SlideShare a Scribd company logo
1 of 16
Resource Scheduling
The Need for Resource Scheduling:
The previous Project Scheduling methods that we have covered have not
considered the constraint of resources. Generally, there are
2 types of projects…..
1. Projects that MUST meet a certain deadline and have ‘unlimited’ resources in
order to meet this. This would use Time Limited Scheduling.
2. Projects that have limited availability of the required resources, however the
project deadline is more flexible. The would use Resource Limited Scheduling.

Note: if a project has both limited time and resources, the project manager must initially
assume that one or the other is flexible. OR, renegotiations will need to take place.
Time Limited Scheduling
Objectives:
▪ Determine exactly what resources the project requires;
▪ Make these resources available for when they are needed;
▪ Use each resource as efficiently as possible
– Resource Smoothing: this defines the act of maximising resources efficiency. Despite having
‘umlimited’ resorurces, it is still necessary to try to keep costs down as much as possible.
The Resources Loading Chart:
Activity

Description

Staff

Duration Earliest Start Time Float Latest Finish Time

A

Prepare offices

2

12

0

0

12

B

Procure equipment

2

8

0

4

12

C

Design tests

1

5

0

17

22

D

Install equiptment

4

10

12

0

22

E

Test system

3

10

22

0

32

F

Train users

1

5

12

15

32

Consider the
adjacent
example which
is adapted from
Field & Keller
‘Project
Management’
1998:
We will build the
previous information
into a ‘Resource
Loading Chart’
Observations:
▪ From the previous slide’s graph we can immediately tell how many
staff are needed at any one time.
▪ For example – in week 10, we can identify that only 2 staff members
are required. Whereas in week 14 there are 5 staff members required.

▪ The method of creating this chart, by positioning one activity at a
time, is called Serial Scheduling.
Note: The bottom row of the graph could also be described as the ‘critical
path’. Each of these items as Float=0. This row can be described as the
Base Line.
Resource Levelling:
▪ As identified in the previous slides, our chart contains
‘extreme peaks’. For example, weeks 1-5.
▪ Resource levelling helps to avoid this.
▪ As we have several activities which contain float, we can try
to move these activities to ‘level’ out the staff distribution:
Obviously this still
isn’t ideal as we still
have a ‘peak’ during
week 13. However we
have levelled s much
as possible, and in
turn we have reduced
costs.
Resource Limited Scheduling
Objectives:
▪ To adjust the project’s time to adapt to fixed level of
resources.
▪ In the previous example, we realised it would take 5 staff to
create the office in 32 weeks.

▪ Now, let’s consider how long it would take if the staff level
were fixed at 4.
Parallel Scheduling:
▪ Definition: Starting at the beginning of a project and
considering all the eligible activities, in a parallel manner.
▪ An eligible activity would be one which could be started if
the resources were available.
Let’s re-consider the example….
Activity

Dependency

Staff

Duration

Latest Start
Time

Float Latest Finish Time

A

N/A

2

12

0

0

12

B

N/A

2

8

4

4

12

C

N/A

1

5

17

17

22

D

A and B

4

10

12

0

22

E

C and D

3

10

22

0

32

F

A and B

1

5

27

15

32

Example
In Excel, Have a
go at plotting
the chart with
the strict
resource limit of
4:
The Result
Sources and Further Reading:
▪ Fiiled, M. and Keller, M. (1998), Croatia: Thomson Learning
– Chapter 3.4

▪ Moder, J., Philips, C. and Davis, E. (1983), Project management with CPM, PERT and
project diagramming, New York: Van Nostrand Reinhold Publishers
▪ Kerzner, H. (2009) Project Management, New Jersey: John Wiley & Sons, 10th edn.
– Chapter 12

More Related Content

What's hot

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
Khem Singh
 

What's hot (20)

Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Wbs
WbsWbs
Wbs
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 

Similar to Resource Scheduling

Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
Nicola2903
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
sslovepk
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
briancrawford30935
 

Similar to Resource Scheduling (20)

Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Resource management
Resource managementResource management
Resource management
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
Project management teaching
Project management   teachingProject management   teaching
Project management teaching
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
 
Part II: Planning Time: Determining When and How Much
Part II: Planning Time: Determining When and How MuchPart II: Planning Time: Determining When and How Much
Part II: Planning Time: Determining When and How Much
 
Resource Allocation In Software Project Management
Resource Allocation In Software Project ManagementResource Allocation In Software Project Management
Resource Allocation In Software Project Management
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 

More from Nicola2903

Network diagrams
Network diagramsNetwork diagrams
Network diagrams
Nicola2903
 
Critical path method
Critical path methodCritical path method
Critical path method
Nicola2903
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
Nicola2903
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
Nicola2903
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
Nicola2903
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
Nicola2903
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project Scheduling
Nicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
Nicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
Nicola2903
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
Nicola2903
 

More from Nicola2903 (12)

Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Estimating
EstimatingEstimating
Estimating
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Estimating
EstimatingEstimating
Estimating
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project Scheduling
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 

Recently uploaded

Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 

Recently uploaded (20)

Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 

Resource Scheduling

  • 2. The Need for Resource Scheduling: The previous Project Scheduling methods that we have covered have not considered the constraint of resources. Generally, there are 2 types of projects….. 1. Projects that MUST meet a certain deadline and have ‘unlimited’ resources in order to meet this. This would use Time Limited Scheduling. 2. Projects that have limited availability of the required resources, however the project deadline is more flexible. The would use Resource Limited Scheduling. Note: if a project has both limited time and resources, the project manager must initially assume that one or the other is flexible. OR, renegotiations will need to take place.
  • 4. Objectives: ▪ Determine exactly what resources the project requires; ▪ Make these resources available for when they are needed; ▪ Use each resource as efficiently as possible – Resource Smoothing: this defines the act of maximising resources efficiency. Despite having ‘umlimited’ resorurces, it is still necessary to try to keep costs down as much as possible.
  • 5. The Resources Loading Chart: Activity Description Staff Duration Earliest Start Time Float Latest Finish Time A Prepare offices 2 12 0 0 12 B Procure equipment 2 8 0 4 12 C Design tests 1 5 0 17 22 D Install equiptment 4 10 12 0 22 E Test system 3 10 22 0 32 F Train users 1 5 12 15 32 Consider the adjacent example which is adapted from Field & Keller ‘Project Management’ 1998:
  • 6. We will build the previous information into a ‘Resource Loading Chart’
  • 7. Observations: ▪ From the previous slide’s graph we can immediately tell how many staff are needed at any one time. ▪ For example – in week 10, we can identify that only 2 staff members are required. Whereas in week 14 there are 5 staff members required. ▪ The method of creating this chart, by positioning one activity at a time, is called Serial Scheduling. Note: The bottom row of the graph could also be described as the ‘critical path’. Each of these items as Float=0. This row can be described as the Base Line.
  • 8. Resource Levelling: ▪ As identified in the previous slides, our chart contains ‘extreme peaks’. For example, weeks 1-5. ▪ Resource levelling helps to avoid this. ▪ As we have several activities which contain float, we can try to move these activities to ‘level’ out the staff distribution:
  • 9. Obviously this still isn’t ideal as we still have a ‘peak’ during week 13. However we have levelled s much as possible, and in turn we have reduced costs.
  • 11. Objectives: ▪ To adjust the project’s time to adapt to fixed level of resources. ▪ In the previous example, we realised it would take 5 staff to create the office in 32 weeks. ▪ Now, let’s consider how long it would take if the staff level were fixed at 4.
  • 12. Parallel Scheduling: ▪ Definition: Starting at the beginning of a project and considering all the eligible activities, in a parallel manner. ▪ An eligible activity would be one which could be started if the resources were available. Let’s re-consider the example….
  • 13. Activity Dependency Staff Duration Latest Start Time Float Latest Finish Time A N/A 2 12 0 0 12 B N/A 2 8 4 4 12 C N/A 1 5 17 17 22 D A and B 4 10 12 0 22 E C and D 3 10 22 0 32 F A and B 1 5 27 15 32 Example
  • 14. In Excel, Have a go at plotting the chart with the strict resource limit of 4:
  • 16. Sources and Further Reading: ▪ Fiiled, M. and Keller, M. (1998), Croatia: Thomson Learning – Chapter 3.4 ▪ Moder, J., Philips, C. and Davis, E. (1983), Project management with CPM, PERT and project diagramming, New York: Van Nostrand Reinhold Publishers ▪ Kerzner, H. (2009) Project Management, New Jersey: John Wiley & Sons, 10th edn. – Chapter 12