH DEMAND NEVER FALLS. LOAD REQUIRED TO BE SUPPLIED 100 % • PEAK LOAD : MAX. LOAD SUPPLIED – IT MAY BE 15 – 20 % OF TIME • INTERMEDIATE LOAD : LOAD SUPPLIED BETWEEN BASE AND PEAK. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 4. LOAD CURVE & LOAD DURATION CURVE S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 5. Load duration curve S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 6. 700 • RATED CAPACITY OF UNIT : Installed Capacity • PEAK LOAD : MAXIMUM LOAD PRODUCED • AVERAGE LOAD : GENERATED POWER /HOURS • INSTALLED CAPCITY = 1000 MW • TOTAL PLANNED SHUT DOWN = 720 Hrs. • FORCED OUTAGE = 50 Hrs. • UNIT IN SERVICE = 8760-720-50 =7990 Hrs. 0-6 6-8 8-9 9-17 18-20 20-22 22-24 600 700 800 900 750 700 650 Daily loading pattern of a Power Station (in MWs) S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 7. • MAX LOAD = 900 MW • MINI LOAD = 600 MW • AVERAGE LOAD = SUM OF LOAD/TOTAL HOURS = 6X600+2X700+800+8X900+3X750+2X700+2X650 24 = 17950/24 =747.91 MW LOAD FACTOR = AVERAGE LOAD/PEAK LOAD = 747.91/900 = 0.831 CAPACITY FACTOR = AVERAGE LOAD/RATED CAPACITY = 747.91/1000 = 0.74791 RESERVE FACTOR =LOAD FACTOR/CAPACITY FACTOR =0.831/0.74791= 1.111 USE FACTOR = AV.LOADX8760/INST.CAP.X HOURS RUN = 747.91X8760/1000X7990 =0. , Say 0.819S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 8. DEMAND & DIVERSITY FACTORs IF LIGHTING LOAD = 35 KW , MACHIENRIES LOAD = 450 KW, MISC. LOAD = 15 KW are connected 200 Nos of 60 W BULB IN SERVICE FOR 16 Hours. 5 nos. of M/c of 1500 W and 10 nos. of M/c OF 750 W IN SERVICE for 2 Shifts, 7 hours/Shift. CONNECTED LOAD : SUM OF RATED CAPACITY OF ALL EQUIPMENTS AND OUTLETS ON CONSUMER’S CIRCUIT CONNECTED LOAD =35+ 450+15=500 KW L.L = 16X60X 200 =19200 W = 19.2 KW M.L.= 2X7X5X1500+ 2X7X10X750=210000 W = 210 KW MISC.L= 5 KW DEMAND FACTOR = ACTUAL MAX. CONSUMPTION TOTAL CONNECTED LOAD = 19.2 + 210 +5/500 =234.2/500 =0.4684 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 9. DIVERSITY FACTOR = TOTAL LOAD CONNECTED/MAX. CONSUMPTION DIV. FACTOR (SYSTEM)= 500/234.2 = 2.1349 DIV. FACTOR (L.L.) = 35/19.2 =1.8229 DIV. FACTOR (M.L.) = 450/210 = 2.1428 DIV. FACTOR (Misc. L.) = 15/5 = 3 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 10. • HEAT RATE =Heat Input (I)/Net kW output(L) • Plant Net Efficiency = Net output(L)/Heat Input (I) • INCREMENTAL HEAT RATE :Amount of energy needed to generate additional output at any given load • When plant output decreases, heat rate increases, where as the incremental heat rate decreases. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 11. COST/PER K.W • DETERMINED BY • FIXED COST + O & M COST+ FUEL COST • COST IS BASED ON POWER EXPORTED YEARLY • FIXED COST : INTEREST, DEPRECIATION, INSURANCE, TAXES ON CAPITAL INVESTED. • CAPITAL COST = CONSTRUCTION COST+ LAND COST • CONSTRUCTION COST = DESIGN+ PRICE OF EQPTS+ TRANSPORT+ ERECTION + COMMISSIONING S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 12. Total Annual Cost ( Ct ) Cc = Construction cost = 1430 Cr. I = INTEREST RATE = 12 % = 0.12 D= DEPRECIATION = 100/15 =6.67 % = 0.0667 T= TAXES = 14 % = 0.14 W = TOTAL ANNUAL WAGES = 126 Cr. M = MTCE. CHARGES = 30 Cr. Cf = Fuel Cost = Cost of fuel including its trans. Ct= I + D + T x Cc +(W+M)+ Cf 100 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 13. • Fuel cost : Total fuel required (T) x Cost/T • Total fuel reqd.= Total Power generated/Fuel Kg/Kwh • C.F.= 85% Installed = 420 MW • C.F.= Average load/Installed capacity • Ave.load = 0.85x420 =357 MW • Total power generated =0.85x420x103 x8760 =312.732X 107 KWH Fuel reqd./KWh = 1 Kg. (Net Heat rate = 1Kg/1KWh) • S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 14. Annual Fuel reqd.=312.732X10 7 Kg.=3127320T Fuel Cost =3127320X1600 =Rs. 5003712000 =500.03712X10 7 Total cost = (0.12+0.067+0.14)x1450x107 +(120+30) 107 + fuel cost = 474.15 X 107 +150 X 107 +500.3712 X 107 = 1124.5212 Cr. Cost/Unit = Total Cost/Units Generated = 1124.5212/312.732 =3.5958 Cost of Generation = Rs. 3.60/kW Profit margin = 43 p/unit : Selling price = 3.6 +0.43 =4.03 Auxiliary consumed = 8 %: Power exported = (1-0.08)x units generated =0.92x312.732 x107 Units: Revenue=4.03x0.92x312.732 Cr. = 1159.485163 Cr. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 15. Determine the generating cost per unit of 80 MW power station with the following data Capital cost = Rs. 160 x 107 ; Annual cost of fuel = Rs. 32 x 106 ; Annual wages and taxes = Rs. 36 x 106 ; Interest and depreciation = 10 % of capital cost : Annual load factor = 45 % Assume, Maximum load = 80 MW Load factor = 0.45 = Average load /Maximum load Average load = 0.45 x 80 = 36 MW Total energy generated = Average load x 8760 = 36 x 8760 = 315.360 x106 kWH (units) Generation cost = Fixed cost + Running Cost Fixed cost = % of (interest + depreciation ) on Capital cost Fixed cost = 0.1 x 160 x 107 = Rs.160 x 106 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 16. Running cost = Annual fuel cost + Annual wages and taxes = 32 x 106 + 36 x 106 = 68 x 106 Generation Cost = 160 x 106 + 68 x106 = Rs. 228 x 106 Cost of generation of 1 unit = Total generation cost/Total energy generated (units) = 228 x106 /315.360 x106 = Rs.0. 7229 = 72.3 paise. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 17. Find the cost of generation per kWh from the following data : Capacity of the plant = 150 MW ; capital cost = Rs. 20,000 per kW installed. Interest and depreciation = 10 % on capital ; Fuel consumption = 1.2 kg/kWh; Fuel cost = Rs. 400 per tone; salaries, wages, repair and maintenance=Rs.150x106 per year; Max. demand = 120 MW ; load factor = 50 % Load factor = Average load/max. demand = 0.5 Average load = 0.5 x 120 MW = 60 MW Total energy produced=Average loadx8760 = 60 x103 x 8760 =525.6 x 106 kWh(units) Capital cost = 20000 x 150 x 103 =Rs. 300 x 107 Total cost of generation = Fixed cost + Running cost Fixed cost = % (Interest + depreciation) x Capital cost = 0.1 x 300 x 107 = Rs. 300 x 106 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 18. Fuel consumption / unit = 1.2 kg/kWh Fuel requirement for annual generation = 1.2 x 525. 6 x 106 = 630.72x106 kg. = 630.72 x103 T. Annual fuel cost = 630.72 x 103 x 400 = Rs. 252.288 x 106 Cost on salaries, wages, repair and maintenance = Rs. 150 x 106 Running cost =Rs. 252.288 x 106 + Rs. 150 x 106 = Rs.402.288 x 106 Total generation cost = Fixed cost + Running cost = Rs.300x106 + Rs. 402.288 x 106 = Rs. 702.288 x 106 Cost of generation/unit = Total generation cost/Total energy produced = Rs. 702.288 x 106 / 525.6 x 106 = Rs. 1.34 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 19. DEPRECIATION • STRAIGHT LINE METHOD : • DEPRECIATION OCCURS UNIFORMLY • MONEY SAVED NEGLECTS ANY INTEREST • IF ‘A’ = CAPITAL , G= SALVAGE VALUE, N= YEARS OF USEFUL LIFE THEN DPRECIATION “D”=(A-G)/N S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 20. DEPRECIATION • SINKING FUND METHOD : • SUM OF MONEY IS SET ASIDE EVERY YEAR & INVESTED TO EARN COMPOUND INTEREST • IF “P” IS SUM INVESTED EVERY YEAR FOR ‘N’ YEARS TO HAVE DPRECIATION AMOUNT ‘S’ AND THE RATE OF INTEREST IS ‘I’ • VALUE OF MONEY AT END OF 1 YEAR = P • VALUE AT THE END OF 2 YEAR = (P+Pi) + P • VALUE AT 3RD YEAR = (P+Pi)Xi +Pi+P • VALUE AT N-1 YEAR = P(1+i) (N-1-1) • VALUE AT N YEAR = P(1+i) (N-1) • SUM OF INVESTMENT in N YEARS = P+P(1+i)….+P (1+i) (N-1) • S = P (1+i) (N) -1) = A – G =A’ : P= A’ i i (1+i) (N) -1) S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 21. PRESENT WORTH • IFSUMOF“P”ISINVESTEDNOW, • ITSVALUEWILLGETDECREASE • GEOMETRICALLYOVERTHEYEARS • THERATEOFDECREASEIS“i” • PRESENTWORTHIN“N”YEARS=P/(1+i) N • IFP=110:I=10% • P.W.AFTER1YEAR=110/(1+.1)=110/1.1=100 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 22. Reliability of Power Plant Total no. of hours a power plant is available for power generation is an important factor in designing a power Plant. This factor is called as availability factor or reliability factor. No. of hours a plant is not in service due to stoppage of units due to various causes while the unit in service are called as Forced outage hours. Forced outage hours has to be below 2 % for efficient operation. Forced outage is a measure of Reliabilty of Unit In a year a power plant has to be stopped to undertake annual maintenance works , which may vary to 30 days to 25 days. In addition to these Plant may not be in service due to stoppage of units on some causes while in operation , that is called forced outages. Ratio total no. of hours units in service in a year to Total no. of hours after deducting annual maintenance hours is availability factor. Availability factor of a power plant is expected to maintain above 90 % to operate economical. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 23. • As forced outages increase the operation and maintenance costs, proven reliability of equipment and regular preventive maintenance are essential not only to guarantee electric supply but also for overall economical operation of plant • Costs of power generation can be reduced by  Selecting equipment of longer life and proper capacities  Running the Plant at high load factor  Increasing the efficiency of power plant  Carrying out proper maintenance of equipments to avoid breakdowns and forced outages  Keeping proper supervision and trained manpower so as to keep lesser break downs and efficient operation  Using a plant of simple and proven design S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 24. SELECTION OF CAPACITY TOTAL CAPACITY REQUIRED BASED ON MAXIMUM DEMAND EXPECTED GROWTH OF DEMAND ANTICIPATED RESERVE CAPACITY REQUIRED S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 25. SIZE OF UNITS • VARIATION OF LOAD DURING 24 HOURS • TOTAL UNITS CONNECTED TO GRID • MINI. STRAT-UP & SHUTDOWN PERIOD • MANITEANCE PLANNED • PLANT EFFICIENCY Vs SIZE • COST/MW, SPACE /KW Vs SIZE S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 26. LOCATION OF THERMAL POWER PLANT • AVAILABLITY OF FUEL • AVAILABLITY OF COOLING WATER • LAND COST • CHARACTER OF SOIL • DISPOSAL OF ASH • WIND DIRECTION & WATER CURRENT • RAIL & ROAD CONNECTION • ACCOMODATION FOR STAFF • ZONE -FREE FROM EARTH QUAKE • SECURITY CONSIDERATIONS. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 27. HYDRO ELEC. POWER PLANT • HYDRO : BASED ON AVAILABLITY OF WATER AND UTILISABLE WATER HEAD • INITIAL COST WILL BE VERY HIGH • RUNNING COST WILL BE LESS • TAKES MORE TIME TO CONSTRUCT • DIFFICULT TO CONVINCE PEOPLE • POWER CAN BE PRODUCED BY TAKING LESS TIME • MOSTLY MULTI PURPOSE LIKE … IRRIGATION, FLOOD CONTROL , POWER GENERATION, PUMPING STATION. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 28. Problems • 1. A Power Plant has the following annual factors : Load factor = 0.75, Capacity factor= 0.6, Use Factor =0.65. Max. demand is 60 MW. • Estimate a) The Annual energy produced, • b) the reserve capacity and C) hours of operation and hours during which plant was not in service Load factor = Average Load/Max. Load 0.75 = Average Load/60 MW Average load = 60 x 0.75 = 45 MW a) Annual Energy produced = Average load x 24 x 365 = 45x24x365 = 394200 MWH =394.2 x106 kWh S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 29. Capacity factor = Aver. Load/Installed capacity 0.6 = 45/installed capacity Installed capacity = 45/0.6 = 75 MW b) Reserve capacity = Installed – max. Load = 75 – 60 = 15 MW Use factor = Energy Produced/Max. energy possible 0.65 = 394.2 x 106 /75 x running hours c)Running hours = 394.2x 106 /75x0.65 = 8086.154 hrs. Unit not in service = 8760-8086.154 = 673.846hrs. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 30. 2. A power station of 30 MW capacity has the annual max. demand of 25 MW. It supplies loads having max. demands of 10 MW, 8.5 MW,5MW and 4.5 MW. The annual load factor is 45%. Estimate a) Average load, b)Energy supplied in a year, c)the diversity factor and d) Demand factor. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 31. • Peak Load = 25 MW • Connected load = 10+ 8.5+5+ 4.5 = 28 MW • Load factor = Aver.load/Peak load • 0.45= Aver.Load/Peak load • Aver.load=peak loadx0.45=25x 0.45=11.25MW Energy produced=11.25x8760=98.550x 106 units Demand factor = Peak load /Connected load = 25/28 =0.8928 Diversity factor = Connected load/Peak load = 28/25 = 1.12 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 32. • A central power station has annual load factor, capacity factor and use factor as 60 %, 40 % and 45 % respectively. The maximum load is 15 MW. Estimate (a) the annual energy production and revenue earned if the cost of energy is Rs. 1 /kWh, (b) the reserve capacity over and above the peak load and (c) the hours per year the station is not in service. Load factor = 0.6 ; Capacity factor = 0.4 ; use factor = 0.45 ; peak load = 15 MW Load factor = Average load/Peak load Average load = load factor x peak load = 0.6 x 15 = 9 MW Total power generated in a year = Average load x 8760 hours = 9 x 8760 = 78840 MWH =78.84 x106 kWh Cost of energy /unit = Rs.1 Total revenue earned = Total power generated x cost/unit = 78.84 x106 x1 = Rs. 78.84 x106 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 33. Capacity factor = 0.4 = Average load/Installed capacity = 9/installed capacity Installed capacity = 9/0.4 = 22.5 MW Reserve capacity = Installed capacity – Maximum load = 22.5 – 15 = 7.5 MW Use factor = Total power generated/ ( Installed capacity x Total running hours) 0.45 = 78.84 x106 /22.5 x total running hours Total running hours = 78.84 x106 /22.5 x0.45 = 7786 hours Hours per year not in service = 24 x 365 – running hours = 8760- 7786 = 974 hours. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 34. A power station of 30 MW capacity has the maximum annual demand of 25 MW. It supplies loads having maximum demands of 10 MW, 8.5 MW, 5 MW and 4.5 MW. The annual load factor is 45 %. Estimate a) the average load b) the energy supplied per year c) diversity factor and d) demand factor. Given Installed capacity = 30 MW, Maximum demand = 25 MW, Demands connected loads in MW = 10, 8.5, 5, 4.5; Annual load factor = 0.45 Load factor = 0.45 = Average Load/Maximum load = 0.45 = Average Load/25 Average Load = 25 x 0.45 = 11.25 MW Energy supplied in a year = Average load x 8760 = 11.25 x 8760 =98.55x106 kWH. Load connected = 10 + 8.5+ 5 + 4.5 = 28 MW Demand factor = Maximum load/ Connected load = 25/28 =0.89 Diversity factor = Connected load/Maximum load = 28/25 = 1.12 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 35. 3. A Power Station has a maximum demand of 10,000 kW and the daily load on the Station is as follows : Time kW Time kW 6 a.m to 8 a.m. 3500 5 p.m. to 7 p.m. 8500 8 a.m. to 12 noon 8000 7 p.m. to 9 p.m. 10000 12 noon to 1 p.m. 3000 9 p.m. to 11 p.m. 4500 1 p.m. to 5 p.m. 7500 11 p.m. to 6 a.m. 2000 a) Draw the load curve and load duration curve b) Choose the size and no. of generating Units c) Draw up the operating schedule of the Units d) What reserve plant would be necessary e) Calculate Load factor, Plant capacity factor and Use factor of the station. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 36. Load (kW) - duration 10000 - 2 hours 8500 - 2 hours 8000 - 4 hours 7500 - 4 hours 4500 - 2 hours 3500 - 2 hours 3000 - 1 hr. 2000 - 7 hrs. Load requirements and its duration can be had from load Duration curve Max. load required = 10000 kW Minimum load required = 2000 kW Reserve capacity assumed = 2500 kW S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 37. 4 units of 2500 kW for running and 2500 kW as stand by , so 5 nos. of 2500 kW are to be selected. Operating schedule : 1 unit of 2500 kW run for – 24 hours 2 units of 2500 kW run for – 17 hours 3 units of 2500 kW run for - 12 hours 4 units of 2500 kW run for - 8 hours Instead of 2500 kW unit if 2000 kW is selected, then no. of units required including reserve of 2000 kW = 10000+2000/2000 = 6 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 38. Then operating schedule will be 1 unit of 2000 kW run for 24 hours 2 units of 2000 kW run for 17 hours 3 units of 2000 kW run for 14 hours 4 units of 2000 kW run for 8 hours 5 units of 2000 kW run for 4 hours. Load factor = Average load/Max load Average load = (10x2+8.5x2+8x4+7.5x4+4.5x2+ 3.5x2+3x1+2x7)MWH/24 = 132/24 = 5.5 MWh Load factor = 5.5/10 = 0.55 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 39. • Capacity factor = Average load /Installed Cap. • Capacity factor = 5.5/12.5 (or) 5.5/12 =0.44 (or) 0.45833 Use factor = Energy produced/Max. energy possible = 5.5 x24/12.5 x24 (or) 5.5x24/12 x24 =044 (or) 0.45833 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 40. 4.Determine the Generating cost per unit of 80 MW Power Station with the following data: • Capital Cost = Rs.160 Cr. • Annual fuel Cost = Rs.3.2 Cr. • Annual wages = Rs. 3.6 cr. • Interest and Depreciation = 10 % • Annual load factor = 45 % Assume capacity = Peak load = 80 MW Average load = peak load x load factor = 80x0.45 = 36 MW Energy produced in a year = 36x24x365 = 315.36x106 units S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 41. Generation cost = total cost/Total energy produced Cost = Fixed cost + Running cost Fixed Cost = (Int.+ Depreci.) x Constn. Cost = 160x 107 x 0.1 =Rs. 160 x 106 Running Cost = Annual Fuel cost + Annual Mtce cost = 3.2 + 3.6 = 6.8 Cr. = Rs. 68 x 106 Total cost = Rs. (160 + 68 ) x 106 Generation Cost = 228 x 106 / 315.36 x 106 = Rs. 0.7229 = 72.29 paise S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 42. 5. A Plant costing Rs. 65,000 has a useful life of 15 Years. Find the amount which should be saved annually to replace the equipment at the end of time a) by the straight-line method b) by the sinking fund method , if the annual rate of compound interest is 5%. Assume salvage value of the equipment is Rs.5000 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 43. Plant cost = A = Rs. 65000 Salvage Cost = G = Rs. 5000 No. of years = N = 15 Depreciation by straight line method : Depreciation charge per year = (A-G)/N = (65000 – 5000)/15 = 60000/15 = Rs.4000 Depreciation by sinking fund method : •A’ = Capital cost – salvage value = 65000 – 5000 = Rs. 60000 •Rate of compound interest = I = 5 % •No. of years = N = 15 •Amount to be kept side per year = P •P = (A’ x i) /{(1+i)N - 1} = (60000 x 0.05)/ {(1+.05)15 – 1 } •P=3000/ (1.0515 – 1) = 3000/(2.07893 -1) = 3000/1.07893 = Rs. 2780 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 44. The incremental fuel costs for two generating units A and B of s power plant are given by the following relations; dFA /dPA = 0.06 PA + 11. 4 dFB /dPB = 0.07 PB + 10 where P is the power in MW and F is the fuel cost in rupees per hour. Find the economic loading of the two units when the total load to be supplied by the power station is 150 MW. Find the increase in fuel cost per hour if the load is equally shared by the two units. Given dFA /dPA = 0.06 PA + 11. 4 dFB /dPB = 0.07 PB + 10 Total load = PA + PB = 150 MW PA = 150 – PB S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 45. The condition for economic loading demands equal incremental heat rate of the two units which leads to dFA /dPA = dFB /dPB 0.06 PA + 11. 4 = 0.07 PB + 10 0.06 PA - 0.07 PB = 10 – 11.4 = - 1.4 0.06 (150- PB ) – 0.07 PB = - 1.4 9 -0.06 PB - 0.07 PB = - 1.4 -0.13 PB = - 10.4 0.13 PB = 10.4 PB = 10.4/0.13 = 80 MW : PA = 150 -80 = 70 MW If load is equally shared by units ie. PA = PB = 150/2 = 75 MW S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 46. Then increase in fuel cost of unit A is given by 75 ƪ70 dFA x dPA = [ 0.06 PA 2 /2 + 11.4 PA ]75 70 dPA = {( 0.06 x 752 )/2 + 11.4 x 75)} – { (0.06 x 702 )/2 + 11.4 x 70)} =Rs. 78.75 Then increase in fuel cost of unit B is given by 75 ƪ80 dFB x dPB = [ 0.07 PB 2 /2 + 10 PB ]75 80 dPB = {( 0.07 x 752 )/2 + 10 x 75)} – { (0.76 x 802 )/2 + 10 x 80)} = Rs.- 77.125 Net increase in fuel cost = 78.75 – 77.125 = Rs. 1.63 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 47. The loads on a power plant with respect to time for 24 hours are given below Time (hours) :0-6 : 6-8: 8-12:12-14:14-18:18-22:22-24 Load (MW) : 40: 50 : 60 : 50: 70 :80 : 40 Draw the load curve and find out the load factor of the power station. If the loads above 60 MW are taken by unit of 20 MW capacity, find out the load factor and the use factor of the standby unit. Total load in 24 hours = 6x 40 + 2x50+ 4x 60 +2x 50 + 4x 70 + 4x 80 + 2 x40 = 1360 MWH Average load = 1360/24 =56.67 MW Load factor of station = Average load/peak load = 56.67/80 = 0.70833=0.71 Loads taken by standby unit (load above 60 MW) are 70-60 = 10 MW between 14 and 18 hours ie for 4 hours, 80-60 = 20 MW between 18 and 22 hours ie for 4 hours.S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 48. Total Loads taken by standby unit = 4 x 10 + 4 x 20 = 120 MWH Average load = 120/8 = 15 MW Load factor = average load/peak load = 15/20 = 0.75 Capacity use factor = Total power generated/ (Installed capacity x hours of operation) =120/(20x8) = 120/160 =0.75 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 49. A central power station has annual load factor, capacity factor and use factor as 60 %, 40 % and 45 % respectively. The maximum load is 15 MW. Estimate (a) the annual energy production and revenue earned if the cost of energy is Rs. 1 /kWh, (b) the reserve capacity over and above the peak load and (c) the hours per year the station is not in service. Load factor = 0.6 ; Capacity factor = 0.4 ; use factor = 0.45 ; peak load = 15 MW Load factor = Average load/Peak load Average load = load factor x peak load = 0.6 x 15 = 9 MW Total power generated in a year = Average load x 8760 hours = 9 x 8760 = 78840 MWH =78.84 x106 kWh Cost of energy /unit = Rs.1 Total revenue earned = Total power generated x cost/unit = 78.84 x106 x1 = Rs. 78.84 x106 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 50. Capacity factor = 0.4 = Average load/Installed capacity = 9/installed capacity Installed capacity = 9/0.4 = 22.5 MW Reserve capacity = Installed capacity – Maximum load = 22.5 – 15 = 7.5 MW Use factor = Total power generated/ ( Installed capacity x Total running hours) 0.45 = 78.84 x106 /22.5 x total running hours Total running hours = 78.84 x106 /22.5 x0.45 = 7786 hours Hours per year not in service = 24 x 365 – running hours = 8760- 7786 = 974 hours. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 51. A power station is said to have a use factor of 47 % and capacity factor of 40 %. For how many hours in a year was the power station not in service. Given use factor = 0.47 ; Capacity factor = 0.4 Use factor = kWH generated in a year / (Installed capacity x operating hours) Capacity factor = kWH generated in a year/(Installed capacity x 8760 hours) 0.4/0.47 = (kWH generated in a year/Installed capacityx8760) / (kWH generated in a year/Installed capacity x running hours ) 0.4/0.47 = Operating Hours /8760 Operating Hours = 0.4 x 8760 /0.47 = 7455 hours Hours not in service = 8760 – operating hours = 8760- 7455 = 1305 hours. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 52. The following data pertain to a power plant ; Installed capacity = 200 MW; Capital cost = Rs. 4000 x 106 ; Annual cost of fuel, taxes and salaries =Rs. 600 x106 ; Rate of interest = 5 % of the capital; Rate of depreciation = 6 % of the capital ; Annual load factor = 65 %; Capacity factor = 55 % energy used in running the plant auxiliaries = 4 % of total units generated. Determine a) the reserve capacity and b) the cost of power generation Load factor = Average load/peak load = 0.65 Capacity factor = Peak load / Installed capacity = 0.55 Peak load = 0.55 x Installed capacity = 0.55 x 200 = 110 MW. Reserve capacity = Installed capacity – Peak load = 200 -110 = 90 MW Load factor = 0.65 = Average load / peak load Average load = 0.65 x 110 MW = 71.5 MW S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 53. Energy generated = Average load x 8760 hrs. = 626.34x 106 kWH Power generated used in auxiliaries = 4 % Total units exported = 0.96 x 626.34 x106 units = 601.286 x 106 units. Total generation cost = Fixed Cost + Running Cost Fixed Cost = % of (Rate of Interest + depreciation) x Capital cost = % (5 + 6) x 4000x106 = 0.11 x 4000 x 106 = Rs. 440 x 106 Running cost = 600 x 106 Total generation cost = 440 x 106 + 600 x 106 = Rs. 1040 x 106 Considering total energy produced Cost of generation = Total generation cost / Energy generated = 1040 x 106 /626.34 x 106 = Rs. 1.66 Considering auxiliaries consumption total energy exported Cost of generation = 1040 x 106 /601.286 x 106 = Rs. 1.73S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 54. • A power plant has the following annual factors; • Load factor = 70%; capacity factor = 50 % ; use factor = 60 %; max. demand = 20 MW Estimate a) annual energy production; b) reserve capacity over and above the peak load and c) the hours per year during which plant is not in service. Load factor = Average load/Max. demand Average load = Load factor x Max. demand = 0.7 x 20 MW= 14 MW. Annual energy produced = Average load x 8760 hours = 122.640 x 106 units. Capacity factor = Max. demand / Installed capacity = 0.5 Installed capacity = Max. demand/ Capacity factor = 20/0.5 = 40 MW Reserve capacity = Installed capacity – Max. demand = 40 -20 = 20 MW. Use factor = Total energy produced/ Installed capacity x Running hours = 0.6 Running hours = 14 x 8760/(40 x 0.6) =5110 hours Hours per year during which plant is not in service = 8760 – 5110 = 3650 hours. S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)
  • 55. • The connected loads of a consumer consist of 10 electric bulbs of 60 W each and 2 electric heaters of 1000 W each. His maximum demand is 1500 W. On an average, he uses 8 bulbs for 5 hours a day and one heater for 3 hours a day. Estimate his average load, monthly energy consumption and load factor. Total load in a day = 8 bulbs x 5 hours x 60 W + 1 heater x 3 hours x 1000 W = 8x 5 x 60 + 1 x 3 x 1000 = 2400 + 3000 = 5400 kWh Average load = 5400 kWh/24 = 225 kWh Monthly consumption = 30 days x average load = 30 x 225 kWh = 6750 kWh Load factor = Average load/max. demand = 225/1500 = 0. 15 S.PALANIVEL ASSOCIATE PROF./MECH. ENGG KAMARAJ COLLEGE OF ENGG. & TECH. VIRUDHUNAGAR(NEAR)

Editor's Notes

  1. 106