SlideShare a Scribd company logo
1 of 11
Commissioning-Specific Best Practices during the
Construction Phase
global-cxm.com
Index
• Introduction
• Conducting a Great Initial Meeting
• Completing Pre-Functional Checklists by
the Commissioning Authority
• Becoming Part of the Solution
• Customising Functional Performance
Testing
• Social Connections
• Contact Details
Introduction
 Staying abreast of project updates and developing a rapport with all the parties involved in the
project are important aspects of the commissioning process.
 Interestingly, there are handful of best practices that the best commissioning management
company in the UK can integrate into each stage of the commissioning process to make it
more effective.
 Keep reading to know about such practices that you can use during the important phase of
construction.
Conducting a Great Initial Meeting
 When conducted appropriately, the initial meeting should make the
project team feel quite confident that the commissioning
management firm is available at all times to ensure the project
completes successfully.
 In addition to offering support to the team, best practices for the
initial meeting include the following:
 Scheduling the meeting mindfully. It should not be scheduled too
early. Reason being, contractors may forget about the commissioning
process if too much time passes by. Whereas, if you conduct it after
equipment installation, you would miss crucial opportunities to assess
submittals and inform the process. The right time is when contractors
are available on site and the construction phase has just started, but
equipment is yet to be installed.
 It may appear obvious, but the initial meeting must include a complete review of the
commissioning authority process. Present a master list of equipment that requires
commissioning, testing duration and prerequisites, along with pre-functional
checklists, so that each member of the team properly understand what they should
expect along the way.
 Maintaining the momentum of the meeting is important. This can be done by visiting
the site soon after the meeting and interacting with contractors while showing
interest in their work to understand the project in a better way through keen
observation.
Completing Pre-Functional Checklists by the
Commissioning Authority
 Instead of depending on installation contractors, the
commissioning authority should take the responsibility
to complete the documentation of pre-functional
checklist.
 While acting as the most effective supporter of the
project owner, the commission authority can check
appropriate installation early on in order to prevent
systemic problems from occurring in the first place.
Becoming Part of the Solution
 Project teams admire commissioning management companies that work beyond generating lists of
problems.
 That is to say, the commission authority should put in efforts to be part of the solution.
 The commissioning deficiencies log is certainly a crucial communication tool to track deficiencies that
cannot be fixed immediately.
 Every deficiency is assigned to a suitable member of the project team.
 This log should define every deficiency with clarity while offering suggestions on how to resolve the issue.
 When completing the pre-functional checklist on site, the commissioning authority should try its best to
build rapport with the members of the project team, who have the responsibility to install equipment.
 When a deficiency is identified, this will help the commissioning authority know who they should contact
to in order to discuss the deficiency – either to resolve it right away or to offer recommendations for
faster resolution.
Customising Functional Performance Testing
 After the approval of submittals, Functional Performance Testing
(FPT) documentation must be completed.
 The documentation should describe any particular installation or
operational requirements from the manufacturer, along with test
procedures developed through years of commissioning experience.
 Specific control sequences should be used that are developed by the
design team to check the response of equipment to changes in the
status, like transition from heating to cooling or enabling the
economizer mode.
 Does the equipment set back when set points are attained? Does the
equipment for backup power work in the event of an emergency
power failure? Is the direct digital controls interface working
perfectly, without errors?
 Such questions can easily be addressed if the commissioning
authority possess a comprehensive FPT documentation, uses test
procedures in an organised manner and records the outcomes, so
that testing can be done again during re-commissioning in future.
Social Media Connections
Contact Details
https://www.global-cxm.com/commissioning/
Global Commissioning Management
Unit 2, Chestfield Business Park, Whitstable, Kent,
CT5 3JB
+441227649087, +447580017944
THANK YOU

More Related Content

Similar to Commissioning-Specific Best Practices during the Construction Phase

BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSOlivia Wilson
 
Reconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and StartupReconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and StartupOlivia Wilson
 
Commissioning Management Organization | Building Commissioning Firms
Commissioning Management Organization | Building Commissioning FirmsCommissioning Management Organization | Building Commissioning Firms
Commissioning Management Organization | Building Commissioning FirmsOlivia Wilson
 
8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project CommissioningOlivia Wilson
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionOlivia Wilson
 
How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...Olivia Wilson
 
How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...Olivia Wilson
 
Commissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdfCommissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdfRommelTolentino8
 
Boost Equipment Performance, Save Money With Proactive Maintenance
Boost Equipment Performance, Save Money With Proactive MaintenanceBoost Equipment Performance, Save Money With Proactive Maintenance
Boost Equipment Performance, Save Money With Proactive MaintenanceJames Fitzgerald
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2optReza Abed
 
Maximizing_Uptime_in_MC_Facilities
Maximizing_Uptime_in_MC_FacilitiesMaximizing_Uptime_in_MC_Facilities
Maximizing_Uptime_in_MC_FacilitiesJoe Soroka
 
Improving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning PhaseImproving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning PhaseOlivia Wilson
 
Chapter 3 Static Techniques
Chapter 3 Static TechniquesChapter 3 Static Techniques
Chapter 3 Static TechniquesZetryan Satria
 
Automation Project Survival Guide.pptx
Automation Project Survival Guide.pptxAutomation Project Survival Guide.pptx
Automation Project Survival Guide.pptxRaymund Gatoc
 
5 steps project change control process
5 steps project change control process5 steps project change control process
5 steps project change control processPM Majik
 
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docxRUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docxsusanschei
 
The Case for Agile testing
The Case for Agile testingThe Case for Agile testing
The Case for Agile testingCognizant
 
Implementing a testing strategy
Implementing a testing strategyImplementing a testing strategy
Implementing a testing strategyDaniel Giraldo
 
Master transfer.pdf
Master transfer.pdfMaster transfer.pdf
Master transfer.pdfApVirtuoso
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseOlivia Wilson
 

Similar to Commissioning-Specific Best Practices during the Construction Phase (20)

BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
 
Reconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and StartupReconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and Startup
 
Commissioning Management Organization | Building Commissioning Firms
Commissioning Management Organization | Building Commissioning FirmsCommissioning Management Organization | Building Commissioning Firms
Commissioning Management Organization | Building Commissioning Firms
 
8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning8 Best Practices for New Project Commissioning
8 Best Practices for New Project Commissioning
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-Construction
 
How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...
 
How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...How to Navigate the Commissioning Process From Planning to Post Construction_...
How to Navigate the Commissioning Process From Planning to Post Construction_...
 
Commissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdfCommissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdf
 
Boost Equipment Performance, Save Money With Proactive Maintenance
Boost Equipment Performance, Save Money With Proactive MaintenanceBoost Equipment Performance, Save Money With Proactive Maintenance
Boost Equipment Performance, Save Money With Proactive Maintenance
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2opt
 
Maximizing_Uptime_in_MC_Facilities
Maximizing_Uptime_in_MC_FacilitiesMaximizing_Uptime_in_MC_Facilities
Maximizing_Uptime_in_MC_Facilities
 
Improving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning PhaseImproving Handover from Construction Phase to Commissioning Phase
Improving Handover from Construction Phase to Commissioning Phase
 
Chapter 3 Static Techniques
Chapter 3 Static TechniquesChapter 3 Static Techniques
Chapter 3 Static Techniques
 
Automation Project Survival Guide.pptx
Automation Project Survival Guide.pptxAutomation Project Survival Guide.pptx
Automation Project Survival Guide.pptx
 
5 steps project change control process
5 steps project change control process5 steps project change control process
5 steps project change control process
 
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docxRUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docx
 
The Case for Agile testing
The Case for Agile testingThe Case for Agile testing
The Case for Agile testing
 
Implementing a testing strategy
Implementing a testing strategyImplementing a testing strategy
Implementing a testing strategy
 
Master transfer.pdf
Master transfer.pdfMaster transfer.pdf
Master transfer.pdf
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning Phase
 

More from Olivia Wilson

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Olivia Wilson
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxOlivia Wilson
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareOlivia Wilson
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Olivia Wilson
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareOlivia Wilson
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareOlivia Wilson
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfOlivia Wilson
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System Olivia Wilson
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection ChecklistsOlivia Wilson
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfOlivia Wilson
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxOlivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about CommissioningOlivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about CommissioningOlivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTOlivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTOlivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work SystemOlivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work SystemOlivia Wilson
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKOlivia Wilson
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKOlivia Wilson
 
Important Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and ValidationImportant Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and ValidationOlivia Wilson
 

More from Olivia Wilson (20)

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptx
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko Software
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko Software
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko Software
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdf
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdf
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptx
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
 
Important Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and ValidationImportant Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and Validation
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 

Commissioning-Specific Best Practices during the Construction Phase

  • 1. Commissioning-Specific Best Practices during the Construction Phase global-cxm.com
  • 2. Index • Introduction • Conducting a Great Initial Meeting • Completing Pre-Functional Checklists by the Commissioning Authority • Becoming Part of the Solution • Customising Functional Performance Testing • Social Connections • Contact Details
  • 3. Introduction  Staying abreast of project updates and developing a rapport with all the parties involved in the project are important aspects of the commissioning process.  Interestingly, there are handful of best practices that the best commissioning management company in the UK can integrate into each stage of the commissioning process to make it more effective.  Keep reading to know about such practices that you can use during the important phase of construction.
  • 4. Conducting a Great Initial Meeting  When conducted appropriately, the initial meeting should make the project team feel quite confident that the commissioning management firm is available at all times to ensure the project completes successfully.  In addition to offering support to the team, best practices for the initial meeting include the following:  Scheduling the meeting mindfully. It should not be scheduled too early. Reason being, contractors may forget about the commissioning process if too much time passes by. Whereas, if you conduct it after equipment installation, you would miss crucial opportunities to assess submittals and inform the process. The right time is when contractors are available on site and the construction phase has just started, but equipment is yet to be installed.
  • 5.  It may appear obvious, but the initial meeting must include a complete review of the commissioning authority process. Present a master list of equipment that requires commissioning, testing duration and prerequisites, along with pre-functional checklists, so that each member of the team properly understand what they should expect along the way.  Maintaining the momentum of the meeting is important. This can be done by visiting the site soon after the meeting and interacting with contractors while showing interest in their work to understand the project in a better way through keen observation.
  • 6. Completing Pre-Functional Checklists by the Commissioning Authority  Instead of depending on installation contractors, the commissioning authority should take the responsibility to complete the documentation of pre-functional checklist.  While acting as the most effective supporter of the project owner, the commission authority can check appropriate installation early on in order to prevent systemic problems from occurring in the first place.
  • 7. Becoming Part of the Solution  Project teams admire commissioning management companies that work beyond generating lists of problems.  That is to say, the commission authority should put in efforts to be part of the solution.  The commissioning deficiencies log is certainly a crucial communication tool to track deficiencies that cannot be fixed immediately.  Every deficiency is assigned to a suitable member of the project team.  This log should define every deficiency with clarity while offering suggestions on how to resolve the issue.  When completing the pre-functional checklist on site, the commissioning authority should try its best to build rapport with the members of the project team, who have the responsibility to install equipment.  When a deficiency is identified, this will help the commissioning authority know who they should contact to in order to discuss the deficiency – either to resolve it right away or to offer recommendations for faster resolution.
  • 8. Customising Functional Performance Testing  After the approval of submittals, Functional Performance Testing (FPT) documentation must be completed.  The documentation should describe any particular installation or operational requirements from the manufacturer, along with test procedures developed through years of commissioning experience.  Specific control sequences should be used that are developed by the design team to check the response of equipment to changes in the status, like transition from heating to cooling or enabling the economizer mode.  Does the equipment set back when set points are attained? Does the equipment for backup power work in the event of an emergency power failure? Is the direct digital controls interface working perfectly, without errors?  Such questions can easily be addressed if the commissioning authority possess a comprehensive FPT documentation, uses test procedures in an organised manner and records the outcomes, so that testing can be done again during re-commissioning in future.
  • 10. Contact Details https://www.global-cxm.com/commissioning/ Global Commissioning Management Unit 2, Chestfield Business Park, Whitstable, Kent, CT5 3JB +441227649087, +447580017944