SlideShare a Scribd company logo
1 of 15
How to Navigate the
Commissioning Process:
From Planning to Post-
Construction
Introduction
While the commissioning process means an up-
front cost to construction project owners, it can
be well-compensated by savings in the long run
through reduced repairs, enhanced energy
efficiency, higher occupant satisfaction and
increased safety. Here, we will dig deeper into
the construction commissioning process for new
buildings. Continue reading to understand how
building commissioning firms should navigate the
commissioning process, right from its
involvement during the initial planning to its key
role throughout the lifespan of the building.
Start with the
Completion in
Mind
In the commissioning process, the very first step is
to be taken by the commissioning team. It entails
collaborating with the project team, to figure out
the budget and scope of commissioning, which
will important to have a funding estimate. The
building commissioning firms work with the
project team to form the commissioning team.
While the team formation will be based on the
size, complexity and type of the project at hand,
one should never pass go and collect any amount
until the commissioning team is well aligned with
the overall process of project delivery.
Once the commissioning team is aligned, it will
work closely with the project team to understand
the project-specific goals. These requirements
will evolve throughout each phase of the project,
but the initial commissioning plan will act as the
basic framework to be used to assess the project
from time to time.
Start with
the Completion
in Mind
Understanding
the Plan
The design phase of the project is the chance for
the project architects and engineers to assess
concept, design and construction documents in
order to ensure that the building systems are
designed and will operate in the correct manner.
This is the time when commissioning
requirements are incorporated into the design
document.
Communication is important in the design phase. If
every member of the project team, including the
designers, engineers, contractors and owner,
speak different languages, many issues may arise
on the project because of miscommunication.
The commissioning team should be able to
speak everyone’s language, which will aid
in identifying possible omissions
and errors early on during the design
phase. This will also help
reduce installation problems while
mitigating issues that normally arise
during the startup phase.
Understanding
the Plan
Creating
Checklists &
Conducting
Training
During the construction phase, the
commissioning team assesses contractors’
submittals, creates construction checklists
for the installation team and perform site
visits. Once the construction checklists are
created, functional performance testing
begins. The commissioning team will check if
the building’s systems were installed
properly and are functioning appropriately,
while following up with the troubleshooting
requirements, if any.
Creating Checklists
& Conducting
Training
Creating Checklists
&
Conducting Traini
ng
After reporting the progress to the
project owner, training for the
operations and maintenance personnel
are conducted, so that they acquire the
skills and knowledge to keep the
building function properly – just like
well-oiled machinery. Here, a system-
based approach to training is necessary
that helps staff understand how the
systems are interrelated.
Handing Over
the Keys
Once the commissioning team is done with
the tests and the contractors are done
with the required adjustments, the keys
are handed over to the project owner.
The final report to the owner comprises
an overview of the objectives defined at
the commencement of the project, an
exhaustive assessment of the design
documents, a summary of the tests done
on the equipment installed, a record of
the problems identified as well as an
overview of maintenance and operations
procedures, along with training
documentation.
Final Words
Due to weather conditions and seasonal
changes, not every building system can be
tested comprehensively during the
construction phase. For instance, a water
chilling system should be tested during the
winter season as well as summer season to
see if it can bear both cool and full loads. In
such a case, the commissioning agent will
come back at a later time to conduct the
season-specific testing, the result of which,
will be updated in the final report.
Final Words
Moreover, it is important to understand that
once a new building undergoes the initial
commissioning process, it is obvious for the
building systems and the system’s
components to observe regular wear and
tear, along with a slight drop in their
performance. Some building owners choose
to have ongoing commissioning to keep the
building function properly with periodic
monitoring and maintenance. It is
recommended to have a commissioning
professional revisit your building at least
once every year so as to keep the
commissioned systems in check.
Final Words
From the initial planning to continuous
monitoring and maintenance, there’s more
to building commissioning than you could
think initially. By starting with the project
completion in mind, ensuring proper
communication across teams, and keeping a
detailed record of documents and future
planning, a commissioning management
system can ensure that your building systems
are efficient and safe at all times, eventually
allowing project owners to make sustainable
and prudent investments.
Contact Us
Gecko Software, Unit 2
Chest field Business Park
Whitstable | Kent
CT5 3JB
Email: admin@geckosoftware.co
Call Support: +44 (0) 1227 649 045

More Related Content

Similar to Navigate the Building Commissioning Process

8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project CommissioningOlivia Wilson
 
8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project CommissioningOlivia Wilson
 
Construction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxConstruction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxlexfred55
 
Construction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxConstruction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxlexfred55
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseOlivia Wilson
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseOlivia Wilson
 
Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016L Douglas Sargent Jr
 
Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016L Douglas Sargent Jr
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to considerOlivia Wilson
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to considerOlivia Wilson
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning Olivia Wilson
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning Olivia Wilson
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group
 

Similar to Navigate the Building Commissioning Process (20)

8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning
 
8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning
 
Construction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxConstruction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptx
 
Construction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxConstruction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptx
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
 
Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016
 
Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning
 
CEM unit -I ppt.pptx
CEM unit -I ppt.pptxCEM unit -I ppt.pptx
CEM unit -I ppt.pptx
 
CEM unit -I ppt.pptx
CEM unit -I ppt.pptxCEM unit -I ppt.pptx
CEM unit -I ppt.pptx
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 

More from Olivia Wilson

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Olivia Wilson
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxOlivia Wilson
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareOlivia Wilson
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Olivia Wilson
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareOlivia Wilson
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareOlivia Wilson
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfOlivia Wilson
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System Olivia Wilson
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection ChecklistsOlivia Wilson
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionOlivia Wilson
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfOlivia Wilson
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxOlivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about CommissioningOlivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about CommissioningOlivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTOlivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTOlivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work SystemOlivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work SystemOlivia Wilson
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKOlivia Wilson
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKOlivia Wilson
 

More from Olivia Wilson (20)

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptx
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko Software
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko Software
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko Software
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdf
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-Construction
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdf
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptx
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
 

Recently uploaded

2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiMalviyaNagarCallGirl
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCRsoniya singh
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFOrient Homes
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...Khaled Al Awadi
 

Recently uploaded (20)

2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
 

Navigate the Building Commissioning Process

  • 1. How to Navigate the Commissioning Process: From Planning to Post- Construction
  • 2. Introduction While the commissioning process means an up- front cost to construction project owners, it can be well-compensated by savings in the long run through reduced repairs, enhanced energy efficiency, higher occupant satisfaction and increased safety. Here, we will dig deeper into the construction commissioning process for new buildings. Continue reading to understand how building commissioning firms should navigate the commissioning process, right from its involvement during the initial planning to its key role throughout the lifespan of the building.
  • 3. Start with the Completion in Mind In the commissioning process, the very first step is to be taken by the commissioning team. It entails collaborating with the project team, to figure out the budget and scope of commissioning, which will important to have a funding estimate. The building commissioning firms work with the project team to form the commissioning team. While the team formation will be based on the size, complexity and type of the project at hand, one should never pass go and collect any amount until the commissioning team is well aligned with the overall process of project delivery.
  • 4. Once the commissioning team is aligned, it will work closely with the project team to understand the project-specific goals. These requirements will evolve throughout each phase of the project, but the initial commissioning plan will act as the basic framework to be used to assess the project from time to time. Start with the Completion in Mind
  • 5. Understanding the Plan The design phase of the project is the chance for the project architects and engineers to assess concept, design and construction documents in order to ensure that the building systems are designed and will operate in the correct manner. This is the time when commissioning requirements are incorporated into the design document. Communication is important in the design phase. If every member of the project team, including the designers, engineers, contractors and owner, speak different languages, many issues may arise on the project because of miscommunication.
  • 6. The commissioning team should be able to speak everyone’s language, which will aid in identifying possible omissions and errors early on during the design phase. This will also help reduce installation problems while mitigating issues that normally arise during the startup phase. Understanding the Plan
  • 7.
  • 8. Creating Checklists & Conducting Training During the construction phase, the commissioning team assesses contractors’ submittals, creates construction checklists for the installation team and perform site visits. Once the construction checklists are created, functional performance testing begins. The commissioning team will check if the building’s systems were installed properly and are functioning appropriately, while following up with the troubleshooting requirements, if any.
  • 10. Creating Checklists & Conducting Traini ng After reporting the progress to the project owner, training for the operations and maintenance personnel are conducted, so that they acquire the skills and knowledge to keep the building function properly – just like well-oiled machinery. Here, a system- based approach to training is necessary that helps staff understand how the systems are interrelated.
  • 11. Handing Over the Keys Once the commissioning team is done with the tests and the contractors are done with the required adjustments, the keys are handed over to the project owner. The final report to the owner comprises an overview of the objectives defined at the commencement of the project, an exhaustive assessment of the design documents, a summary of the tests done on the equipment installed, a record of the problems identified as well as an overview of maintenance and operations procedures, along with training documentation.
  • 12. Final Words Due to weather conditions and seasonal changes, not every building system can be tested comprehensively during the construction phase. For instance, a water chilling system should be tested during the winter season as well as summer season to see if it can bear both cool and full loads. In such a case, the commissioning agent will come back at a later time to conduct the season-specific testing, the result of which, will be updated in the final report.
  • 13. Final Words Moreover, it is important to understand that once a new building undergoes the initial commissioning process, it is obvious for the building systems and the system’s components to observe regular wear and tear, along with a slight drop in their performance. Some building owners choose to have ongoing commissioning to keep the building function properly with periodic monitoring and maintenance. It is recommended to have a commissioning professional revisit your building at least once every year so as to keep the commissioned systems in check.
  • 14. Final Words From the initial planning to continuous monitoring and maintenance, there’s more to building commissioning than you could think initially. By starting with the project completion in mind, ensuring proper communication across teams, and keeping a detailed record of documents and future planning, a commissioning management system can ensure that your building systems are efficient and safe at all times, eventually allowing project owners to make sustainable and prudent investments.
  • 15. Contact Us Gecko Software, Unit 2 Chest field Business Park Whitstable | Kent CT5 3JB Email: admin@geckosoftware.co Call Support: +44 (0) 1227 649 045