SlideShare a Scribd company logo
1 of 15
Download to read offline
THE DIFFERENCE BETWEEN QC
INSPECTIONS AND
COMMISSIONING INSPECTIONS
COMMISSIONING MANAGEMENT ORGANIZATION
Understanding Construction Quality
Control
• Construction quality control is a type of management
system that aims to ensure that the deliverable fulfils the
guidelines and standards laid by the client.
• These may include completion of the project within the
scope of predefined work as well as avoiding disputes
throughout the project’s life cycle.
• Quality is established by the client and regulatory
agencies, and is usually based on regulatory and
environmental guidelines.
• All the quality assurance procedures and requirements
are recorded in the construction quality management
plan.
• There are two major facets of quality in construction:
quality assurance (QA) and quality control (QC).
• While quality assurance describes the quality
management-specific expectations and how to attain
quality, quality control explains the plan to achieve the
same.
• The construction quality control manager oversees this
plan throughout different phases of the project.
Understanding Construction
Commissioning
• Building commissioning is a methodical process of
balances and checks to ensure that building equipment
and systems are constructed, designed, and operated for
optimal performance.
• The commissioning management company brings an all-
encompassing approach to the process of design, and is
accountable for thoroughly reviewing construction-specific
documentation, testing and validating the specific
equipment post installation, and checking if building staff
are trained properly to operate and maintain the installed
equipment.
• Apart from ensuring that building components, including
cooling, heating, refrigeration and water systems, and air
handling work as they are expected to be, commissioning
companies in the UK also aim to lower maintenance and
operational costs as well as improve the building’s energy
usage.
• Although installation contractors and design professionals
are eventually accountable for testing building systems
and ensuring the quality of the installation, the
commissioning team provides a second pair of ears and
eyes throughout the entire construction process –
checking for any deficiencies as well as preventing and
resolving possible issues before the building becomes
fully operational.
QC Inspections vs. Commissioning
Inspections
• Commissioning is a complex process, particularly the
phase of transition to commissioning from construction.
• However, with the proper documentation, it can be
simplified substantially.
• This is where the documents for QC and Commissioning
Inspections comes in.
• There are basically 3 types of documents that have to be
defined during the transition.
 Inspection Test Plans (ITPs)
 Mechanical Completion Checklists
 Pre-commissioning Checklists.
• Let’s look at these three types of documents in detail.
Inspection and Test Plans
• Primarily, these are part of the construction-specific
quality control documents.
• Inspection and test plans, acronymed as ITPs, list the
quality inspections to be done in order to confirm
appropriate installation, once the systems are installed.
• For instance, a mechanical ITP is a checklist that includes
the torque values that need to be confirmed after
equipment installation.
• Every bolt is torque-checked to see if they are torqued
appropriately.
• Another ITP example can be a checklist to verify and confirm if
equipment is installed correctly, including flushing of pipes to
confirm they contain no debris, pressure or leak testing to verify
that the piping has no leaks – and as part of the QC inspection
documentation, it confirms that piping has been installed
correctly.
• An example of electrical ITPs can be a checklist, comprising all
the inspections that need be done on all cables after being
pulled.
• This may include point-to-point testing and Megger checking.
Megger testing confirms that there is no damage to the cables,
with its dielectric properties being maintained well post
installation.
• Point-to-point testing confirms that the cable has been
terminated appropriately to the right terminal blocks in the
automation cubicle.
• All ITPs are specific to individual subsystems. Once all ITPs
are done, the mechanical completion documentation begins.
Mechanical Completion
• Mechanical completion is the process of formal handover
to the commissioning team from the construction team.
• Every mechanical completion contains all the ITPs
associated with a specific subsystem, and the mechanical
completion checklist will include the documentation, which
is needed as part of that specific handover.
• Once all the items listed in the mechanical completion
checklist is completed, the checklist is verified and signed
off, indicating handover to the commissioning team, which
can then start with the pre-commissioning testing.
Commissioning Inspections
• Commissioning inspections are specified in pre-
commissioning checklists. An example of a pre-
commissioning mechanical checklist can be a pump and a
motor that need startup for the very first time.
• In such a checklist, a bump test will be performed to verify
rotation, an uncoupled run will be done to see there are
no issues, a coupled run will be done to verify current
draw, and an initial run-in will be done to check flow and
pressure rates.
• An example of a pre-commissioning electrical checklist
can be powering up an automation cubicle for the very
first time.
• Such a checklist will include primary communication
checks, set-point and alarm checks, monitoring and
control checks, loop checks, and so forth.
• Once all pre-commissioning inspections are done, the
systems can further be tested during the commissioning
testing phase.
• To make their entire commissioning inspection process
faster, smoother and more efficient, most commissioning
management companies rely on advanced commissioning
management software like Cobia that helps ensure clear
tracking, traceability and accountability for every stage of
the commissioning process.
Conclusion
• With the discussion above, the major difference between
QC inspections and commissioning inspections is quite
clear.
• Hence, it can be concluded that while QC inspections
confirm that the equipment has been installed
appropriately, commissioning inspections verifies that the
equipment is functioning correctly.
FOLLOW US
WORK WITH US
Email
efox@global-cxm.com
Contact number
Website
https://www.global-cxm.com/
+441227649087, +447580017944
Difference Between Quality Control Inspection and Commissioning Inspection

More Related Content

What's hot

Mechanical Maintenance Supervisor CV
Mechanical  Maintenance  Supervisor CVMechanical  Maintenance  Supervisor CV
Mechanical Maintenance Supervisor CVvaithiya nathan
 
00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)Mohammad Khan
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guidelineMahmoud Ezz
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfMDAbdullah621330
 
Shutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramShutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramLife Cycle Engineering
 
Resume instrumentation engineer
Resume instrumentation engineer Resume instrumentation engineer
Resume instrumentation engineer zahirtec
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Manoj New Resume
Manoj New ResumeManoj New Resume
Manoj New ResumeManoj Patel
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technipignitetribes
 
APM Best Practices - Reliability Added Value
APM Best Practices - Reliability Added ValueAPM Best Practices - Reliability Added Value
APM Best Practices - Reliability Added ValueStork
 
CV Oil and Gas Field Operator Nishanth P Joy
CV Oil and Gas Field Operator Nishanth P JoyCV Oil and Gas Field Operator Nishanth P Joy
CV Oil and Gas Field Operator Nishanth P JoyNISHANTH JOY
 

What's hot (20)

Mechanical Maintenance Supervisor CV
Mechanical  Maintenance  Supervisor CVMechanical  Maintenance  Supervisor CV
Mechanical Maintenance Supervisor CV
 
cv piping(1)
cv piping(1)cv piping(1)
cv piping(1)
 
Oil & Gas Maintenance Guide
Oil & Gas Maintenance GuideOil & Gas Maintenance Guide
Oil & Gas Maintenance Guide
 
00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guideline
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Shutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramShutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement Program
 
Resume instrumentation engineer
Resume instrumentation engineer Resume instrumentation engineer
Resume instrumentation engineer
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
Reliability engineering ppt-Internship
Reliability engineering ppt-InternshipReliability engineering ppt-Internship
Reliability engineering ppt-Internship
 
DEMOBILIZATION PLAN.docx
DEMOBILIZATION PLAN.docxDEMOBILIZATION PLAN.docx
DEMOBILIZATION PLAN.docx
 
Manoj New Resume
Manoj New ResumeManoj New Resume
Manoj New Resume
 
Mechanical Supervisor
Mechanical SupervisorMechanical Supervisor
Mechanical Supervisor
 
Instrument Supervisor CV
Instrument Supervisor CVInstrument Supervisor CV
Instrument Supervisor CV
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
APM Best Practices - Reliability Added Value
APM Best Practices - Reliability Added ValueAPM Best Practices - Reliability Added Value
APM Best Practices - Reliability Added Value
 
CV Oil and Gas Field Operator Nishanth P Joy
CV Oil and Gas Field Operator Nishanth P JoyCV Oil and Gas Field Operator Nishanth P Joy
CV Oil and Gas Field Operator Nishanth P Joy
 

Similar to Difference Between Quality Control Inspection and Commissioning Inspection

Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc trainingDiaz Susetyo
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementEdwinJacob5
 
Quality checking
Quality checkingQuality checking
Quality checkingArjun kumar
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completionRonie Chu
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installationswan saiful arini
 
Validation of utilities
Validation of utilitiesValidation of utilities
Validation of utilitiesMasarrat Khan
 
Introduction to validation
Introduction to validation Introduction to validation
Introduction to validation Ankush Sule
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning pptDayasagar Govidaraju
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptxDayasagar Govidaraju
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemArpitSuralkar
 
Bioprocess Validation
Bioprocess Validation Bioprocess Validation
Bioprocess Validation Pramod Pal
 
Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21jsgibby
 

Similar to Difference Between Quality Control Inspection and Commissioning Inspection (20)

Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract management
 
Quality checking
Quality checkingQuality checking
Quality checking
 
Validation
ValidationValidation
Validation
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Validation of utilities
Validation of utilitiesValidation of utilities
Validation of utilities
 
Introduction to validation
Introduction to validation Introduction to validation
Introduction to validation
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning ppt
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptx
 
019113
019113019113
019113
 
Presentation1
Presentation1Presentation1
Presentation1
 
Commissioning Planning Meeting
Commissioning Planning MeetingCommissioning Planning Meeting
Commissioning Planning Meeting
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
QC Basheer CV
QC Basheer CVQC Basheer CV
QC Basheer CV
 
Bioprocess Validation
Bioprocess Validation Bioprocess Validation
Bioprocess Validation
 
Quality management
Quality managementQuality management
Quality management
 
Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21
 

More from Olivia Wilson

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Olivia Wilson
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxOlivia Wilson
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareOlivia Wilson
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Olivia Wilson
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareOlivia Wilson
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareOlivia Wilson
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfOlivia Wilson
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System Olivia Wilson
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection ChecklistsOlivia Wilson
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionOlivia Wilson
 
How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...Olivia Wilson
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfOlivia Wilson
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxOlivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about CommissioningOlivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about CommissioningOlivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTOlivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTOlivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work SystemOlivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work SystemOlivia Wilson
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKOlivia Wilson
 

More from Olivia Wilson (20)

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptx
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko Software
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko Software
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko Software
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdf
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-Construction
 
How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdf
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptx
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
 

Recently uploaded

Call Girls In Sector 85 Noida 9711911712 Escorts ServiCe Noida
Call Girls In Sector 85 Noida 9711911712 Escorts ServiCe NoidaCall Girls In Sector 85 Noida 9711911712 Escorts ServiCe Noida
Call Girls In Sector 85 Noida 9711911712 Escorts ServiCe NoidaDelhi Escorts Service
 
NAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALLNAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALLNiteshKumar82226
 
Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...
Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...
Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...aakahthapa70
 
BHOPAL CALL GIRL 92628*71154 BHOPAL CALL
BHOPAL CALL GIRL 92628*71154 BHOPAL CALLBHOPAL CALL GIRL 92628*71154 BHOPAL CALL
BHOPAL CALL GIRL 92628*71154 BHOPAL CALLNiteshKumar82226
 
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝thapagita
 
Russian Call Girls in Goa %(9316020077)# Russian Call Girls in Goa By Russi...
Russian Call Girls  in Goa %(9316020077)# Russian Call Girls  in Goa By Russi...Russian Call Girls  in Goa %(9316020077)# Russian Call Girls  in Goa By Russi...
Russian Call Girls in Goa %(9316020077)# Russian Call Girls in Goa By Russi...Goa Call Girls Service Goa escort agency
 
Call Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In Karachi
Call Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In KarachiCall Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In Karachi
Call Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In KarachiAyesha Khan
 
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...aakahthapa70
 
▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂
▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂
▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂door45step
 
Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝Lipikasharma29
 
Call Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash Payment
Call Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash PaymentCall Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash Payment
Call Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash Paymentaakahthapa70
 
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...aakahthapa70
 
Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7
Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7
Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7Ayesha Khan
 
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...riyaescorts54
 
Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...
Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...
Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...Ayesha Khan
 
Call Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts ServiceCall Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts ServiceLipikasharma29
 
Call Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls Service
Call Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls ServiceCall Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls Service
Call Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls ServiceAyesha Khan
 
Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...
Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...
Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...Ayesha Khan
 
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...aakahthapa70
 

Recently uploaded (20)

Call Girls In Sector 85 Noida 9711911712 Escorts ServiCe Noida
Call Girls In Sector 85 Noida 9711911712 Escorts ServiCe NoidaCall Girls In Sector 85 Noida 9711911712 Escorts ServiCe Noida
Call Girls In Sector 85 Noida 9711911712 Escorts ServiCe Noida
 
NAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALLNAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALL
 
Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...
Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...
Call Girls In {{Connaught Place Delhi}}96679@38988 Indian Russian High Profil...
 
BHOPAL CALL GIRL 92628*71154 BHOPAL CALL
BHOPAL CALL GIRL 92628*71154 BHOPAL CALLBHOPAL CALL GIRL 92628*71154 BHOPAL CALL
BHOPAL CALL GIRL 92628*71154 BHOPAL CALL
 
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
 
Russian Call Girls in Goa %(9316020077)# Russian Call Girls in Goa By Russi...
Russian Call Girls  in Goa %(9316020077)# Russian Call Girls  in Goa By Russi...Russian Call Girls  in Goa %(9316020077)# Russian Call Girls  in Goa By Russi...
Russian Call Girls in Goa %(9316020077)# Russian Call Girls in Goa By Russi...
 
Call Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In Karachi
Call Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In KarachiCall Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In Karachi
Call Girls In Karachi || 03070433345 || Sexy & Affordable Call Girls In Karachi
 
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
 
▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂
▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂
▶ ●─Cash On Delivery Call Girls In ( Sector 63 Noida )꧁❤⎝8375860717⎠❤꧂
 
Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Paharganj Delhi 💯 Call Us 🔝9667422720🔝
 
Call Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash Payment
Call Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash PaymentCall Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash Payment
Call Girls In {Aerocity Delhi} 9667938988 Cheap Price Your Budget & Cash Payment
 
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
 
Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7
Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7
Call Girls In Lahore || 03010449222 ||Lahore Call Girl Available 24/7
 
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
 
Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...
Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...
Karachi Escort Girls -03278838827- Top 100 + Independent Call Girls for Night...
 
Call Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts ServiceCall Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts Service
 
Call Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket Delhi
Call Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket DelhiCall Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket Delhi
Call Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket Delhi
 
Call Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls Service
Call Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls ServiceCall Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls Service
Call Girls in Lahore || 03090999379 || Get 30% Off on Hot Call Girls Service
 
Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...
Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...
Call Girls In Islamabad || 03274885999 || 24/7 Service Islamabad Call Girls &...
 
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
Call Girls In {Laxmi Nagar Delhi} 9667938988 Indian Russian High Profile Girl...
 

Difference Between Quality Control Inspection and Commissioning Inspection

  • 1. THE DIFFERENCE BETWEEN QC INSPECTIONS AND COMMISSIONING INSPECTIONS COMMISSIONING MANAGEMENT ORGANIZATION
  • 2. Understanding Construction Quality Control • Construction quality control is a type of management system that aims to ensure that the deliverable fulfils the guidelines and standards laid by the client. • These may include completion of the project within the scope of predefined work as well as avoiding disputes throughout the project’s life cycle. • Quality is established by the client and regulatory agencies, and is usually based on regulatory and environmental guidelines. • All the quality assurance procedures and requirements are recorded in the construction quality management plan.
  • 3. • There are two major facets of quality in construction: quality assurance (QA) and quality control (QC). • While quality assurance describes the quality management-specific expectations and how to attain quality, quality control explains the plan to achieve the same. • The construction quality control manager oversees this plan throughout different phases of the project.
  • 4. Understanding Construction Commissioning • Building commissioning is a methodical process of balances and checks to ensure that building equipment and systems are constructed, designed, and operated for optimal performance. • The commissioning management company brings an all- encompassing approach to the process of design, and is accountable for thoroughly reviewing construction-specific documentation, testing and validating the specific equipment post installation, and checking if building staff are trained properly to operate and maintain the installed equipment.
  • 5. • Apart from ensuring that building components, including cooling, heating, refrigeration and water systems, and air handling work as they are expected to be, commissioning companies in the UK also aim to lower maintenance and operational costs as well as improve the building’s energy usage. • Although installation contractors and design professionals are eventually accountable for testing building systems and ensuring the quality of the installation, the commissioning team provides a second pair of ears and eyes throughout the entire construction process – checking for any deficiencies as well as preventing and resolving possible issues before the building becomes fully operational.
  • 6. QC Inspections vs. Commissioning Inspections • Commissioning is a complex process, particularly the phase of transition to commissioning from construction. • However, with the proper documentation, it can be simplified substantially. • This is where the documents for QC and Commissioning Inspections comes in. • There are basically 3 types of documents that have to be defined during the transition.  Inspection Test Plans (ITPs)  Mechanical Completion Checklists  Pre-commissioning Checklists. • Let’s look at these three types of documents in detail.
  • 7. Inspection and Test Plans • Primarily, these are part of the construction-specific quality control documents. • Inspection and test plans, acronymed as ITPs, list the quality inspections to be done in order to confirm appropriate installation, once the systems are installed. • For instance, a mechanical ITP is a checklist that includes the torque values that need to be confirmed after equipment installation. • Every bolt is torque-checked to see if they are torqued appropriately.
  • 8. • Another ITP example can be a checklist to verify and confirm if equipment is installed correctly, including flushing of pipes to confirm they contain no debris, pressure or leak testing to verify that the piping has no leaks – and as part of the QC inspection documentation, it confirms that piping has been installed correctly. • An example of electrical ITPs can be a checklist, comprising all the inspections that need be done on all cables after being pulled. • This may include point-to-point testing and Megger checking. Megger testing confirms that there is no damage to the cables, with its dielectric properties being maintained well post installation. • Point-to-point testing confirms that the cable has been terminated appropriately to the right terminal blocks in the automation cubicle. • All ITPs are specific to individual subsystems. Once all ITPs are done, the mechanical completion documentation begins.
  • 9. Mechanical Completion • Mechanical completion is the process of formal handover to the commissioning team from the construction team. • Every mechanical completion contains all the ITPs associated with a specific subsystem, and the mechanical completion checklist will include the documentation, which is needed as part of that specific handover. • Once all the items listed in the mechanical completion checklist is completed, the checklist is verified and signed off, indicating handover to the commissioning team, which can then start with the pre-commissioning testing.
  • 10. Commissioning Inspections • Commissioning inspections are specified in pre- commissioning checklists. An example of a pre- commissioning mechanical checklist can be a pump and a motor that need startup for the very first time. • In such a checklist, a bump test will be performed to verify rotation, an uncoupled run will be done to see there are no issues, a coupled run will be done to verify current draw, and an initial run-in will be done to check flow and pressure rates. • An example of a pre-commissioning electrical checklist can be powering up an automation cubicle for the very first time.
  • 11. • Such a checklist will include primary communication checks, set-point and alarm checks, monitoring and control checks, loop checks, and so forth. • Once all pre-commissioning inspections are done, the systems can further be tested during the commissioning testing phase. • To make their entire commissioning inspection process faster, smoother and more efficient, most commissioning management companies rely on advanced commissioning management software like Cobia that helps ensure clear tracking, traceability and accountability for every stage of the commissioning process.
  • 12. Conclusion • With the discussion above, the major difference between QC inspections and commissioning inspections is quite clear. • Hence, it can be concluded that while QC inspections confirm that the equipment has been installed appropriately, commissioning inspections verifies that the equipment is functioning correctly.
  • 14. WORK WITH US Email efox@global-cxm.com Contact number Website https://www.global-cxm.com/ +441227649087, +447580017944